You are on page 1of 25

Detailed Project Report of Water Supply,Narsinghgarh District Rajgarh

ESTIMATE FOR WATER TREATMENT PLANT (WTP)

SoR RATE AMOUNT


S.N. DESCRIPTION QTY. UNIT
Reference (RS.) (Rs.)

1 Water Treatment Plants - Conventional

Designing (structurally, hydraulically & aesthetically), providing and


constructing and commissioning Conventional Water Treatment Plant
consisting of Civil Works, including cost of providing and applying
Epoxy paint to inside surface of water retaining structures in contact
SOR Vol. 1
1 with Chlorine and providing anti-termite treatment to entire structure
Chater 18
below ground level, Mechanical and Electrical components of various
sub-works as given below : including necessary hydraulic testing,
structural testing, equipment testing and trial run for 3 months, etc.
complete as directed by Engineer-in-charge . ( turn-key job ).

Cost of 1 MLD Treatment Plant 1.00 No. 6,800,000.00 6,800,000.00


Add per MLD above 5 MLD upto10 MLD 1.00 No. 5,200,000.00 5,200,000.00

Flocculator : Conforming to I.S. 7208 of 1974 ( Type-C) with


detention period of 30 minutes

Clarifier : Vertical flow / Horizontal flow circular tank, weir loading


with mechanical sludge scraper conforming to I.S. 10313/1982,
detention period, overflow rate for average design flow for different
types of sedimentation tanks shall be as follows.

Total 12,000,000.00
Water distribution network - Mungaoli
Bill of Quantity of water distribution network
Basic Rate
S. No. Reference Description Unit Qty Total Amount (Rs.)
(Rs.)

1 Demolishing of existing roads (water distribution network)


1.2 SOR - Roads and Dismantling of flexible/rigid pavements manually/by mechanical means
Bridges - CHAPTER 2 including disposal of material to 1000 meters distance as per direction of
Engineer-in-charge
Cum 147.39 420.00 61903.80
61903.80

Dismantling of cement concrete pavement i/c breaking to pieces not


exceeding 0.02 cum in volume and stock piling at designated locations and
disposal of dismantled materials up to a lead upto 1000 meter, stacking
serviceable and unserviceable materials separately and as per relevant
clauses of section-200.
Cum 25.35 749.00 18987.15

Sub Total 18,987.15

2 EARTHWORK FOR CUTTING, FILLING AND DISPOSAL OF SURPLUS EARTH (water distribution network)
2.1 SOR - CHAPTER 3 - Excavation for roadway in ordinary rock with hydraulic excavator
Roads and Bridges including cutting and loading in tippers, transporting to embankment site
(Point 3.4) with in all lifts and lead upto 1000 m, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections as per
relevent clauses of section-300 of specification.

Cum 2848.25 112.00 319004.55

Sub Total 319,004.55

3 PROVIDING AND LAYING Tile road/CC/Bituminous pavements (water distribution network)


Providing and laying bituminous macadam with hot mix plant using
crushed aggregates of specified grading premixed with bituminous binder,
transported to site, laid over a previously prepared surface with mechanical
paver finisher to the required grade, level and alignment and rolled as per
SOR Vol. III - Chapter 5 clauses 501.6 and 501.7 to achieve the desired compaction complete in all
respects and as per relevant clauses of section-504.

Grading I ( 80-100mm thickness ) bitumen content 3.3% (VG-30) Cum 147.39 5231 770997.09
5.3 (i)
Construction of dowel jointed, plain cement concrete pavement in M-30
grade concrete over a prepared sub base with 43 or higher grade cement,
coarse and fine aggregate conforming to IS:383 maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed form or slip
form paver with spreading the concrete by shovels, rakes compacted using
needle, screed and plate vibrator and finished in a continuous operation
including provision of contraction, expansion, and longitudinal joints, joint
SOR Vol. III - Chapter 6 filler, separation membrane, sealant primer, joint sealant, debonding strip, cum 25.35 5583 141529.05
(Pt. 6.2) placing of dowel bar,tie rod admixtures as approved, curing compound,
finishing to lines and grades as per approved drawings as per IRC-15 2011
and as per relevant clauses of section-602 of specifications complete
excluding cost of steel in dowel ber & tie rod etc.

Cutting Kharanja road and making good the same including supply
SOR Vol. 1 - Chapter of extra quantities of Kharanja, moorum.
18 (pt. 18.54) Sqm 2848.25 703 2002323.1947

Sub Total 2,914,849.33

4 Providing Moorum/Sand bedding (water distribution network)


SOR Vol. III - Chapter Filling with moorum for pipe bedding or over the pipe including supply of
18 (18.3.3) moorum/sand
110 mm dia Cum 742.46 720 534569.76
140 mm dia Cum 0.00 720 0.00
160 mm dia Cum 0.00 720 0.00
200 mm dia Cum 3.12 720 2246.40
Total Cum

Sub Total 536,816.16


5 PROVIDING AND LAYING OF PIPES (water distribution network)
5.1 CHAPTER 7 - WATER Providing, laying, Jointing & field testing of High Density Polyethylene
SUPPLY, SEWERAGE pipes, (HDPE) confirming to IS 4984/ 14151/ 12786/ 13488 with necessary
AND TUBE WELL jointing material like mechanical connector or jointing pipes by heating to
WORKS (Point 7) the ends of pipes with the help of Teflon coated electric mirror/ heater to
the
required temperature and then pressing the ends together against each
other, to form a monolithic & leak proof joint by thermosetting process. It
may be required to be done with Jacks/Hydraulic Jacks/ But fusion
machine. (50mm & above fusion jointed & below 50mm mechanical
jointed)
7.1.17 110 mm dia m 7279 354.00 2,576,766.00
7.1.15 140 mm dia m 0 572.00 -
7.1.14 160 mm dia m 0 743.00 -
7.1.9 200 mm dia m 26 1151.00 29,926.00
2,606,692.00

Providing & fixing of Cast iron double flanged sluice valves as per
I.S.:14846-2000 fitted with cast iron cap including jointing & testing with
cost of jointing material such as bolts, nuts, rubber insertions etc. all
complete

100 mm dia No. 1 5227.00 5,227.00


Total 5,227.00

Providing & fixing following ductile iron single chamber triple function
temper proof air valves, small orifice with screwed end as per IS:14845-
2000 including jointing & testing with cost of jointing material and rubber
insertion all complete as per IS:13095-1991

100 mm dia No. 1 17127.00 17,127.00


Total 17,127.00

House Connections No. 480 3000.00 1,440,000.00


Sub Total 1,440,000.00
Grand Total 7,920,606.99
Detail of Measurement of water distribution network - Narsinghgarh
Bredth Depth
S.No. Reference Item Description Unit No. Length (m) Quantity
(B) (m)

1 Demolishing of existing roads (water distribution network)


Dismantling of flexible/rigid pavements manually/by mechanical means including disposal of
material to 1000 meters distance as per direction of Engineer-in-charge
For 90 mm diameter pipe - BT Road 1 0 0.30 0.10 0.00
For 110 mm diameter pipe - BT road 1 4913 0.30 0.10 147.39
For 125 mm diameter pipe - BT road 1 0 0.42 0.10 0.00
For 140 mm diameter pipe - BT Road 1 0 0.44 0.10 0.00
For 160 mm diameter pipe - BT Road 1 0 0.46 0.10 0.00
For 180 mm diameter pipe - BT Road 1 0 0.48 0.10 0.00
For 200 mm diameter pipe - BT Road 1 0 0.50 0.10 0.00
For 225 mm diameter pipe - BT Road 1 0 0.52 0.10 0.00
For 250 mm diameter pipe - BT road 1 0 0.55 0.10 0.00
For 280 mm diameter pipe - BT road 1 0 0.58 0.10 0.00
For 315 mm diameter pipe - BT road 1 0 0.61 0.10 0.00
For 355 mm diameter pipe - BT road 1 0 0.65 0.10 0.00
For 400 mm diameter pipe - BT road 1 0 0.70 0.10 0.00
Total 147.39

Dismantling of cement concrete pavement i/c breaking to pieces not exceeding 0.02 cum in volume
and stock piling at designated locations and disposal of dismantled materials up to a lead upto 1000
meter, stacking serviceable and unserviceable materials separately and as per relevant clauses of
section-200.

