Professional Documents
Culture Documents
194
(e) Each access must be locked unless age capacity, only the protective en-
it is continuously guarded. During nor- closure must be monitored.
mal operations, an access may be un-
locked only by persons designated in § 193.2915 Alternative power sources.
writing by the operator. During an An alternative source of power that
emergency, a means must be readily meets the requirements of § 193.2445
available to all facility personnel with- must be provided for security lighting
in the protective enclosure to open and security monitoring and warning
each access. systems required under §§ 193.2911 and
193.2913.
§ 193.2907 Protective enclosure con-
struction. § 193.2917 Warning signs.
(a) Each protective enclosure must (a) Warning signs must be conspicu-
have sufficient strength and configura- ously placed along each protective en-
tion to obstruct unauthorized access to closure at intervals so that at least one
the facilities enclosed. sign is recognizable at night from a dis-
(b) Openings in or under protective
tance of 30m (100 ft.) from any way that
enclosures must be secured by grates,
could reasonably be used to approach
doors or covers of construction and fas-
the enclosure.
tening of sufficient strength such that
(b) Signs must be marked with at
the integrity of the protective enclo-
least the following on a background of
sure is not reduced by any opening.
sharply contrasting color:
[Amdt. 193–2, 45 FR 70409, Oct. 23, 1980, as The words ‘‘NO TRESPASSING,’’ or
amended by Amdt. 193–12, 61 FR 27793, June
3, 1996; 61 FR 45905, Aug. 30, 1996]
words of comparable meaning.
[Amdt. 193–2, 45 FR 70409, Oct. 23, 1980, as
§ 193.2909 Security communications. amended at 47 FR 32720, July 29, 1982]
A means must be provided for:
(a) Prompt communications between PART 194—RESPONSE PLANS FOR
personnel having supervisory security ONSHORE OIL PIPELINES
duties and law enforcement officials;
and Subpart A—General
(b) Direct communications between
all on-duty personnel having security Sec.
duties and all control rooms and con- 194.1 Purpose.
194.3 Applicability.
trol stations.
194.5 Definitions.
194.7 Operating restrictions and interim op-
§ 193.2911 Security lighting.
erating authorization.
Where security warning systems are
not provided for security monitoring Subpart B—Response Plans
under § 193.2913, the area around the fa-
194.101 Operators required to submit plans.
cilities listed under § 193.2905(a) and 194.103 Significant and substantial harm;
each protective enclosure must be illu- operator’s statement.
minated with a minimum in service 194.105 Worst case discharge.
lighting intensity of not less than 2.2 194.107 General response plan requirements.
lux (0.2 ftc) between sunset and sunrise. 194.109 Submission of state response plans.
194.111 Response plan retention.
§ 193.2913 Security monitoring. 194.113 Information summary.
194.115 Response resources.
Each protective enclosure and the
194.117 Training.
area around each facility listed in 194.119 Submission and approval procedures.
§ 193.2905(a) must be monitored for the 194.121 Response plan review and update
presence of unauthorized persons. Mon- procedures.
itoring must be by visual observation APPENDIX A TO PART 194—GUIDELINES FOR
in accordance with the schedule in the THE PREPARATION OF RESPONSE PLANS
security procedures under § 193.2903(a) APPENDIX B TO PART 194—HIGH VOLUME
wreier-aviles on DSK3TPTVN1PROD with CFR
531
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00543 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
§ 194.1 49 CFR Ch. I (10–1–11 Edition)
SOURCE: 58 FR 253, Jan. 5, 1993, unless oth- (3) Active membership in a local or
erwise noted. regional oil spill removal organization
that has identified specified personnel
Subpart A—General and equipment to be available within
stipulated response times for a speci-
§ 194.1 Purpose. fied geographic area.
This part contains requirements for Environmentally sensitive area means
oil spill response plans to reduce the an area of environmental importance
environmental impact of oil discharged which is in or adjacent to navigable
from onshore oil pipelines. waters.
