Professional Documents
Culture Documents
Electrostatic Precipitators
Erection Manual
1. Range of Application
2. Normative Reference
2
1 Range of Application
1.1 This manual applies to the proper erection of electrostatic precipitator (ESP) and
1.2 When the special rules of similar type ESPs imported from abroad as well as
some products disagree with this manual, those special rules should be carried
out.
2 Normative Reference
Clause in the following standards that have been quoted by this manual will
Erection Projects
Portion
3.1 Storage of the equipment after its arrival at the jobsite should be as follows:
3.1.1 The place for storage should be properly arranged. It must be a solid area
with flood control and drainage measures and suitable for loading and unloading.
3
3.1.3 The packing, transportation, marking and storage of ESP’s parts/components
3.2.1 The open-case inspection of equipment should be jointly carried out by the
a. There are complete technical documents such as packing list, supplying list,
etc.
b. Model number, specification and quantity shown by the name plates on the
any parts that can not be repaired, they should be discarded and replaced
them.
4.1 The erection contractor must be familiar with the structure and performance of the
equipment, relevant design drawings and technical documents. He should make the
4.2 Work involving ground leveling, platform setting-up and preparation of lifting
cranes and special implements is to be carried out in accordance with the construction
organization plans.
according to JB/T5909.1-4.
4
4.4 The manufacturer should tell the detailed technology to the erection contractor
and when necessary, send personnel for technical guidance during the erection..
5.1.1 Types of connection of steel column or support bearing with foundation should
5.1.2 The embedded parts and bolts must meet the requirements on the drawing .And
the strength of concrete must meet the design requirements. For allowable deviation
5.2.1 Mark the centre lines and contour lines of each plane of the support structure
5
5.2.2 Allowable deviation in elevation of each loading point in the support structure is
5.3 Bearings
5.3.1 The bearings should be placed in strict accordance with the requirements of the
bilateral bearings. Temporarily fix the bearings. The temporary fixtures must be strong,
and they are removed or the fixing bolts are returned to where the drawing requires
after the bottom beam is erected but before the equipment is put into operation.
5.3.2 Deviation in elevation of each bearing as measured from its upper surface is
≤±3 mm.
5.3.3 All the welding between the support bearings and related elements should be
5.4.1 Mark the longitudinal and transverse centre lines on all bottom beams, lift the
deformation-resistance when applying welds. After a bottom beam is erected the gap
5.4.4 Upper gas screen plates in the dust hoppers are mounted after the collecting
plates are erected and adjusted. The gap between the bottom surface of the rapping
6
bar in the collecting row and the gas screening plate there should be in strict
the collecting plate’s free thermal expansion. The cut-out in the upper screening plate
5.5.1 When the internal walkways are put into place, pay attention not to weld their
expandable ends. For the parts that are to guide the collecting plates, they should be
5.6.1 Before erection, measure the actual length of each column and prepare filler
pieces of suitable thickness. Then mark the centre lines and contour lines of all
measuring planes.
5.6.3 Part of the platforms and stair ways can be erected after the inner roof is
installed to facilitate further installation. The stairways must be solidly and reliably
5.7.1 Voltage-withstand tests should be made on the porcelain insulators before their
installation. When mounting the insulators, special care should be taken to avoid them
mm. And allowable deviation between the centers of tie rod, dust screen tube and
5.7.2 Discharge major frames are to be assembled either partly on the ground or in
the electric fields. Refer to Figure 4. The upper middle and bottom minor frames are
usually assembled within the electric fields. After the minor frames are assembled, the
7
a. The allowable deviation of the centers of the two rectangular tubes in the same
b. Allowable deviation in distance between the suspension frame and the upper
c. After the discharge system’s frames are installed in the form of a cage, lift the
collecting plates in to it. Each plate should be corrected and the tolerances in
Use a handling device (See Figure 6) to put the collecting plates one by one
Each plate is attached with a clamp after it is put into the frame.
how the heads of the plates are attached for lifting. Figure 11 shows the
8
e. During the process of plates’ insertion into the gap between the suspension
frame and minor frames, the guiding frame should be released layer by layer.
Correct the plates after they are located. Allowable deviation in voltage
Figure 5 Figure 6
9
f. If the bottom portion of the collecting plates is fixed by using concave and
convex bushes, the tightening torque for the bolt should be 160 N.m.