For 90 mm diameter pipe - CC Road 1 0 0.30 0.15 0.00


For 110 mm diameter pipe - CC Road 1 520 0.30 0.15 23.40
For 125 mm diameter pipe - CC Road 1 0 0.42 0.15 0.00
For 140 mm diameter pipe - CC Road 1 0 0.44 0.15 0.00
For 160 mm diameter pipe - CC Road 1 0 0.46 0.15 0.00
For 180 mm diameter pipe - CC Road 1 0 0.48 0.15 0.00
For 200 mm diameter pipe - CC Road 1 26 0.50 0.15 1.95
For 225 mm diameter pipe - CC Road 1 0 0.52 0.15 0.00
For 280 mm diameter pipe - CC Road 1 0 0.55 0.15 0.00
For 315 mm diameter pipe - CC Road 1 0 0.61 0.15 0.00
For 355 mm diameter pipe - CC Road 1 0 0.65 0.15 0.00
For 400 mm diameter pipe - CC Road 1 0 0.70 0.15 0.00
Total 25.35

2 EARTHWORK FOR CUTTING, FILLING AND DISPOSAL OF SURPLUS EARTH (water distribution network)
1.0 Excavation for roadway in ordinary rock with hydraulic excavator including cutting and loading in
tippers, transporting to embankment site with in all lifts and lead upto 1000 m, trimming bottom
and side slopes in accordance with requirements of lines, grades and cross sections as per relevent
clauses of section-300 of specification.

90 mm dia 1 0.00 0.49 0.79 0.00


110 mm dia 1 7279.00 0.51 0.81 3006.95
125 mm dia 1 0.00 0.53 0.83 0.00
140 mm dia 1 0.00 0.54 0.84 0.00
160 mm dia 1 0.00 0.56 0.86 0.00
180 mm dia 1 0.00 0.58 0.88 0.00
200 mm dia 1 26.00 0.60 0.90 14.04
225 mm dia 1 0.00 0.63 0.93 0.00
250 mm dia 1 0.00 0.65 0.95 0.00
280 mm dia 1 0.00 0.68 0.98 0.00
315 mm dia 1 0.00 0.72 1.02 0.00
355 mm dia 1 0.00 0.76 1.06 0.00
400 mm dia 1 0.00 0.80 1.10 0.00
Total Cum 3020.99
2848.25
4 Providing Moorum/Sand bedding (water distribution network)
Filling with moorum for pipe bedding or over the pipe including supply of moorum/sand
90 mm dia Cum 1 0.00 0.49 0.20 0.00
110 mm dia Cum 1 7279.00 0.51 0.20 742.46
125 mm dia Cum 1 0.00 0.53 0.20 0.00
140 mm dia Cum 1 0.00 0.54 0.20 0.00
160 mm dia Cum 1 0.00 0.56 0.20 0.00
180 mm dia Cum 1 0.00 0.58 0.20 0.00
200 mm dia Cum 1 26.00 0.60 0.20 3.12
225 mm dia Cum 1 0.00 0.63 0.20 0.00
250 mm dia Cum 1 0.00 0.65 0.20 0.00
280 mm dia Cum 1 0.00 0.68 0.20 0.00
315 mm dia Cum 1 0.00 0.72 0.20 0.00
355 mm dia Cum 1 0.00 0.76 0.20 0.00
400 mm dia Cum 1 0.00 0.80 0.20 0.00
Total Cum 745.58

5 PROVIDING AND LAYING OF PIPES (water distribution network)


Providing, laying, Jointing & field testing of High Density Polyethylene pipes, (HDPE) confirming
to IS 4984/ 14151/ 12786/ 13488 with necessary jointing material like mechanical connector or
jointing pipes by heating to the ends of pipes with the help of Teflon coated electric mirror/ heater
to the
2.1
required temperature and then pressing the ends together against each other, to form a monolithic
& leak proof joint by thermosetting process. It may be required to be done with Jacks/Hydraulic
Jacks/ But fusion machine. (50mm & above fusion jointed & below 50mm mechanical jointed)

90 mm dia m 1 0.00 0.00


110 mm dia m 1 7279.00 7279.00
125 mm dia m 1 0.00 0.00
140 mm dia m 1 0.00 0.00
160 mm dia m 1 0.00 0.00
180 mm dia m 1 0.00 0.00
200 mm dia m 1 26.00 26.00
225 mm dia m 1 0.00 0.00
250 mm dia m 1 0.00 0.00
280 mm dia m 1 0.00 0.00
315 mm dia m 1 0.00 0.00
355 mm dia m 1 0.00 0.00
400 mm dia m 1 0.00 0.00

Providing & fixing of Cast iron double flanged sluice valves as per I.S.:14846-2000 fitted with cast
iron cap including jointing & testing with cost of jointing material such as bolts, nuts, rubber
insertions etc. all complete
100 mm dia No. 1 1

Providing & fixing following ductile iron single chamber triple function temper proof air valves,
small orifice with screwed end as per IS:14845-2000 including jointing & testing with cost of
jointing material and rubber insertion all complete as per IS:13095-1991

100 mm dia No. 1 1

4 OVER HEAD TANKS


Designing (structurally & aesthetically), and constructing RCC elevated service reservoirs of
following capacity with RCC staging consisting of columns, internal and external bracings spaced
vertically as per staging of the ESR. including excavation in all types of strata, foundation
concrete, cement plaster with water proofing compound to the inside face of the container
including refilling & disposing off the surplus stuff within a lead of 50 meters, all labour and
material charges including lowering, laying, erecting, hoisting and jointing of pipe assembly of
inlet, outlet, scour, overflow and bypass arrangements as per departmental design, providing and
Chapter 24- fixing accessories such as Stainless steel Ladder inside and MS ladder with GI railing outside, C.I.
REINFORCED
manhole frame and covers, water level indicators, lightening conductor, G.I. pipe railing around
CEMENT
CONCRETE walk way and top slab, providing staircase from ground level to roof level, M.S. grill gate of 2 mtr.
ELEVATED height with locking arrangement of approved design , Brick masonry chambers for all valves,
SERVICE ventilating shafts, providing and applying three coats of cement paint to the structure including
RESERVOIRS roof slab, epoxy painting to internal surface & anti termite treatment for underground parts of the
(24.1) structure and giving satisfactory water tightness test as per I.S. code, The job to include painting
the name of the scheme and other details on the reservoir as per the directions of Engineer-in-
Charge.

