CONSULTANT COMMENTS
PROJECT TITLE PROPOSED RESIDENTIAL BUILDING‐1B+G+4F
DATE DATE: OCTOBER 12, 2021
PIN N0. PIN NO: 69040040
PLOT N0. A‐13
LOCATION FOXHILLS DISTRICT LUSAIL
CLIENT MR. AHMAD MOHD A. I. AL‐ASMAKH/
MR. MOHAMMED NASSER A.S. AL‐EMADI
MAIN CONTRACTOR AL WEFAQ
CONSULTANT ATAK ENGINEERING CONSULTANT
MECH’L CONSULTANT ENG’R. EMERSON
ENG’R.
DESCRIPTION CONSULTANT SITE VISIT INSPECTION
INSPECTION NO. 01
CONSULTANT COMMENTS MAIN CON REPLY
FIRE FIGHTING SYSTEM
a) Effective Fire Water Storage Tank labeling capacity is
not provided.(shall be clearly indicated on the tank wall
in lettering a minimum height of 100 mm)
b) Diesel tank label capacity is not provided
c) Fire pumps pressure setting label is not provided.
d) Non provision of labels and directional arrows in
piping at fire pumps room
e) Fire sprinkler pipeline directional arrows are not
provided @ Basement
f) Fire pump room identification label is not provided.
g) Siamese connection identification labels are not
provided
B. Documents to be submit
a) Hydrostatic test pressure report.
b) Flushing test report.
c) Fire Pumps test report.
d)Shaft Alignment report.
e)Submit the updated QCDD approved products
certificate of all life safety products provided in the
project.
f) Submit the QCDD approved FFS drawings.
MECHANICAL VENTILATION
A. Basement Ventilation System
a) Non provision of identification mark and arrows for
basement ventilation duct (EAD and SAD).
b) Fresh air fan motor installed on the Ground for the
basement floor fresh air supply facing the road, as per
approved MV drawing reflected facing the right hand
wall.
c) Non provision of labels in exhaust and fresh air supply
equipment’s which are installed in the ground floor
B. Staircases Pressurization System
a) Installed pressurization ducts are not provided with
insulation and cladding @ Roof floor.
b) Non provision of smoke duct detectors in the air
supply to the pressurized stairwell as reflected in the
QCDD approved stair pressurization system.
c) Non provision of sand trap louver in pressurization
duct as reflected in the QCDD approved with drawing
no. MV‐08‐ General Details‐2.
C. Exhaust Duct System
a) Installed exhaust duct is obstruction going to
Emergency Generator.(Roof Floor)
D. Documents to be submit
a) Car park ventilation test reports.
b) Tabulated test data for static pressure differential
(SPD) per floor (Staircase pressurization). The SPD
reading must be at 50 Pa when all doors are closed, 25
Pa if one door is open, and 12.5 Pa for three doors open.
c) Submit the QCDD approved MV drawings.
ELEVATOR/ LIFT
a) Lifts shall be provided with safety instructions inside
the cabin.
b)” In case of Fire Do not Use Lift” in Arabic/English
signage shall be provided on lift lobby.
c) Lifts shall home to ground upon receipt of fire alarm.
Homing on alternate floor shall be provided.
d) Emergency Landing Device (ELD) shall be provided for
each lift
D. Documents to be submit
a) Elevator testing report.
b) Emergency landing device (ELD) reports.
c) Sequence of operation.