Professional Documents
Culture Documents
FLOOR AREA
WATER LINE
FEED UP TO TANK
Materials No. of Pcs
Check valve 1
Water meter 1
1" Gate Valve before pump 2
1" pipe from CV to M to CT
No. of pipe Length # of pipe
WD 1 9 2.25 3
Well 1 30.5 7.625 8
1" PPR pipe from CT to storage tank
No. of pipe Length # of pipe
1 26.1 6.525 7
FITTINGS
1" Male thread skt 4
1" Tee 2
1" Gate Valve after pump 4
1" Double Union 7
1" Coupling 7
1" - 90 deg Elbow 20
PLUMBING
SEPTIC VAULT
Materials No. of Pcs
4" x 4" PVC Sanitary Tee 4
4" PVC Clean out 4
4" PVC Coupling 4
4" PVC S1000 2
SUMMARY
Materials No. of Pcs
4" PVC Pipe S1000 19
4" PVC Clean out 4
4" x 4" PVC Sanitary Tee 11
4" PVC 90 deg elbow 6
4" PVC 45 deg elbow 9
4" PVC Coupling 9
4" PVC Clean out 7
4" x 2" PVC Tee 26
2" PVC pipe S1000 11
2" PVC Pipe S600 36
2" PVC 90 Deg Elbow 37
2" PVC 45 Deg Elbow 14
2" x 2" PVC Tee 28
2" Coupling 4
2" Clean Out cover 5
Floor Drain 30
COMPUTATION OF QUANTITIES
A. FOOTING STRUCTURE;
Footing: Number of Width Length Thickness Area Volume
Structure (m) (m) (m) (Sq m) (Cu m)
F1 5 2.10 2.10 0.45 4.41 9.92
F2 2 2.40 2.40 0.50 5.76 5.76
F3 1 1.90 1.90 0.45 3.61 1.62
F4 2 1.60 1.60 0.45 2.56 2.30
CF1 1 2.00 4.00 0.50 8.00 4.00
TOTAL 24.34 23.60
B. COLUMN STRUCTURE:
B.1.1 COLUMN (FROM TOP OF FOOTING TO 2ND FLOOR)
Number of Width Length Height Area Volume
Structure (m) (m) (m) (Sq m) (Cu m)
Grid 1, A,B,C,D C1 4 0.45 0.45 5.80 0.20 4.64
Grid 2, A,B,C,D C1 4 0.45 0.45 5.80 0.20 4.64
Grid 3, A,B,C,D C1 4 0.45 0.45 5.80 0.20 4.64
Sub-total= 13.92
SUMMARY OF COLUMN:
TOTAL(Footing to 2nd Floor)= 14.64
TOTAL(2nd Floor to 3rd Floor)= 6.81
TOTAL(3rd Floor to 4rth Floor)= 6.81
TOTAL(4rth Floor to Roof Beam)= 6.81
TOTAL(Roof Beam to Top of Firewall)= 3.39
TOTAL= 38.46
C. BEAM STRUCTURES:
C.1 GROUND FLOOR
Number of Dept Width Length Area Volume
Structure (m) (m) (m) (Sq m) (Cu m)
Grid 1, A-D GB-I 1 0.40 0.30 9.40 0.12 1.13
Grid 1', A-B GB-I 1 0.40 0.30 1.90 0.12 0.23
Grid 2, A-D GB-I 1 0.40 0.30 7.80 0.12 0.94
Grid 3, A-D GB-I 1 0.40 0.30 9.40 0.12 1.13
LEFT TO RIGHT
Grid A, 2-3 GB-I 1 0.40 0.30 4.80 0.12 0.58
Grid B, 1-3 GB-I 1 0.40 0.30 9.60 0.12 1.15
Grid C, 1-3 GB-I 1 0.40 0.30 9.60 0.12 1.15
Grid D, 2-3 GB-I 1 0.40 0.30 4.80 0.12 0.58
TOTAL 6.89
SUMMARY OF BEAMS:
Ground Floor= 6.89
Second Floor= 11.19
Third Floor= 11.38
Fourth Floor= 10.62
Roof Beam= 6.86
TOTAL= 46.94
D. SLAB STRUCTURE
Area Thickness Volume
(Sq m) (m) (Cu m)
Ground Floor 142.8 0.1 14.28
Second Floor 124.17 0.1 12.42
Third Floor 128.93 0.1 12.89
Fourth Floor 129.12 0.1 12.91
Roof Slab 111.13 0.1 11.11
TOTAL 63.61
E. SHEAR WALL:
From top of footing to Bottom of 2nd Floor Beam
Width Height Length Area Volume
(m) (m) (m) (Sq m) (Cu m)
Grid A, 1-2 Footing 0.60 0.25 3.30 0.15 0.50
Grid A, 1-2 Wall 0.2 5.05 4.8 1.01 4.85
Grid 2, A-B Wall 0.20 5.05 1.60 1.01 1.62
Grid D, 1-2 Footing 0.60 0.25 3.30 0.15 0.50
Grid A, 1-2 Wall 0.2 5.05 4.8 1.01 4.85
Total= 12.32
F. CISTERN TANK:
No. of Width Length Area Thickness Volume
Structure (m) (m) (sq m) (m) (cu m)
Bottom Slab 1 1.40 1.80 2.52 0.20 0.50
Top Slab 1 1.40 1.80 2.52 0.20 0.50
1.00
Less: Manhole 0.38 0.20 0.08
Total= 0.92
G. STAIRS:
No. of Width Length Area Thickness Volume
Structure (m) (m) (sq m) (m) (cu m)
Slab 1 2 0.85 2.90 2.47 0.10 0.50
Rise/Run 16 0.21 0.30 0.03 0.85 0.48
Slab 1 6 0.85 2.80 2.38 0.10 1.44
Rise/Run 48 0.21 0.30 0.03 0.85 1.44
Landing 4 1.40 1.85 1.30 0.10 0.52
Total= 4.38
1.1 10.34
1.1 2.09
1.1 8.58
1.1 10.34
1.1 5.28
1.1 10.56
1.1 10.56
1.1 5.28
63.03
0.85 8.9675
1.2 11.28
0.85 1.615
1.2 11.28
0.7 1.75
1.2 11.28
0 0
1.2 1.56
1.2 11.52
1.2 13.08
1.2 13.08
1.2 13.08
98.4925
0.85 8.9675
1.2 12.36
0.85 2.38
1.2 11.28
0.7 1.75
1.2 11.28
0 0
1.2 1.56
1.2 11.52
1.2 13.08
1.2 13.08
1.2 13.08
100.3375
0.85 8.9675
1.2 12.36
0.85 2.38
1.2 11.28
0.7 1.75
1.2 11.28
0 0
1.2 1.56
0.8 7.68
1.2 13.08
1.2 13.08
1.2 13.08
96.4975
COMPUTATION OF QUANTIES:
RSB
FOOTINGS: No. Width Length Bar length No. of Bars No. of 16mm Weight Total Wgt.
16mm (m) (m) (m) (pcs) pcs kgs./m Kgs.
F1 5 2.10 2.10 2.35 28.00 5.60 1.578 530.21
F2 2 2.40 2.40 2.65 34.00 8.50 1.578 321.91
F3 1 1.90 1.90 2.15 12.00 2.40 1.578 45.45
F4 2 1.60 1.60 1.85 10.00 1.67 1.578 63.25
CF1 1 2.00 4.00 2.25 35.00 7.00 1.578 132.55
4.25 23.00 11.50 1.578 217.76
142.00 36.67 Sub-total= 1,311.13
COLUMNS:
From Footing to 2nd Floor
Height Length, RSB No. of RSB No. of Weight Total Wgt.
(m) (m) pcs. Column kgs./m Kgs.
16mm 9.00 9.20 24.00 12.00 1.578 4,181.07
Sub-Total 4,181.07
COLUMN STIFFENERS
Main Reinforcement (10mm diameter):
From Ground to Roof Beam
Height Length of RSB No. of RSB No. of at 12m Bar No. of 10mm Total Wgt.
(m) (m) pcs. Column No. of pcs pcs Kgs.
Grid 3, B-D 10mm 13.10 13.5 4.00 2 1.13 9.04 66.82
Grid B, 1-3 10mm 13.10 13.5 4.00 2 1.13 9.04 66.82
Grid C, 1-3 10mm 13.10 13.5 4.00 2 1.13 9.04 66.82
Grid D, 1-3 10mm 13.10 13.5 4.00 2 1.13 9.04 66.82
Sub-Total (10mm x 12m)= 36.16 267.28
Column Ties
BEAMS:
GROUND FLOOR:
No. of Beams Length, RSB No. of Bars At 12 Bar, No. No. of 16mm Weight Total Wgt.
Pcs. (m) pcs. pcs. pcs. kgs./m Kgs.
