𝑳𝒔 = 𝟐 𝒄𝒖𝒔𝒕𝒐𝒎𝒆𝒓𝒔
𝟒
𝑳𝒒 = 𝒐𝒓 𝟏. 𝟑𝟑 𝒐𝒓 𝟏 𝒄𝒖𝒔𝒕𝒐𝒎𝒆𝒓𝒔
𝟑
𝑾𝒔 = 𝟎. 𝟏 𝒐𝒓 𝟔 𝒎𝒊𝒏𝒖𝒕𝒆𝒔
𝟏
𝑾𝒒 = 𝒐𝒓 𝟒 𝒎𝒊𝒏𝒖𝒕𝒆𝒔
𝟏𝟓
ℷ 20
𝑃𝑤 = =
𝜇 30
𝑷𝒘 = 𝟔𝟔. 𝟔𝟕 %
II. Multi-channel/Single-Phase System
A bank has three (3) loan officers on duty, each of whom can serve four (4) customers
per hour. Every hour, ten (10) loan applicants arrive at the loan department and join a
common queue. What are the system’s operating characteristics?
1. The probability of zero (0) customer in the system (P0)
Answer:
𝟏
𝑷𝟎 = 𝒇𝒐𝒓 𝑴𝝁 > 𝝀
𝑴−𝟏 𝟏 𝝀
𝒏 𝟏 𝝀 𝑴 𝑴𝝁
[∑𝒏−𝟎 𝒏! (𝝁) ] + 𝑴! ∙ (𝝁) ∙
𝑴𝝁 − 𝝀
λ = 10
µ=4
M=3
𝟏
𝑷𝟎 = 𝟏
𝟎 1 𝟏𝟎 𝟏 𝟏𝟎 𝟐 𝟏 𝟏𝟎 𝟑 𝟑(𝟒)
[∑𝟑−𝟏
𝒏−𝟎
𝟏
(𝟏𝟎 ) + ( ) ] + ∙ ( ) ] + [ ( ) ][ ]
𝟎!! 𝟒 1! 𝟒 𝟐! 𝟒 𝟑! 𝟒 𝟑(𝟒) − 𝟏𝟎
𝟏 𝟏 𝟏
𝑷𝟎 = = =
𝟏𝟎 𝟐𝟓 𝟏𝟐𝟓 𝟏𝟐 𝟓𝟑 𝟏𝟐𝟓 𝟐𝟐. 𝟐𝟓
𝟏 + 𝟒 + 𝟖 + 𝟒𝟖 [ 𝟐 ] 𝟒𝟖 + 𝟖
𝑷𝟎 = 𝟎. 𝟎𝟒𝟒𝟗 𝒐𝒓 𝟒. 𝟒𝟗%
𝟏𝟎 (𝟒)(𝟏𝟎⁄𝟒)𝟑 10 𝟔𝟐𝟓 10
= 𝟐
(𝟎. 𝟎𝟒𝟒𝟗) + = (0.0449) +
(𝟑 − 𝟏)! (𝟑(𝟒) − 𝟏𝟎) 4 (𝟐)(𝟒) 4
𝟔𝟐𝟓 10 10
= (𝟎. 𝟎𝟒𝟒𝟗) + = 3.51 +
𝟖 4 4
𝑳𝒔 = 𝟔. 𝟎𝟏 𝒐𝒓 𝟔 𝒄𝒖𝒔𝒕𝒐𝒎𝒆𝒓𝒔
𝑳𝒒 = 𝟑. 𝟓𝟏 𝒐𝒓 𝟒 𝒄𝒖𝒔𝒕𝒐𝒎𝒆𝒓𝒔
4. Average waiting time of each customer in the system (Ws)
Answer:
𝑳𝒔 6.01
𝑾𝒔 = =
𝝀 10
6. The probability that all the system servers are currently busy (Pw)
Answer:
Pw = 1 − 𝐏𝟎
= 1 − 𝟎. 𝟎𝟒𝟒𝟗