High volume area means an area
§ 194.3 Applicability. which an oil pipeline having a nominal
This part applies to an operator of an outside diameter of 20 inches (508 milli-
onshore oil pipeline that, because of its meters) or more crosses a major river
location, could reasonably be expected or other navigable waters, which, be-
to cause substantial harm, or signifi- cause of the velocity of the river flow
cant and substantial harm to the envi- and vessel traffic on the river, would
ronment by discharging oil into or on require a more rapid response in case of
any navigable waters of the United a worst case discharge or substantial
States or adjoining shorelines. threat of such a discharge. Appendix B
to this part contains a list of some of
§ 194.5 Definitions. the high volume areas in the United
Adverse weather means the weather States.
conditions that the operator will con- Line section means a continuous run
sider when identifying response sys- of pipe that is contained between adja-
tems and equipment to be deployed in cent pressure pump stations, between a
accordance with a response plan. Fac- pressure pump station and a terminal
tors to consider include ice conditions, or breakout tank, between a pressure
temperature ranges, weather-related pump station and a block valve, or be-
visibility, significant wave height as tween adjacent block valves.
specified in 33 CFR Part 154, Appendix Major river means a river that, be-
C, Table 1, and currents within the cause of its velocity and vessel traffic,
areas in which those systems or equip- would require a more rapid response in
ment are intended to function. case of a worst case discharge. For a
Barrel means 42 United States gallons list of rivers see ‘‘Rolling Rivers, An En-
(159 liters) at 60 °Fahrenheit (15.6 cyclopedia of America’s Rivers,’’ Richard
°Celsius). A. Bartlett, Editor, McGraw-Hill Book
Breakout tank means a tank used to: Company, 1984.
(1) Relieve surges in an oil pipeline Maximum extent practicable means the
system or limits of available technology and the
(2) Receive and store oil transported practical and technical limits on a
by a pipeline for reinjection and con- pipeline operator in planning the re-
tinued transportation by pipeline. sponse resources required to provide
Contract or other approved means is: the on-water recovery capability and
(1) A written contract or other le- the shoreline protection and cleanup
gally binding agreement between the capability to conduct response activi-
operator and a response contractor or ties for a worst case discharge from a
other spill response organization iden- pipeline in adverse weather.
tifying and ensuring the availability of Navigable waters means the waters of
the specified personnel and equipment the United States, including the terri-
within stipulated response times for a torial sea and such waters as lakes, riv-
specified geographic area; ers, streams; waters which are used for
(2) Certification that specified equip- recreation; and waters from which fish
ment is owned or operated by the pipe- or shellfish are taken and sold in inter-
wreier-aviles on DSK3TPTVN1PROD with CFR
532
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00544 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
Pipeline and Hazardous Materials Safety Admin., DOT § 194.7
oil, sludge, oil refuse, oil mixed with Response zone means a geographic
wastes other than dredged spoil. area either along a length of pipeline
Oil spill removal organization means an or including multiple pipelines, con-
entity that provides response re- taining one or more adjacent line sec-
sources. tions, for which the operator must plan
On-Scene Coordinator (OSC) means the for the deployment of, and provide,
federal official designated by the Ad- spill response capabilities. The size of
ministrator of the EPA or by the Com- the zone is determined by the operator
mandant of the USCG to coordinate after considering available capability,
and direct federal response under sub- resources, and geographic characteris-
part D of the National Contingency tics.
Plan (40 CFR part 300).
Specified minimum yield strength
Onshore oil pipeline facilities means
new and existing pipe, rights-of-way means the minimum yield strength, ex-
and any equipment, facility, or build- pressed in pounds per square inch, pre-
ing used in the transportation of oil lo- scribed by the specification under
cated in, on, or under, any land within which the material is purchased from
the United States other than sub- the manufacturer.
merged land. Stress level means the level of tangen-
Operator means a person who owns or tial or hoop stress, usually expressed as
operates onshore oil pipeline facilities. a percentage of specified minimum
Pipeline means all parts of an onshore yield strength.
pipeline facility through which oil Worst case discharge means the larg-
moves including, but not limited to, est foreseeable discharge of oil, includ-
line pipe, valves, and other appur- ing a discharge from fire or explosion,
tenances connected to line pipe, pump- in adverse weather conditions. This
ing units, fabricated assemblies associ- volume will be determined by each
ated with pumping units, metering and pipeline operator for each response
delivery stations and fabricated assem- zone and is calculated according to
blies therein, and breakout tanks. § 194.105.
