Risk assessment form

Name of assessor Badar Alsiyabi Date 06.09.2022

Time 1500 Hrs Work area Fahud Overhead Line Area

Task being assessed Replacing 33KV OHL wooden Poles by Concrete Poles

New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
1- Working at hight 1- Worker-15 1- Fall down from 1- Valid PTW. 1- Bucket Truck Operation & 28.09.2022
2- Forman-3 height due to 2- Valid equipments inspection before Maintenance Team
3- Engineers -2 collapse of bucket test Certificates . working start. Lead Fahud
Truck. 3- Safety harness,. 2- Safety harness
2-Fall down from 4- PPE as per job 3 6 18 inspection prior to 2 5 10
height due to loss of requirements start..
stability. ( Helmets , Gloves). 3- Training and
awareness
(working at high).

2- Lifting equipment 1- Worker-15 1- Cranes falling 1- Valid PTW. 1- Crane inspection HSE Inspector 30.09.2022
2- Forman-3 over due to strong 2- Valid equipments prior to start.
3- Engineers -2 wind, unsafe loads, test Certificate. 2- Sling check prior
2- Falling of load 3- Sling test to start.
due to sling cut off . Certificate. 5 3- Following lifting 3
3 15 2 6
procedure.
4- Training and
awareness ( lifting )
Risk assessment form

New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
3- Electrocution 1- Worker-15 1- Electric Shock 1- Valid PTW. 1- Following Operation & 30.09.2022
2- Forman-3 2- Using Of 2- Valid equipments ESR/ESOP rules. Maintenance Team
3- Engineers -2 Unauthorized test Certificates . 2- Test equipments Lead Fahud
Electrical test 4- PPE as per job checking before
equipments. requirements 4 testings 3
4 16 2 6
( Electric Gloves , 3- Training and
eye protection). awareness of
working in HV lines.
4- Skilled
electrician required.

4- Manual Handling 1- Worker-15 1- Back Pain, 1- Valid PTW. 1- Training and HSE Inspector 30.09.2022
2- Forman-3 Fatigue / Personnel 2- Manual handling awareness of
3- Engineers -2 injury / Damage to procedure on site. manual handling.
material due to 3- Notice Board with 2- Use mechanical
laying OHL cables & Manual Handling 4 device for lifting/ 3
its accessories . 3 12 2 6
techniques . shifting and pulling
heavy load.
3- Increase no's of
workers ( if
required)

Review date 06.09.2022 Signature

Training Provider name Soresh