The rates are applicable for staging height of 10 m. These rates shall be increased or decreased for
per metre variation in this staging height as below. No. 0.00 0.00

10 to 16 m staging - 2% per metre.


16 to 20 m staging - 3% per metre 0
20 m and above - 4% per metre

OHT Staging Height 18


8mt. Extra (2% as per SoR)

House Connections No. 480


Pipe Abstract of Distribution System

90 mm to 400 mm HDPE Pipe Length (m) with Diameter wise


Scheme

90 110 125 140 160 180 200 225 250 280 315
Mungaoli 7279 26
0 7279 0 0 0 0 26 0 0 0 0
*15 mm use for FHTC Connection
Road Type
S.No. Road Length
1 BT 0
2 CC 587
3 Kaccha 777
4 Kharanja
Total 1364
Total
Length
(m)
355 400
7305
0 0 7305
ID Label Start Node Stop Node Length (m) Diameter (mm) Material Hazen-Williams C

98 P-1 R-1 J-6 29 200 HDPE 140


593 P-2 J-50 J-6 36 140 HDPE 140
647 P-3 J-6 J-7 13 140 HDPE 140
610 P-4 J-98 J-50 42 140 HDPE 140
93 P-5 J-137 J-141 167 140 HDPE 140
530 P-6 J-141 J-144 34 140 HDPE 140
181 P-7 R-2 J-1 26 200 HDPE 140
548 P-8 J-150 J-149 16 140 HDPE 140
521 P-9 J-63 J-143 160 110 HDPE 140
644 P-10 J-185 J-143 188 110 HDPE 140
534 P-11 J-144 J-149 36 110 HDPE 140
619 P-12 J-7 J-18 20 110 HDPE 140
620 P-13 J-18 J-42 23 110 HDPE 140
643 P-14 J-196 J-185 214 110 HDPE 140
586 P-15 J-1 J-2 35 110 HDPE 140
523 P-16 J-137 J-98 16 110 HDPE 140
609 P-17 J-137 J-98 16 110 HDPE 140
547 P-18 J-151 J-150 22 110 HDPE 140
402 P-19 J-5 J-28 65 110 HDPE 140
656 P-20 J-33 J-34 10 110 HDPE 140
660 P-21 J-198 J-196 121 110 HDPE 140
519 P-22 J-42 J-63 6 110 HDPE 140
552 P-23 J-156 J-151 35 110 HDPE 140
405 P-24 J-28 J-40 30 110 HDPE 140
406 P-25 J-40 J-53 7 110 HDPE 140
553 P-26 J-156 J-159 34 110 HDPE 140
198 P-27 J-159 J-162 23 110 HDPE 140
585 P-28 J-5 J-1 85 110 HDPE 140
156 P-29 J-162 J-164 24 110 HDPE 140
662 P-30 J-15 J-33 20 110 HDPE 140
390 P-31 J-4 J-13 95 110 HDPE 140
250 P-32 J-164 J-169 37 110 HDPE 140
540 P-33 J-144 J-145 42 110 HDPE 140
392 P-34 J-13 J-14 22 110 HDPE 140
265 P-35 J-169 J-175 45 110 HDPE 140
581 P-36 J-14 J-31 29 110 HDPE 140
555 P-37 J-150 J-163 212 110 HDPE 140
427 P-38 J-81 J-78 22 110 HDPE 140
414 P-39 J-76 J-82 61 110 HDPE 140
395 P-40 J-2 J-4 11 110 HDPE 140
542 P-41 J-145 J-147 40 110 HDPE 140
621 P-42 J-34 J-37 31 110 HDPE 140
426 P-43 J-83 J-81 47 110 HDPE 140
424 P-44 J-100 J-97 17 110 HDPE 140
582 P-45 J-31 J-76 100 110 HDPE 140
659 P-46 J-204 J-198 104 110 HDPE 140
488 P-47 J-64 J-37 28 110 HDPE 140
577 P-48 J-163 J-166 33 110 HDPE 140
536 P-49 J-149 J-147 33 110 HDPE 140
516 P-50 J-15 J-7 55 110 HDPE 140
661 P-51 J-7 J-15 55 110 HDPE 140
258 P-52 J-175 J-178 38 110 HDPE 140
483 P-53 J-79 J-64 33 110 HDPE 140
649 P-54 J-166 J-168 44 110 HDPE 140
346 P-55 J-178 J-179 101 110 HDPE 140
408 P-56 J-53 J-78 37 110 HDPE 140
617 P-57 J-79 J-89 107 110 HDPE 140
520 P-58 J-63 J-50 6 110 HDPE 140
261 P-59 J-179 J-180 54 110 HDPE 140
666 P-60 J-206 J-204 155 110 HDPE 140
399 P-61 J-2 J-3 21 110 HDPE 140
425 P-62 J-97 J-83 38 110 HDPE 140
618 P-63 J-89 J-111 105 110 HDPE 140
517 P-64 J-15 J-16 36 110 HDPE 140
206 P-65 J-180 J-182 15 110 HDPE 140
633 P-66 J-84 J-85 12 110 HDPE 140
431 P-67 J-100 J-112 65 110 HDPE 140
416 P-68 J-96 J-101 52 110 HDPE 140
338 P-69 J-182 J-183 96 110 HDPE 140
665 P-70 J-208 J-206 72 110 HDPE 140
415 P-71 J-82 J-96 65 110 HDPE 140
588 P-72 J-88 J-91 15 110 HDPE 140
272 P-73 J-70 J-53 51 110 HDPE 140
362 P-74 J-183 J-186 126 110 HDPE 140
418 P-75 J-101 J-105 35 110 HDPE 140
599 P-76 J-75 J-70 35 110 HDPE 140
650 P-77 J-168 J-174 60 110 HDPE 140
397 P-78 J-5 J-3 100 110 HDPE 140
623 P-79 J-35 J-34 120 110 HDPE 140
503 P-80 J-33 J-27 34 110 HDPE 140
664 P-81 J-210 J-208 126 110 HDPE 140
434 P-82 J-105 J-110 63 110 HDPE 140
580 P-83 J-91 J-97 26 110 HDPE 140
640 P-84 J-199 J-198 201 110 HDPE 140
471 P-85 J-50 J-66 93 110 HDPE 140
435 P-86 J-110 J-113 54 110 HDPE 140
605 P-87 J-82 J-84 71 110 HDPE 140
369 P-88 J-186 J-187 148 110 HDPE 140
634 P-89 J-85 J-88 10 110 HDPE 140
455 P-90 J-43 J-35 84 110 HDPE 140
506 P-91 J-27 J-16 23 110 HDPE 140
606 P-92 J-84 J-83 16 110 HDPE 140
420 P-93 J-105 J-100 88 110 HDPE 140
645 P-94 J-168 J-170 122 110 HDPE 140
607 P-95 J-105 J-106 50 110 HDPE 140
461 P-96 J-42 J-51 102 110 HDPE 140
432 P-97 J-112 J-117 52 110 HDPE 140
668 P-98 J-212 J-210 33 110 HDPE 140
190 P-99 J-187 J-188 23 110 HDPE 140
508 P-100 J-16 J-19 19 110 HDPE 140
446 P-101 J-125 J-111 97 110 HDPE 140
630 P-102 J-174 J-177 581 110 HDPE 140
164 P-103 J-188 J-189 15 110 HDPE 140
133 P-104 J-189 J-190 8 110 HDPE 140
144 P-105 J-86 J-85 12 110 HDPE 140
409 P-106 J-78 J-75 47 110 HDPE 140
142 P-107 J-190 J-191 11 110 HDPE 140
445 P-108 J-111 J-120 110 110 HDPE 140
556 P-109 J-112 J-119 90 110 HDPE 140
513 P-110 J-23 J-19 20 110 HDPE 140
667 P-111 J-214 J-212 43 110 HDPE 140
557 P-112 J-119 J-124 17 110 HDPE 140
590 P-113 J-86 J-88 9 110 HDPE 140
437 P-114 J-113 J-134 118 110 HDPE 140