Qualified individual means an
English-speaking representative of an [58 FR 253, Jan. 5, 1993, as amended by Amdt.
operator, located in the United States, 194–3, 63 FR 37505, July 13, 1998; Amdt. 194–4,
available on a 24-hour basis, with full 70 FR 8746, Feb. 23, 2005]
authority to: activate and contract
with required oil spill removal organi- § 194.7 Operating restrictions and in-
zation(s); activate personnel and equip- terim operating authorization.
ment maintained by the operator; act (a) An operator of a pipeline for
as liaison with the OSC; and obligate which a response plan is required under
any funds required to carry out all re- § 194.101, may not handle, store, or
quired or directed oil response activi- transport oil in that pipeline unless the
ties. operator has submitted a response plan
Response activities means the contain- meeting the requirements of this part.
ment and removal of oil from the water (b) An operator must operate its on-
and shorelines, the temporary storage shore pipeline facilities in accordance
and disposal of recovered oil, or the with the applicable response plan.
taking of other actions as necessary to
(c) The operator of a pipeline line
minimize or mitigate damage to the
section described in § 194.103(c), may
environment.
Response plan means the operator’s continue to operate the pipeline for
core plan and the response zone appen- two years after the date of submission
dices for responding, to the maximum of a response plan, pending approval or
extent practicable, to a worse case dis- disapproval of that plan, only if the op-
charge of oil, or the substantial threat erator has submitted the certification
of such a discharge. required by § 194.119(e).
wreier-aviles on DSK3TPTVN1PROD with CFR
Response resources means the per- [Amdt. 194–4, 70 FR 8746, Feb. 23, 2005]
sonnel, equipment, supplies, and other
resources necessary to conduct re-
sponse activities.
533
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00545 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
§ 194.101 49 CFR Ch. I (10–1–11 Edition)
12 hours after the initiation of the dis- welded pipe, manufactured prior to
charge, any navigable waters, public 1970, operates at a maximum operating
drinking water intake, or environ- pressure established under § 195.406 that
mentally sensitive areas. corresponds to a stress level greater
534
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00546 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
Pipeline and Hazardous Materials Safety Admin., DOT § 194.107
than 50 percent of the specified min- sence of such historic data, the opera-
imum yield strength of the pipe, tor’s best estimate), multiplied by the
(4) Is located within a 5 mile (8 kilo- maximum flow rate expressed in bar-
meter) radius of potentially affected rels per hour (based on the maximum
public drinking water intakes and daily capacity of the pipeline), plus the
could reasonably be expected to reach largest line drainage volume after
public drinking water intakes, or shutdown of the line section(s) in the
(5) Is located within a 1 mile (1.6 kilo- response zone expressed in barrels
meter) radius of potentially affected (cubic meters); or
environmentally sensitive areas, and (2) The largest foreseeable discharge
could reasonably be expected to reach for the line section(s) within a response
these areas. zone, expressed in barrels (cubic me-
[58 FR 253, Jan. 5, 1993, as amended by Amdt. ters), based on the maximum historic
194–3, 63 FR 37505, July 13, 1998] discharge, if one exists, adjusted for
any subsequent corrective or preven-
§ 194.105 Worst case discharge. tive action taken; or
(a) Each operator shall determine the (3) If the response zone contains one
worst case discharge for each of its re- or more breakout tanks, the capacity
sponse zones and provide the method- of the single largest tank or battery of
ology, including calculations, used to tanks within a single secondary con-
arrive at the volume. tainment system, adjusted for the ca-
(b) The worst case discharge is the pacity or size of the secondary contain-
largest volume, in barrels (cubic me- ment system, expressed in barrels
ters), of the following: (cubic meters).
(1) The pipeline’s maximum release (4) Operators may claim prevention
time in hours, plus the maximum shut- credits for breakout tank secondary
down response time in hours (based on containment and other specific spill
historic discharge data or in the ab- prevention measures as follows:
Credit
Prevention measure Standard (percent)
[58 FR 253, Jan. 5, 1993, as amended by Amdt. maintenance, and emergencies, which
194–3, 63 FR 37505, July 13, 1998; Amdt. 194–4, is prepared in compliance with 49 CFR