5.9.1 Installation of tubular barbed wires. Check the wires and install them in strict
or upside down. The tightening torques at the round and oblong holes should follow
the requirements in the drawing, i.e. to enable the wires’ free thermal expansion but
not allow them to sway. Then weld the bolts dead. Allowable deviation in distance
≤7m ≤5 mm
>7m ≤10 mm
a. During the erection of spiral wires these found to have surface scratches,
obvious material defects or loose contact with the hooks must be discarded.
10
b. The spiral wires are to be stretched by a special tool with a cord (Fig. 12).
During the stretching of the wire, the wire must be allowed to turn freely. When
the wire is stretched to a point which is only 200~300 mm from the lower ring,
the erector should slow down his speed of stretching and gently insert the wire’s
lower hook into the ring. Overstretching the wire is forbidder. Any wire that is
5.10.1 Erection must be in strict accordance with the approved drawings. Hammers
can be mounted on to a rapping shaft only after the shaft’s coaxiality is kept less
than 3 mm. The allowable deviation between the centers of the rapping hammer
5.10.2 All welds applied to the shaft and the anvil should be made with electrodes T
506 or T507.
5.10.3 Check the direction of rotation of the shaft. Manually turn the shaft to see if it is
all right. After energizing the motor, make a trial run of the rapping shaft: it should
5.11 Erection of the inlet and outlet nozzles and gas distribution plates
5.11.1 Depending upon the lifting capacity of the crane, the nozzle can be lifted after it
is entirely assembled.
5.11.2 Put the gas distribution plates in place exactly as per the drawings.
11
5.12 Erection of the outer roof and the penthouse. Pay attention to the outer roof’s
thermal expansion.
5.13 Erection of ash discharge equipment, inspection doors and other mechanical
parts. After the doors are installed, check to see if they can be opened smoothly and
closed hermetically.
5.14.1 The thermal insulation is designed based on the manufacturer’s practice and
5.15 Lagging sheets should be securely mounted and give a good appearance.
6.1 While making erection plans, preventive measures for deformation due to welding
6.2 Missing welds and false welds are strictly forbidden, especially for internal parts.
6.3 Make sure the ESP casing is welded gas-light. Pay attention to the repair welding
6.4 The adjustment of the spacing between the collecting plates and the discharge
wires is extremely important to the ESP performance such as collecting efficiency. The
collecting rows and discharge frames must be carefully inspected and adjusted to
6.5 Take special care of the welding at the following places due to limited space
or too many stiffeners. Welds should pass 3-level inspection to avoid missing
or false welding.
a. Welds between the 4 corners of a hopper and the bottom beam bearing;
b. Welds between the stiffeners around the upper opening of a hopper and
c. Welds between the casing pillars and the longitudinal beams and
12
between the girder and the longitudinal and the horizontal beams;
d. Welds between the hoppers and the connecting plates of inlet and
7.1 Dismantle and remove all temporary devices and scaffoldings. Apply remedial
7.2 Make an overall cleaning inside the ESP. No tools, metal scraps or other odds and
ends are allowed to be left inside. Seal the access doors tightly.
7.4 Check the oil level of the speed-reducer to see that it meets the specified
requirement.
7.5 ESP casing and auxiliaries are firmly and properly earthed. Earthing bolts/nuts
and locking bolts/nuts are well connected and earthed in accordance with regulation
7.6 Remove the temporary fixtures for the support bearings or return the fixing bolts to
7.7 Check the dielectric resistance of the discharge system to see that it meets
JB/T5909.1-4.
8.2 The no-load voltage step-up tests of ESP should be made as per Appendix B,
8.3 Make gas-tightness tests of ESP casing by means of smoke bombs, kerosene
penetration etc.
13
Appendix A
(Normative Appendix)
14
Appendix B
(Normative Appendix)
B1 Contents of commissioning
In order to make the ESP wants to reach the expected effect, it must have good
erection quality, and the commissioning work after the erection is the essential way for
B2.1 The commissioning work of ESP should be executed by the erection contractor.