282 P-115 J-191 J-192 55 110 HDPE 140
474 P-116 J-134 J-135 43 110 HDPE 140
635 P-117 J-66 J-68 46 110 HDPE 140
639 P-118 J-201 J-199 23 110 HDPE 140
559 P-119 J-124 J-129 16 110 HDPE 140
462 P-120 J-51 J-54 42 110 HDPE 140
398 P-121 J-3 J-4 9 110 HDPE 140
608 P-122 J-106 J-108 133 110 HDPE 140
451 P-123 J-45 J-43 38 110 HDPE 140
413 P-124 J-75 J-76 45 110 HDPE 140
638 P-125 J-93 J-91 12 110 HDPE 140
641 P-126 J-7 J-9 50 110 HDPE 140
433 P-127 J-117 J-118 18 110 HDPE 140
442 P-128 J-128 J-125 25 110 HDPE 140
356 P-129 J-192 J-193 117 110 HDPE 140
545 P-130 J-152 J-151 47 110 HDPE 140
284 P-131 J-170 J-174 56 110 HDPE 140
560 P-132 J-129 J-132 22 110 HDPE 140
654 P-133 J-95 J-93 34 110 HDPE 140
504 P-134 J-27 J-23 16 110 HDPE 140
627 P-135 J-54 J-57 34 110 HDPE 140
494 P-136 J-135 J-138 99 110 HDPE 140
616 P-137 J-122 J-118 47 110 HDPE 140
565 P-138 J-126 J-122 41 110 HDPE 140
172 P-139 J-108 J-109 17 110 HDPE 140
441 P-140 J-133 J-128 70 110 HDPE 140
653 P-141 J-96 J-95 11 110 HDPE 140
403 P-142 J-28 J-29 54 110 HDPE 140
631 P-143 J-216 J-214 187 110 HDPE 140
642 P-144 J-9 J-11 20 110 HDPE 140
646 P-145 J-170 J-171 5 110 HDPE 140
567 P-146 J-126 J-127 37 110 HDPE 140
308 P-147 J-119 J-117 84 110 HDPE 140
373 P-148 J-197 J-196 161 110 HDPE 140
439 P-149 J-134 J-133 32 110 HDPE 140
626 P-150 J-57 J-59 19 110 HDPE 140
367 P-151 J-176 J-175 145 110 HDPE 140
448 P-152 J-43 J-44 143 110 HDPE 140
255 P-153 J-193 J-194 36 110 HDPE 140
275 P-154 J-110 J-109 58 110 HDPE 140
561 P-155 J-132 J-133 76 110 HDPE 140
598 P-156 J-103 J-101 40 110 HDPE 140
90 P-157 J-120 J-121 69 110 HDPE 140
92 P-158 J-120 J-121 69 110 HDPE 140
359 P-159 J-181 J-180 120 110 HDPE 140
473 P-160 J-66 J-67 114 110 HDPE 140
636 P-161 J-68 J-72 71 110 HDPE 140
551 P-162 J-158 J-156 63 110 HDPE 140
591 P-163 J-59 J-60 15 110 HDPE 140
453 P-164 J-45 J-49 103 110 HDPE 140
501 P-165 J-23 J-25 22 110 HDPE 140
528 P-166 J-141 J-142 102 110 HDPE 140
596 P-167 J-115 J-113 43 110 HDPE 140
569 P-168 J-127 J-130 37 110 HDPE 140
343 P-169 J-68 J-74 101 110 HDPE 140
554 P-170 J-159 J-161 46 110 HDPE 140
340 P-171 J-199 J-200 99 110 HDPE 140
571 P-172 J-203 J-201 98 110 HDPE 140
615 P-173 J-121 J-122 25 110 HDPE 140
335 P-174 J-205 J-204 93 110 HDPE 140
332 P-175 J-165 J-164 91 110 HDPE 140
329 P-176 J-202 J-201 91 110 HDPE 140
564 P-177 J-125 J-126 65 110 HDPE 140
543 P-178 J-155 J-152 63 110 HDPE 140
320 P-179 J-207 J-206 86 110 HDPE 140
323 P-180 J-89 J-90 85 110 HDPE 140
311 P-181 J-209 J-208 78 110 HDPE 140
576 P-182 J-47 J-45 27 110 HDPE 140
526 P-183 J-98 J-99 71 110 HDPE 140
299 P-184 J-211 J-210 68 110 HDPE 140
290 P-185 J-167 J-166 61 110 HDPE 140
602 P-186 J-171 J-173 54 110 HDPE 140
604 P-187 J-11 J-12 52 110 HDPE 140
538 P-188 J-147 J-148 52 110 HDPE 140
541 P-189 J-145 J-146 51 110 HDPE 140
277 P-190 J-194 J-195 51 110 HDPE 140
495 P-191 J-138 J-140 50 110 HDPE 140
510 P-192 J-19 J-20 20 110 HDPE 140
269 P-193 J-52 J-51 48 110 HDPE 140
266 P-194 J-153 J-152 48 110 HDPE 140
481 P-195 J-65 J-64 47 110 HDPE 140
218 P-196 J-106 J-107 47 110 HDPE 140
104 P-197 J-31 J-32 0 110 HDPE 140
247 P-198 J-172 J-171 34 110 HDPE 140
244 P-199 J-184 J-185 34 110 HDPE 140
611 P-200 J-29 J-32 80 110 HDPE 140
235 P-201 J-54 J-55 31 110 HDPE 140
232 P-202 J-213 J-212 31 110 HDPE 140
465 P-203 J-57 J-58 32 110 HDPE 140
229 P-204 J-10 J-11 30 110 HDPE 140
500 P-205 J-23 J-22 30 110 HDPE 140
412 P-206 J-76 J-77 29 110 HDPE 140
227 P-207 J-26 J-25 28 110 HDPE 140
597 P-208 J-104 J-103 28 110 HDPE 140
224 P-209 J-8 J-9 28 110 HDPE 140
221 P-210 J-215 J-214 28 110 HDPE 140
215 P-211 J-60 J-62 27 110 HDPE 140
562 P-212 J-129 J-128 34 110 HDPE 140
212 P-213 J-160 J-161 27 110 HDPE 140
209 P-214 J-56 J-57 27 110 HDPE 140
492 P-215 J-37 J-38 27 110 HDPE 140
497 P-216 J-138 J-139 25 110 HDPE 140
200 P-217 J-157 J-158 24 110 HDPE 140
192 P-218 J-17 J-18 23 110 HDPE 140
589 P-219 J-87 J-86 23 110 HDPE 140
476 P-220 J-135 J-136 23 110 HDPE 140
187 P-221 J-131 J-132 22 110 HDPE 140
600 P-222 J-70 J-69 21 110 HDPE 140
592 P-223 J-60 J-61 21 110 HDPE 140
178 P-224 J-41 J-42 21 110 HDPE 140
184 P-225 J-123 J-124 21 110 HDPE 140
570 P-226 J-130 J-129 45 110 HDPE 140
175 P-227 J-102 J-103 17 110 HDPE 140
169 P-228 J-39 J-40 17 110 HDPE 140
166 P-229 J-80 J-81 16 110 HDPE 140
595 P-230 J-116 J-115 16 110 HDPE 140
457 P-231 J-35 J-36 15 110 HDPE 140
512 P-232 J-20 J-21 15 110 HDPE 140
159 P-233 J-114 J-115 14 110 HDPE 140
139 P-234 J-29 J-30 13 110 HDPE 140
153 P-235 J-46 J-47 13 110 HDPE 140
584 P-236 J-72 J-73 12 110 HDPE 140
150 P-237 J-24 J-25 12 110 HDPE 140
147 P-238 J-154 J-155 12 110 HDPE 140
575 P-239 J-48 J-47 12 110 HDPE 140
136 P-240 J-71 J-72 9 110 HDPE 140
130 P-241 J-92 J-93 8 110 HDPE 140
127 P-242 J-94 J-95 8 110 HDPE 140
612 P-243 J-32 J-31 0 110 HDPE 140
Flow (Absolute) (m³/day) Velocity (m/s) Headloss Gradient (m/km) Headloss (m) PIPE STATUS ROAD TYPE

