Professional Documents
Culture Documents
Target
No Item Action Party
Date
Group 2
Topic : How to improve for managing sub contractor
Way Forward:
- From annual change to conduct random site
audit
- From 1 department evaluation to multiple
department evaluation
- Create more competition within sub contractor
- Logistic : Constant monitoring, install
GPS/tracking system, early call out
- Reward /incentives
Group 3
Topic : How to improve effectiveness to control the risk
Way Forward:
- Preventive Maintenance System/PMS
- SMART action item
- Periodic review to confirm the implementation-
include 3rd party visit/audit
- Accountable of assign person
- Sharing the lesson learnt via LPT
- Refresh training
- MOC
- Risk verification-continue monitoring
- Management visibility & follow up
- Recognition
Minutes Of Meeting
- Risk registered maintained and up to date
- Hazard hunt
7.0 AOB
7.1 Mr. Alfian encouraged to Contractor’s top management
for participating in Management HSE Visit (MHSEV) to Contractor End Nov
rig. However they should obtain Offshore Safety 2014
Passport (OSP).