The relevant people such as the representatives from the construction contractor,
manufacturer and user etc. should join in. Appoint a commander in chief leaders for
sheet. If there is any problem, it should be coordinated and settled in time. During the
commissioning, arisen problems, solutions and all kinds of data should be recorded
seriously. After finishing the commissioning, write down the conclusions in the
15
B2.2 The commissioning staff should read the equipment specifications and relevant
technical data seriously and be familiar with the equipment and systems. They should
work according to the items, methods, steps and requests specified in the
commissioning program.
B2.3 Prepare the consumable materials, greases and apparatuses and tools which
are needed in the commissioning work. Main apparatuses and tools are as follows:
preferred);
g. Incandescent bulbs with rated load of 220V, 100W*2, 1 set (of self make)
h. Insulating rod 10KV triarticular, 1 set (for the use of electric discharge);
Commander in chief: 1
Operator: 2
Electrical 2~3
Coordinator 1~2
Total: 10~15
16
a. Communal facilities are all ready (water, compressed air, electricity and so on);
B2.6 Records of checking and testing results will be effective only with the cosigner by
the manufacturer, the erection company and the user. After the commissioning, a
final report will be prepared with the three parties’ signatures and then will be
filed.
B3.1 Check the main insulating parts of H.V. net, such as H.V. isolating switch,
They all should pass voltage resistance test. Use a 2500V megohmmeter to
measure the H.V. net. Before the insulation piece is contaminated, its insulation
B3.2 Before the assembling and commissioning of H.V. silicon rectifying transformer,
check to see that the air in the buchholz relay should be discharged.
B3.3 Check to see that the H.V. isolating switches can be operated agilely and can
reach the right position. For switches that have secondary contacts, the contact
B3.4 Check the cable head, to see there should be no oil leak phenomenon.
B3.5 Items which should be tested before the commissioning of H.V. silicon rectifying
transformer should follow the operating instruction manual for electric control
equipment.
B3.6 If the H.V. output of the silicon rectifying transformer is using H.V. power cable,
17
a. H.V. cable oil strength test: its one-off breakdown voltage should not be less
The voltage of direct current withstanding voltage test for the special direct current
If other specification power cable is used for substitution, its withstanding voltage
standard and the duration should follow power cable direct current withstanding
Test Standard)”
During the tests: Voltage can be stepped up by increments of 0.25, 0.5, 0.75, 1
time the test voltage. Each step will stay one minute. Leakage current value will be
B3.7 If one of the following problems appears in the cable direct leakage current test,
it means cable insulation may have defects. The defective part should be found and it
B3.8 The test of control cabinet should be done according to the operation manual of
B3.9 All sorts of insulators installed on ESP, including feed-through insulator, emitting
support insulator, rapping shaft insulator and so on, should be inspected for their
exterior surface before the installation according to the electric insulator standard. The
B3.10 All sorts of insulators should undergo the insulation resistance measurement
18
and AC withstanding voltage test before the installation and this should accord with
B3.11 Motors on rapping, dampers and ash discharge gear should be inspected
B3.12 The type and parameters on the nameplate of electric heater should accord
with the design requirements. Before the installation, visual inspection should be done
with no damage found. Using a 500V megameter to measure the insulation resistance,
and the value should be more than 50MΩ. If it is less than 50MΩ,the heater should be
B4 ESP sealing test: After finishing the ESP installation, and before laying the
insulation, sealing inspection should be done. For sealing inspection, either kerosene
B4.1 Purpose: Using smoke from the 65-1 military fuming can to check the sealing
a. Properly sealing the ESP proper, including: I/O ducts, hoppers, and
inspection doors etc. should be sealed and closed with suitable means;
b. Each time prepare three 65-1 military fuming cans for every ESP, one of the 3
cans is spare;
c. One axial flow blower should be installed at the inlet of specified inspection
door;
e. Enough fire-fighting materials should be prepared and all should be put at the
assigned place;
19
g. Organize 6~10 inspectors, each one takes charge of a section.
b. Lighting up the fuming cans (for method of application, refer to the operation
instructions of fuming can). After the fuming can is fuming normally, people
d. According to the division of work, check if there is any smoke leakage and
use white paint to mark the exact place where there is a leakage;
e. Open the inspection doors and remove the inner smoke. Stop the axial flow
f. Repeat the smoke bomb test until there is no leakage in the whole sealing.
a. During the working time, all firing people must wear gas masks;
b. After the fuming, all staff must leave the inner of the ESP. After closing the
d. When the cans are fuming, no repair welding for leaking area is allowed.
