Professional Documents
Culture Documents
PT Weekly Report
PT Weekly Report
Total hrs 54
Figure 1 mould for compaction test Figure 2 2.5 kg hammer for compaction
Total hrs 54
Total hrs 54
Figure 2 apparatus for measuring the swelling of a sample during soaking for CBR test
Total hrs 54
Total hrs 54
Total hrs 54
SIEVEANALYSIS
Sieveanalysisisalsoknownasparticlesizedistribution( grading).
uartering refers to the process of obtaining a small relative quantity of sample by dividing a large quantities ofmaterial into quarters (
ur nearly equal parts) and combining the two opposite parts , then dividing then combiningtheseveralrounds untila smallrepresentativeis
btained.
Percent passingoneachsievewascalculated
%passing=100%-%retained.
Total hrs 54
Concrete refers to the mixture of binding material, fine aggregate, coarse aggregate and water. Coarse
aggregates may be natural or crushed stone, ranging in size between 5mm to 25mm, and the fine aggregates
usually natural sand ranging in size between 0.6mm to 2. 0mm.The water used should be fresh as the one that is
suitable for human consumption. Concrete is strong in compression but weak in tension. Concrete was graded
according to their strength.
Concrete work: concrete for pile was class 30 in the which was done under following main procedures
• Batching: refers to the process of measuring different concrete materials such as cement, coarse aggregate,
sand, water for making concrete.
• Mixing: In this process all the materials are mixed in required proportion until the paste show the uniform
color and consistency by using concrete mixer.
• Transportation: When mixing was done properly the freshly made concrete was then transported to the
intended site.
• Compaction: refers to the process in which air bubbles are eliminated from the freshly placed concrete in order
to increase the strength of concrete.
• Curing: is the process in which the concrete keeps its moisture for a certain time period to complete the
hydration process.
Monday 9
◆ Rainfall
Tuesday ◆ Atterberg Limit Tests (Liquid limit, plastic limit, linear 9
shrinkage, plasticity index) for C1 design was performed.
◆ Atterberg Limit Tests (Liquid limit, plastic limit, linear
Wednesday shrinkage, plasticity index) for C1 design was performed. 9
Total hrs 54