Grid 1,2,3, A-D
Main Bars 3.00 10.80 4.00 1.11 10.80 1.578 204.51 0.9
Cut Bars @ A 3.00 1.00 4.00 12.00 1.00 1.578 18.94 0.0833333
Cut Bars @ Ctr 3.00 1.05 4.00 11.43 1.05 1.578 19.88 0.0875
Cut Bars @ B 3.00 1.80 4.00 6.67 1.80 1.578 34.08 0.15
Cut Bars @ Ctr 3.00 2.28 4.00 5.26 2.28 1.578 43.17 0.19
Cut Bars @ C 3.00 2.35 4.00 5.11 2.35 1.578 44.50 0.1958333
Cut Bars @ Ctr 3.00 2.49 4.00 4.82 2.49 1.578 47.15 0.2075
Cut Bars @ D 3.00 1.50 4.00 8.00 1.50 1.578 28.40 0.125
SECOND FLOOR:
No. of Beams Length, RSB No. of Bars At 12 Bar, No. No. of 16mm Weight Total Wgt.
Pcs. (m) pcs. pcs. pcs. kgs./m Kgs.
Grid 1, A-D
Main Bars 1.00 10.80 4.00 1.11 3.60 1.578 68.17
Cut Bars @ A 1.00 1.00 5.00 12.00 0.42 1.578 7.95
Cut Bars @ Ctr 1.00 1.05 5.00 11.43 0.44 1.578 8.33
Cut Bars @ B 1.00 1.80 5.00 6.67 0.75 1.578 14.20
Cut Bars @ Ctr 1.00 2.28 5.00 5.26 0.95 1.578 17.99
Cut Bars @ C 1.00 2.35 5.00 5.11 0.98 1.578 18.56
Cut Bars @ Ctr 1.00 2.49 5.00 4.82 1.04 1.578 19.69
Cut Bars @ D 1.00 1.50 5.00 8.00 0.63 1.578 11.93
Grid A, 1-3
Main Bars 1.00 13.14 4.00 1.10 3.66 1.578 69.31
Cut Bars @ 1 1.00 3.30 6.00 3.64 1.65 1.578 31.24
Cut Bars @ Ctr 1.00 2.88 6.00 4.17 1.44 1.578 27.27
Cut Bars @ 2 1.00 2.85 6.00 4.21 1.43 1.578 27.08
Cut Bars @ Ctr 1.00 3.15 6.00 3.81 1.58 1.578 29.92
Cut Bars @ 3 1.00 1.80 6.00 6.67 0.90 1.578 17.04
THIRD FLOOR:
No. of Beams Length, RSB No. of Bars At 12 Bar, No. No. of 16mm Weight Total Wgt.
Pcs. (m) pcs. pcs. pcs. kgs./m Kgs.
Grid 1, 'A-D
Main Bars 1.00 12.44 4.00 1.04 3.86 1.578 73.09
Cut Bars @ A 1.00 1.85 5.00 6.49 0.78 1.578 14.77
Cut Bars @ Ctr 1.00 0.96 5.00 12.50 0.40 1.578 7.57
Cut Bars @ B 1.00 1.80 5.00 6.67 0.75 1.578 14.20
Cut Bars @ Ctr 1.00 2.28 5.00 5.26 0.95 1.578 17.99
Cut Bars @ C 1.00 2.35 5.00 5.11 0.98 1.578 18.56
Cut Bars @ Ctr 1.00 2.49 5.00 4.82 1.04 1.578 19.69
Cut Bars @ D 1.00 1.50 5.00 8.00 0.63 1.578 11.93
Grid A, 1-3
Main Bars 1.00 13.14 4.00 1.10 3.66 1.578 69.31
Cut Bars @ 1 1.00 3.25 6.00 3.69 1.63 1.578 30.87
Cut Bars @ Ctr 1.00 2.88 6.00 4.17 1.44 1.578 27.27
Cut Bars @ 2 1.00 2.85 6.00 4.21 1.43 1.578 27.08
Cut Bars @ Ctr 1.00 3.15 6.00 3.81 1.58 1.578 29.92
Cut Bars @ 3 1.00 1.75 6.00 6.86 0.88 1.578 16.66
FOURTH FLOOR:
No. of Beams Length, RSB No. of Bars At 12 Bar, No. No. of 16mm Weight Total Wgt.
Pcs. (m) pcs. pcs. pcs. kgs./m Kgs.
Grid 1, 'A-D
Main Bars 1.00 12.44 4.00 1.04 3.86 1.578 73.09
Cut Bars @ A 1.00 1.85 5.00 6.49 0.78 1.578 14.77
Cut Bars @ Ctr 1.00 0.96 5.00 12.50 0.40 1.578 7.57
Cut Bars @ B 1.00 1.80 5.00 6.67 0.75 1.578 14.20
Cut Bars @ Ctr 1.00 2.28 5.00 5.26 0.95 1.578 17.99
Cut Bars @ C 1.00 2.35 5.00 5.11 0.98 1.578 18.56
Cut Bars @ Ctr 1.00 2.49 5.00 4.82 1.04 1.578 19.69
Cut Bars @ D 1.00 1.50 5.00 8.00 0.63 1.578 11.93
Grid A, 1-3
Main Bars 1.00 13.14 4.00 1.10 3.66 1.578 69.31
Cut Bars @ 1 1.00 3.25 6.00 3.69 1.63 1.578 30.87
Cut Bars @ Ctr 1.00 2.88 6.00 4.17 1.44 1.578 27.27
Cut Bars @ 2 1.00 2.85 6.00 4.21 1.43 1.578 27.08
Cut Bars @ Ctr 1.00 3.15 6.00 3.81 1.58 1.578 29.92
Cut Bars @ 3 1.00 1.75 6.00 6.86 0.88 1.578 16.66
ROOF DECK:
No. of Beams Length, RSB No. of Bars At 12 Bar, No. No. of 16mm Weight Total Wgt.
Pcs. (m) pcs. pcs. pcs. kgs./m Kgs.
Grid 1, 'A-D
Main Bars 1.00 12.44 4.00 1.04 3.86 1.578 73.09
Cut Bars @ A 1.00 1.85 2.00 6.49 0.31 1.578 5.87
Cut Bars @ Ctr 1.00 0.96 2.00 12.50 0.16 1.578 3.03
Cut Bars @ B 1.00 1.80 2.00 6.67 0.30 1.578 5.68
Cut Bars @ Ctr 1.00 2.28 2.00 5.26 0.38 1.578 7.20
Cut Bars @ C 1.00 2.35 2.00 5.11 0.40 1.578 7.57
Cut Bars @ Ctr 1.00 2.49 2.00 4.82 0.42 1.578 7.95
Cut Bars @ D 1.00 1.50 2.00 8.00 0.25 1.578 4.73
BEAM STIRUPPS:
GROUND FLOOR:
No. of Length Length St No. of Stirrups at 12m Bar No. of 10mm Total Wgt.
Beam (m) (m) pcs pcs pcs Kgs.
Grid 1,2,3,
A-B 3.00 1.60 1.2 51.00 10.00 5.10 37.70
B-C 3.00 3.80 1.2 93.00 10.00 9.30 68.75
C-D 3.00 3.80 1.2 93.00 10.00 9.30 68.75
Grid 1', A-B 1.00 1.90 1.2 19.00 10.00 1.90 14.04
Grid A,B,C,D, 1-3 8.00 3.80 1.2 312.00 10.00 31.20 230.63
Sub-total (Ground Floor)= 568.00 56.80 419.87
SECOND FLOOR:
No. of Length Length St No of St at 12m Bar No. of 10mm Total Wgt.
Beam (m) (m) pcs pcs pcs Kgs.
Grid 1,2,3,
A-B 3.00 1.60 1.3 51.00 9.23 5.53 40.88
B-C 3.00 3.80 1.3 93.00 9.23 10.08 74.51
C-D 3.00 3.80 1.3 93.00 9.23 10.08 74.51
Grid 1', A-B 1.00 1.90 0.7 19.00 17.14 1.11 8.21
Grid '1, A-B 1.00 1.90 0.9 19.00 13.33 1.43 10.57
Grid '1, B-D 2.00 3.90 0.9 66.00 13.33 4.95 36.59
Grid 2, A-B, St 1.00 1.60 0.7 17.00 17.14 0.99 7.32
Grid 2, A'-A 1.00 1.00 0.7 13.00 17.14 0.76 5.62
Grid A,B,C,D, 1-3 8.00 4.80 1.3 312.00 9.23 33.80 249.85
Grid A,B,C,D, '1-1 4.00 1.20 1.3 52.00 9.23 5.63 41.62
Sub-total (Second Floor)= 735.00 74.36 549.68
THIRD FLOOR:
No. of Length Length St No. of Stirrups at 12m Bar No. of 10mm Total Wgt.
Beam (m) (m) pcs pcs pcs Kgs.
Grid 1,2,3,
A-B 3.00 1.60 1.3 51.00 9.23 5.53 40.88
B-C 3.00 3.80 1.3 93.00 9.23 10.08 74.51
C-D 3.00 3.80 1.3 93.00 9.23 10.08 74.51
Grid 1', 'A-A 1.00 1.00 0.7 13.00 17.14 0.76 5.62
Grid 1', A-B 1.00 1.90 0.7 19.00 17.14 1.11 8.21
Grid '1, A-B 1.00 1.90 0.9 19.00 13.33 1.43 10.57
Grid '1, B-D 2.00 3.90 0.9 66.00 13.33 4.95 36.59
Grid 1, 'A-A 1.00 1.60 0.7 17.00 17.14 0.99 7.32
Grid 2, A-B, St 1.00 1.60 0.7 17.00 17.14 0.99 7.32
Grid 2, A'-A 1.00 1.00 0.7 13.00 17.14 0.76 5.62
Grid A,B,C,D, 1-3 8.00 4.80 1.3 312.00 9.23 33.80 249.85
Grid A,B,C,D, '1-1 4.00 1.20 1.3 52.00 9.23 5.63 41.62
Sub-total (Third Floor)= 765.00 76.11 562.62
FOURTH FLOOR:
No. of Length Length St No. of Stirrups at 12m Bar No. of 10mm Total Wgt.
