Title: BUSINESS PROCESS PROCEDURE

Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

Work Instruction

Create General Maintenance Task list IA05

Purpose
Use this procedure to create General Maintenance Task list.

Trigger
Perform this procedure when you want to create a General Maintenance Task list.

Prerequisites
 All the details related to Maintenance Task list like Planning Plant, Work Centers, Planner Groups and
Strategy should be created/ configured before doing this transaction.
 The user should be familiar with all the terminology related to Task lists like Group, Group Counter,
Strategy etc.

Menu Path
Use the following menu path to begin this transaction:
Logistics  Plant Maintenance  Preventive Maintenance  Work Scheduling  Task Lists  General
Maintenance Task Lists Create

Transaction Code
IA05

Helpful Hints
 IA05 is the SAP transaction code for creating a General Maintenance Task list.
 General maintenance task lists are task lists that are used for general maintenance tasks. They do not
refer to a specific technical object. Using general maintenance task lists, you can define and manage
sequences of maintenance tasks centrally, and use them for work scheduling.
 Field values can be queried using the F4 help wherever available. This can be done either by placing
the cursor in the field and pressing F4, or by clicking on the match code that appears next to the
field.

Last changed on: Last changed by: Version: 1.0 Page:


1 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

 You can click on a field and press F1 to view the Field help. This allows you to understand the field and
decide what contents should be entered.

Procedure

Create General Maintenance Task list

 Enter the T-Code IA05 and click on icon to create General Maintenance Task list.

 You can also double click on the menu “Create” as highlighted in the below screenshot to create
General Maintenance task list.

SAP Easy Access

Last changed on: Last changed by: Version: 1.0 Page:


2 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

 This opens the screen as shown below.

 Enter the group name for task list “GT1” and click on the enter icon as marked in the
above screen.
 This opens the screen as shown below.

Last changed on: Last changed by: Version: 1.0 Page:


3 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

 The description of the fields for the above screen is given below:

Field Name Description Sample data

Task list description Describes the routing. general task list for tpcil

Planning plant Key that identifies the maintenance 1i01


planning plant.

Work center Key identifying the work center. MECH

Task list usage Key specifying the areas in which the 4


task list can be used. For Plant
maintenance it should be “4”

Planner Group Key which identifies the planner group MBP


responsible for maintaining the task list.

Status You use the status key to indicate 3


the processing status of a task list.
Use Released (General) with code
“3”.

Key identifying a maintenance strategy .


Maintenance strategy B

Last changed on: Last changed by: Version: 1.0 Page:


4 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

 The completed screen for this is as shown below.

 Click on the tab “Operation”.


 This displays the screen as shown below.

Last changed on: Last changed by: Version: 1.0 Page:


5 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

 The description of the fields for the above screen is given below:

Field Name Description Sample data

Control Key Determines which business transactions PM01


should be executed for the object that
belongs to the task list or order (for
example scheduling or costing).

Operation Description Describes the operation. Replace the spares

Work Amount of work involved in performing 4


the activity.

Unit Unit for Work. HR

No Number of the capacities required of the 2


capacity category to carry out the
operation.

Unit Unit for Duration. HR

Last changed on: Last changed by: Version: 1.0 Page:


6 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

Field Name Description Sample data

Calculation Type Calculation key for duration, work or 1 – Calculate Duration


number of required capacities in the
activity.

 The completed screen for this is as shown below.

 If user wants to enter the component for an operation select operation and click on
Components as marked in the above screen shot.

 Click on the save icon .


 This displays the screen as shown below.

Last changed on: Last changed by: Version: 1.0 Page:


7 of 8
10/12/22
Title: BUSINESS PROCESS PROCEDURE
Organization/Area: Master Data-Task List

Creation of General Task List


File Name: Release: ECC 6.0

Responsibility: Plant Maintenance Status

 Notice the General Task list created message at the bottom of the screen as marked above.

 Click to return to the SAP Easy Access screen.

 0You have completed this transaction.

Result
You have created a General Maintenance Task list.