Professional Documents
Culture Documents
Contents
1. Introduction....................................................................................................................................................................1
1.1 General.......................................................................................................................................................................1
1.2 Location.....................................................................................................................................................................1
1.3 Accessibility..............................................................................................................................................................1
1.4 The Objective of Upgrading of Yeka Lalessa SSI Project......................................................................................2
1.5 Previous Construction and Traditional Irrigation.................................................................................................2
2. Scope of the Irrigation Infrastructure Design..............................................................................................................3
3. Command Area................................................................................................................................................................4
4. Canal Offtake Arrangement............................................................................................................................................5
4.1 Main canal offtake.....................................................................................................................................................5
4.2 Off take on primary and secondary canals.............................................................................................................5
5. Layout of the Canal System............................................................................................................................................6
5.1 Scheme layout...........................................................................................................................................................6
5.1.1 Water Abstraction.............................................................................................................................................6
5.1.2 Conveyance System...........................................................................................................................................7
5.1.3. Distribution System..........................................................................................................................................7
5.2. Canal System............................................................................................................................................................9
5.3. Land preparation.....................................................................................................................................................9
6. Canal Capacity...............................................................................................................................................................11
6.1 General.....................................................................................................................................................................11
6.2. Climate....................................................................................................................................................................11
6.3. Need for Irrigation.................................................................................................................................................12
6.4. Irrigation efficiency...............................................................................................................................................12
6.5. Irrigation Water Requirement..............................................................................................................................13
7. Hydraulic Design of the Canal Section........................................................................................................................14
7.1 General.....................................................................................................................................................................14
7.1.1 Maximum Velocity and Roughness Coefficient.............................................................................................16
7.1.2 Canal cross-sections and Side slopes.............................................................................................................16
7.1.3 Bed width / Depth ratio..................................................................................................................................17
7.1.4. Canal Embankments.......................................................................................................................................17
7.1.5 Freeboard to embankment top......................................................................................................................17
7.2 Tertiary Canal.....................................................................................................................................................17
7.3 Field Canal...........................................................................................................................................................17
7.4 Drainage Canals......................................................................................................................................................18
8. Canal Structures............................................................................................................................................................18
8.1 General.....................................................................................................................................................................18
8.2 Division Box............................................................................................................................................................19
8.3 Off takes or turn-outs (plot intakes).....................................................................................................................19
8.4 Road crossing and foot bridge...............................................................................................................................19
1. Introduction
1.1 General
Yakka Lalessa Small Irrigation Scheme was constructed in1974 E.C. West Arsi Zone
Negeelle Arsi Woreda. It serves about 160 Households. Since its construction major
maintenance has been made to the scheme.
Yeka Lalessa SSI project was conceived as part of an effort to guarantee and enhance food
security and improve the living standard of the farmers through a small-scale irrigation
development. The project is irrigates about 60 hectares of land by farmers managed small-
scale irrigation scheme.
1.2 Location
Yeka Lalessa upgrading irrigation project area is located in the West Arsi Administrative
Zone, Nagelle Arsi woreda at about 52 km distance North of Shashemene town, capital of the
zonal administration, and 12km from Nagelle Arsi town, the capital of Nagelle Arsi woreda.
The diversion site is located at
Latitude-802439 (UTM) Northing
Longitude-491511 (UTM ) Easting
Altitude of about 2760 masl.
1.3 Accessibility
Access to the project area is possible from Nagelle Arsi (Nagelle Arsi woreda town) by using All
weather road connecting Nagelle Arsi to Goljota town, this road crosses the project area at about
12km from Nagelle Arsi town .And the weir axis is located at about 1km from this road in the south
direction. Hence, before commencement of Main Canal construction of access road of about 1km is
necessary to make the construction machinery, equipment and labor mobility easy.
The Main Canal irrigation design shall ensure reliability, equity and flexibility of water
delivery to farmers. It will aim at reducing conflicts among water users and will lead to
lower operation and maintenance costs.