Beam (m) (m) pcs pcs pcs Kgs.
Grid 1,2,3,
A-B 3.00 1.60 1.3 51.00 9.23 5.53 40.88
B-C 3.00 3.80 1.3 93.00 9.23 10.08 74.51
C-D 3.00 3.80 1.3 93.00 9.23 10.08 74.51
Grid 1', 'A-A 1.00 1.00 0.7 13.00 17.14 0.76 5.62
Grid 1', A-B 1.00 1.90 0.7 19.00 17.14 1.11 8.21
Grid '1, A-B 1.00 1.90 0.9 19.00 13.33 1.43 10.57
Grid '1, B-D 2.00 3.90 0.9 66.00 13.33 4.95 36.59
Grid 1, 'A-A 1.00 1.60 0.7 17.00 17.14 0.99 7.32
Grid 2, A-B, St 1.00 1.60 0.7 17.00 17.14 0.99 7.32
Grid 2, A'-A 1.00 1.00 0.7 13.00 17.14 0.76 5.62
Grid A,B,C,D, 1-3 8.00 4.80 1.3 312.00 9.23 33.80 249.85
Grid A,B,C,D, '1-1 4.00 1.20 1.3 52.00 9.23 5.63 41.62
Sub-total (Fourth Floor)= 765.00 76.11 562.62
ROOF BEAM:
No. of Length Length St No. of Stirrups at 12m Bar No. of 10mm Total Wgt.
Beam (m) (m) pcs pcs pcs Kgs.
Grid 1,2,3,
A-B 3.00 1.60 0.9 51.00 13.33 3.83 28.31
B-C 3.00 3.80 0.9 93.00 13.33 6.98 51.60
C-D 3.00 3.80 0.9 93.00 13.33 6.98 51.60
Grid 1', 'A-A 1.00 1.00 0.9 13.00 13.33 0.98 7.24
Grid 1', A-B 1.00 1.90 0.9 19.00 13.33 1.43 10.57
Grid '1, A-B 1.00 1.90 0.9 19.00 13.33 1.43 10.57
Grid '1, B-D 2.00 3.90 0.9 66.00 13.33 4.95 36.59
Grid 1, 'A-A 1.00 1.60 0.9 17.00 13.33 1.28 9.46
Grid A,B,C,D, 1-3 8.00 4.80 0.9 312.00 13.33 23.40 172.97
Grid A,B,C,D, '1-1 4.00 1.20 0.9 52.00 13.33 3.90 28.83
Sub-total (Roof Beam)= 735.00 55.16 407.74
SECOND FLOOR
Grid '1, A-D 85.00 340.00 0.35 119.00 2.38
Grid 1, A-D 79.00 553.00 0.40 221.20 4.43
Grid 2,3, A-D 158.00 948.00 0.45 426.60 8.54
Grid 1', A-B 19.00 95.00 0.35 33.25 0.67
Grid 2, 'A-B 30.00 150.00 0.35 52.50 1.05
Grid A,B,C,D, '1-3 364.00 2,548.00 0.35 891.80 17.84
Sub-total (Second Floor)= 34.91
THIRD FLOOR
Grid '1, A-D 85.00 340.00 0.35 119.00 2.38
Grid 1, 'A-D 92.00 644.00 0.40 257.60 5.16
Grid 2,3, A-D 158.00 948.00 0.45 426.60 8.54
Grid 1', 'A-B 32.00 160.00 0.35 56.00 1.12
Grid 2, 'A-B 30.00 150.00 0.35 52.50 1.05
Grid A,B,C,D, '1-3 364.00 2,548.00 0.35 891.80 17.84
Sub-total (Third Floor)= 36.09
FOURTH FLOOR
Grid '1, A-D 85.00 340.00 0.35 119.00 2.38
Grid 1, 'A-D 92.00 644.00 0.40 257.60 5.16
Grid 2,3, A-D 158.00 948.00 0.45 426.60 8.54
Grid 1', 'A-B 32.00 160.00 0.35 56.00 1.12
Grid 2, 'A-B 30.00 150.00 0.35 52.50 1.05
Grid A,B,C,D, '1-3 364.00 2,548.00 0.35 891.80 17.84
Sub-total (Fourth Floor)= 36.09
ROOF DECK
Grid '1, A-D 85.00 340.00 0.3 102.00 2.04
Grid 1, 'A-D 92.00 368.00 0.35 128.80 2.58
Grid 2,3, A-D 158.00 632.00 0.35 221.20 4.43
Grid 1', 'A-B 32.00 128.00 0.35 44.80 0.90
Grid A,B,C,D, '1-3 364.00 1,456.00 0.35 509.60 10.20
Sub-total (Roof Deck)= 20.15
RSB No. of Length, RSB No. of Bars At 12 Bar, No. No. of 10mm Weight Total Wgt.
Structure (m) pcs. pcs. pcs. kgs./m Kgs.
Grid A,D, 1-2
Footing 2.00 3.22 3.00 3.73 1.61 0.616 11.90
Ties 2.00 0.55 23.00 21.82 2.11 0.616 15.60
Wall, Hor. 2.00 4.92 23.00 2.44 18.86 0.616 139.41
Wall, Vert. 2.00 6.05 19.00 1.98 19.16 0.616 141.63
Grid 2, A-B
Footing Due to combined footing
B-C 1.00 0.55 9.00 21.82 0.42 0.616 3.10
Wall, Hor. 1.00 1.80 23.00 6.67 3.45 0.616 25.50
Wall, Vert. 1.00 6.05 7.00 1.98 3.53 0.616 26.09
Sub-total (10mm x 12m)= 49.14 363.23
TIE Wire No. No of Bars No. Joints Length of TW Total Length Qty of TW
pcs (m) (m) (kgs)
Grid A,D, 1-2
Footing 2 69.00 138.00 0.3 41.40 0.83
Wall, Hor. 2 437.00 874.00 0.3 262.20 5.25
Grid 2, A-B
Wall, Hor. 1 161.00 161.00 0.3 48.30 0.97
Total, Shear Wall Tie Wire= 7.05
CISTERN TANK
No. of Length, RSB No. of Bars At 12 Bar, No. No. of 10mm Weight Total Wgt.
Structure (m) pcs. pcs. pcs. kgs./m Kgs.
Bottom Slab
x-direction 1.00 2.00 7.00 6.00 1.17 0.616 8.65
y-direction 1.00 1.50 9.00 8.00 1.13 0.616 8.35
Top Slab
x-direction 1.00 2.00 7.00 6.00 1.17 0.616 8.65
y-direction 1.00 1.50 9.00 8.00 1.13 0.616 8.35
4.60 34.00
Less: Manhole= 3.02
Sub-total (10mm x 12m)= 4.00 30.98
TIE Wire No. No of Bars No. Joints Length of TW Total Length Qty of TW
pcs (m) (m) (kgs)
STAIRS
No. of Length, RSB No. of Bars At 12 Bar, No. No. of 10mm Weight Total Wgt.
Structure (m) pcs. pcs. pcs. kgs./m Kgs.
