SORSOGON PRINTING PRESS

FIRE EXIT STAIRS

MATERIAL COST
NO. DESCRIPTION QTY. UNIT UNIT PRICE AMOUNT
1 G.I Pipe 1 1/2"S40 22 pieces 2,015.00 44,330.00
3 RSB 10mm 10 pieces 196.95 1,969.50
4 Angle Bar 3/16" x 1" x 1" 16 pieces 1,300.00 20,800.00
5 Angle Bar 3/16" x 1 1/2" x 1 1/2" 12 pieces 1,495.00 17,940.00
6 Angle Bar 3/16" x 2" x 2" 9 pieces 1,690.00 15,210.00
7 Angle Bar 1/4" x 2" x 2" 4 pieces 1,690.00 6,760.00
8 Angle Bar 1/4" x 3" x 3" 2 pieces 3,120.00 6,240.00
9 Flat Bar 3/16" x 1" 25 pieces 390.00 9,750.00
10 Welding rod 3/32" Ø6013 4 packs 975.00 3,900.00
11 Welding rod 3/32" Ø6011 1 packs 1,040.00 1,040.00
12 Dyna bolt 3/8" SØ 50 pieces 35.75 1,787.50
13 Dyna bolt 1/2"Ø 20 pieces 52.00 1,040.00
14 Metal Primer Gray 3 gallons 1,482.00 4,446.00
15 Lacquer Thinner 2 gallons 715.00 1,430.00
16 Paint brush 2" 6 pieces 52.00 312.00
17 Pillow block 1 1/2"Ø 2 pieces 1,254.50 2,509.00
18 Shafting 1 1/2"Ø 3 feet 1,137.50 3,412.50
19 High tensile nut and washer 1 1/4"Ø 4 pairs 227.50 910.00
20 High tensile nut and washer 1/2"Ø x 2 1/2" 4 pairs 143.00 572.00
21 Drill Bit 1 lot 2,600.00 2,600.00
22 Cutting disc thin 3mmx4"Ø 5 boxes 877.50 4,387.50
23 Cutting disc thick 5mmx4"Ø 2 boxes 1,137.50 2,275.00
24 Grinding disc 4"Ø 2 boxes 1,618.50 3,237.00
25 Cutting Wheel 14 Ø 2 pieces 268.78 537.55
26 Checkered Plate 3/16" 3 pieces 15,600.00 46,800.00
27 Checkered Plate 1/8" 2 pieces 5,850.00 11,700.00
28 Oxy- Acetylene 1 lot 13,000.00 13,000.00
29 Cement 3 bags 331.50 994.50
30 Sand and Gravel 1 lot 2,275.00 2,275.00
TOTAL 232,165.05

I. MATERIAL COST 232,165.05


II. MOBILIZATION 20,000.00
III. LABOR COST 120,000.00
IV. ADMIN COST 55,824.76
GRAND TOTAL( VAT EXCLUDED) 427,989.81

PREPARED BY:

ENGR. NARDITO M. CORNELIO, JR