70 FR 8747, Feb. 23, 2005; Amdt. 194–5, 70 FR 195.402.
35042, June 16, 2005]
(b) An operator must certify in the
response plan that it reviewed the NCP
§ 194.107 General response plan re-
quirements. and each applicable ACP and that its
response plan is consistent with the
(a) Each response plan must include NCP and each applicable ACP as fol-
procedures and a list of resources for lows:
responding, to the maximum extent (1) As a minimum to be consistent
practicable, to a worst case discharge with the NCP a facility response plan
and to a substantial threat of such a must:
discharge. The ‘‘substantial threat’’ (i) Demonstrate an operator’s clear
term is equivalent to abnormal oper- understanding of the function of the
ations outlined in 49 CFR 195.402(d). To Federal response structure, including
wreier-aviles on DSK3TPTVN1PROD with CFR
comply with this requirement, an oper- procedures to notify the National Re-
ator can incorporate by reference into sponse Center reflecting the relation-
the response plan the appropriate pro- ship between the operator’s response
cedures from its manual for operations, organization’s role and the Federal On
535
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00547 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
§ 194.109 49 CFR Ch. I (10–1–11 Edition)
Scene Coordinator’s role in pollution (x) Plan review and update proce-
response; dures;
(ii) Establish provisions to ensure the (2) An appendix for each response
protection of safety at the response zone that includes the information re-
site; and quired in paragraph (c)(1)(i)–(ix) of this
(iii) Identify the procedures to obtain section and the worst case discharge
any required Federal and State permis- calculations that are specific to that
sions for using alternative response response zone. An operator submitting
strategies such as in-situ burning and a response plan for a single response
dispersants as provided for in the appli- zone does not need to have a core plan
cable ACPs; and and a response zone appendix. The op-
(2) As a minimum, to be consistent erator of a single response zone on-
with the applicable ACP the plan must: shore pipeline shall have a single sum-
(i) Address the removal of a worst mary in the plan that contains the re-
case discharge and the mitigation or quired information in § 194.113.7; and
prevention of a substantial threat of a (3) A description of the operator’s re-
worst case discharge; sponse management system including
(ii) Identify environmentally and the functional areas of finance, logis-
economically sensitive areas; tics, operations, planning, and com-
(iii) Describe the responsibilities of mand. The plan must demonstrate that
the operator and of Federal, State and the operator’s response management
local agencies in removing a discharge system uses common terminology and
and in mitigating or preventing a sub- has a manageable span of control, a
stantial threat of a discharge; and clearly defined chain of command, and
(iv) Establish the procedures for ob- sufficient trained personnel to fill each
taining an expedited decision on use of position.
dispersants or other chemicals. [Amdt. 194–4, 70 FR 8747, Feb. 23, 2005]
(c) Each response plan must include:
(1) A core plan consisting of— § 194.109 Submission of state response
(i) An information summary as re- plans.
quired in § 194.113, (a) In lieu of submitting a response
(ii) Immediate notification proce- plan required by § 194.103, an operator
dures, may submit a response plan that com-
(iii) Spill detection and mitigation plies with a state law or regulation, if
procedures, the state law or regulation requires a
(iv) The name, address, and telephone plan that provides equivalent or great-
number of the oil spill response organi- er spill protection than a plan required
zation, if appropriate, under this part.
(v) Response activities and response (b) A plan submitted under this sec-
resources, tion must
(vi) Names and telephone numbers of (1) Have an information summary re-
Federal, State and local agencies quired by § 194.113;
which the operator expects to have pol- (2) List the names or titles and 24-
lution control responsibilities or sup- hour telephone numbers of the quali-
port, fied individual(s) and at least one al-
(vii) Training procedures, ternate qualified individual(s); and
(viii) Equipment testing, (3) Ensure through contract or other
approved means the necessary private
(ix) Drill program—an operator will
personnel and equipment to respond to
satisfy the requirement for a drill pro-
a worst case discharge or a substantial
gram by following the National Pre-
threat of such a discharge.
paredness for Response Exercise Pro-
gram (PREP) guidelines. An operator [58 FR 253, Jan. 5, 1993, as amended by Amdt.
choosing not to follow PREP guidelines 194–4, 70 FR 8748, Feb. 23, 2005]
must have a drill program that is
wreier-aviles on DSK3TPTVN1PROD with CFR
536
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00548 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
Pipeline and Hazardous Materials Safety Admin., DOT § 194.117
other locations from which response (b) An operator shall identify in the
activities may be conducted, for exam- response plan the response resources
ple, in field offices, supervisors’ vehi- which are available to respond within
cles, or spill response trailers. the time specified, after discovery of a
(b) Each operator shall provide a worst case discharge, or to mitigate
copy of its response plan to each quali- the substantial threat of such a dis-
fied individual. charge, as follows:
[58 FR 253, Jan. 5, 1993, as amended by Amdt. Tier 1 Tier 2 Tier 3
194–4, 70 FR 8748, Feb. 23, 2005]
High volume area ...... 6 hrs ........ 30 hrs ...... 54 hrs.