Ground Floor to Second Floor
Bottom bars 2.00 4.26 8.00 2.82 5.68 0.616 41.99
BB, Horizontal 2.00 0.77 13.00 15.58 1.67 0.616 12.34
Top bars 2.00 4.30 5.00 2.79 3.59 0.616 26.54
TB, Horizontal 2.00 0.77 15.00 15.58 1.93 0.616 14.27
Cut Bars 2.00 0.80 8.00 15.00 1.07 0.62 7.91
2.00 2.20 8.00 5.45 2.94 0.62 21.73
Landing, Hor 2.00 1.87 8.00 6.42 2.50 0.62 18.48
TIE Wire No. No of Bars No. Joints Length of TW Total Length Qty of TW
pcs (m) (m) (kgs)
Ground Floor to Second Floor
Bottom bars 2.00 104.00 208.00 0.3 62.40 1.25
Top bars 2.00 75.00 150.00 0.3 45.00 0.90
Cut Bars 2.00 64.00 128.00 0.3 38.40 0.77
Landing 1.00 64.00 64.00 0.3 19.20 0.39
5.10638298
4.52830189
5.58139535
6.48648649
5.33333333
2.82352941
402.56 7,622.88
177.12
1.125 3.696 66.528
H 2100
H/2 1050
7.5 2 50 100 7.5
5 100 500 9.6 2.4
3 150 450 -2.4
10 1050
13.6363636
h 3050 24
H/2 1525
18.75 2 50 100
4 100 400
3 150 450
3 200 600 950
12 1550 3100
7.5
h 2750
H/2 1375
2 50 100 8.57142857 8
4 100 400
3 150 450
13.6363636 2 200 400 950
11 1350 2700 -25
18.75
8.57142857
24
12
8.57142857
12
8.57142857
24
20 8.57142857
20
h 2800 h 2500
2 8.57142857 2 50 100 2 50 100
6 100 600 6 100 600
1 6 150 900 4 150 600
2 6 200 1200 6 200 1200
1 20 2800 18 2500
1
3 h 1100 h 2300
2 50 100 2 50 100
4 100 400 6 100 600
2,004.41 4 150 600 4 150 600
518.15882 200 0 5 200 1000
10 1100 17 2300
h 3200
2 50 100
6 100 600
6 150 900
8 200 1600
22 3200
17.6736
5.87016
7.89
5.87016
275.2032
45.4464
79.5312
71.9568
79.5312
45.4464
1,075.06
l 1600 l 3800
H/2 800 H/2 1900
2 50 100 1 50 50
4 100 400 5 100 500
2 150 300 9 150 1350
8 800 15 1900
l 1900 l 4800
H/2 950 H/2 2400
2 50 100 2 50 100
4 100 400 5 100 500
3 150 450 12 150 1800
9 950 19 2400
l 3900 l 1200
H/2 1950 H/2 600
2 50 100 1 50 50
5 100 500 4 100 400
9 150 1350 1 150 150
16 1950 6 600
l 1000
H/2 500
2 50 100
4 100 400
150 0
6 500
2502.48768
RSB
L W H # VOL CONC T L
# L TL # L TL
142.8 0.1 1 14.28 4.33333 1 618.8 4.33333 1 618.8
14.994
spended Slab
111.3 0.1 1 0 6.92593 1 770.85556 6.92593 1 770.856
0
RSB NO. OF PCS.
WT FORMS 10 mm DIA.
762.362 103.13333333
800.48 109
FRONT
GF - 2nd Grid 1, A-B 3.50 1.60 5.60 0.72 3.36
Grid 1', B-D 3.50 8.4 29.40 15.36
Grid 2, A-B 3.50 2.00 7.00
Grid 2', A-B 3.50 2.00 7.00
Grid 2'', C-D 3.50 2.20 7.70 1.47
Grid 2''', C'-D 3.50 2.20 7.70
Grid 2'''', A-D 3.50 8.40 29.40
REAR
F-Wall Grid 3, A-D 3.50 10.50 36.75 7.70 4.10
LEFT SIDE
GF - 2nd Grid A, 1-2 3.50 5.30 18.55
Grid A, 2-2' 3.50 4.00 14.00 1.40 1.76 3.57 0.24
Grid B, 1-2 3.50 4.90 17.15 2.16 1.47
Grid B, 2-2' 3.50 2.00 7.00 0.90 1.47
Grid B, 2'-3 3.50 1.20 4.20 1.89
Grid C, 1'-2' 3.50 7.20 25.20 2.98
Grid C', 2-3 3.50 1.80 6.30 1.47
RIGHT SIDE
Grid D, 1-2 3.50 5.30 18.55
Grid D, 2-3 3.50 5.30 18.55 3.06 2.16
Sub-total 260.05 15.14 11.79 30.06 0.24
SUMMARY:
LEFT SIDE
2nd - 3rd Grid A, 1'-1 3.20 1.50 4.80
Grid A, 1-2 3.20 5.30 16.96 1.92 0.54 0.44
Grid B, 1-2 3.20 5.30 16.96 1.92 2.16
Grid B, 2-3 3.20 3.90 12.48 1.28 1.76 1.89 2.4
Grid B', 2'-3' 3.20 2.90 9.28 1.47
Grid C, '1-1 3.20 1.60 5.12 0.54
Grid C, 1-2' 3.20 6.30 20.16 2.56 2.61 3.36
Grid C, 2'-2" 3.20 2.90 9.28
RIGHT SIDE
Grid D, 1-3 3.20 13.30 42.56 4.48 5.45
Sub-total 257.28 18.56 22.87 13.65 9.68
SUMMARY
LEFT SIDE
3rd - 4rth Grid A, 1'-1 3.20 1.50 4.80 0.59
Grid 'A, 1-2 3.20 5.60 17.92 1.92 6.435
Grid A', 1-2 3.20 5.30 16.96
Grid B, 2-3 3.20 3.90 12.48 1.28 1.76 1.89 2.4
Grid B', 2'-2" 3.20 2.90 9.28 1.47
Grid C, '1-1 3.20 1.60 5.12 0.59
Grid C, 1-2' 3.20 6.30 20.16 2.56 2.61 3.36
Grid C', 2'-2" 3.20 2.90 9.28
RIGHT SIDE
Grid D, 1-3 3.20 13.30 42.56 4.48 4.10
Sub-total 260.48 16.64 18.46 13.65 15.68
SUMMARY
LEFT SIDE
4rth-RD Grid A, 1'-1 3.20 1.50 4.80 0.39
Grid 'A, 1-2 3.20 5.60 17.92 7.04
Grid A', 1-2 3.20 5.30 16.96 0.30
Grid B, 2-3 3.20 3.90 12.48 1.28 1.17 1.89 2.4
Grid B', 2'-2'' 3.20 2.90 9.28 1.47
Grid C, '1-1 3.20 1.60 5.12 0.72
Grid C, 1-2' 3.20 6.30 20.16 2.56 1.92 3.36
Grid C, 2'-2" 3.20 2.90 9.28
RIGHT SIDE
Grid D, 1-3 3.20 13.30 42.56 4.48 3.36
Sub-total 260.48 14.72 17.84 13.65 16.28
SUMMARY
RIGHT SIDE
Grid D, 1-3 2.30 13.30 30.59 2.76
Sub-total 124.25 5.68 0.00 2.94 3.32
SUMMARY
Net Area
(Sq m)
5.52 6" CHB
Shear wall
7.04 6" CHB
13.52 4" CHB
4.63 4" CHB
2.31 4" CHB
22.23 4" CHB
4.83 4" CHB
Shear wall
13.33 6" CHB
Net Area
(Sq m)
Net Area
(Sq m)
Net Area
(Sq m)
Net Area
(Sq m)
MEZZANINE FLOOR
UNIT PRICE
ITEMS QTY UNIT
MATERIALS LABOR CONTINGENCY
FLOOR
1 4" x 4" x 7 4 PCS 3,070.00 3,070.00 921.00
2 2" x 2" x 4 3 PCS 1,294.00 1,294.00 388.20
3 2" x 4" x 1. 19 PCS 1,098.00 1,098.00 329.40
4 2" x 2" x 1. 1 PCS 781.00 781.00 234.30
5 1/2" Dyna B 32 PCS 50.00 50.00 15.00
6 1/2" Concrete 1 PCS 450.00 450.00 135.00
7 5/32" Steel D 4 PCS 105.00 105.00 31.50
8 3/8" Steel Dr 2 PCS 295.00 295.00 88.50
9 Welding Ro 8 KGS 100.00 100.00 30.00
10 4" Cutting D 12 PCS 35.00 35.00 10.50
11 1/2" Phenol 14 PCS 750.00 750.00 225.00
12 1 1/2" Blac 2 BOX 220.00 220.00 66.00
13 Red Oxide 3 GAL 420.00 420.00 126.00
14 Paint Thinne 3 LIT 150.00 150.00 45.00
15 4" Paint Roll 3 PCS 80.00 80.00 24.00
16 4" Paint Bru 3 PCS 60.00 60.00 18.00
17 Paint Tray 2 PCS 180.00 180.00 54.00
SUB-TOTAL
WALL
1 4.5mm Ficem Board7 PCS 430.00 258.00 103.20
2 0.5mm Metal Stud12 PCS 195.00 117.00 46.80
3 0.5mm Metal Track10 PCS 195.00 117.00 46.80
4 5/32 x 1/2" Blind Rivet
1 BOX 500.00 300.00 120.00
5 1/2" Hardie Screw1 BOX 700.00 420.00 168.00
6 Hardie Putty 2 GAL 350.00 210.00 84.00
Hardie
7 Perporated 1 PCS 300.00 180.00 72.00
Tape
Sand Paper
8 (#120 & 1 M 250.00 150.00 60.00
#80)
Primer -
9 1 GAL 900.00 540.00 216.00
Flat Latex
16
12.8
6.4
19.8
12
14.4
3
42
WELD 126.4 m 17.696
21.075
418,970.30
UNIT PRICE AMOUNT
7,061.00 28,244.00
2,976.20 8,928.60
2,525.40 47,982.60
1,796.30 1,796.30
115.00 3,680.00
1,035.00 1,035.00
241.50 966.00
678.50 1,357.00
230.00 1,840.00
80.50 966.00
1,725.00 24,150.00
506.00 1,012.00
966.00 2,898.00
345.00 1,035.00
184.00 552.00
138.00 414.00
414.00 828.00
SUB-TOTAL 127,684.50
791.20 5,538.40
358.80 4,305.60
358.80 3,588.00
920.00 920.00
1,288.00 1,288.00
644.00 1,288.00
552.00 552.00
460.00 460.00
1,656.00 1,656.00
1,288.00 1,288.00
14,720.00 29,440.00
SUB-TOTAL 50,324.00
TOTAL 178,008.50
SUMMARY OF EQUIPMENT RENTAL, LABOR RATES & MATERIAL COST
CONSTRUCTION MATERIALS
228 42.77673546
700
450
12.9179532 320.00
220 88
5.92072855 82.67490048
749.320527
999 166
0.45
ROOF DECK
Tiles
Materials Unit Qty. Unit Cost
a. Floor Tiles 30cm x 30cm Pcs 1,252.00 69.00
b. Tile Adhesive Bag 23.00 350.00
c. Tile grout Kg. 29.00 150.00
d. Sand Cu m 6.00 400.00
Sub-total
Second Floor
Third Floor
Fourth Floor
Roof Deck
GRILLS
UNIT COST
ITEM QUANTITY UNIT
MATERIAL LABORCONTINGENCY
10mm Square bar 30 pcs 219.65 87.86 46.1265
40mm x 3mm Flat 7 pcs 336 134.4 70.56
Miscelleneous
4" Cutting Disk 15 pcs 35 14 7.35
Welding Rod 7 kgs 100 40 21
Red Oxide Primer 1 pail 2021 808.4 424.41
Paint Thinner 1 gal 400 160 84
QDE Top Coat Paint 1 pail 3488 1395.2 732.48
1" Paint Brush 4 pcs 40 16 8.4
TOTAL 6639.65 2655.86 1394.327
CK
or Plastering Works
Qty=
or Painting Works
Qty=
k
i
Lumpsum
AMOUNT
10,609.10
3,786.72
845.25
1,127.00
3,253.81
644.00
5,615.68
257.60
26,139.16
Rubber Paint Works
Unit Qty. Unit Cost Materials Cost Labor Cost Contingency Total Cost
gal 11.00 3,080.00 33,880.00 13,552.00 7,114.80 54,546.80
gal 11.00 1,547.00 17,017.00 6,806.80 3,573.57 27,397.37
gal 2.00 800.00 1,600.00 640.00 336.00 2,576.00
Pcs 2.00 80.00 160.00 64.00 33.60 257.60
Pcs 2.00 85.00 170.00 68.00 35.70 273.70
Pcs 2.00 70.00 140.00 56.00 29.40 225.40
Sub-total 52,967.00 21,186.80 11,123.07 85,276.87
41.24 sq.m.
