1. FABRICATE CELLAR DECK AND TRANSFER PUMP ACCESS PLATFORM, 2.

2. INSTALL DECK LEGS, COLUMNS AND VERTICAL BRACES C/W TEMPORARY 3. LIFT UP MAIN DECK AND PUT IT ABOVE CELLAR DECK
LIFT UP AND PUT IT ABOVE CROSS BEAM SUPPORT SUPPORT ON CELLAR DECK

M EI N DO
ELANG INDAH

4. INSTALL VERTICAL BRACES AT DECK LEG ROW A2 BELOW MAIN DECK 5. INSTALL STAIR LANDING TOS EL.(+)14.693 AND PSV ACCESS PLATFORM
INSTALL COLUMNS AND VERTICAL BRACES C/W TEMPORARY SUPPORT TOS EL.(+)14.700 ON MAIN DECK PHM NORTH SISI NUBI
AND JUMELAI PROJECT
ON MAIN DECK

DR 19 NOV 2019
JML1
TOPSIDE FABRICATION SEQUENCE
DR 19 NOV 2019
SHEET 1
MI 20 NOV 2019
ID 20 NOV 2019

A 19 NOV 2019 DR MI ID ISSUED FOR PROPOSAL


6. LIFT UP UPPER DECK AND PUT IT ABOVE MAIN DECK 7. CONTINUE TO INSTALL PEDESTAL CRANE AND ALL MISCELLANEOUS ITEMS
AND REMOVE ALL TEMPORARY SUPPORTS

M EI N DO
ELANG INDAH

PHM NORTH SISI NUBI


AND JUMELAI PROJECT

DR 19 NOV 2019
JML1
TOPSIDE FABRICATION SEQUENCE
DR 19 NOV 2019
SHEET 2
MI 20 NOV 2019
ID 20 NOV 2019

A 19 NOV 2019 DR MI ID ISSUED FOR PROPOSAL


1. FABRICATE CELLAR DECK AND TRANSFER PUMP ACCESS PLATFORM, 2. INSTALL DECK LEGS, COLUMNS AND VERTICAL BRACES C/W TEMPORARY 3. LIFT UP MAIN DECK AND PUT IT ABOVE CELLAR DECK
LIFT UP AND PUT IT ABOVE CROSS BEAM SUPPORT SUPPORT ON CELLAR DECK

M EI N DO
ELANG INDAH

4. INSTALL VERTICAL BRACES AT DECK LEG ROW A2 BELOW MAIN DECK 5. INSTALL STAIR LANDING TOS EL.(+)14.693 AND PSV ACCESS PLATFORM
INSTALL COLUMNS AND VERTICAL BRACES C/W TEMPORARY SUPPORT TOS EL.(+)14.700 ON MAIN DECK PHM NORTH SISI NUBI
AND JUMELAI PROJECT
ON MAIN DECK

DR 19 NOV 2019
WPS3
TOPSIDE FABRICATION SEQUENCE
DR 19 NOV 2019
SHEET 1
MI 20 NOV 2019
ID 20 NOV 2019

A 19 NOV 2019 DR MI ID ISSUED FOR PROPOSAL


6. LIFT UP UPPER DECK AND PUT IT ABOVE MAIN DECK 7. CONTINUE TO INSTALL PEDESTAL CRANE AND ALL MISCELLANEOUS ITEMS
AND REMOVE ALL TEMPORARY SUPPORTS

M EI N DO
ELANG INDAH

PHM NORTH SISI NUBI


AND JUMELAI PROJECT

DR 19 NOV 2019
WPS3
TOPSIDE FABRICATION SEQUENCE
DR 19 NOV 2019
SHEET 2
MI 20 NOV 2019
ID 20 NOV 2019

A 19 NOV 2019 DR MI ID ISSUED FOR PROPOSAL


1. FABRICATE CELLAR DECK AND TRANSFER PUMP ACCESS PLATFORM, 2. INSTALL DECK LEGS, COLUMNS AND VERTICAL BRACES C/W TEMPORARY 3. LIFT UP MAIN DECK AND PUT IT ABOVE CELLAR DECK
LIFT UP AND PUT IT ABOVE CROSS BEAM SUPPORT SUPPORT ON CELLAR DECK

M EI N DO
ELANG INDAH

4. INSTALL VERTICAL BRACES AT DECK LEG ROW A2 BELOW MAIN DECK 5. INSTALL STAIR LANDING TOS EL.(+)14.693 AND PSV ACCESS PLATFORM
INSTALL COLUMNS AND VERTICAL BRACES C/W TEMPORARY SUPPORT TOS EL.(+)14.700 ON MAIN DECK PHM NORTH SISI NUBI
AND JUMELAI PROJECT
ON MAIN DECK

DR 19 NOV 2019
WPN4
TOPSIDE FABRICATION SEQUENCE
DR 19 NOV 2019
SHEET 1
MI 20 NOV 2019
ID 20 NOV 2019

A 19 NOV 2019 DR MI ID ISSUED FOR PROPOSAL


6. LIFT UP UPPER DECK AND PUT IT ABOVE MAIN DECK 7. CONTINUE TO INSTALL PEDESTAL CRANE AND ALL MISCELLANEOUS ITEMS
AND REMOVE ALL TEMPORARY SUPPORTS

M EI N DO
ELANG INDAH

PHM NORTH SISI NUBI


AND JUMELAI PROJECT

DR 19 NOV 2019
WPN4
TOPSIDE FABRICATION SEQUENCE
DR 19 NOV 2019
SHEET 2
MI 20 NOV 2019
ID 20 NOV 2019

A 19 NOV 2019 DR MI ID ISSUED FOR PROPOSAL