PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 1 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
SUMMARY OF REVISION
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 2 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
Table of Contents
2. Reference documents
3. Responsibilities
4. Safety Requirement
6. Attachments
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 3 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
2. References Documents:
Aramco CSM
Aramco GI
4. Responsibilities:
Project Manager
construction activity as per project specification in compliance with Quality, Schedule and
HSE requirement.
Construction Manager
The construction manager it is the responsibility of that construction activities are executed
according to the relevant project specification, in compliance with Quality, Schedule and HSE requirement.
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 4 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
HSE Officer
The Safety Officer has monitor the implementation and adherence to this procedure and
corrective action.
Piping Supervisor
The piping supervisor it is responsibility of that all work is carried out to the required quality
and safety. The existing pipe cutting marking shall be checked as per the latest IFC drawings
5. Safety Requirements:
All work force shall be completed their safety induction and relevant trainings before
100% PPE shall be implemented (Hard hat, coverall, safety shoes and safety glasses,
Respirators).
Use safety harness with 100% tie-off on the work at height areas.
A Tool Box Talk (TBT) shall be carried out by the Supervisor at the work site.
A copy of job Safety Analysis (JSA) should be kept on job for reference.
Maintain the necessary standards of cleanliness and tidiness within the workplace.
Barricades shall be erected to keep unauthorized personnel away at the proper distance
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 5 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
All tools shall be inspected and monthly color coded to be used at work place.
Site Safety representative shall be present at the job site at all times while personnel are
working.
Safety Officers shall be assigned to monitor safety condition of the work area, and are
authorized to stop any activities if the conditions at the site changed such that to continue
The tool most often used for cutting metal is the hacksaw. A hacksaw is a saw with a frame
and a blade designed for cutting metal. It is designed so new blades can be installed easily.
Hand hacksaw blades are made in 8-inch, 10-inch, and 12-inch lengths, with 14, 18, 24, or
Pipe shall be lifted up to enough height and provide proper support under the pipe for easy
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 6 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
Select a blade with enough teeth per inch so two or three teeth are in contact with the metal
at all times.
There must be few enough teeth to the inch to allow the gullets to carry off the chips without
clogging.
Fasten the blade into the hacksaw frame with the teeth pointing away from the handle of the
saw. Make sure the blade is fastened securely so it will not twist and break.
Secure properly the pipe in the executing area, so it’s makes the sawing easier because the
piece is held firmly and does not spring back and forth.
Place the saw on the mark. Then pull it toward you using a little pressure to start the kerfs.
To help get the saw started in the proper place, a notch can be cut at the mark with a file.
Apply slight pressure on the forward strokes of the hacksaw, and release the pressure on
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 7 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
the return strokes to insure proper cutting and to lessen the danger of breaking the blade.
Run the saw evenly, using long strokes, with all the teeth cutting to prevent wear on a small
Apply continuously the coolant or water while cutting in progress up to fully cutting of pipe.
Provide tray or blanket under the cutting area to catch all scrap metal to prevent from the
The pneumatic hacksaw is an air drive. It is designed with pipe clamping system for 90 deg
cut, Hacksaw blade with guide and air connecting coupling. Hacksaw blades are made in 8
inch to 37 inch lengths, with 14, 18, 24, or 32 teeth per inch.
Pipe shall be lifted up to enough height and provide proper support under the pipe for easy
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 8 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
Wear safety glasses and working hand gloves during operate the machine.
Select a blade with enough teeth per inch so two or three teeth are in contact with the metal
at all times.
There must be few enough teeth to the inch to allow the gullets to carry off the chips without
clogging.
Fasten the blade into the Pneumatic hacksaw frame with the teeth pointing away from the
guide of the saw. Make sure the blade is fastened securely so it will not twist and break.
Mark on the pipe at the point, which pipe you are desired to cut.
Secure properly the pipe in the executing area, so it’s makes the sawing easier because the
piece is held firmly and does not spring back and forth.
Connect the hose pipe in between the machine and air line with safety latches.
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 9 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
Slowly open air line valve for supply the air to machine.
Place the saw on the mark. Hold the air controlling throttle to control the cutting speed of the
machine. In the starting of cutting open the air slowly and then increase up to required speed
for cutting.
Then using a little pressure to start the kerfs. To help get the saw started in the proper place,
a notch can be cut at the mark with a file. Use power to more press the hacksaw towards
pipe and gradually increase the power continuously up to fully cutting of the pipe.
Apply continuously the coolant or water while cutting in progress up to fully cutting of pipe.
Provide tray or blanket under the cutting area to catch all scrap metal to prevent from the
Split frame cold cutter is air driven and capable of both cutting and beveling all grades of
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 10 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
Pipe shall be lifted up to enough height and provide proper support under the pipe for easy
The split frame shall be required minimum sitting area from the fittings and weld joints, which
If required, additional support shall be provided nearer to beveling machine in pipe for
Wear safety glasses and working hand gloves during operate the machine.
Select the cutting tool and beveling tool with enough length as per the manufacturer manual.
The cutting tool shall be fixed 1mm deeper than the bevel tool. So cutting and beveling can
be done smoothly.
Mark on the pipe at the point, which pipe you are desired to cut.
Secure properly the pipe in the executing area, so it’s hold the machine easier because the
The machine shall be fixed with pipe which can be holding after cutting of the pipe piece.
Connect the hose pipe in between the machine and air line with safety latches.
Slowly open air line valve for supply the air to machine.
a) Tighten the tool tightening knob up to beveling tool touch with the pipe profile.
b) Hold the air controlling throttle to control the cutting speed of the machine.
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 11 of 12
PROJECT NAME: REPLACE HIC AFFECTED VESSELS - NORTH GAWAR FACILITIES CUSTOMER: SAUDI ARAMCO
PROJECT LOCATION: NORTH GAWAR FACILITIES - SAUDI ARABIA BI-10-10215 CONTRACT NO: 6600048365
c) In the starting, supply the air slowly and then increase up to required speed for cutting and
care to be taken that more loads should not come on the machine and blades.
d) The tool feed will be automatic for every 360 degree of machine rotation up to fully cutting of
the pipe.
e) Apply continuously the coolant while cutting in progress and up to fully cutting of pipe.
f) Provide tray under the cutting area to catch all scrap metal to prevent from the spreading of
7. Attachments:
______________________________________________________________________________________________________________________________________
Disclaimer: This document has been prepared by National Contracting Company Ltd (NCC) for Saudi Aramco Company and contains proprietary information and may only be released to third parties with prior
approval.
Page 12 of 12