B5.1 The inspection and adjustment of the center-to-center distance between emitting
a. Collecting plates should be 100% corrected on the ground, they are 100%
b. The quality of emitting wires should be checked one by one. If there is any
defect or it is extended beyond its working length during the installation, the
c. Check all walkways, and the front and back of each walkway should be
20
checked;
e. During the inspection and adjustment, in the vertical and horizontal direction,
all walkways should take the distance from the out wall of every vertical
square pipe for the emitting minor frame to the flange outboard of wind
f. In the vertical direction, check 5~9 points for one side of each walkway, i.e.
one point of each horizontal supporting pipe on emitting minor frame will use
tailored “T” gauge for testing, and records should be made. Unqualified parts
B5.2 All sharp angles and burrs in every part of the collecting and emitting electrodes
should be removed. The inner of casing field except emitting wire and collecting plate
should be checked carefully. In the field, the places where the distance between
emitting system and other insulators is less than the distance between different
B5.3 Bolts for every part of collecting plate, emitting major frame, emitting minor frame,
collecting & emitting rapping should all be tightened and welded dead.
B5.4 The contact position of emitting & collecting hammer and anvil should accord
B5.6 Check if the damper motor, rapping speed reducer motor, ash discharge motor
21
etc. are rotating smoothly or not. The tightness of chain is moderate. Each lubricated
B5.7 The sealing tightness of adjusting gate, baffle, induced draft fan, ash discharge
device, roof panel, inspection door which are connected to the duct are very well.
B5.8 The welding seams for each part should be deep-set. There is no wrong welding
B5.9 Each support insulator should contact stably and should be under uniform stress.
Each shaft insulator and feed-through insulator should be clean and dry.
B5.10 The ESP proper’ s earthing resistance should be less than 2Ω.
B5.11 Use a 2500V megohmmeter to measure the insulation resistance of the voltage
regulating net, and the value should be more than 1000 megohm.
B5.12 The ESP shell and the positive electrode cable of H.V. T/R should be perfect
and tightened.
B5.13 The operating mechanism of H.V. isolating switch should be flexible and in the
exact position.
B5.14 Use a 500V megohmmeter to check the rapping motor, damper motor, ash
discharge motor and the insulation condition of cables. Their insulation resistance
B5.15 Check the wiring between each part is right or not as per the drawings.
B6.1 After the wiring inspection of the ESP electrical system is finished, energize the
ESP and then make the driving test of each system and no load commissioning test
B6.2 Low voltage operation control unit should be powered on for check. Main items
include: Alarm system test, rapping loop inspection, ash discharge loop inspection,
B6.3 Before the ESP is powered on, wires which connect each cabinet and ESP lower
22
voltage components should be disconnected from the terminal block. After it is
powered on, each power switch on the cabinet should be started and each supply
B6.4 During the alarm system is manually started or automatically started, its
instantaneous, delayed sound and light signal should act exactly and relieve reliably.
B6.5 Methods and requirements for rapping loop inspection are as follows:
a. Trial operation: first the contactor in the panel should be disconnected from the
power line of the motor, then the switch should be closed and current should be
delivered.
Manual mode: switch on and switch off for 3 times. The contactor’s switch on and
switch off should be correct. Signal light word board should be as per design
requirements.
Automatic program control mode: set a rapping cycle, repeat action for 3 cycles.
Rapping time sequence should be correct. Switch on and switch off of main loop and
signal light word should be correct. Testing rapping time on site can be adjusted.
After tests are finished, power should be cut off and the motor connection should be
recovered;
Manual mode: After startup. Check the rotating direction of the motor, it should
be in accordance with the requirement of the control unit. Switch on and switch off for
3 times. Starting current value, no load current value and each phase current value
should be measured.
Automatic program control mode should be executed to work for 3 cycles. All
After the test is correct, power should be cut off and the coupling of shaft
23
c. Cold-run commissioning operation under the rated load; the switch should be
setting value of protected unit is exact or not. Switch on and switch off 3 times and all
should be normal.
Check the contact point where the hammer is rapping at the anvil. Its all pre
reserved values should be as per design requirements. Rotating is agile and there is
Automatic program control mode: Try to rap for 3 cycles and the execution
should be correct.