Updating the existing, if available, computation of the actual evapo-transpiration, crop
water requirement, irrigation demand/duty using the existing and recent agronomic,
climatologic and soil data using more appropriate methodologies.
Establish design criteria for irrigations structures to be approved by the client and to be
used in the final design stage,
Design proper Main Canal irrigation system compatible with local conditions and
management capabilities,
Establish flood protection measures for the command area and canal structures and
design the respective drainage system accordingly,
Planning and layout of the irrigation system, which include irrigation canals, drainage
channels, inspection roads and alignments, canal spacing, canal length, location of
structures, and water profiles along canal and drains at specified reaches, which is most
economical, easily manageable and aligned with topographic feature and geological
investigation.
Determination and estimation of water application conveyance and other losses and
irrigation efficiencies and consideration of those parameters in design steps.
Check and test hydraulic and structural designs of main canal considering total demand
and the required capacity and the base flow availability,
Prepare general plans and drawings for all irrigation infrastructure and irrigation systems
designs,
Prepare comprehensive specifications and bill of quantities for irrigation scheme and
feasible construction schedule accordingly. The work items and construction schedules
3. Command Area
The boundary of a command area is dictated by the topographical features like natural
drainage, foot hills etc. The size depends on the proposed Full Supply Level (FSL) of the canal
at intake level. In Beta irrigation project, the command boundary is delineated between the
foot slopes of mountains on both right and left banks and Huluqa River. The proposed
potential command area of Beta irrigation project, was 70ha. However, due to the rugged
topographic feature of the land, the proposed size of area could not be obtained during actual
delineation of the command area after the detailed topographic map has been prepared. The
total area delineated during topographic surveying is 97.7ha, out of which only irrigable net
area of 36ha, but when the Right and Left of Earthen Main Canal upgraded to Lined, the
irrigable net area increase to 50ha could be obtained on both banks.
The right bank command area extends up to 3km length from the diversion weir. The
width of the area is in the order of 200m. The total area found to be irrigable is 35ha. There is
180m ideal main canal length to reach the irrigable area.
The left bank command extends up to 2km length form the diversion weir site. The
nature of topography of the area on this side is mainly disturbed with small rolling hills and
undulating feature. Hence, only a total of 15ha of area is found potentially irrigable.
The topographic feature of the command area is such that there is no drainage line crossing
the canals. Therefore, no cross drainage structures were proposed.
hydrology, hydro geologic condition of the stream is discussed in detail on the study and
design part of headwork.
The following photo shows the headwork of the scheme (Photo taken on 28/9/2022)
The location of headland structures in relation to the maximum ground level is the
unit of the provision of drainage.
The irrigation is provided to rotation in the tertiary and field canals. Whereas main
canal and secondary canal flow is continues flow type in the irrigation hours a day;
Second, target application depths derived from an analysis of share of the diverted water with
respect to the area of the field unit and crop water requirement.
Third, with the above relation and with topographic reference Maximum water level in the
tertiary off take along tertiary canal has been determined.
Fourth, the crest level of the Tertiary off take has been determined based on the respective
width of water way. In addition the tertiary irrigation layout have been set mainly basing the
topographic and soil properties, crop characteristics, and compatibility of the system with the
farm operation. The detail design process finally set to the flow rates and their duration that
maximizes application efficiency. So it is proper the design of the tertiary irrigation system
is used out from the field condition.
The tertiary irrigation system derives the water from the main canal/secondary systems. It is
proposed for to be made earthen canal. Water level regulators, Check drops shall be applied at
tertiary based on field topography and check of the field canal. As principle Sliding stop log
are used for distribution to each field canal.
Consequently the most important issue in the layout process have been tertiary unit of the
distribution system. Tertiary canal normally receive water from Secondary canal. This canal is
aligned along the terrain ridges.
The following are important elements in the preparation of layout:
Important topographical factors;
Field slope and its uniformity
Off take points and levels are the most in the design of secondary canals.
Boundaries of the tertiary units are determined based on topographic features
particularly drainage channels
Sizes of the canals are determined based on the requirement in the field unit
and share of water for respective areas planned to irrigate for each field unit
The hydraulic designs of the conveyance and distribution system are set for the following
functions.