§ 194.113 Information summary. All other areas ........... 12 hrs ...... 36 hrs ...... 60 hrs.
537
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00549 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
§ 194.119 49 CFR Ch. I (10–1–11 Edition)
(2) Records for personnel engaged in Guard (USCG) if a Federal on-scene co-
response, other than operator per- ordinator (FOSC) has concerns about
sonnel, shall be maintained as deter- the operator’s ability to respond to a
mined by the operator. worst case discharge.
(c) Nothing in this section relieves an (e) If OPS has not approved a re-
operator from the responsibility to en- sponse plan for a pipeline described in
sure that all response personnel are § 194.103(c), the operator may submit a
trained to meet the Occupational Safe- certification to OPS that the operator
ty and Health Administration (OSHA) has obtained, through contract or
standards for emergency response oper- other approved means, the necessary
ations in 29 CFR 1910.120, including vol- personnel and equipment to respond, to
unteers or casual laborers employed the maximum extent practicable, to a
during a response who are subject to worst case discharge or a substantial
those standards pursuant to 40 CFR threat of such a discharge. The certifi-
part 311. cate must be signed by the qualified in-
dividual or an appropriate corporate of-
§ 194.119 Submission and approval
procedures. ficer.
(f) If OPS receives a request from a
(a) Each operator shall submit two FOSC to review a response plan, OPS
copies of the response plan required by may require an operator to give a copy
this part. Copies of the response plan of the response plan to the FOSC. OPS
shall be submitted to: Office of Pipe- may consider FOSC comments on re-
line Safety, Pipeline and Hazardous sponse techniques, protecting fish,
Materials Safety Administration, De- wildlife and sensitive environments,
partment of Transportation, PHP 80, and on consistency with the ACP. OPS
1200 New Jersey Avenue, SE., Wash- remains the approving authority for
ington, DC 20590–0001. Note: Submission the response plan.
of plans in electronic format is pre-
ferred. [58 FR 253, Jan. 5, 1993, as amended byAmdt.
(b) If PHMSA determines that a re- 194–4, 70 FR 8748, Feb. 23, 2005; 70 FR 1140,
sponse plan requiring approval does not Mar. 8, 2005; 73 FR 16570, Mar. 28, 2008; 74 FR
2894, Jan. 16, 2009]
meet all the requirements of this part,
PHMSA will notify the operator of any § 194.121 Response plan review and
alleged deficiencies, and to provide the update procedures.
operator an opportunity to respond, in-
cluding the opportunity for an infor- (a) Each operator shall update its re-
mal conference, on any proposed plan sponse plan to address new or different
revisions and an opportunity to correct operating conditions or information. In
any deficiencies. addition, each operator shall review its
(c) An operator who disagrees with response plan in full at least every 5
the PHMSA determination that a plan years from the date of the last submis-
contains alleged deficiencies may peti- sion or the last approval as follows:
tion PHMSA for reconsideration within (1) For substantial harm plans, an op-
30 days from the date of receipt of erator shall resubmit its response plan
PHMSA’s notice. After considering all to OPS every 5 years from the last sub-
relevant material presented in writing mission date.
or at an informal conference, PHMSA (2) For significant and substantial
will notify the operator of its final de- harm plans, an operator shall resubmit
cision. The operator must comply with every 5 years from the last approval
the final decision within 30 days of date.