After the mechanical and electrical inspections are qualified, it should be normal
when the continuous rapping is going on for not less than 8 hours.
B6.6 The method and requirement for the inspection of ash discharge loop and ash
a. During the trial operation: Power supply wiring of the motor should be taken
apart for the lower end of the terminal block, then the switch should be closed and
Automatic mode: manually simulate the operating condition of ash level should
After the test is passed, power should be cut off and the motor connection should
be recovered;
Manual mode: Start the motor, and make sure its rotating direction is correct. The
starting current value and three phase current value of the motor should be measured.
24
Automatic mode: Simulative start and stop for 3 times. The position signal and
After no load trial run is normal, power should be cut off and mechanical load
should be recovered.
Manual mode: When it is started, starting current value and three phase current
value should be measured and current setting value of thermal element should be
checked.
Automatic mode: Simulative starting for 3 times, trial operation should be normal.
For the thermal state ash level linkage test, it should be done under the actual
After mechanical and electrical inspection is qualified, continuous trial run should
be in process for 8 hours. It is required that the rotation should be agilely and there is
B6.7 Inspections of the undercurrent heating alarm and the temperature test loop. Its
value, and check the current setting value of thermal element. Signal and
b. If the heating loop is equipped with undercurrent alarm, any of the electric
be activated;
c. Temperature control mode: Simulative start and stop for twice. Contactor and
the temperature drops down to the lower limit setting value, the heating
25
device should start automatically.
B6.8 Low voltage control loop commissioning should be executed according to the
Under the condition of disconnecting the L.V. side wire of the silicon T/R, make
local and remote switching test, test items including simulating gas, over current, trip
drive with temperature limitation protection, liquid level, temperature warning & safety
linking, air cooling interlocking, etc. All the lighting, sound and signal should be
correct.
B7.2 Commissioning of H.V. control loop includes: setting of the controlling inserts and
adjustment of limiting parameters for no load test equipment in an open loop and a
closed loop.
B7.4 Commissioning of H.V. silicon T/R control loop should be carried out as per the
B7.5 Open loop test method and requirements of H.V. silicon T/R control loop as
below:
a. The open loop test can be done at a simulating table or controlling cubicle,
inserts. If tested on a controlling cubicle, disconnect all wires in the main loop,
and connect two lamps (220V, 100W for each one) to be nominal loading;
26
b. For detailed test method see the operation manual of electric controlling
equipment
B7.6 Closed loop test should be executed according to the commissioning manual of
B8.1 Intention
In order to guarantee the safe operation of the ESP, the discharging rapping,
collecting rapping, gas distribution screen rapping and ash-discharge devices must
undergo trial-run separately during the installation and before ESP is put into
operation, to check the running condition of driving and rapping parts, and to make
B8.2 Preparations:
the rapping frame, rapping driving shaft and rapping hammer which have
drawings;
e. For collecting rapping, the hammer should strike on the centre of the anvil ±4
mm, and the angle of the adjacent rapping hammer should comply with the
f. For the discharging rapping, the matching of pin wheels should be correct.
27
Clear the shaft insulator and remove rubbish.
Check the air tightness of driving mechanism, the angle of two adjacent
collecting rapping.
B8.3 Trial-Run
a. Carry out 2-hour no load running test for the collecting motor, to check
whether there are abnormal heating phenomena, vibration and noise, and
it;
c. Rotation as per the rapping direction during trial run, not to rotate in the
d. Start up the collecting shaft system, stop it by pressing the emergency button
when the motor reaches its maximum speed, if the shaft system has rotated
less than one cycle, start it up again as per the above method. Do not switch
e. Make trial run for 1 hour according to the requirements. Inspect completely
28
a. Switch off power to all the motors, seal the local switches;
b. It is not allowed to make adjustment and repair when the ESP is running;
inspection.
