SCOPE OF WORK TO INSTAL AND RELOCATE TEMPORARY POWER FOR LIGHTING AND WALL OUTLETS AT LOT 201/202A

No Description Location Quantity Unit Remarks


1 LOT 201

1.1 Disconnect and relocate existing power source for SDB-C1 and SDB-D1 from AC Plant Room 1 lot
SDB-U-AC3
1.2 Install new 250amp breaker and cable feeder Transformer room 2 set Replace existing cover

1.3 Connect the breaker with cable feeder including tapping to buss bar at MSB- Transformer room 1 lot
3A for SDB-C1 at MSB-1A and SDB-D1 at MSB-2A
1.4 Replace existing relay protection at SDB-C1 and SDB-D1 panels with range Ex Mold Room area 1 lot Replace existing protection
150amp to 400amp
1.5 Disconnect temporary power for emergency to EWB Panel 1st floor from MSB- Transformer room
3A
2 LOT 202A

Install temporarry distribution panel from at DB-ROOF panel room and cable
2.1 feeder to 3rd, 2nd and 1st floor electrical room, complete with wiring and Roof top 1 lot Standard Infineon Panel
protection (Earth Fault Relay and Over load Relay), incoming out going
indicator light.
2.2 Install 3 set breaker @150amp and wiring Roof top 1 lot
2.3 Supply and install galvanized cable tray All floor 1 lot

2.4 Connect to Lighting and Power wall outlet panel at 3rd floor panel SD3-LP and 3rd Floor
SDB3-PP
2.5 Connect to Lighting and Power wall outlet panel at 2nd floor panel SD2-LP and 2nd Floor 1 lot
SDB2-PP
2.6 Connect to Lighting and Power wall outlet panel at 1st floor panel SD1-LP and 1st Floor
SDB1-PP
2.7 Disconnect and reconnect the power source of elevator/lift from ESDB 1st 1st Floor 1 lot
floor to DB Lift
2.8 All floor 1 lot
Install Voltage and Ampere indicator to all existing panel at each floor.
3 Repainting panel cover, reffer to Infineon standard color
4 Clean and repainting the wall of rooftop electrical room
1 lot
5 Repainting the floor with epoxy, reffer to Infineon electrical room and install
new rubber mat.
6 Fix all wires in each panel.
Transformer room and
7 Disconnect and re-route the lift power cable from current temporary source 1 lot
and connect to DB Utility to be in permanent source DB-FL 1 room

The result of this work must be safe and carried out properly
Rp1,400,000 9 Rp155,556
15 2333333.3 4666667