Task being assessed Replacing 33KV OHL wooden Poles by Concrete Poles
New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
1- Working at hight 1- Worker-15 1- Fall down from 1- Valid PTW. 1- Bucket Truck Operation & 28.09.2022
2- Forman-3 height due to 2- Valid equipments inspection before Maintenance Team
3- Engineers -2 collapse of bucket test Certificates . working start. Lead Fahud
Truck. 3- Safety harness,. 2- Safety harness
2-Fall down from 4- PPE as per job 3 6 18 inspection prior to 2 5 10
height due to loss of requirements start..
stability. ( Helmets , Gloves). 3- Training and
awareness
(working at high).
2- Lifting equipment 1- Worker-15 1- Cranes falling 1- Valid PTW. 1- Crane inspection HSE Inspector 30.09.2022
2- Forman-3 over due to strong 2- Valid equipments prior to start.
3- Engineers -2 wind, unsafe loads, test Certificate. 2- Sling check prior
2- Falling of load 3- Sling test to start.
due to sling cut off . Certificate. 5 3- Following lifting 3
3 15 2 6
procedure.
4- Training and
awareness ( lifting )
Risk assessment form
New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
3- Electrocution 1- Worker-15 1- Electric Shock 1- Valid PTW. 1- Following Operation & 30.09.2022
2- Forman-3 2- Using Of 2- Valid equipments ESR/ESOP rules. Maintenance Team
3- Engineers -2 Unauthorized test Certificates . 2- Test equipments Lead Fahud
Electrical test 4- PPE as per job checking before
equipments. requirements 4 testings 3
4 16 2 6
( Electric Gloves , 3- Training and
eye protection). awareness of
working in HV lines.
4- Skilled
electrician required.
4- Manual Handling 1- Worker-15 1- Back Pain, 1- Valid PTW. 1- Training and HSE Inspector 30.09.2022
2- Forman-3 Fatigue / Personnel 2- Manual handling awareness of
3- Engineers -2 injury / Damage to procedure on site. manual handling.
material due to 3- Notice Board with 2- Use mechanical
laying OHL cables & Manual Handling 4 device for lifting/ 3
its accessories . 3 12 2 6
techniques . shifting and pulling
heavy load.
3- Increase no's of
workers ( if
required)