B9.1 Before the installation of electrical heaters, the types and parameters marked on
the nameplate should be checked to see whether they are according to the design
requirements or not, and the insulation resistance, which should not to be less than 50
B9.2 Before the application of voltage rating, measure the insulation resistance first to
confirm whether it is as per the requirements, if there is a long time before ESP’s
B9.4 The test of Thermostat-controlled electrical heaters can be executed only after
B10.1 After the HV thyristor rectifier passes the no-load performance test, the ESP
29
B10.2 Sequence of cold load commissioning without gas:
Put the LV operating & control devices, especially the heating loop, into operation
first. Check the devices to see that they work properly. Then put the HV system into
B10.3 Before the HV system is put into operation, make sure that the LV system
a, The rapping systems are working properly , the rappers for each field operate
in the design order , and the rapping time and cycle should meet the set values ;
b. The ash conveying and unloading systems are working properly, and the
unloading time and delay time should meet the set values;
B10.4 Procedure of voltage step-up test: First carry out the static voltage step-up test;
Notes:
(1) By static voltage step-up test, it means that the ESP’s rapping systems are off
and the I.D. fans at the ESP’s outlet are off, too. That is, the fields are in a static state.
(2) By dynamic voltage step-up test, it means that all the LV and HV systems of
the ESP are operating except that there is no gas passing through.
a. Before the voltage step-up test in individual fields is carried out, first put the
heating system for insulator chambers into use. Open the inspection doors of
chambers, remove all the humidity on the chamber walls and on the insulators, then
close the doors and turn on the HV isolating switches the components of which should
be exactly positioned. After the field is energized, turn on the oscillograph and pay
special attention to the ware form of the current feed-back signals. Press the start-up
button and both the current and voltage should rise slowly. Watch closely the meters
on the control panel and the current feed-back wave form. When there is a failure in
30
the protective link, the HV electric equipment will be damaged. During the normal
voltage increase, all the meters on the control panel should have corresponding
indications and the current feed-back wave form should be symmetrical dual
half-wave.
b. During the initial period of voltage step-up, if the primary and the secondary
currents rise rapidly but there is no indication on the voltmeter, there is a short circuit
in the secondary loop. When there are primary and secondary voltages only and they
rise rapidly, the secondary loop is open. When there are indications for the secondary
voltage and current while the primary current is greater than the rated value, the
primary voltage is around 220V and the angle of ignition is greater than 95%, there is
brought down and the ESP turned off immediately. After trouble-shooting is carried out,
c, During the voltage step-up test , when the secondary voltage is far below its
rated value , there is flashover in the HV net or in the related field . If there is no
flashover in the HV net or the field, but the flashover-controlling link in the HV control
adjustment should be made on the taps of the HV thyristor T/R set, on the taps of the
reactor and in the control section until the “false flashover” disappears.
d. During the voltage step-up test, all the meters should be calibrated. HV static
meters can be used to measure the outlet of the HV T/R. For the convenience of
calibration, the indication on the secondary voltmeter can be calibrated when the
secondary voltage is raised to 40~50 KV and when there is no flashover. At the same
time, use a megameter to measure the feed-back sampling resistance and take it as a
fixed value. Then, according to Ohm’s law the indication on the secondary ammeter
can be calibrated.
31
e. The adjustment of the taps of the HV T/R and reactor can be made on the
basis of the current feed-back wave form. The principle is: Adjust the tap until the
wave form of the current feed-back signal becomes round and smooth with a
maximum angle of ignition. To make the wave form as close as the ideal form is
mostly desired.
Since the capacity of a HV T/R is determined by the current densities on both plate
and wire as well as the breakdown voltage under the condition that there is gas
passing the ESP , when the voltage step-up test is made in an ESP with air only , due
to the greater current density of the air , the capacity of a HV T/R energizing a single
field would usually not be fixed . That is, the secondary current would be locked after it
reaches the rated value, while the secondary voltage can’t reach the breakdown value.
In such a case, two HV T/R sets of the same capacity can be linked in parallel to
after each of the two HV T/R sets is separately adjusted for the same field and it has
been confirmed that there is no trouble either in the power source or in the field to be
tested . To energize in parallel, connect the two T/R sets after the damping resistors.
This can be realized either by HV isolating switch to switch over onto a linking bus bar
ground) . During the energization by two T/R sets, start-up should be synchronous by
means of the selection switches of “Manual step-up” and “Terminate” to step up the
voltage of the two T/R sets at the same time. If the same of the current value of the
two T/R sets is not up to the rated value, keep the rise of the voltage until there is
flashover in the field . At this point, the secondary current is the sum of the two T/R
set’s current values and the secondary voltage is the average of their secondary
voltage values.