Qty. Unit Cost Materials Cost Labor Cost Contingency Total Cost
19.00 290.00 5,510.00 5,510.00 1,653.00 12,673.00
19.00 60.00 1,140.00 1,140.00 342.00 2,622.00
1.55 1,000.00 1,550.00 1,550.00 465.00 3,565.00
2.00 195.00 390.00 390.00 117.00 897.00
Sub-total 8,200.00 8,200.00 2,460.00 18,860.00
41.24 sq.m.
Qty. Unit Cost Materials Cost Labor Cost Contingency Total Cost
2 90.00 180.00 108.00 43.20 331.20
6 650.00 3,900.00 2,340.00 936.00 7,176.00
14 450.00 6,300.00 3,780.00 1,512.00 11,592.00
6 714.00 4,284.00 2,570.40 1,028.16 7,882.56
14 650.00 9,100.00 5,460.00 2,184.00 16,744.00
4 85.00 340.00 204.00 81.60 625.60
4 70.00 280.00 168.00 67.20 515.20
3 80.00 240.00 144.00 57.60 441.60
9 120.00 1,080.00 648.00 259.20 1,987.20
25 900.00 22,500.00 13,500.00 5,400.00 41,400.00
5 290 1,450.00 870.00 348.00 2,668.00
2 250.00 500.00 300.00 120.00 920.00
Sub-total 10,380.00 6,228.00 2,491.20 92,283.36
200,022.95
Multi-Rib Cladding Finish
Unit Cost
Item Quantity Unit
Material Cost Labor Contingency Unit Price
0.4mm MultiRib (std.) 200.2 l.m. 320.00 256.00 86.40 662.40
0.4mm Plain Sheet 13 l.m. 320.00 256.00 86.40 662.40
Welding Rod 8 kg 100.00 80.00 27.00 207.00
4" x 4" x 7mm Angle Bar 5 pcs 3,070.00 2,456.00 828.90 6,354.90
2" x 2" x 4mm Angle Bar 12 pcs 1,294.00 1,035.20 349.38 2,678.58
1/2" Dyna Bolt 36 pcs 50.00 40.00 13.50 103.50
Red Oxide 6 gal 420.00 336.00 113.40 869.40
2" x 3" x 6mm C-Purlins 36 pcs 1,317.60 1,054.08 355.75 2,727.43
1/2" Concrete Drill Bit 1 pcs 450.00 360.00 121.50 931.50
5/32" Steel Drill Bit 4 pcs 105.00 84.00 28.35 217.35
3/8" Steel Drill Bit 2 pcs 295.00 236.00 79.65 610.65
Bolt 920 pcs 20.00 16.00 5.40 41.40
50mm Tok Screws 3156 pcs 2.65 2.12 0.72 5.49
Total 14,265.61
VS
Total
7,508.96 2.0742143
15,999.29
16,010.41
15,992.52
5,997.01
61,508.18
Total
15,392.00
30,784.01
30,784.01
30,784.01
10,261.34
118,005.35
179,513.53
DETAILED ESTIMATES
2.1 FOOTING
Qty= 23.60 Cu. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 24.78 4,608.00 114,186.24 45,674.50 159,860.74
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 3,425.59 3,425.59 1,370.24 4,795.83
Sub-total 117,611.83 47,044.74 164,656.57
2.2 BEAMS
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 7.23 4,608.00 33,336.58 13,334.63 46,671.21
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,000.10 1,000.10 400.04 1,400.14
C. Pumpcrete w/ accessories Cu m 7.23 250.00 1,808.63 723.45 2,532.08
Sub-total 36,145.31 14,458.12 50,603.43
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 11.75 4,608.00 54,141.70 21,656.68 75,798.38
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,624.25 1,624.25 649.70 2,273.95
C. Pumpcrete w/ accessories Cu m 11.75 300.00 3,524.85 1,409.94 4,934.79
Sub-total 59,290.80 23,716.32 83,007.12
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 11.95 4,608.00 55,060.99 22,024.40 77,085.39
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,651.83 1,651.83 660.73 2,312.56
C. Pumpcrete w/ accessories Cu m 11.95 350.00 4,182.15 1,672.86 5,855.01
Sub-total 60,894.97 24,357.99 85,252.96
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 11.15 4,608.00 51,383.81 20,553.52 71,937.33
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,541.51 1,541.51 616.60 2,158.11
C. Pumpcrete w/ accessories Cu m 11.15 400.00 4,460.40 1,784.16 6,244.56
Sub-total 57,385.72 22,954.28 80,340.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 7.20 4,608.00 33,191.42 13,276.57 46,467.99
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 995.74 995.74 398.30 1,394.04
C. Pumpcrete w/ accessories Cu m 7.20 450.00 3,241.35 1,296.54 4,537.89
Sub-total 37,428.51 14,971.41 52,399.92
2.3 COLUMNS
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 15.37 4,608.00 70,834.18 28,333.67 99,167.85
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 2,125.03 2,125.03 850.01 2,975.04
C. Pumpcrete w/ accessories Cu m 15.37 250.00 3,843.00 1,537.20 5,380.20
Sub-total 76,802.21 30,720.88 107,523.09
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 7.15 4,608.00 32,949.50 13,179.80 46,129.30
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 988.49 988.49 395.40 1,383.89
C. Pumpcrete w/ accessories Cu m 7.15 300.00 2,145.15 858.06 3,003.21
Sub-total 36,083.14 14,433.26 50,516.40
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 7.15 4,608.00 32,949.50 13,179.80 46,129.30
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 988.49 988.49 395.40 1,383.89
C. Pumpcrete w/ accessories Cu m 7.15 350.00 2,502.68 1,001.07 3,503.75
Sub-total 36,440.67 14,576.27 51,016.94
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 7.15 4,608.00 32,949.50 13,179.80 46,129.30
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 988.49 988.49 395.40 1,383.89
C. Pumpcrete w/ accessories Cu m 7.15 400.00 2,860.20 1,144.08 4,004.28
Sub-total 36,798.19 14,719.28 51,517.47
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 3.56 4,608.00 16,402.18 6,560.87 22,963.05
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 492.07 492.07 196.83 688.90
C. Pumpcrete w/ accessories Cu m 3.56 450.00 1,601.78 640.71 2,242.49
Sub-total 18,496.03 7,398.41 25,894.44
Materials Unit Qty. Unit Cost Materials Cost Labor Cost S&C
a. Ready Mix Concrete(plus 5% loss) Cu m 1.95 4,608.00 8,995.55 3,598.22 1,889.07
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 2,072.77 2,072.77 829.11 435.28
a. RSB, Grade 60 Kgs. 17.96 55.00 987.80 395.12 1,382.92
C. Rough finish Cu m 1.95 350.00 683.26 273.30 143.48
Sub-total 12,739.38 5,095.75 3,850.75
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 14.99 4,608.00 69,092.35 27,636.94 96,729.29
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 2,072.77 2,072.77 829.11 2,901.88
C. Pumpcrete w/ accessories Cu m 14.99 350.00 5,247.90 2,099.16 7,347.06
Sub-total 76,413.02 30,565.21 106,978.23
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 13.04 4,608.00 60,092.93 24,037.17 84,130.10
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,802.79 1,802.79 721.12 2,523.91
C. Pumpcrete w/ accessories Cu m 13.04 350.00 4,564.35 1,825.74 6,390.09
Sub-total 66,460.07 26,584.03 93,044.10
2.4.3 3F Qty= 12.89 Cu. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 13.53 4,608.00 62,366.98 24,946.79 87,313.77
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,871.01 1,871.01 748.40 2,619.41
C. Pumpcrete w/ accessories Cu m 13.53 350.00 4,737.08 1,894.83 6,631.91
Sub-total 68,975.07 27,590.02 96,565.09
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 13.56 4,608.00 62,463.74 24,985.50 87,449.24
