Use the Step Back 5x5 for Dynamic Risk Review

Figure 1 – TRIC Page 1


Procedure Reference HAZARDS CON CONTROL SHEET Job Card/Permit #/HAZ-ID# 3179
_______________________________________ Use this section to breakdown the job into steps, identify the hazards ___________________________________
_______________________________________ and controls and assign responsibilities for the controls. ___________________________________
Job Description: Manual and Mechanical excavation at Fuel station
Task: Hazards: Controls: Responsibilities: Are controls
Break the job down into a logical What hazards did your find for each What controls are in place or will you put in place? Who will be responsible in place?
sequence of steps task? each of those controls? Yes No
 Site –Per  Miscommunication  Identify hazards in the site
 PPE'S not available  Full PPE'S all times
 Slip, trip and fall  Housekeeping before state the job Site Supervisor
 Unaware about the hazard at work  TBT and Muster point
site, muster points, and protocols

 Assessing work areas prior  Existing hazard or new hazard not  Ensure that all hazard exist on the area are noted and discussed. Site Supervisor
commence activities identified  Ensure that good housekeeping maintained, safe access and egress provided.
 Access and egress not available  Ensure that everybody assessing the area are wearing complete and Standard
 Slip, trips and fall PPE’s.
 Manual Excavation Casting  Ensure that all workers are wearing complete and standard PPE’s such as; Dust
concrete and by using Cutter Mask, Hardhat, working gloves, safety shoes, safety glass, and coveralls.
machine  Poor hand tools and damage  Ensure that PTW and ERW certificates are approved and available.
 Install PVC P equipment
 Ensure that all workers attended HSE induction and ERW training
 Body injuries
 Supervisor available at all times
 Dust accumulation  Check hand tools and equipment before start the working
 We are must be wearing full PPE'S in the site
 Falling of personnel  Ensure that all workers area wearing complete and standard PPE’s such as;
Dust Mask, Hardhat, working gloves, safety shoes, safety glass, and coveralls
 Noise
 Barriers and safety sings available and posted Site Supervisor
 Damage equipment  Unauthorized personnel not allowed entering within the work areas
 Effected Eye, Skin Contact,  Unfinished work must be fully barricaded
Inhalation and Ingestion  Ensure that safe access and egress are available
 Skin irritation to hands  Ear plug Check the equipment before start the work
 Contamination of clothing  Follow the MSDS attach in the permit First aide
 Wash exposed areas thoroughly with soap and water after handling.
 Do not wash skin or hands with concrete, use hand cleaner.
 Wear gloves that are impervious to concrete
 Wash work clothes separately from other clothing; rinse washer after thoroughly
after use

Debrief: use this space to record any comments or new learning from the job

____________________________________________________________________________________________________________________________________________

Life Saving
Rules
Tick & discuss
rules that apply
Figure 2 – TRIC Page 2