Safety Inspection Checklist Regional Office:

Project:
Date:
Carry out safety inspections of items below. Inspector:
Check(✔) the evaluation. [P: Pass (Accomplished) F: Fail (Correction is needed) NA: Not Applicable] *Check 'F', even though you find only one failure.
Items Points to check Evaluation Comments
Fall Accident Prevention P F NA

Safety belt / Double lanyard safety belts/harness are used by all workers working at height and around openings when
harness, reattaching is required.
Lifeline Lifelines or other safety equipment to connect safety belt are set properly.
All braces and planks (walking boards) are installed. (In case planks are lacking, the spots are reinforced with
Prefabricated single pipes.
scaffolding
Ladders are set at proper intervals. Indication is shown clearly.
Ladders, guardrails (2 rails for over 900h), toe boards, and working platforms are well-maintained.
Rolling tower
Wheel brakes function and are used properly during operations.
Use of top 3 steps is prohibited when standing on more than 2m height. (excluding a type with work platform
Stepladder and guardrails at the top step.)
In case two people working together, one is holding a ladder steady.
Temporary steps, No one is working on a mobile ladder. (It is prohibited in principle.)
Mobile ladders Steps are provided to go up/down more than 1.5m.
Indicate resonsible person information to the protection such as PIC photo, Nme and contact number (more
than 2m fall)
【Openings not in use 】
Cover materials are strong enough to support the weight of a man.

Openings
Covers are fixed tightly not to move, and indications of openings are clearly displayed.
【Openings in use】
Strong guardrails, such as single pipes (GI pipes) are set around openings. (2 rails for over 900h)
Indications of openings are clearly displayed.
Safety nets to prevent falling/flying objects are attached.
Horizontal safety nets are installed without gaps.
Steel Erection
Horizontal safety nets have enough strength and are not to be broken easily.
Vehicle & Heavy Machinery Accident Prevention P F NA

(※) Preoperational inspection is conducted and the records are kept.

(※) Based on the result of inspection, if an obvious malfunction is found for brake/ safety device/ driving gear/
hydraulic system, the use of the machine is prohibited. (Repair arrangement is done.)
Common items
Implementation status of periodical inspection which is specified in laws/regulation is checked.
Operator/driver has necessary qualification.
(※) When an operator leaves the seat, the engine is stopped. Working device such as bucket is lowered to
the ground in case of backhoe etc.
Construction No workers are around the machine. Measures to keep people from entering are taken. (barricades,
vehicles, watchman)
Hoisting • handling Prevention measures for accidental movement are taken when dump truck/ concrete truck/ trailer is parked or
machinery stopped on a slope. (Pulling the key out, Wheel stops)
Entering the area under a suspended load is prohibited.
Cranes, Mobile A person who gives signals is appointed, and the signaling ways are confirmed.
cranes and
The ground surface is reinforced properly for using outriggers.
Concrete pump
trucks The check sheet which mentioned in Memorundum16-13 to prevent crane accident is used. (Keywords:
overload prevention device, Key with a string, Periodical inspections, Operator Induction Training, Operating experience,
Operator's qualification, The release key for safety device is under the control)
Slinging tools such as wires and slings are inspected by color codes.
Slinging Work 3.3.3 activity is carried out
Mismatched wire rope or slings are NOT used.
Protection for the Passages for pedestrians are secured and are well-maintained.
general public Indication of vehicle gate, guide signals, and security equipment are set properly.
Site speed limit signs are posted (20km/h or less as a rule), and no one breaks the speed limits.
When a vehicle is backed up, a flagger guides the vehicle properly.

Others ・Don't allow construction vehicle to park on the crowded public road

・Traffic guiding is properly done on crowded public road by guiding personnel.(Prioritize the safety
of third-party vehicles. Always keep an eye on general vehicles to secure the own safety. Execute with
2 people guidance as necessary)

Prevention of Heavy Material Collapse P F NA

Temporary lay- Collapse prevention measures are taken for heavy materials which might fall by toppling. (Materials: PC, steel
down work truss, steel beam, glass, SD (steel door), system formwork, unitized rebar, etc.).

Regarding handling heavy materials which might fall by toppling on a trolley or hand pallet jack, there is no
obstruction (steps, slopes, etc.) in the handling route. (Materials: mechanical device, glass, steel, etc.)
Handling work
Trolleys or pallets are large and bearable enough for materials to handle. There are sufficient number of
workers.
Collapse prevention measures (guy wires, supports, etc.) are planned and taken in order to prevent heavy
Installation work
materials from collapsing. (Materials: steel column, steel beam, unitized wall rebar, system formwork,
Hot Work and Utility lines P F NA

Post-operation inspection is conducted by Shimizu staff after 2 to 3 hours later


Hot work is strictly prohibited around flammable materials such as urethane foam or expanded polystyrene.
Hot Work
Signs "Flammable" etc. is displayed.
Fire extinguishers are set, and smoking is controlled.
Indication of underground utilities are provided at laying location on site./ Primary survey for the U/G cable
Utility lines
carried out?
Related electricity P F NA

ELCB are installed to Outlet distribution board (standard sensitivity current 30mA/0.1second)
Distribution board Ground wire is installed to D/board
Lock for D/board is done, PIC name, contact phone number are indicated
electroscope. PIC Staff and worker of electrical work have electroscope.
Cable No cable damage?, Insulation OK? Ground wire OK? Regular Inspection for temporary cable OK?

Others P F NA

Lack of Oxygen No entry protection (barricade or opening cover)OK? And No entry & danger sine board OK?
(※) Site 5S is put into practice successfully. (Point out at least one item.)
Job site
5S: Sort-out, Orderly Arrangement, Cleaning, Maintenance, Discipline

(※) Penalty System is put into effect at each project site, including the following rules. (When an operator
leaves the seat, the engine is stopped and bucket of backhoe is lowered to the ground. Crane operator turn
Penalty System off the Overload prevention device during hoisting . Not working without using safety belt at height.
(※) Penalty System is recognized by all workers. (How and how often workers are reminded of Penalty
System?)
rev. 2019.1