PT.

WILWATIKTA PUSAKA ENERGI


NOKAN 3 MHPP Project

SUMMARY

PT Wilwatikta Pusaka Energi is a company founded in Jakarta with the intention to develop renewable
energy potency in Indonesia.
The project highlight of PT Wilwatikta Pusaka Energi is the Nokan 3 MHPP, located in Kemumu
Village, Arma Jaya Sub-District, North Bengkulu Regency, Bengkulu Province, with planned capacity
of 5 MW and estimated plant factor of 66.41%.
PT. Bangkahulu Kapindho Energi has undertook the Pre-Feasibility Study (Pre-FS) to ensure the site is
potentially feasible to be developed as an MHPP in an Independent Power Producer (IPP) project, and
currently in-depth Feasibility Study is being developed by Indokoei International.
As of date, “Izin Prinsip” by the Regent of Bengkulu Utara, “Rekomendasi Teknis Kepala Dinas
Kehutanan Survey Pemetaan Dinas Kehutanan” by local Forestry Service, and “Rekomendasi Gubernur
untuk Pembangunan PLTMH” has been issued to PT Bangkahulu Kapindho Energi. Currentlly
AMDAL is ongoing.

Page 1 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Company Name PT Wilwatikta Persada Energi


Company Gedung Imora Lt 4,
Address Jl. Pangeran Jayakarta No 50,
Mangga Dua Selatan
Jakarta Pusat
Holding PT Warnawangsa Energi Abadi
Company
Holding Menara Rajawali Lt.23,
Company’s Jl. DR Ide Anak Agung Gde Agung
Address Lot#5.1,
Kawasan Mega Kuningan
MHPP Location Kemumu Village, Arma Jaya Sub-
District, North Bengkulu Regency,
Bengkulu Province
Plant Capacity 5.0 MW
Est. Electricity 29.41 Gwh
Generated
(GWh)
Project Indokoei International (currently
Consultant developing Feasibility Study)
Project Progress Pra Feasibility Study
Topographic Survey
Hydrology Survey

Page 2 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Feasibility Study (Ongoing)


Permit Progress: Izin Prinsip
Peta Hasil Penelahan Peta Kehutanan
Rekomendasi Teknis Kepala Dinas
Kehutanan mengenai Survey Pemetaan
Dinas Kehutanan
Rekomendasi Gubernur
AMDAL (Ongoing)

Page 3 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

LOCATION
The potential location of Nokan 3 Mini Hydro Power Plant (MHPP) was identified in Kemumu Village,
Arma Jaya Sub-District, North Bengkulu Regency, Bengkulu Province harnessing hydro-potential of
Nokan River. It is about 60 km from Bengkuku City which can be reached approximately 2-3 hours by
car.
02 der 16 min 52.97 det E; 3 der 23 min 16.91 det S
Downstream 102 der 16 min 29.21 det E; 3 der 23 min 58.38 det S

Coordinate – Weir 3023’16.91”S and


102016’52.97”E
Coordinate – Powerhouse 3023’58.38”S and
102016’29.21”E

Page 4 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Page 5 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

SITE CONDITION

Weir Power House


Topography
Survey Result
of Nokan
MHPP

Page 6 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

HYDROLOGY
The methods applied to estimate long-term daily discharge is the catchment area and rainfall ratio based
on the discharge data of Air Ketahun River at Air Ketahun Tunggang AWLR Station. The data is
available for a period of 7 years, which is between 1994 and 2012. Then, it was checked and compared
with the discharge estimated by using NRECA (National Rural Electric Cooperative Association) and
FJ Mock Method based on rainfall data of Kurotidur, Argamakmur and Baturoto Station. The discharge
data from the AWLR station was transferred to the weir of Nokan 3 MHPP by applying catchment ratio
of 0.103 (100 km2/968.8 km2) and annual rainfall ratio of 1 since they are located in the similar rainfall
contour (4,000 mm).

The Flow Duration Curve (FDC) of the Nokan 3 MHPP site is established and used for power
generation planning and production energy simulation together with optimization of development
scheme. The figure below shows FDC of daily discharge of Nokan 3 MHPP based on the low flow
analysis.