issuance unless PHMSA allows addi- (b) If a new or different operating
tional time. condition or information would sub-
(d) For response zones of pipelines de- stantially affect the implementation of
scribed in § 194.103(c) OPS will approve a response plan, the operator must im-
the response plan if OPS determines mediately modify its response plan to
wreier-aviles on DSK3TPTVN1PROD with CFR
that the response plan meets all re- address such a change and, within 30
quirements of this part. OPS may con- days of making such a change, submit
sult with the U.S. Environmental Pro- the change to PHMSA. Examples of
tection Agency (EPA) or the U.S. Coast changes in operating conditions that
538
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00550 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216
Pipeline and Hazardous Materials Safety Admin., DOT Pt. 194, App. A
would cause a significant change to an the response plans required by 49 CFR Part
operator’s response plan are: 194. Operators are referenced to the most
(1) An extension of the existing pipe- current version of the guidance documents
listed below. Although these documents con-
line or construction of a new pipeline
tain guidance to assist in preparing response
in a response zone not covered by the plans, their use is not mandatory:
previously approved plan; (1) The ‘‘National Preparedness for Re-
(2) Relocation or replacement of the sponse Exercise Program (PREP) Guide-
pipeline in a way that substantially af- lines’’ (PREP), which can be found using the
fects the information included in the search function on the USCG’s PREP Web
response plan, such as a change to the page, http://www.uscg.mil;
worst case discharge volume; (2) The National Response Team’s ‘‘Inte-
(3) The type of oil transported, if the grated Contingency Plan Guidance,’’ which
type affects the required response re- can be found using the search function at the
National Response Center’s Web site, http://
sources, such as a change from crude www.nrt.org and;
oil to gasoline; (3) 33 CFR Part 154, Appendix C, ‘‘Guide-
(4) The name of the oil spill removal lines for Determining and Evaluating Re-
organization; quired Response Resources for Facility Re-
(5) Emergency response procedures; sponse Plans.’’
(6) The qualified individual;
(7) A change in the NCP or an ACP Response Plan: Section 1. Information Summary
that has significant impact on the Section 1 would include the following:
equipment appropriate for response ac- (a) For the core plan:
tivities; and (1) The name and address of the operator;
(8) Any other information relating to and
circumstances that may affect full im- (2) For each response zone which contains
plementation of the plan. one or more line sections that meet the cri-
teria for determining significant and sub-
(c) If PHMSA determines that a
stantial harm as described in § 194.103, a list-
change to a response plan does not ing and description of the response zones, in-
meet the requirements of this part, cluding county(s) and state(s).
PHMSA will notify the operator of any (b) For each response zone appendix:
alleged deficiencies, and provide the (1) The information summary for the core
operator an opportunity to respond, in- plan;
cluding an opportunity for an informal (2) The name and telephone number of the
conference, to any proposed plan revi- qualified individual, available on a 24-hour
sions and an opportunity to correct basis;
any deficiencies. (3) A description of the response zone, in-
cluding county(s) and state(s) in which a
(d) An operator who disagrees with a
worst case discharge could cause substantial
determination that proposed revisions harm to the environment;
to a plan are deficient may petition (4) A list of line sections contained in the
PHMSA for reconsideration, within 30 response zone, identified by milepost or sur-
days from the date of receipt of vey station number or other operator des-
PHMSA’s notice. After considering all ignation.
relevant material presented in writing (5) The basis for the operator’s determina-
or at the conference, PHMSA will no- tion of significant and substantial harm; and
tify the operator of its final decision. (6) The type of oil and volume of the worst
case discharge.
The operator must comply with the
(c) The certification that the operator has
final decision within 30 days of obtained, through contract or other ap-
issuance unless PHMSA allows addi- proved means, the necessary private per-
tional time. sonnel and equipment to respond, to the
[58 FR 253, Jan. 5, 1993, as amended by Amdt. maximum extent practicable, to a worst case
194–1, 62 FR 67293, Dec. 24, 1997; Amdt. 194–4, discharge or a substantial threat of such a
70 FR 8748, Feb. 23, 2005; 70 FR 11140, Mar. 8, discharge.
2005] Response Plan: Section 2. Notification
Procedures
APPENDIX A TO PART 194—GUIDELINES
Section 2 would include the following:
wreier-aviles on DSK3TPTVN1PROD with CFR
539
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00551 Fmt 8010 Sfmt 8002 Y:\SGML\223216.XXX 223216
Pt. 194, App. A 49 CFR Ch. I (10–1–11 Edition)
(b) A checklist of notifications the oper- (c) Procedures for coordinating the actions
ator or qualified individual is required to of the operator or qualified individual with
make under the response plan, listed in the the action of the OSC responsible for moni-
order of priority; toring or directing those actions;
(c) Names of persons (individuals or orga- (d) Oil spill response organizations avail-
nizations) to be notified of a discharge, indi- able, through contract or other approved
cating whether notification is to be per- means, to respond to a worst case discharge
formed by operating personnel or other per- to the maximum extent practicable; and
sonnel; (e) For each organization identified under
(d) Procedures for notifying qualified indi- paragraph (d) of this section, a listing of:
viduals; (1) Equipment and supplies available; and
(e) The primary and secondary commu- (2) Trained personnel necessary to con-
nication methods by which notifications can tinue operation of the equipment and staff
be made; and the oil spill removal organization for the
(f) The information to be provided in the first 7 days of the response.