1,653.80 0.61 1.89 0.06 EXISTING CC ROAD


890.3 0.67 3.41 0.12 EXISTING BT ROAD
754.1 0.57 2.51 0.03 EXISTING BT ROAD
652 0.49 1.91 0.08 EXISTING BT ROAD
616 0.46 1.72 0.29 EXISTING CC ROAD
580.8 0.44 1.55 0.05 EXISTING CART ROAD
579.9 0.21 0.27 0.01 PROPOSE CC ROAD
532.5 0.4 1.32 0.02 EXISTING CART ROAD
418.8 0.51 2.73 0.44 EXISTING CART ROAD
388.6 0.47 2.38 0.45 PROPOSE BT ROAD
363.1 0.44 2.1 0.08 EXISTING CART ROAD
357.3 0.44 2.03 0.04 EXISTING CC ROAD
349.6 0.43 1.95 0.04 EXISTING CC ROAD
347.8 0.42 1.94 0.41 PROPOSE BT ROAD
328 0.4 1.74 0.06 PROPOSE BT ROAD
316.7 0.39 1.63 0.03 EXISTING CART ROAD
316.7 0.39 1.63 0.03 EXISTING BT ROAD
310.1 0.38 1.57 0.03 EXISTING CART ROAD
301.1 0.37 1.48 0.1 EXISTING CC ROAD
290.8 0.35 1.39 0.01 EXISTING BT ROAD
290.7 0.35 1.39 0.17 PROPOSE BT ROAD
280.2 0.34 1.3 0.01 EXISTING BT ROAD
275.9 0.34 1.26 0.04 EXISTING CART ROAD
271.4 0.33 1.22 0.04 EXISTING CC ROAD
265.3 0.32 1.17 0.01 EXISTING CC ROAD
254.9 0.31 1.09 0.04 EXISTING CART ROAD
237.2 0.29 0.95 0.02 PROPOSE CC ROAD
237 0.29 0.95 0.08 PROPOSE BT ROAD
233.1 0.28 0.92 0.02 PROPOSE CC ROAD
217.2 0.26 0.81 0.02 EXISTING BT ROAD
215.1 0.26 0.8 0.08 EXISTING CC ROAD
212 0.26 0.77 0.03 PROPOSE TILES ROAD
208 0.25 0.75 0.03 EXISTING CART ROAD
205 0.25 0.73 0.02 EXISTING CC ROAD
204.8 0.25 0.73 0.03 PROPOSE TILES ROAD
200.7 0.24 0.7 0.02 PROPOSE BT ROAD
200.6 0.24 0.7 0.15 EXISTING CART ROAD
196.1 0.24 0.67 0.01 EXISTING CC ROAD
192.2 0.23 0.65 0.04 EXISTING CC ROAD
192.2 0.23 0.65 0.01 PROPOSE BT ROAD
192 0.23 0.64 0.03 EXISTING CART ROAD
190.2 0.23 0.63 0.02 EXISTING BT ROAD
187.3 0.23 0.62 0.03 EXISTING CC ROAD
186.5 0.23 0.61 0.01 EXISTING CC ROAD
185.3 0.23 0.6 0.06 PROPOSE BT ROAD
182.5 0.22 0.59 0.06 PROPOSE BT ROAD
180.4 0.22 0.57 0.02 PROPOSE BT ROAD
179.4 0.22 0.57 0.02 PROPOSE BT ROAD
176.7 0.22 0.55 0.02 EXISTING CART ROAD
176.7 0.22 0.55 0.03 EXISTING BT ROAD
176.5 0.21 0.55 0.03 EXISTING BT ROAD
172.4 0.21 0.53 0.02 PROPOSE TILES ROAD
166.9 0.2 0.5 0.02 EXISTING BT ROAD
162.2 0.2 0.47 0.02 PROPOSE BT ROAD
160.3 0.2 0.46 0.05 PROPOSE BT ROAD
159 0.19 0.45 0.02 EXISTING CC ROAD
154.8 0.19 0.43 0.05 EXISTING BT ROAD
153.6 0.19 0.42 0 EXISTING CART ROAD
146.9 0.18 0.39 0.02 PROPOSE TILES ROAD
144 0.18 0.38 0.06 PROPOSE BT ROAD
130.1 0.16 0.31 0.01 EXISTING CC ROAD
122.1 0.15 0.28 0.01 EXISTING CC ROAD
121.6 0.15 0.28 0.03 EXISTING BT ROAD
121.6 0.15 0.28 0.01 EXISTING BT ROAD
120.1 0.15 0.27 0 PROPOSE CC ROAD
115.6 0.14 0.25 0 PROPOSE TILES ROAD
115.4 0.14 0.25 0.02 EXISTING CC ROAD
113.3 0.14 0.24 0.01 EXISTING CC ROAD
110.5 0.13 0.23 0.02 PROPOSE BT ROAD
109.4 0.13 0.23 0.02 PROPOSE BT ROAD
107.2 0.13 0.22 0.01 EXISTING CC ROAD
103.8 0.13 0.21 0 PROPOSE TILES ROAD
98.1 0.12 0.19 0.01 PROPOSE TILES ROAD
91.3 0.11 0.16 0.02 PROPOSE BT ROAD
91 0.11 0.16 0.01 EXISTING CC ROAD
87 0.11 0.15 0.01 PROPOSE TILES ROAD
86.4 0.11 0.15 0.01 PROPOSE BT ROAD
85.8 0.1 0.15 0.01 EXISTING CC ROAD
85.7 0.1 0.14 0.02 EXISTING CC ROAD
80.1 0.1 0.13 0 PROPOSE BT ROAD
78.7 0.1 0.12 0.02 PROPOSE BT ROAD
71.7 0.09 0.1 0.01 EXISTING CC ROAD
71.5 0.09 0.1 0 PROPOSE BT ROAD
71.3 0.09 0.1 0.02 PROPOSE BT ROAD
69.4 0.08 0.1 0.01 EXISTING BT ROAD
68.2 0.08 0.09 0.01 EXISTING CC ROAD
67.9 0.08 0.09 0.01 PROPOSE CART ROAD
67.6 0.08 0.09 0.01 PROPOSE BT ROAD
65.8 0.08 0.09 0 PROPOSE TILES ROAD
65.4 0.08 0.09 0.01 EXISTING CC ROAD
64.1 0.08 0.08 0 EXISTING BT ROAD
56.4 0.07 0.07 0 PROPOSE CART ROAD
56.3 0.07 0.07 0.01 EXISTING CC ROAD
56.2 0.07 0.07 0.01 PROPOSE BT ROAD
55.2 0.07 0.06 0 EXISTING CC ROAD
54.4 0.07 0.06 0.01 EXISTING CC ROAD
54.3 0.07 0.06 0 EXISTING CC ROAD
53.1 0.06 0.06 0 PROPOSE BT ROAD
52.8 0.06 0.06 0 PROPOSE CC ROAD
50.7 0.06 0.05 0 EXISTING BT ROAD
50.4 0.06 0.05 0.01 EXISTING CC ROAD
50.3 0.06 0.05 0.03 PROPOSE BT ROAD
49.5 0.06 0.05 0 PROPOSE CC ROAD
47.6 0.06 0.05 0 PROPOSE CC ROAD
46.8 0.06 0.05 0 PROPOSE CC ROAD
46.3 0.06 0.05 0 EXISTING CC ROAD
45.9 0.06 0.05 0 PROPOSE CC ROAD
44.2 0.05 0.04 0 EXISTING CC ROAD
43.2 0.05 0.04 0 EXISTING CART ROAD
41.3 0.05 0.04 0 EXISTING BT ROAD