Conveying the flow in the canal,
Water measurement,
Distribution of water in the tertiary,
Turning the flow in the tertiary canals on and off.
The primary or main canals are contour canal types for the entire length. For distribution of
water to fields of cultivators network of distribution system is planned which consists of the
following:
i) Tertiary canals taking off from Secondary canals,
ii) Field canals taking off from Tertiary canals.
6. Canal Capacity
6.1 General
The aim of this irrigation upgrading Design is the determination of the quantity of water
required for the growth of a plant, which serve as the basis for the design of irrigation canal
and structures. The determination of irrigation water requirement therefore need the study
and analysis of cropping pattern, estimation of crop water requirement, estimation of
effective rainfall and estimation of irrigation efficiency.
6.2. Climate
The project area is located an altitude of 2760ma.s.l which is classified as Dega agro climatic
classification. The mean maximum average annual temperature of the area is 19.874 0c and the
mean minimum average annual temperature of 7.25 0c, in which the highest mean maximum
temperature of 22.16 0C and a mean minimum temperature of 5.14 0C were recorded in
February and December months respectively.
The rain fall index showing the relative dryness or wetness of a month is known as rainfall
coefficient is considered for the project. Rainfall index is defined as the ratio of mean monthly
rainfall to rainfall module (one-twelfth of the annual total).
MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Mean RF(mm) 50.08 39.26 141.08 150.78 126.55 123.44 115.11 141.15 154.62 120.03 26.95 29.62
80% Dependable
RF(mm)
8.60 8.20 40.70 62.80 84.90 83.40 91.30 116.40 114.50 78.50 9.60 1.80
RF Coefficient 0.50 0.39 1.40 1.49 1.25 1.22 1.14 1.40 1.53 1.19 0.27 0.29
Accordingly, the time spanning from March to October represent big rainfall with moderate
concentration. The rest of the moths are under the category of dry period. There are four dry
months from November to February with rainfall coefficient of less than 0.6. Hence, irrigation
by stream diversion is required if crop production is envisaged in the long period of October
to March.
Moreover, the analysis and evaluation of the climatic data from utilized climatological station,
Kofele, show that there is significant moisture deficit in the months of October to March. This
shows that there would be a need for irrigation.
7.1 General
Canals are designed to distribute water properly in the system that will make Beta irrigation
possible and efficient. The purpose of upgrading design of main and secondary canal lines is
to distribute water just as evenly from the intake to the Tertiary canals and further to the
command area. Drains are designed to dispose of the water from the field which may create
water logging in the field. Soil and crop characteristics represent basic quantities in the
compatibility of the canal hydraulic parameters. Diversion water and respective command
areas are important variables for designation of command statement and design of canal
Section.
For the design, discharge for the proposed irrigated area is first worked out with duty without
flexibility factor and then the discharge is calculated with flexibility factor for the canal for
which design is considered. The lined part of the canal is designed as rectangular section and
the unlined part as trapezoidal section.
The hydraulic design of all the canals has been done using Flow master software by Manning's
method.
Where:
Out Puts
V = Average velocity (m/sec),
H = Water depth (m),
B/H = ratio b/n depth & width
T = Top width (m)
Where:
Q= Design discharge (m3/s),
N = Manning roughness coefficient (n=0.018 for masonry),
S= Design bed slope (m/m),
R=Hydraulic radius (m),
A=Cross sectional area of flow=B*H.
B should be determined for best hydraulic rectangular section i.e. B=2*H and
Perimeter P=4H. Hence, R=H/2 for flow depth, H, of the canal.
The maximum velocities are determined based on the USBR design recommendations.
Maximum velocity is to be 0.70m/s and at worst condition and higher depth up to 0.80m/sec
and minimum velocity is taken up to 0.26m/s. The Manning’s coefficient in earthen channel
varies with the bed material. Canals lined with grass and sod is taken the value n = 0.03.
selected as the maximum feasible after examination of the ground slopes, soil types and
infiltration rate.