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,873.91 1,873.91 749.56 2,623.47
C. Pumpcrete w/ accessories Cu m 13.56 400.00 5,422.20 2,168.88 7,591.08
Sub-total 69,759.85 27,903.94 97,663.79
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 11.67 4,608.00 53,754.62 21,501.85 75,256.47
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,612.64 1,612.64 645.06 2,257.70
C. Pumpcrete w/ accessories Cu m 11.67 450.00 5,249.48 2,099.79 7,349.27
Sub-total 60,616.74 24,246.70 84,863.44
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 12.94 4,608.00 59,609.09 23,843.64 83,452.73
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 1,788.27 1,788.27 715.31 2,503.58
C. Pumpcrete w/ accessories Cu m 12.94 300.00 3,880.80 1,552.32 5,433.12
Sub-total 65,278.16 26,111.27 91,389.43
2.6 STAIRS
Qty= 4.38 Cu. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Ready Mix Concrete(plus 5% loss) Cu m 4.60 4,608.00 21,192.19 8,476.88 29,669.07
b. Misc. Hardwares (3% of Materials Cost) Lot 1.00 635.77 635.77 254.31 890.08
Sub-total 21,827.96 8,731.19 30,559.15
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. RSB, Grade 60 Kgs. 30,562.88 52.50 1,604,551.02 641,820.41 2,246,371.43
b. # 16 Tie Wire Kgs. 386.89 80.00 30,951.20 12,380.48 43,331.68
c. Misc. Hardwares(2% of Materials) Lot 1.00 32,710.04 32,710.04 13,084.02 45,794.06
Sub-total 1,668,212.26 667,284.91 2,335,497.17
2.8.1 Footing to GF
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 4'x8'x1/4" Phenolic Board Pc. 9.00 950.00 8,550.00 3,420.00 11,970.00
b. 2"x3"x8' Rough Lumber Pc. 96.00 240.00 23,040.00 9,216.00 32,256.00
c. 2"x2"x8' Rough Lumber Pc. 48.00 180.00 8,640.00 3,456.00 12,096.00
d. Assorted CWN Kgs. 5.00 80.00 400.00 160.00 560.00
Sub-total 40,630.00 16,252.00 56,882.00
2.8.3 GF To 3F Columns
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 4'x8'x1/4" Phenolic Board Pc. 89.00 950.00 84,550.00 33,820.00 118,370.00
b. 2"x3"x8' Rough Lumber Pc. 144.00 240.00 34,560.00 13,824.00 48,384.00
c. 2"x2"x8' Rough Lumber Pc. 72.00 180.00 12,960.00 5,184.00 18,144.00
d. Assorted CWN Kgs. 11.00 80.00 880.00 352.00 1,232.00
Sub-total 132,950.00 53,180.00 186,130.00
2.8.4 2F Beams
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 4'x8'x1/4" Phenolic Board Pc. 17.00 950.00 16,150.00 6,460.00 22,610.00
b. 2"x3"x8' Rough Lumber Pc. 34.00 240.00 8,160.00 3,264.00 11,424.00
c. 2"x2"x8' Rough Lumber Pc. 9.00 180.00 1,620.00 648.00 2,268.00
d. Assorted CWN Kgs. 7.00 80.00 560.00 224.00 784.00
Sub-total 26,490.00 10,596.00 37,086.00
2.8.5 2F To 3F Columns
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 4'x8'x1/4" Phenolic Board Pc. 20.00 950.00 19,000.00 7,600.00 26,600.00
b. 2"x3"x8' Rough Lumber Pc. 144.00 240.00 34,560.00 13,824.00 48,384.00
c. 2"x2"x8' Rough Lumber Pc. 72.00 180.00 12,960.00 5,184.00 18,144.00
d. Assorted CWN Kgs. 11.00 80.00 880.00 352.00 1,232.00
Sub-total 67,400.00 26,960.00 94,360.00
2.8.6 3F Beams
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 4'x8'x1/4" Phenolic Board Pc. 15.00 80.00 1,200.00 0.00 1,200.00
b. 2"x3"x8' Rough Lumber Pc. 64.00 300.00 19,200.00 0.00 19,200.00
c. 2"x2"x8' Rough Lumber Pc. 11.00 1,700.00 18,700.00 0.00 18,700.00
d. Assorted CWN Kgs. 7.00 60.00 420.00 0.00 420.00
Sub-total 39,520.00 0.00 39,520.00
Note: FORMS of the Ground Beam/Column to Third Floor Column/Beam will be re-use in
the Third floor column to the roof column/beam.
2.9 SCAFFOLDINGS
Qty= 1.00 Lot
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Assorted GI Pipe scaffolding materials
with complete accessories.
at Rental Basis Lumpsum 1.00 200,000.00 200,000.00 80,000.00 280,000.00
Sub-total 200,000.00 80,000.00 280,000.00
9,072,203.18
106,200.00
164,656.57
91,389.43
11,453.10
2,335,497.17
AT No of forms
HT WD 2.4 PnB say No. of PnB
2 0.45 5.333333 5 24 4.8 5
0.35 6.857143 6 24 4 4
56,882.00
AT
HT WD 2.4 PnB No. of PnB
2 4.8 4 16
1.6 1.333333 2.666667 3
53,102.00
AT No of forms at 3.05m ht
HT WD 2.4 PnB say No. of PnB no of forms
3.05 0.45 2.666667 2 24 12 12 1.5 18
0.35 3.428571 3 24 8 8 1.5 12
186,130.00
AT No of forms
Length WD 2.4 PnB say No. of PnB
4.8 0.45 5.333333 5 57.5 11.5 12
0.45 5.333333 8 28 3.5 3.5
0.45 1 8 10 1.25 1.5
1.625 1.5
Slab
10.5 8.75 9 45
10.6 4.416667 5
AT No of forms
Length WD 2.4 PnB say No. of PnB
4.8 0.45 5.333333 5 32 6.4 7
0.3 8 8 32 4 4
0.25 1 8 32 4 4
DETAILED ESTIMATES
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. CHB 4" thk Pc. 1,489.00 14.00 20,846.00 8,338.40 29,184.40
b. CHB 6" thk Pc. 668.00 19.00 12,692.00 5,076.80 17,768.80
c. Portland Cement Bag 176.00 245.00 43,120.00 17,248.00 60,368.00
d. Washed Sand Cu m 10.00 400.00 4,000.00 1,600.00 5,600.00
e. 10mmØ x 6m RSB Kg. 412.00 52.50 21,630.00 8,652.00 30,282.00
f. G.I Tie Wire Kg. 6.00 80.00 480.00 192.00 672.00
Sub-total 102,768.00 41,107.20 143,875.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 199.00 245.00 48,755.00 19,502.00 68,257.00
b. Washed Sand Cu m 7.00 400.00 2,800.00 1,120.00 3,920.00
Sub-total 51,555.00 20,622.00 72,177.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 3.00 245.00 735.00 294.00 1,029.00
b. Washed Sand Cu m 3.00 400.00 1,200.00 480.00 1,680.00
Sub-total 1,935.00 774.00 2,709.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Conc. Neutralizer Gal 16.00 90.00 1,440.00 576.00 2,016.00
b. Paint Primer Gal 16.00 650.00 10,400.00 4,160.00 14,560.00
c. Masonry Putty Gal 22.00 450.00 9,900.00 3,960.00 13,860.00
d. Finishing Paint, Semi-gloss Gal 32.00 714.00 22,848.00 9,139.20 31,987.20
e. Skim coat Bag 11.00 650.00 7,150.00 2,860.00 10,010.00
f. Assorted Paint Brush Pc. 27.00 70.00 1,890.00 756.00 2,646.00
g. Assorted Paint Roller Pc. 20.00 85.00 1,700.00 680.00 2,380.00
h. Roller Pan Pc. 12.00 80.00 960.00 384.00 1,344.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 2,100.00
j. Waterproofing (Flexibond) Gal 21.00 1,700.00 35,700.00 14,280.00 49,980.00
k. Cement Bag 4.00 245.00 980.00 392.00 1,372.00
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 2,940.00
Sub-total 96,568.00 38,627.20 135,195.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Polished Floor Tiles 60cm x 60cm Pc. 197.00 250.00 49,250.00 19,700.00 68,950.00
b. Non- Skid Floor Tiles 30cm x 30cm Pc. 180.00 90.00 16,200.00 6,480.00 22,680.00
c. Cement Mortar Bag 54.00 245.00 13,230.00 5,292.00 18,522.00
d. Tile Adhesive Bag 10.00 350.00 3,500.00 1,400.00 4,900.00
e. Tile grout Kg. 43.00 150.00 6,450.00 2,580.00 9,030.00
f. Sand Cu m 4.00 400.00 1,600.00 640.00 2,240.00
Sub-total 90,230.00 36,092.00 126,322.00
1.1.c.2 CR Tiles
LS CR Floor Tiles= 2.77 Sq. m.