initial and each follow-up notification, in-
cluding the following: Response Plan: Section 5. List of Contacts
(1) Name of pipeline; Section 5 would include the names and ad-
(2) Time of discharge; dresses of the following individuals or orga-
(3) Location of discharge; nizations, with telephone numbers at which
(4) Name of oil involved; they can be contacted on a 24-hour basis:
(5) Reason for discharge (e.g., material fail- (a) A list of persons the plan requires the
ure, excavation damage, corrosion); operator to contact;
(6) Estimated volume of oil discharged; (b) Qualified individuals for the operator’s
(7) Weather conditions on scene; and areas of operation;
(8) Actions taken or planned by persons on (c) Applicable insurance representatives or
scene. surveyors for the operator’s areas of oper-
ation; and
Response Plan: Section 3. Spill Detection and (d) Persons or organizations to notify for
On-Scene Spill Mitigation Procedures activation of response resources.
Section 3 would include the following:
(a) Methods of initial discharge detection; Response plan: Section 6. Training Procedures
(b) Procedures, listed in the order of pri- Section 6 would include a description of
ority, that personnel are required to follow the training procedures and programs of the
in responding to a pipeline emergency to operator.
mitigate or prevent any discharge from the
pipeline; Response plan: Section 7. Drill Procedures
(c) A list of equipment that may be needed Section 7 would include a description of
in response activities on land and navigable the drill procedures and programs the oper-
waters, including— ator uses to assess whether its response plan
(1) Transfer hoses and connection equip- will function as planned. It would include:
ment; (a) Announced and unannounced drills;
(2) Portable pumps and ancillary equip- (b) The types of drills and their fre-
ment; and quencies. For example, drills could be de-
(3) Facilities available to transport and re- scribed as follows:
ceive oil from a leaking pipeline; (1) Manned pipeline emergency procedures
(d) Identification of the availability, loca- and qualified individual notification drills
tion, and contact telephone numbers to ob- conducted quarterly.
tain equipment for response activities on a (2) Drills involving emergency actions by
24-hour basis; and assigned operating or maintenance personnel
(e) Identification of personnel and their lo- and notification of the qualified individual
cation, telephone numbers, and responsibil- on pipeline facilities which are normally un-
ities for use of equipment in response activi- manned, conducted quarterly.
ties on a 24-hour basis. (3) Shore-based spill management team ta-
bletop drills conducted yearly.
Response Plan: Section 4. Response Activities (4) Oil spill removal organization field
Section 4 would include the following: equipment deployment drills conducted
(a) Responsibilities of, and actions to be yearly.
taken by, operating personnel to initiate and (5) A drill that exercises the entire re-
supervise response actions pending the ar- sponse plan for each response zone, would be
rival of the qualified individual or other re- conducted at least once every 3 years.
wreier-aviles on DSK3TPTVN1PROD with CFR
540
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00552 Fmt 8010 Sfmt 8002 Y:\SGML\223216.XXX 223216
Pipeline and Hazardous Materials Safety Admin., DOT Pt. 194, App. B
(b) Procedures to review the plan after a Major rivers Nearest town and state
worst case discharge and to evaluate and
record the plan’s effectiveness. Arkansas River ...................... N. Little Rock, AR.
Arkansas River ...................... Jenks, OK.
Response plan: Section 9. Response Zone Arkansas River ...................... Little Rock, AR.
Black Warrior River ............... Moundville, AL.
Appendices.
Black Warrior River ............... Akron, AL.
Each response zone appendix would provide Brazos River .......................... Glen Rose, TX.
the following information: Brazos River .......................... Sealy, TX.
Catawba River ....................... Mount Holly, NC.
(a) The name and telephone number of the Chattahoochee River ............. Sandy Springs, GA.
qualified individual; Colorado River ....................... Yuma, AZ.
(b) Notification procedures; Colorado River ....................... LaPaz, AZ.
(c) Spill detection and mitigation proce- Connecticut River .................. Lancaster, NH.
dures; Coosa River ........................... Vincent, AL.
Cumberland River .................. Clarksville, TN.
(d) Name, address, and telephone number Delaware River ...................... Frenchtown, NJ.
of oil spill response organization; Delaware River ...................... Lower Chichester, NJ.