41.1 0.05 0.04 0 PROPOSE BT ROAD
41 0.05 0.04 0 EXISTING CART ROAD
40.9 0.05 0.04 0 PROPOSE CC ROAD
40.7 0.05 0.04 0 EXISTING CC ROAD
40.2 0.05 0.04 0 PROPOSE CART ROAD
37.9 0.05 0.03 0 EXISTING BT ROAD
37.5 0.05 0.03 0 PROPOSE BT ROAD
34.8 0.04 0.03 0 PROPOSE BT ROAD
34.6 0.04 0.03 0 EXISTING CART ROAD
33.6 0.04 0.03 0 EXISTING CC ROAD
32.9 0.04 0.02 0 EXISTING CC ROAD
31.1 0.04 0.02 0 EXISTING CC ROAD
30 0.04 0.02 0 PROPOSE BT ROAD
29.8 0.04 0.02 0 EXISTING CC ROAD
27.8 0.03 0.02 0 PROPOSE BT ROAD
26.9 0.03 0.02 0 PROPOSE BT ROAD
26.8 0.03 0.02 0 EXISTING CC ROAD
26.6 0.03 0.02 0 EXISTING CC ROAD
25.3 0.03 0.02 0 PROPOSE BT ROAD
25.2 0.03 0.02 0 EXISTING CART ROAD
24.4 0.03 0.01 0 PROPOSE CART ROAD
23.7 0.03 0.01 0 EXISTING CART ROAD
22.5 0.03 0.01 0 PROPOSE BT ROAD
22.4 0.03 0.01 0 PROPOSE BT ROAD
21.7 0.03 0.01 0 EXISTING CC ROAD
21.6 0.03 0.01 0 PROPOSE BT ROAD
21.2 0.03 0.01 0 EXISTING CC ROAD
19.9 0.02 0.01 0 PROPOSE BT ROAD
18.1 0.02 0.01 0 PROPOSE CC ROAD
17.9 0.02 0.01 0 EXISTING CC ROAD
17.2 0.02 0.01 0 PROPOSE BT ROAD
16.7 0.02 0.01 0 EXISTING CC ROAD
16.3 0.02 0.01 0 PROPOSE BT ROAD
15.9 0.02 0.01 0 PROPOSE BT ROAD
15.8 0.02 0.01 0 PROPOSE BT ROAD
15.2 0.02 0.01 0 EXISTING CART ROAD
14.3 0.02 0.01 0 PROPOSE CART ROAD
14 0.02 0.01 0 PROPOSE BT ROAD
13.9 0.02 0.01 0 EXISTING CC ROAD
12.6 0.02 0 0 EXISTING BT ROAD
12.6 0.02 0 0 PROPOSE BT ROAD
12.4 0.02 0 0 EXISTING CC ROAD
12 0.01 0 0 PROPOSE TILES ROAD
11.6 0.01 0 0 PROPOSE TILES ROAD
11.5 0.01 0 0 EXISTING CART ROAD
11.4 0.01 0 0 PROPOSE TILES ROAD
11.3 0.01 0 0 EXISTING CC ROAD
11.3 0.01 0 0 EXISTING CC ROAD
10.4 0.01 0 0 PROPOSE BT ROAD
9.9 0.01 0 0 EXISTING BT ROAD
9.8 0.01 0 0 PROPOSE BT ROAD
9.7 0.01 0 0 EXISTING CART ROAD
9.7 0.01 0 0 PROPOSE CC ROAD
9 0.01 0 0 EXISTING CC ROAD
8.8 0.01 0 0 EXISTING BT ROAD
8.8 0.01 0 0 EXISTING CART ROAD
8.8 0.01 0 0 PROPOSE CART ROAD
8.8 0.01 0 0 EXISTING CART ROAD
8.8 0.01 0 0 PROPOSE BT ROAD
8.7 0.01 0 0 EXISTING CART ROAD
8.6 0.01 0 0 PROPOSE BT ROAD
8.5 0.01 0 0 PROPOSE BT ROAD
8.5 0.01 0 0 EXISTING CC ROAD
8.1 0.01 0 0 PROPOSE BT ROAD
7.9 0.01 0 0 PROPOSE CART ROAD
7.9 0.01 0 0 PROPOSE CART ROAD
7.6 0.01 0 0 PROPOSE BT ROAD
7.4 0.01 0 0 EXISTING CART ROAD
7.4 0.01 0 0 PROPOSE CART ROAD
7.4 0.01 0 0 PROPOSE CART ROAD
6.7 0.01 0 0 PROPOSE CART ROAD
6.5 0.01 0 0 PROPOSE BT ROAD
6.1 0.01 0 0 EXISTING CART ROAD
5.9 0.01 0 0 PROPOSE CART ROAD
5.3 0.01 0 0 PROPOSE CART ROAD
4.7 0.01 0 0 PROPOSE BT ROAD
4.5 0.01 0 0 PROPOSE BT ROAD
4.5 0.01 0 0 EXISTING CART ROAD
4.4 0.01 0 0 EXISTING CART ROAD
4.4 0.01 0 0 PROPOSE TILES ROAD
4.4 0.01 0 0 PROPOSE BT ROAD
4.2 0.01 0 0 EXISTING BT ROAD
4.2 0.01 0 0 PROPOSE TILES ROAD
4.2 0.01 0 0 PROPOSE TILES ROAD
4.1 0 0 0 PROPOSE BT ROAD
4.1 0 0 0 PROPOSE TILES ROAD
4 0 0 0 PROPOSE CC ROAD
3 0 0 0 PROPOSE TILES ROAD
3 0 0 0 PROPOSE TILES ROAD
2.8 0 0 0 EXISTING CC ROAD
2.7 0 0 0 PROPOSE TILES ROAD
2.7 0 0 0 PROPOSE TILES ROAD
2.6 0 0 0 PROPOSE BT ROAD
2.6 0 0 0 PROPOSE TILES ROAD
2.6 0 0 0 PROPOSE BT ROAD
2.5 0 0 0 PROPOSE BT ROAD
2.5 0 0 0 PROPOSE TILES ROAD
2.5 0 0 0 PROPOSE TILES ROAD
2.5 0 0 0 PROPOSE TILES ROAD
2.4 0 0 0 PROPOSE TILES ROAD
2.4 0 0 0 PROPOSE TILES ROAD
2.4 0 0 0 EXISTING CART ROAD
2.3 0 0 0 PROPOSE CC ROAD
2.3 0 0 0 PROPOSE CC ROAD
2.3 0 0 0 EXISTING BT ROAD
2.1 0 0 0 EXISTING BT ROAD
2.1 0 0 0 PROPOSE CC ROAD
2 0 0 0 PROPOSE CC ROAD
2 0 0 0 PROPOSE CC ROAD
2 0 0 0 EXISTING BT ROAD
1.9 0 0 0 PROPOSE CC ROAD
1.8 0 0 0 PROPOSE TILES ROAD
1.8 0 0 0 PROPOSE CC ROAD
1.8 0 0 0 PROPOSE CC ROAD
1.8 0 0 0 PROPOSE CC ROAD
1.7 0 0 0 EXISTING CART ROAD
1.5 0 0 0 PROPOSE CC ROAD
1.4 0 0 0 PROPOSE CC ROAD
1.4 0 0 0 PROPOSE CC ROAD
1.4 0 0 0 PROPOSE CART ROAD
1.3 0 0 0 EXISTING CC ROAD
1.3 0 0 0 EXISTING BT ROAD
1.2 0 0 0 PROPOSE CC ROAD
1.1 0 0 0 PROPOSE CC ROAD
1.1 0 0 0 PROPOSE CC ROAD
1.1 0 0 0 PROPOSE BT ROAD
1 0 0 0 PROPOSE CC ROAD
1 0 0 0 PROPOSE CC ROAD
1 0 0 0 PROPOSE BT ROAD
0.8 0 0 0 PROPOSE CC ROAD
0.7 0 0 0 PROPOSE CC ROAD
0.7 0 0 0 PROPOSE CC ROAD
0.1 0 0 0 EXISTING CC ROAD
ID Label Elevation (m) Demand (m³/day) Hydraulic Grade (m) Pressure (m H2O)