In Beta canal network there are twenty-seven field canals originating from the tertiary canals.
Field canals design capacity should be optimum so as to be managed by an individual farmer.
The capacity of field canals is designed to be equal to the capacity of the corresponding
tertiary canal. The capacity of the field canals in Bata canal system varies from 0.0029 to
0.011m3/sec. Apart from the discharge, velocity, and bed slope of the canal, all other design
criterion of the field canals and the corresponding tertiary are similar(side slope=1, bed
width, b=0.3m, Manning’s roughness coefficient , N= 0.025 and free board 0.2).
8. Canal Structures
8.1 General
The introduction of modern irrigation scheme should strive for high efficiency of water
distribution and application on the farms. This can be achieved through provision of
appropriate irrigation structures in the system. The main types of structures required to
facilitate the distribution systems and included in Beta irrigation project are:
i) Division Boxes,
ii) Off takes,
iii) Road Culvert and
iv) Foot bridge.
They are designed as simply as possible to be operated by the farmers.The structures are
made of masonry and/or concrete. Hence the analysis has been made for sizing of appropriate
structures. A minimum 1.5m length of cemented stone pitching is provided as a protection at
the inlet and outlet of the division box structure.
Whenever canal crosses existing roads, having communication links between two places a
crossing structure shall be provided. In Beta project there is one major road crossing the tow
right and left main canals. There are two footpaths existing in the command area. The two
footpaths cross the main canal and one of the foot paths cross the other canal elements in the
network. For both the road crossings and foot paths rectangular box culvert has been
proposed to be provided. The detail of these structures has been presented in the respective
drawing.
9. Bill of Quantities, Specification and Cost Estimation of Beta Yeka Lalessa SSI Project
for Upgrading and Improved Items.
Table: 9.1 Bill of Quantity and Cost Estimation
18*.9*.25)m
1.3 Plastering two rounds the m2 25.2 258.0 6,503.87
two side faces and weir crest 0 9
top length 18*.9m (1:2
mortar, 25cm thick)
1.4 Intake gate (5mm thick, cm X pcs 1.0 32,500.0 32,500.0
60cm, and supported by 0 0 0
10mm bars, with 2.5m high
frame of 5mm thickness and
50mm spindle) supply and
proper installation
1.5 Gate providing on Weir Body pcs 1.0 12,500.0 12,500.0
as spillway during winter 0 0 0
time gate at top of exsting
weir height with (5mm thick,
cm .25X 1.2m, and with fixing
frames and plates supply and
proper installation
1.5 Existing Stilling Basin
Maintenance
1.6 Stair concrete 1:3:4 with m3 7.5 2,918.3 22,062.5
dimension of 18*1.65*.1 6 3 7
1.7 plastering of all round stair m2 72.0 258.0 18,582.4
(1:2) 0 9 8
Sub Total A 130,082.5
6
2 Main Canal-1 Left Side
7
8 Drop Structures
Construction (1m fall, 12 in
No)
8.1 Site Clearance m2 36.0 34.8 1,254.60
0 5
8.2 Excavations for the structure m3 144. 145.0 20,891.5
00 8 2
8.3 Hard coring with hard rock m3 14.4 828.0 11,924.3
(20cm) 0 8 5
8.4 Concrete (1:3:4) for bed and m3 10.8 2,918.3 31,517.9
