ESTIMATE REPORT
1|P a g e
4 CHOONDY 45 60
TOTAL 375 450
Registered Office: Vydyuthi Bhavanam, Pattom, Thiruvananthapuram 695 004, Website: www.kseb.in
2|P a g e
feeder is converted to one of the dedicated feeder of DIC, then three outlets are
required.
In normal condition it is possible. But when one transformer is under
maintenance, the entire load cannot withstand by the other two transformers, because
most of them are dedicated feeders and no possibility for back feeding. So supply
interruption may occur.
Hence I request to consider all these circumstances. If one of the
transformers is upgraded to 20 MVA, or constructing on more 12.5MVA transformer
bay, then the supply can be maintained smoothly. The Estimate was prepared as per
the DSR – 2018 and substation and Transmission data. The work is scheduled as
Deposit work scheme, as per the request of DIC.
Assistant Engineer,