Page 7 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Discharge
FDC of Nokan-3 MHPP Probability 3
40
(m /sec)
10% 13.06
35
20% 9.17
30
3/sec)

30% 7.37
25
39% 6.69
Discharge (m

20 40% 6.58
15 50% 5.90
10 Annual Average = 6.69 m3/sec
60% 5.02
5 70% 4.07
0
80% 3.17
0 10 20 30 40 50 60 70 80 90 100 90% 2.22
Probability (%) 100% 0.44

Page 8 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Flood discharge has been analyzed by Unit Nakayasu Hydrograph and checked by Creagrer’s Curve.
Estimated flood discharge for 10, 50, and 100 years return period is 349 m3/sec, 459 m3/sec, and 509
m3/sec.

Page 9 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

POWER GENERATION
The MHPP is designed with 2 x 2.50 MW or 5.00 MW in total, based on the maximum design discharge
of 6.69 m3/sec at 39 % probable discharge by applying Francis type Turbine. This plan is harnessing
effective head of 100 m. After considering additional discharge for ecological flow at 0.67 m3/sec, the
average gross annual energy production of Nokan 3 MHPP is approximately 29.41 GWh with plant
factor (PF) at 66.41%.

NOKAN-3 MHPP
Installe d Capacity 5.000 MW Required Discharge (39%) = 6.69 m3/sec Min. operation discharge (40% Qd) = 1.34 (m3/s)
(2 x 2.50 ) MW Qd (turbine 1 & 2) = 3.35 m3/sec Eco discharge (m3/s) = 0.67 (m3/s)
Head = 85 m

Annual Ene rgy Output (E), GWh Annual Plant


No Ye ar Jan Fe b Mar Apr May Jun Jul Aug Se p Oct Nov De c Ene rgy Factor
1 2 3 4 5 6 7 8 9 10 11 12 GWh %
1 1993 3.13 2.25 3.06 2.94 3.19 1.66 1.46 0.23 0.87 2.39 2.39 3.19 26.75 60.91%
2 1994 3.12 2.66 3.14 3.26 2.18 1.34 0.43 0.00 0.07 0.14 0.73 2.45 19.52 44.44%
3 1996 3.33 3.45 2.99 3.47 1.58 1.10 1.43 1.28 3.06 3.69 3.57 3.68 32.63 74.30%
4 2006 2.88 2.69 1.96 2.95 2.47 1.38 0.72 0.27 0.85 3.25 3.46 3.36 26.23 59.73%
5 2008 2.35 2.44 3.20 3.14 1.97 1.79 1.22 1.80 3.43 3.27 3.03 3.22 30.86 70.26%
6 2009 3.24 3.02 3.36 2.86 2.60 1.79 1.86 2.76 2.86 3.20 3.28 3.47 34.28 78.06%
7 2011 1.46 1.33 1.00 1.78 1.56 0.76 0.73 0.77 2.04 3.67 3.57 3.69 22.37 50.93%
8 2012 3.16 3.33 2.92 3.57 3.67 2.60 2.66 1.84 2.22 3.50 3.57 3.69 36.73 83.63%
9 2013 3.12 2.71 2.78 3.20 2.72 2.78 2.46 1.79 2.83 3.07 2.96 3.06 33.50 76.27%
10 2014 2.64 2.19 2.74 2.69 2.95 2.40 2.19 3.00 2.57 2.03 2.90 3.03 31.33 71.34%
11 2015 3.44 2.87 3.54 3.45 3.21 2.47 1.70 1.04 1.12 0.96 1.27 1.57 26.65 60.67%
Ave rage 2.87 2.67 2.76 3.04 2.49 1.84 1.54 1.45 2.10 2.68 2.83 3.12 29.41 66.41%
Maximum 3.44 3.45 3.54 3.57 3.67 2.78 2.66 3.00 3.43 3.69 3.57 3.69 36.73 83.63%
Minimum 1.46 1.33 1.00 1.78 1.56 0.76 0.43 0.00 0.07 0.14 0.73 1.57 19.52 44.44%

Page 10 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

DESIGN SUMMARY
No Item Unit Alternative-1
1 Hydrological Conditions
Catchment area Sq.km 100
Annual mean rainfall Mm 4,456
Annual mean discharge Cu.m/ 6.96
sec
50-year peak flood Cu.m/ 459
sec
100-year peak flood Cu.m/ 509
sec
2 Hydropower Planning
Max. plant/design discharge Cu.m/ 6.69
sec
Min. plant/design discharge Cu.m/
sec
Normal water level at weir M 456.5
Normal water level at head M 454.1
tank/ pond
Axis Turbine M 470
Gross head M 87.54
Net head M 85.00