(e) Response activities and response re- Gila River ............................... Gila Bend, AZ.
sources including— Grand River ........................... Bosworth, MO.
(1) Equipment and supplies necessary to Illinois River ........................... Chillicothe, IL.
Illinois River ........................... Havanna, IL.
meet § 194.115, and
James River ........................... Arvonia, VA.
(2) The trained personnel necessary to sus- Kankakee River ..................... Kankakee, IL.
tain operation of the equipment and to staff Kankakee River ..................... South Bend, IN.
the oil spill removal organization and spill Kankakee River ..................... Wilmington, IL.
management team for the first 7 days of the Kentucky River ...................... Salvisa, KY.
response; Kentucky River ...................... Worthville, KY.
Maumee River ....................... Defiance, OH.
(f) Names and telephone numbers of Fed-
Maumee River ....................... Toledo, OH.
eral, state and local agencies which the oper- Mississippi River .................... Myrtle Grove, LA.
ator expects to assume pollution response re- Mississippi River .................... Woodriver, IL.
sponsibilities; Mississippi River .................... Chester, IL.
(g) The worst case discharge volume; Mississippi River .................... Cape Girardeau, MO.
(h) The method used to determine the Mississippi River .................... Woodriver, IL.
worst case discharge volume, with calcula- Mississippi River .................... St. James, LA.
Mississippi River .................... New Roads, LA.
tions; Mississippi River .................... Ball Club, MN.
(i) A map that clearly shows— Mississippi River .................... Mayersville, MS.
(1) The location of the worst case dis- Mississippi River .................... New Roads, LA.
charge, and Mississippi River .................... Quincy, IL.
(2) The distance between each line section Mississippi River .................... Ft. Madison, IA.
in the response zone and— Missouri River ........................ Waverly, MO.
Missouri River ........................ St. Joseph, MO.
(i) Each potentially affected public drink- Missouri River ........................ Weldon Springs, MO.
ing water intake, lake, river, and stream Missouri River ........................ New Frankfort, MO.
within a radius of 5 miles (8 kilometers) of Naches River ......................... Beaumont, TX.
the line section, and Ohio River .............................. Joppa, IL.
(ii) Each potentially affected environ- Ohio River .............................. Cincinnati, OH.
mentally sensitive area within a radius of 1 Ohio River .............................. Owensboro, KY.
mile (1.6 kilometer) of the line section; Pascagoula River .................. Lucedale, MS.
Pascagoula River .................. Wiggins, MS.
(j) A piping diagram and plan-profile draw- Pearl River ............................. Columbia, MS.
ing of each line section, which may be kept Pearl River ............................. Oria, TX.
separate from the response plan if the loca- Platte River ............................ Ogaliala, NE.
tion is identified; and Potomac River ....................... Reston, VA.
(k) For every oil transported by each pipe- Rappahannock River ............. Midland, VA.
line in the response zone, emergency re- Raritan River .......................... South Bound Brook, NJ.
Raritan River .......................... Highland Park, NJ.
sponse data that—
Red River (of the South) ....... Hanna, LA.
(1) Include the name, description, physical Red River (of the South) ....... Bonham, TX.
and chemical characteristics, health and Red River (of the South) ....... Dekalb, TX.
safety hazards, and initial spill-handling and Red River (of the South) ....... Sentell Plantation, LA.
firefighting methods; and Red River (of the North) ........ Wahpeton, ND.
(2) Meet 29 CFR 1910.1200 or 49 CFR 172.602. Rio Grande ............................ Anthony, NM.
Sabine River .......................... Edgewood, TX.
[58 FR 253, Jan. 5, 1993, as amended by Amdt. Sabine River .......................... Leesville, LA.
194–3, 63 FR 37505, July 13, 1998; Amdt. 194–4, Sabine River .......................... Orange, TX.
70 FR 8748, Feb. 23, 2005] Sabine River .......................... Echo, TX.
Savannah River ..................... Hartwell, GA.
Smokey Hill River .................. Abilene, KS.
wreier-aviles on DSK3TPTVN1PROD with CFR
541
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00553 Fmt 8010 Sfmt 8002 Y:\SGML\223216.XXX 223216
Pt. 195 49 CFR Ch. I (10–1–11 Edition)
542
VerDate Mar<15>2010 14:56 Jan 03, 2012 Jkt 223216 PO 00000 Frm 00554 Fmt 8010 Sfmt 8010 Y:\SGML\223216.XXX 223216