32
b, During the no-load voltage step-up commissioning , special personnel should
be assigned to supervise if the HV T/R sets are functioning properly . When the T/R
sets are located on the ESP’s top, there must be longer primary power cables, so the
input voltage on the T/R set’s primary side must be measured and compared with the
indication of the primary voltmeter on the control panel. If the difference is big, make
trouble-shooting.
c. During the HV tests of the fields , make records of all date , such as the
secondary current ; the primary voltage and the primary current each time when the
secondary voltage is increased fields should be drown. The V-I curres for all the fields
made until the curve is up to requirements. For fields using barbed wires with a
voltage distance of 150 mm/200 mm, their secondary voltage can be as high as 20
KV/65 KV or more. For fields using non-barbed wires with a voltage distance of 150
spiral wires, only tests for V-I curres are made and no test for breakdown voltage is
allowed.
B10.6 Dynamic no-load voltage step-up test: If conditions are available, the ESP can
be in continuous operation for 24 hours. Then make an overall inspection on all the
working loops to check their status. Solve all troubles thus found.
B11.1 After the ESP has passed the above static and dynamic no-load voltage step-up
tests, its electric equipment has reached such a condition as to allow flue gas to feed
in. At this point, its mechanical portion should still meet the following:
a, Both inlet and outlet ducts of the ESP have been installed . The boiler is ready
for operation. The I .D. fan has passed the trial run.
b. The whole ash-unloading and conveying system has been installed. The water
33
pumps for ash flushing have passed trial run. The water volume for ash flushing has
B11.2 Flue gas enters the ESP. All inspection doors are tightly closed. LV power suppy
and heating system is on to let temperatures in insulator chambers higher than flue
gas dew point, hence no electric creepage on insulators’ wet surface. By using flue
gas to warm up the ESP , the insulation resistance in the fields is increased to over
B11.3 When the boiler is fired by oil at the initial stage, no HV can be put into use. This
is to avoid any explosion caused by oil within the ESP. This is also to prevent the
plates and wires form forming oil film, which will lead to corrosion. HV can put into use
only the ESP has a load of over 60% and only coal powder is fired (oil guns are
withdrawn in principle).
For boilers using coal gas for ignition, safety operation regulations should be
strictly followed. No HV can put into use before the boiler runs properly in order to
avoid explosion.
Step up voltage in all fields. Compared with the no-load tests, this time both the
B11.4 Select the optimum operation mode as per the field conditions and make the
following settings:
a. The under voltage value should be set to be lower than the lowest corona-initial
voltage;
b. The measurement of the spark flashover threshold voltage should base on the
flashover status in the fields. Adjust the threshold voltage to enable it input the
blockage signal;
c. Draw the V-I curres of operating fields with hot gas and record the values and
B11.5 Suitably adjust the spark ratio as per the operation conditions of each fields.
34
Normally the spark ratio in the inlet field is 20~40 sparks/minute, in the middle fields,
10~30 sparks/minute and in the outlet field, 5~10 sparks/minute (or stabilized at a
higher corona power). For dust with high resistivity, the spark ratio can be increased to
a suitable extent. The actual spark ratio obtained after the efficiency test should
govern.
B11.6 If there is high dust concentration, great gas velocity and uneven gas flow
distribution in a field, there will be frequent flashovers, which can eventually turn to
arcs. In such cases, the sensitivity of the arc-quenching link can be adjusted to
restrain the produce of arcs. However, if the flashover is proper, the arc-quenching link
B11.7 During the operation of ESP with flue gas, the operating modes of the fields are
different. It is necessary to adjust the taps on the T/R set’s primary side or on the
rector, bassed on the actual operating mode, to make the current and feed-back wave
B11.8.1 For the rapping loop, mainly adjust the rapping time and the rapping cycle.
Their settings are basically based on the results of efficiency tests. Ideal settings can
also obtained by repeated adjustments after checking the status of dust adhering to
the plates and wires when the ESP has stopped running.
For hoppers with upper ash-level indicator and control, the ash-unloading time must
be adjusted according to the actual ash volume from each field. Principle for this is to
keep the hopper filled with ash for 1/3 of its height. For the elongation of the
ash-conveying time, the principle is that all the ash within the conveying line can be
entirely transported. For hydraulic ash conveying system, the volume of the flushing
water should be adjusted to such an extent that all the ash deposited in the ash silo
can be flushed.
35