Page 11 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Installed capacity MW 5
Number of unit 2
Unit capacity MW 2 x 2.5
Plant factor % 66.41
Gross Annual Energy GWh 29.41
3 Main Structures
A. WEIR
Coordinate 3023’16.91”S and 102016’52.97”E
Type Concrete
Dimension M B = 30 and h = 4
Crest Elevation m 560
Crest Type Ogee Type
Stilling Basin Type USBR Type II
B. INTAKE GATE
Type Steel Slide
Dimension (Gate) M 2 x (1 m x 2.4 m)
C. SETTLING
BASIN/SAND TRAP
Dimension M Length = 41 m and width = 5.5 m
D. WATERWAY
Type Concrete canal
Length M 2,000
Dimension M 3 x 1.7
Page 12 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Bed Slope 0.8/1,000


E. HEAD POND
Coordinate 3023’58.38”S and 102016’29.21”E
Dimension M Length – 26 m and width = 7 m
Depth of Water M 3
F. PENSTOCK
Type Steel Pipe
Dimension M  1.7 m
Total Length M 400
G. POWER HOUSE
Coordinate 3024’01.31”S and 102016’23.92”E
Type Semi underground
Dimension M Width – 11.40 m, length = 40.53 m
H. TURBINE &
GENERATOR
Type Francis Type with horizontal shaft
Elevation of axis M 470
Capacity Installed MW 2 x 2.5
Combined Efficiency % 89

Page 13 of 14
PT. WILWATIKTA PUSAKA ENERGI
NOKAN 3 MHPP Project

Head Tank
Weir Intake Channel De-silting Basin Waterway Channel B=7m Penstock Powerhouse Tailrace
B = 30 m B = 5.5 m L = 2000 m L = 26 m L = 400 m
B=2x2m L = 41 m i = 0.8/1,000 H= 3 m
H = 1.6 m H=4m
Weir Crest Tras hracks
EL.560 Side Spillway Anchor Blocks @ 100 m approx.
EL. 557.54
Designed FSWL is 557.54 m at Head Tank

Typical W aterway
Turbine Center
River Bed EL. 470 m
H = 1.71
EL. 556 +
Sand Flush Gate
Leveling
1 m x 2.4 m B=3m
Steel Penstock f 1 .7 m
Concrete 1.00 m
f 1 .7 m TWL. 468 m

2 branches
from f 1.2 m
Hydrological Features Initial Assumption of the Salient Features
3
(1) Catchment Area 85.00 km2 (1) Max. Design Discharge 6.69 m /s
(2) Annual Rainfall 3,952 mm (2) Riverbed Level at Intake Weir 452.50 m
(3) Mean Discharge 6.69 m3/s (3) Hight of Intake Weir 4.00 m
(4) Crest of Intake Weir 560.00 m
(4) 10-year Flood Discharge 349.00 m3/s (5) Full Supply Water Level at Head Tank 557.54 m
(5) 50-year Flood Discharge 459.00 m3/s (6) Turbine Center EL. 470.00 m
(6) 100-year Flood Discharge 509.00 m3/s (7) Tail Water Level 468.00 m
(8) Gross & Net Head 87.54 85.00 m
(9) Numbers of Turbine Unit 2
(10) Power output per unit 2.50 kW
(11) Power output in total 5.00 kW

Average Rainfall at Nokan 3 River Basin


FDC of Nokan-3 MHPP 450
40 400

35 350
300
Discharge (m3/sec)

30 Location Intake Site


250
25 Catchment Area 85 km2
Maximum 3 33.02 200
20 (m /s)
Discharge 20% (73-day) 9.17 150
(m 3/s)
15 100
Discharge 39% (146-day) 3
(m /s) 6.69
10 M ax Plant Discharge or Annual Average = 6.69 m3/sec Discharge 50% (182-day) 5.90 50
(m 3/s)
5 Discharge 60% (219-day) (m 3/s) 5.02 0
Mi n Pl a nt Discharge = 1.33 m3/s ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov De
0 Discharge 80% (292-day) (m 3/s) 3.17
0 10 20 30 40 50 60 70 80 90 100 Minimum 100% (m 3/s) 0.44
Probability (%) 6.69
Average (m 3/s)
NOKAN 3 MHPP
SCHEMATIC PROFILE

Page 14 of 14