183 J-1 290.52 14.9 311.27 20.72


393 J-2 289.59 5.8 311.21 21.58
396 J-3 290.02 11.3 311.21 21.14
328 J-4 289.48 10 311.21 21.68
108 J-5 286.45 21.7 311.19 24.69
100 J-6 281.47 9.4 311.17 29.65
348 J-7 281.78 16.8 311.14 29.3
225 J-8 281.87 2.5 311.14 29.21
226 J-9 281.47 8.5 311.14 29.61
230 J-10 281.77 2.6 311.14 29.31
231 J-11 281.22 8.8 311.14 29.86
349 J-12 281.37 4.5 311.14 29.71
111 J-13 286.45 10.1 311.13 24.63
391 J-14 287.93 4.4 311.11 23.14
514 J-15 281.96 14.4 311.11 29.1
505 J-16 281.97 6.8 311.1 29.07
193 J-17 280.94 2 311.1 30.1
194 J-18 281.41 5.7 311.1 29.63
507 J-19 281.91 5.1 311.1 29.13
509 J-20 281.85 3 311.1 29.19
511 J-21 281.61 1.3 311.1 29.43
316 J-22 281.57 2.6 311.1 29.47
498 J-23 281.73 7.6 311.1 29.31
151 J-24 281.53 1 311.1 29.51
152 J-25 281.46 5.4 311.1 29.57
228 J-26 281.42 2.5 311.1 29.62
502 J-27 281.85 6.4 311.1 29.19
401 J-28 288.78 13 311.1 22.27
140 J-29 290.72 12.7 311.09 20.33
141 J-30 291.18 1.1 311.09 19.87
105 J-31 287.96 11.2 311.09 23.09
106 J-32 287.98 7 311.09 23.07
315 J-33 282.06 6.5 311.09 28.98
484 J-34 282.07 14.9 311.08 28.95
454 J-35 282.87 19 311.06 28.14
456 J-36 282.73 1.3 311.06 28.27
304 J-37 281.71 7.4 311.06 29.29
491 J-38 281.29 2.3 311.06 29.72
170 J-39 288.23 1.4 311.06 22.78
171 J-40 287.62 4.7 311.06 23.39
179 J-41 281.01 1.8 311.06 29.98
180 J-42 281.34 13.2 311.06 29.65
307 J-43 283.62 23 311.06 27.38
447 J-44 284.6 12.4 311.06 26.4
449 J-45 283.5 14.6 311.05 27.5
154 J-46 282.23 1.1 311.05 28.77
155 J-47 283.3 4.4 311.05 27.69
306 J-48 282.34 1 311.05 28.66
452 J-49 282.54 9 311.05 28.46
468 J-50 281.22 15.4 311.05 29.77
271 J-51 281.2 16.6 311.05 29.79
270 J-52 281.04 4.2 311.05 29.95
274 J-53 287.41 8.2 311.05 23.6
236 J-54 281.08 9.1 311.05 29.9
237 J-55 280.98 2.7 311.05 30.01
210 J-56 281.2 2.3 311.05 29.79
211 J-57 280.91 4.2 311.05 30.08
240 J-58 285.3 2.6 311.05 25.7
204 J-59 280.97 3 311.05 30.02
216 J-60 280.93 5.5 311.05 30.05
205 J-61 281.15 1.8 311.05 29.84
217 J-62 280.23 2.4 311.05 30.76
518 J-63 281.28 15 311.05 29.71
480 J-64 282.17 9.4 311.04 28.82
303 J-65 282.33 4.1 311.04 28.65
354 J-66 280.48 22 311.04 30.5
472 J-67 280.98 9.9 311.04 30
344 J-68 280.57 18.9 311.04 30.41
264 J-69 290.78 1.8 311.04 20.22
273 J-70 289.35 9.2 311.04 21.65
137 J-71 280.57 0.8 311.04 30.41
138 J-72 280.49 8 311.04 30.49
355 J-73 280.72 1.1 311.04 30.26
345 J-74 280.65 8.8 311.04 30.33
263 J-75 287.65 11 311.04 23.33
242 J-76 286.23 20.4 311.03 24.75
243 J-77 286.57 2.5 311.03 24.41
407 J-78 286.47 9.2 311.03 24.51
477 J-79 281.92 12.2 311.03 29.05
167 J-80 286.88 1.4 311.02 24.09
168 J-81 286.11 7.4 311.02 24.86
318 J-82 285.73 17.2 311 25.22
319 J-83 285 8.8 310.99 25.94
253 J-84 285.99 8.6 310.99 24.95
146 J-85 286.97 3 310.99 23.97
145 J-86 287.47 3.9 310.98 23.47
196 J-87 287.28 2 310.98 23.66
197 J-88 287.01 2.9 310.98 23.93
324 J-89 282.95 25.7 310.98 27.97
325 J-90 281.6 7.4 310.98 29.33
254 J-91 286.58 4.5 310.98 24.35
131 J-92 287.18 0.7 310.98 23.75
132 J-93 287.12 4.6 310.98 23.81
128 J-94 285.79 0.7 310.98 25.14
129 J-95 285.62 4.6 310.98 25.31
297 J-96 284.48 11.1 310.98 26.44
298 J-97 283.45 7 310.98 27.47
522 J-98 280.64 12.6 310.97 30.27
525 J-99 280.06 6.1 310.97 30.85
419 J-100 283.84 14.8 310.97 27.07
114 J-101 282.92 10.9 310.97 28
176 J-102 283.09 1.5 310.97 27.82
177 J-103 282.39 7.4 310.97 28.52
280 J-104 281.34 2.5 310.97 29.57
417 J-105 280.63 20.4 310.96 30.27
219 J-106 280.79 20 310.96 30.11
220 J-107 281.27 4.1 310.96 29.63
428 J-108 281.4 13 310.96 29.5
174 J-109 281.44 6.5 310.96 29.46
276 J-110 282.31 15.2 310.96 28.59
443 J-111 283.88 27 310.95 27.02
430 J-112 282.92 17.9 310.95 27.98
289 J-113 281.67 18.6 310.95 29.22