RS CR Floor Tiles= 3.05 Sq. m.
LS CR Wall Tiles= 14.20 Sq. m. Height of wall tiles=2.00m
RS CR Wall Tiles= 12.60 Sq. m. Height of wall tiles=2.00m
Qty= 32.62 Sq. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Floor Tiles 20cm x 20cm Pc. 153.00 20.00 3,060.00 1,224.00 4,284.00
b. Wall Tiles 20cm x 30cm Pc. 469.00 30.00 14,070.00 5,628.00 19,698.00
c. Cement Mortar Bag 26.00 245.00 6,370.00 2,548.00 8,918.00
d. Tile Adhesive Bag 4.00 350.00 1,400.00 560.00 1,960.00
e. Tile grout Kg. 18.00 150.00 2,700.00 1,080.00 3,780.00
f. Sand Cu m 2.00 400.00 800.00 320.00 1,120.00
g. Tile trim Pc. 4.00 199.00 796.00 318.40 1,114.40
Sub-total 29,196.00 11,678.40 40,874.40
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 307.00 245.00 75,215.00 30,086.00 105,301.00
b. Washed Sand Cu m 17.00 400.00 6,800.00 2,720.00 9,520.00
c. Gravel Cu m 27.00 400.00 10,800.00 4,320.00 15,120.00
d. Formwork L.S. 5% of Material cost 4,640.75 1,856.30 6,497.05
Sub-total 97,455.75 38,982.30 136,438.05
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Water closet/Lavatory w/ Acces. Set 2.00 15,500.00 31,000.00 12,400.00 43,400.00
b. Urinal Set 2.00 4,560.00 9,120.00 3,648.00 12,768.00
Sub-total 40,120.00 16,048.00 56,168.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Fiber Cement Board pc 5.00 485.00 2,425.00 970.00 3,395.00
b. Metal double furring Channel pc 4.00 170.00 680.00 272.00 952.00
c. Metal carrying channel pc 4.00 150.00 600.00 240.00 840.00
d. Wall Angle 1'' x 1'' x 10' pc 6.00 75.00 450.00 180.00 630.00
e. Blind Rivets pc 144 1.50 216.00 86.40 302.40
f. Toks with screw pc 56 6.00 336.00 134.40 470.40
g. W-clip pc 18 5.00 90.00 36.00 126.00
Sub-total 4,797.00 1,918.80 6,715.80
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. D1: Main Door (900x2100) set 1.00 12,500.00 12,500.00 5,000.00 17,500.00
b. D2: Solid Door (800x2100) set 1.00 9,000.00 9,000.00 3,600.00 12,600.00
c. D3: CR Door (700x2100) set 4.00 3,750.00 15,000.00 6,000.00 21,000.00
d. D5: Aluminum Frame (1600x2100) set 1.00 9,240.00 9,240.00 3,696.00 12,936.00
e. D6: Glass Door w/ Tempered Glass (3200x2400) set 2.00 61,950.00 123,900.00 49,560.00 173,460.00
f. D7: Main Door (1000x2100) set 1 13,500.00 13,500.00 5,400.00 18,900.00
g. W6: Aluminum Sliding (600x400) set 1 1,600.00 1,600.00 640.00 2,240.00
Sub-total 184,740.00 73,896.00 258,636.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 2.00 90.00 180.00 72.00 252.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,985.00 2,394.00 8,379.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. CHB 4" thk Pc. 1,367.00 14.00 19,138.00 7,655.20 26,793.20
b. CHB 6" thk Pc. 1,161.00 19.00 22,059.00 8,823.60 30,882.60
c. Portland Cement Bag 229.00 245.00 56,105.00 22,442.00 78,547.00
d. Washed Sand Cu m 13.00 400.00 5,200.00 2,080.00 7,280.00
e. 10mmØ x 6m RSB Kg. 483.00 52.50 25,357.50 10,143.00 35,500.50
f. G.I Tie Wire Kg. 7.00 80.00 560.00 224.00 784.00
Sub-total 128,419.50 51,367.80 179,787.30
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 209.00 245.00 51,205.00 20,482.00 71,687.00
b. Washed Sand Cu m 7.00 400.00 2,800.00 1,120.00 3,920.00
Sub-total 54,005.00 21,602.00 75,607.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Conc. Neutralizer Gal 16.00 90.00 1,440.00 576.00 2,016.00
b. Paint Primer Gal 16.00 650.00 10,400.00 4,160.00 14,560.00
c. Masonry Putty Gal 22.00 450.00 9,900.00 3,960.00 13,860.00
d. Finishing Paint, Semi-gloss Gal 32.00 714.00 22,848.00 9,139.20 31,987.20
e. Skim coat Bag 11.00 650.00 7,150.00 2,860.00 10,010.00
f. Assorted Paint Brush Pc. 27.00 70.00 1,890.00 756.00 2,646.00
g. Assorted Paint Roller Pc. 20.00 85.00 1,700.00 680.00 2,380.00
h. Roller Pan Pc. 12.00 80.00 960.00 384.00 1,344.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 2,100.00
j. Waterproofing (Flexibond) Gal 36.00 1,700.00 61,200.00 24,480.00 85,680.00
k. Cement Bag 7.00 245.00 1,715.00 686.00 2,401.00
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 2,940.00
Sub-total 122,803.00 49,121.20 171,924.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Polished Floor Tiles 60cm x 60cm Pc. 304.00 250.00 76,000.00 30,400.00 106,400.00
b. Non- Skid FloorTiles 30cm x 30cm Pc. 443.00 90.00 39,870.00 15,948.00 55,818.00
c. Cement Mortar Bag 16.00 245.00 3,920.00 1,568.00 5,488.00
d. Tile Adhesive Bag 14.00 350.00 4,900.00 1,960.00 6,860.00
e. Tile grout Kg. 61.00 150.00 9,150.00 3,660.00 12,810.00
f. Sand Cu m 6.00 400.00 2,400.00 960.00 3,360.00
Sub-total 136,240.00 54,496.00 190,736.00
1.2.c.2 CR Tiles
Floor Tiles= 3.69 Sq. m.