under the walls (10cm thick) 0 3 6
8.5 Masonry (1:3 mortar) with m3 28.8 2,606.2 75,059.4
hard rock 0 3 2
8.6 Pointing (1:2 mortar, 3cm m2 18.0 258.0 4,645.62
thick at two rounds) the 0 9
inner and top of the walls
8.7 Compacted back filling m3 2.8 65.5 188.64
8 0
Sub Total I 145,482.1
2
10 Road crossing in no 9
10.1 Excavation on soft formation m3 81 145.0 11,751.4
8 8
10.2 Hard coring (20cm) with m3 27 828.0 22,358.1
very hard rock 8 6
10.3 Masonry (1:3 mortar) m3 16.2 2,606.2 42,220.9
3 3
10.4 C-25 Concrete for slab filing m3 21.6 2,918.3 63,035.9
(1:2:3) 3 3
10.5 Supply, cut, bend and fix in -
position reinforcement bars
10.6 E/ Ф10mm Kg 185.5 167.0 30,978.5
0 0
10.7 A / Ф6 mm Kg 125.5 167.0 20,958.5
0 0
10.8 Plastering (mortar 1:2 ; m2 162 258.0 41,810.5
thickness 3cm) 9 8
10.9 Pointing (1:3 mortar) m2 19.44 258.0 5,017.27
0.015m3 thick 9
11.0 Formwork m2 162 350.0 56,700.0
0 0
11.1 Back fill and compactions m3 16.2 65.5 1,061.10
0
Sub Total J 295,892.4
4
11 Footpath ( 18 in no)
11.1 Excavation on soft formation m3 43.2 145.0 6,267.46
8
11.2 Hard coring (20cm) with m3 14.4 828.0 11,924.3
very hard rock 8 5
11.3 Masonry (1:3 mortar) m3 10.8 2,606.2 28,147.2
3 8
11.4 C-25 Concrete for slab filling m3 7.2 2,606.2 18,764.8
(1:2:3) 3 6
11.5 Supply, cut, bend and fix in -
position reinforcement bars
11.6 A / Ф6 mm Kg 25 167.0 4,175.00
0
11.7 C/ Ф10mm kg 50 167.0 8,350.00
0
11.8 Plastering (mortar 1:2 ; m2 72 258.0 18,582.4
thickness 3cm) 9 8
11.9 Pointing (1:3 mortar) m2 8.64 350.0 3,024.00
0.015m3 thick 0
12 Formwork m2 36 350.0 12,600.0
0 0
12.1 Back fill and compactions m3 10.8 65.5 707.40
0
Sub Total J 112,542.8
3
12 Drainage(stream) crossing
structure (6 in no)
12.1 Excavation on soft formation m3 54.0 145.0 7,834.32
0 8
12.2 Cart away Unwanted soil m3 15.0 75.5 1,132.50
0 0
12.3 Hard coring (20cm) with m3 13.5 828.0 11,179.0
very hard rock 0 8 8
12.4 Masonry (1:3 mortar) m3 10.8 2,606.2 28,147.2
0 3 8
12.5 A / Ф6 mm Kg 72.0 167.0 12,024.0
Yeka Lalessa Irrigation Scheme Maintenance Document Report Page 30
West Arsi Zone Irrigation Development Office
0 0 0
12.6 E/ Ф10mm kg 196. 167.0 32,732.0
00 0 0
12.7 C-25 concrete for filling m3 18.0 2,606.2 46,912.1
(1:3:5) 0 3 4
12.8 Reinforcement bars kg 576. 167.0 96,192.0
(Ø=12mm) 00 0 0
12.9 Plastering (mortar 1:2 ; m2 86.0 167.0 14,362.0
thickness 3cm) 0 0 0
12.10 Pointing (1:3 mortar) m2 5.9 167.0 991.98
0.015m3 thick 4 0
12.11 form work m2 72.0 350.0 25,200.0
0 0 0
12.12 Back fill and compactions m3 72.0 65.5 4,716.00
0 0
Sub Total M 281,423.3
0
Total 3,815,147.
10
Supervision 5% 190,757.3
6
contingence 10% 381,514.7
1
VAT 15% 572,272.0
7
GRAND Total With VAT 4,959,691.
24
Soil conservation works especially along the main canal route and good managed farming
practices are mandatory for sustainability of the scheme. As the farming people in Keraru
Kebele are not acquainted with irrigation practice, there may be unwise utilization of the
implemented irrigation scheme. The common exercises experienced in other areas are like
breaching canals at any place of their preference at the same time inefficient water
application method they are using, causing breaching of the delivery canal and allow the
water to flood the field.