160 J-114 281.59 1.2 310.95 29.31
161 J-115 281.63 6.3 310.95 29.26
288 J-116 281.65 1.4 310.95 29.24
310 J-117 282.77 13.3 310.95 28.13
118 J-118 282.89 5.6 310.95 28
309 J-119 282.01 16.5 310.95 28.88
91 J-120 284.56 21.6 310.95 26.34
31 J-121 283.52 14.2 310.95 27.37
352 J-122 283.3 9.7 310.95 27.59
185 J-123 282.3 1.8 310.95 28.59
186 J-124 282.17 4.6 310.95 28.72
351 J-125 282.82 16.1 310.95 28.07
563 J-126 283.19 12.3 310.95 27.7
566 J-127 283.4 6.4 310.95 27.49
440 J-128 282.64 11.1 310.95 28.25
558 J-129 282.27 10.1 310.95 28.62
568 J-130 283.03 7.1 310.95 27.86
188 J-131 282.19 1.9 310.95 28.7
189 J-132 282.3 10.4 310.95 28.59
438 J-133 281.75 15.4 310.95 29.14
436 J-134 281.61 16.7 310.95 29.28
371 J-135 281.39 14.3 310.95 29.49
475 J-136 281.96 2 310.95 28.93
94 J-137 280.43 17.3 310.95 30.45
493 J-138 280.98 15.1 310.94 29.91
496 J-139 281 2.1 310.94 29.88
372 J-140 280.79 4.4 310.94 30.1
95 J-141 278.65 26.3 310.66 31.94
527 J-142 280.23 8.8 310.66 30.36
384 J-143 279.86 30.2 310.61 30.69
529 J-144 278.98 9.8 310.6 31.56
539 J-145 278.95 11.6 310.57 31.56
531 J-146 280.14 4.4 310.57 30.37
535 J-147 279.25 10.8 310.55 31.23
537 J-148 280.52 4.5 310.55 29.97
533 J-149 279.38 7.4 310.53 31.09
546 J-150 279.51 21.7 310.51 30.93
544 J-151 279.57 9 310.47 30.84
268 J-152 279.96 13.6 310.47 30.45
267 J-153 280.46 4.2 310.47 29.95
148 J-154 280.32 1 310.47 30.09
149 J-155 280.54 6.4 310.47 29.87
550 J-156 279.61 11.4 310.43 30.76
201 J-157 280.13 2.1 310.43 30.24
202 J-158 280.01 7.6 310.43 30.36
199 J-159 279.67 9 310.39 30.66
213 J-160 279.91 2.3 310.39 30.42
214 J-161 279.75 6.3 310.39 30.58
157 J-162 279.77 4.1 310.37 30.54
380 J-163 278.36 21.2 310.36 31.93
158 J-164 279.82 13.2 310.35 30.46
333 J-165 280.01 7.9 310.35 30.28
292 J-166 278.43 11.9 310.34 31.85
291 J-167 278.52 5.3 310.34 31.76
365 J-168 278.28 19.6 310.32 31.97
251 J-169 279.92 7.2 310.32 30.33
285 J-170 277.16 16 310.31 33.08
249 J-171 277.21 8.2 310.31 33.04
248 J-172 277.07 3 310.31 33.17
366 J-173 277.07 4.7 310.31 33.17
286 J-174 277.91 60.5 310.31 32.33
259 J-175 280.23 19.8 310.29 29.99
368 J-176 286.57 12.6 310.29 23.67
381 J-177 286.57 50.3 310.28 23.66
260 J-178 280.56 12.1 310.27 29.65
123 J-179 281.09 13.4 310.22 29.07
207 J-180 281.12 16.4 310.2 29.02
360 J-181 286.57 10.4 310.2 23.58
208 J-182 281.11 9.6 310.19 29.03
339 J-183 281.03 19.2 310.17 29.08
245 J-184 278.56 3 310.16 31.54
246 J-185 278.43 37.8 310.16 31.67
363 J-186 280.58 23.7 310.15 29.52
191 J-187 279 14.8 310.14 31.07
165 J-188 278.68 3.3 310.14 31.39
134 J-189 284.34 2 310.14 25.74
135 J-190 284.34 1.6 310.13 25.74
143 J-191 287.89 5.7 310.13 22.2
283 J-192 281.34 14.9 310.13 28.73
256 J-193 285.67 13.3 310.13 24.41
257 J-194 280.11 7.6 310.13 29.97
278 J-195 281.34 4.4 310.13 28.73
375 J-196 278.34 43 309.75 31.35
374 J-197 278.93 14 309.75 30.76
378 J-198 277.83 36.9 309.58 31.69
341 J-199 279.94 27.9 309.56 29.56
342 J-200 278.62 8.6 309.56 30.88
331 J-201 279.78 18.4 309.56 29.72
330 J-202 278.57 7.9 309.56 30.93
377 J-203 286.57 8.5 309.56 22.94
337 J-204 279.06 30.5 309.52 30.4
336 J-205 277.54 8.1 309.52 31.91
322 J-206 278.79 27.1 309.46 30.61
321 J-207 277.53 7.4 309.46 31.86
313 J-208 278.07 24 309.44 31.32
312 J-209 277.25 6.7 309.44 32.13
301 J-210 276.95 19.7 309.43 32.41
300 J-211 276.67 5.9 309.43 32.69
234 J-212 276.62 9.3 309.43 32.74
233 J-213 275.26 2.7 309.43 34.1
223 J-214 276.02 22.4 309.43 33.34
222 J-215 275.61 2.4 309.43 33.75
383 J-216 286.57 16.3 309.42 22.81
ID Label Is Operable? Diameter (Valve) (mm) Elevation (m) Referenced Pipe Flow (m³/day)
671 ISO-1 0 110 304.56 P-10 388.6
Hydraulic Grade (m) Pressure (m H2O) Velocity (m/s)
310.51 5.94 0.47

You might also like