You are on page 1of 1

AJDAN Waterfront Development – Parcel A1 – Al KHOBBAR PROJECT

SUBMITTAL REVIEW COMMENTS FORM

REVIEW BY: DESIGN CONSULTANT SUPERVISION CONSULTANT PMC OTHER (Specify)

Pre-Qualification Document 1303-SUB-MASA-A-104 R0


TYPE OF SUBMITTAL: SUBMITTAL NO.:

SUB.
Pre-Qualification for Metal Doors and wooden Doors and
REVIEW 1303-SUB-MASA-A-104 R0 C
Frames – Sultanah Allied Industries
SUBJECT: REF. REVIEW / APPR. STATUS:

Item Title / Reference No. of Review Basis


Review Comments (Specify Contract /
No. Document Reviewed
Specification Clauses)
The Submitted Pre-qualification is Revise & resubmit subject to fulfill the project
requirements not limited to the following:
- Update the official registration certificate since it is expired.
1303-SUB-MASA-A-104 R0 - Provide valid certificate from internationally recognized agency having a factory inspection service, and
Factory Inspection Manuals issued by the listing agency to individual manufacturers.
- Successful factory visit to the project parties.

Reviewer’s Name: Mohamed Fawzi Designation: R.E Signature Date 09/09/2018

*Review Status Legends: A-Approved B-Approved As Noted, C- Revise & Resubmit D-Rejected E-For Information

Doc / Form No: PSA-883-PP-02-10-FM Rev.2


Page 1 of 1 Revision Date: 15-Mar-2011