Title: BUSINESS PROCESS PROCEDURE

Organization/Area:

Master Data-Bill Of Material


Change of Material BOM
File Name: Release: ECC 6.0

Responsibility:
Plant Maintenance Status

Work Instruction

Change Material BOM CS02

Purpose
Use this procedure to change Material BOM.

Trigger
Perform this procedure when you want to change Material BOM.

Prerequisites
All the details related to BOM like Material No, BOM Usage, Plant, Item Category etc. should be known.

Menu Path
Use the following menu path to begin this transaction:
Logistics  Plant Maintenance  Management of Technical Objects  Bill of Material  Material BOM 
Change

Transaction Code
CS02

Helpful Hints
 CS02 is the SAP transaction code for creating Material BOM.
 A maintenance bill of material (BOM) is a complete, formally structured list of the components
making up a technical object or an assembly.
 Field values can be queried using the F4 help wherever available. This can be done either by placing

the cursor in the field and pressing F4, or by clicking on the match code that appears next to
the field.
 You can click on a field and press F1 to view the Field help. This allows you to understand the field
and decide what contents should be entered.

Last changed on: Last changed by: Version: 1.0 Page:


1 of 6
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area:

Master Data-Bill Of Material


Change of Material BOM
File Name: Release: ECC 6.0

Responsibility:
Plant Maintenance Status

Procedure

Change Material BOM

 Enter the T-Code CS02 and click on icon to change Material BOM.

 You can also double click on the menu “Change” as highlighted in the below screenshot to change
Material BOM.

Last changed on: Last changed by: Version: 1.0 Page:


2 of 6
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area:

Master Data-Bill Of Material


Change of Material BOM
File Name: Release: ECC 6.0

Responsibility:
Plant Maintenance Status

SAP Easy Access

 This opens the screen as shown below.

Last changed on: Last changed by: Version: 1.0 Page:


3 of 6
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area:

Master Data-Bill Of Material


Change of Material BOM
File Name: Release: ECC 6.0

Responsibility:
Plant Maintenance Status

 Changing Material BOM – Initial screen

 Click on continue icon . This opens the following screen.

 The description of the fields for the above screen is given below:

Last changed on: Last changed by: Version: 1.0 Page:


4 of 6
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area:

Master Data-Bill Of Material


Change of Material BOM
File Name: Release: ECC 6.0

Responsibility:
Plant Maintenance Status

Field Name Description Sample data

Item Category Categorization of the items in a BOM. L


L-Stock Item
N-Non Stock Item

Component Material number of the components IN011200100500001


Quantity of the component.
Quantity 2

Unit The unit for the component quantity. EA

Valid From Specifies the start date for the validity 28.04.2014
period of an object
Valid To End of validity period of an object. 31.12.9999

 Click on the save icon to save the Material BOM.

 Note the Material BOM changed message at the bottom of the screen as marked above.

Last changed on: Last changed by: Version: 1.0 Page:


5 of 6
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area:

Master Data-Bill Of Material


Change of Material BOM
File Name: Release: ECC 6.0

Responsibility:
Plant Maintenance Status

 Click to return to go to SAP Easy Access screen.

Result
You have successfully changed the Material BOM.