Project Name:- Construction of New Two-Lane Bridge (Parallel to existing Naranarayan Setu) with its approaches from Km 0+000

to Km 4+385 across River Brahmaputra on NH-


17 at Jogighopa in the State of Assam on EPC mode.
RFI SUMMARY
Client : National Highways & Infrastructure Development Corporation Limited (NHIDCL), PMU-Bongaigaon, Assam
Authority's Engineer : M/s Chaitanya Projects Consultancy Pvt Ltd. In association with M/s Shree Bhawani Consultancy Services Pvt. Ltd.
EPC Contractor : M/s S. P. Singla Constructions Pvt. Ltd.
Date of Submission: 21-07-2022
Date of Inspection: 22-07-2022
SL. Chainage Activity Inspection Inspection
RFI No. Activity Description
No. Location/ Side Time Result/Remarks
From To
(A) STRUCTURE
Viaduct - South Checking of Cable ducts grouting work of Span P2 - P3 Cable No. 1, 2, 3 & 4 (I-
1 STR/JOGIGHOPA/439 2.+464.6 2+499.6 10:00 AM
Bank Girder G2)
Viaduct - South Checking of Cable ducts grouting work of Span P2 - P3 Cable No. 1, 2, 3 & 4
2 STR/JOGIGHOPA/440 2.+464.6 2+499.6 12:30 PM
Bank (I-Girder G4)
Viaduct - South Checking of Cable ducts grouting work of Span P3 - P4 Cable No. 1, 2, 3 & 4
3 STR/JOGIGHOPA/441 2+499.6 2+534.6 3:30 PM
Bank (I-Girder G1)
Viaduct - South
4 STR/JOGIGHOPA/442 2+639.6 4:00 PM Checking of Reinforcement Cage of P7/2 Working Pile
Bank
(B ) SURVEY
NIL

(C ) LAB
1 LAB/JOGIGHOPA/253 2+569.6 Site Lab 10:00 AM Checking of 7th days concrete Cube compressive strength of Pile P5/3 M-45

Checking of 28th days concrete Cube compressive strength of PSC I-Girder (G2) Span P2-
2 LAB/JOGIGHOPA/254 2+464.6 to 2+499.6 Site Lab 11:00 AM
P3 M-50
(D)HIGHWAY
NIL
No of RFI's 6
Approved
Not-Approved
Not Ready
Requested By Planning Department
Note:
1) Sur- Survey, Str- Structure, Hig- Highway, Lab- Laboratory,

Page 1 of 1