A detailed breakdown of all works within the total cost of 2,000,000/- are

also required for pre / post audits and approval by NHA officials/ account
branch.

Since I have carried out a number of such assignments through UETs.


Therefore I am sending you a tentative breakdown of works. But it is not
final you may increase or decrease to further improve it.

Dr. Muhammad Iqbal

Structural Expert, NHA

STRUCTURAL ASSESSMENT PROPOSAL FOR BAGAR NULLA BRIDGE

Unit price
Stages Description of activities No. Total
(Rs.)

1 Detailed assessment of damages

Extraction of cores from


a.   Girders 16
b.   Transoms 4
2 c.   Pier columns 6
d.   Deck slab 6
e.   And filling of core holes by
non shrink cementatious grout 32 2000/- 64,000/-
(Chemrite NS or its equivalent)

Scaffolding of span 1
Scaffolding of span 2
3 4 100,000/- 400,000/-
Scaffolding of span 3
Scaffolding of span 4

4 Tests.
a.    Testing of cores from
damaged and undamaged spans 32
for comparison.
b.   Testing of steel reinforcement
specimens from damaged and 3
undamaged spans.

Structural analysis of the bridge i.e.


5 actual strength after testing of cores
and Live Load Tests.

Actual live load testing measuring


deflections and strains in  all damaged One
6 and undamaged girders using strain
gauges, deflection transducers, data job
recorders and four fully loaded trucks.

Design/drawings of CFRP
7 (fabric/strips) required with its
Engineer’s Estimate

Final Structural report to improve the


8
lost strength

The above table of scope of works is provided for sample purpose. The
University itself may forward a proposal in a similar format. The submitted
rates should be inclusive of all taxes. The total payment will be based on
actual work activities performed at the site.