Wall Tiles= 18.80 Sq. m. Height of wall tiles=2.00m
Qty= 22.49 Sq. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Floor Tiles 20cm x 20cm Pc. 97.00 20.00 1,940.00 776.00 2,716.00
b. Wall Tiles 20cm x 30cm Pc. 329.00 30.00 9,870.00 3,948.00 13,818.00
c. Cement Mortar Bag 3.00 245.00 735.00 294.00 1,029.00
d. Tile Adhesive Bag 3.00 350.00 1,050.00 420.00 1,470.00
e. Tile grout Kg. 12.00 150.00 1,800.00 720.00 2,520.00
f. Sand Cu m 2.00 400.00 800.00 320.00 1,120.00
g. Tile trim Pc. 3.00 199.00 597.00 238.80 835.80
Sub-total 16,792.00 6,716.80 23,508.80
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 4.00 245.00 980.00 392.00 1,372.00
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 560.00
c. Gravel Cu m 1.00 400.00 400.00 160.00 560.00
d. 12mm Dia. RSB Kgs 26.65 43.00 1,145.95 458.38 1,604.33
e. Formworks L.S. 5% of Material cost 146.30 58.52 204.82
Sub-total 3,072.25 1,228.90 4,301.15
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Water closet/Lavatory w/ Acces. Set 1.00 15,500.00 15,500.00 6,200.00 21,700.00
b. Urinal Set 1.00 4,560.00 4,560.00 1,824.00 6,384.00
c. Kitchen sink Set 1.00 3,000.00 3,000.00 1,200.00 4,200.00
Sub-total 23,060.00 9,224.00 32,284.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Fiber Cement Board pc 30.00 485.00 14,550.00 5,820.00 20,370.00
b. Metal double furring Channel pc 34.00 170.00 5,780.00 2,312.00 8,092.00
c. Metal carrying channel pc 16.00 150.00 2,400.00 960.00 3,360.00
d. Wall Angle 1'' x 1'' x 10' pc 13.00 75.00 975.00 390.00 1,365.00
e. Blind Rivets pc 116 1.50 174.00 69.60 243.60
f. Toks with screw pc 125 6.00 750.00 300.00 1,050.00
g. W-clip pc 158 5.00 790.00 316.00 1,106.00
Sub-total 25,419.00 10,167.60 35,586.60
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. D1: Main Door (900x2100) pc 2.00 12,500.00 25,000.00 10,000.00 35,000.00
b. D2: Solid Door (800x2100) pc 1.00 9,000.00 9,000.00 3,600.00 12,600.00
c. D3: CR Door (700x2100) pc 1.00 3,750.00 3,750.00 1,500.00 5,250.00
d. D4: Room Door (800x2100) pc 2.00 9,000.00 18,000.00 7,200.00 25,200.00
e. D5: Aluminum Frame (1600x2100) pc 1.00 9,240.00 9,240.00 3,696.00 12,936.00
f. W1: Aluminum Powder Coated (1700x1200) pc 1.00 6,240.00 6,240.00 2,496.00 8,736.00
g. W2: Aluminum Powder Coated (1200x1000) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
h. W3: Aluminum Powder Coated (1000x1200) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
i. W4: Aluminum Powder Coated (1200x2000) pc 2.00 7,280.00 14,560.00 5,824.00 20,384.00
Sub-total 94,110.00 37,644.00 131,754.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,895.00 2,358.00 8,253.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. 2" x 1/4" Flat Bar pc 2.00 580.00 1,160.00 464.00 1,624.00
c. Tempered Glass w/ Clip & bolt sq ft 24.00 750.00 18,000.00 7,200.00 25,200.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 22,450.00 8,980.00 31,430.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular pc 29.00 1390 40,310.00 16,124.00 56,434.00
b. 1"x2" Tubular pc 2.00 660.00 1,320.00 528.00 1,848.00
c. 2" x 1/4" Flat Bar pc 1.00 580.00 580.00 232.00 812.00
d. Tempered Glass w/ Clip & bolt Sq ft 13.00 750.00 9,750.00 3,900.00 13,650.00
e. Welding rod kg 3.00 90.00 270.00 108.00 378.00
f. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
g. Cutting disk pc 3.00 60.00 180.00 72.00 252.00
h. Paint brush pc 4.00 70.00 280.00 112.00 392.00
Sub-total 54,130.00 21,652.00 75,782.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Wall Cladding(Front Portion) m 32.00 600.00 19,200.00 7,680.00 26,880.00
b. Wall cladding (Left side portion) m 30.00 600.00 18,000.00 7,200.00 25,200.00
c. Fixed glass w/ frame Sq ft 9.50 340.00 3,230.00 1,292.00 4,522.00
Sub-total 40,430.00 16,172.00 56,602.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. CHB 4" thk Pc. 1,111.00 14.00 15,554.00 6,221.60 21,775.60
b. CHB 6" thk Pc. 1,111.00 19.00 21,109.00 8,443.60 29,552.60
c. Portland Cement Bag 207.00 245.00 50,715.00 20,286.00 71,001.00
d. Washed Sand Cu m 12.00 400.00 4,800.00 1,920.00 6,720.00
e. 10mmØ x 6m RSB Kg. 425.00 52.50 22,312.50 8,925.00 31,237.50
f. G.I Tie Wire Kg. 6.00 80.00 480.00 192.00 672.00
Sub-total 114,970.50 45,988.20 160,958.70
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 202.00 245.00 49,490.00 19,796.00 69,286.00
b. Washed Sand Cu m 7.00 400.00 2,800.00 1,120.00 3,920.00
Sub-total 52,290.00 20,916.00 73,206.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Conc. Neutralizer Gal 16.00 90.00 1,440.00 576.00 2,016.00
b. Paint Primer Gal 16.00 650.00 10,400.00 4,160.00 14,560.00
c. Masonry Putty Gal 23.00 450.00 10,350.00 4,140.00 14,490.00
d. Finishing Paint, Semi-gloss Gal 32.00 714.00 22,848.00 9,139.20 31,987.20
e. Skim coat Bag 12.00 650.00 7,800.00 3,120.00 10,920.00
f. Assorted Paint Brush Pc. 25.00 70.00 1,750.00 700.00 2,450.00
g. Assorted Paint Roller Pc. 15.00 85.00 1,275.00 510.00 1,785.00
h. Roller Pan Pc. 10.00 80.00 800.00 320.00 1,120.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 2,100.00
j. Waterproofing (Flexibond) Gal 34.00 1,700.00 57,800.00 23,120.00 80,920.00
k. Cement Bag 6.00 245.00 1,470.00 588.00 2,058.00
j. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 2,940.00
Sub-total 119,533.00 47,813.20 167,346.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Polished Floor Tiles 60cm x 60cm Pc. 314.00 250.00 78,500.00 31,400.00 109,900.00
b. Non- Skid Floor Tiles 30cm x 30cm Pc. 448.00 90.00 40,320.00 16,128.00 56,448.00
c. Cement Mortar Bag 17.00 245.00 4,165.00 1,666.00 5,831.00
d. Tile Adhesive Bag 14.00 350.00 4,900.00 1,960.00 6,860.00
e. Tile grout Kg. 63.00 150.00 9,450.00 3,780.00 13,230.00
f. Sand Cu m 6.00 400.00 2,400.00 960.00 3,360.00
Sub-total 139,735.00 55,894.00 195,629.00
1.3.c.2 CR Tiles
Floor Tiles= 3.69 Sq. m.
Wall Tiles= 18.80 Sq. m. Height of wall tiles=2.00m
Qty= 22.49 Sq. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Floor Tiles 20cm x 20cm Pc. 97.00 20.00 1,940.00 776.00 2,716.00
b. Wall Tiles 20cm x 30cm Pc. 329.00 30.00 9,870.00 3,948.00 13,818.00
c. Cement Mortar Bag 3.00 245.00 735.00 294.00 1,029.00
d. Tile Adhesive Bag 3.00 350.00 1,050.00 420.00 1,470.00
e. Tile grout Kg. 12.00 150.00 1,800.00 720.00 2,520.00
f. Sand Cu m 2.00 400.00 800.00 320.00 1,120.00
g. Tile trim Pc. 3.00 199.00 597.00 238.80 835.80
Sub-total 16,792.00 6,716.80 23,508.80
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 4.00 245.00 980.00 392.00 1,372.00
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 560.00
c. Gravel Cu m 1.00 400.00 400.00 160.00 560.00
d. 12mm Dia. RSB Kgs 26.65 43.00 1,145.95 458.38 1,604.33
e. Formworks L.S. 5% of Material cost 146.30 58.52 204.82
Sub-total 3,072.25 1,228.90 4,301.15
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Water closet/Lavatory w/ Acces. Set 1.00 15,500.00 15,500.00 6,200.00 21,700.00
b. Urinal Set 1.00 4,560.00 4,560.00 1,824.00 6,384.00
c. Kitchen sink Set 1.00 3,000.00 3,000.00 1,200.00 4,200.00
Sub-total 23,060.00 9,224.00 32,284.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Fiber Cement Board pc 31.00 485.00 15,035.00 6,014.00 21,049.00
b. Metal double furring Channel pc 36.00 170.00 6,120.00 2,448.00 8,568.00
c. Metal carrying channel pc 18.00 150.00 2,700.00 1,080.00 3,780.00
d. Wall Angle 1'' x 1'' x 10' pc 13.00 75.00 975.00 390.00 1,365.00
e. Blind Rivets pc 116 1.50 174.00 69.60 243.60
f. Toks with screw pc 125 6.00 750.00 300.00 1,050.00
g. W-clip pc 158 5.00 790.00 316.00 1,106.00
Sub-total 26,544.00 10,617.60 37,161.60
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. D1: Main Door (900x2100) pc 2.00 12,500.00 25,000.00 10,000.00 35,000.00
b. D2: Solid Door (800x2100) pc 1.00 9,000.00 9,000.00 3,600.00 12,600.00
c. D3: CR Door (700x2100) pc 1.00 3,750.00 3,750.00 1,500.00 5,250.00
d. D4: Room Door (800x2100) pc 2.00 9,000.00 18,000.00 7,200.00 25,200.00
e. D5: Aluminum Frame (1600x2100) pc 1.00 9,240.00 9,240.00 3,696.00 12,936.00
f. W1: Aluminum Powder Coated (1700x1200) pc 1.00 6,240.00 6,240.00 2,496.00 8,736.00
g. W2: Aluminum Powder Coated (1200x1000) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
h. W3: Aluminum Powder Coated (1000x1200) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
i. W4: Aluminum Powder Coated (1200x2000) pc 2.00 7,280.00 14,560.00 5,824.00 20,384.00
Sub-total 94,110.00 37,644.00 131,754.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,895.00 2,358.00 8,253.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. 2" x 1/4" Flat Bar pc 2.00 580.00 1,160.00 464.00 1,624.00
c. Tempered Glass w/ Clip & bolt sq ft 24.00 750.00 18,000.00 7,200.00 25,200.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 22,450.00 8,980.00 31,430.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular pc 29.00 1390.00 40,310.00 16,124.00 56,434.00
b. 1"x2" Tubular pc 2.00 660.00 1,320.00 528.00 1,848.00
c. 2" x 1/4" Flat Bar pc 1.00 580.00 580.00 232.00 812.00
d. Tempered Glass w/ Clip & bolt Sq ft 13.00 750.00 9,750.00 3,900.00 13,650.00
e. Welding rod kg 3.00 90.00 270.00 108.00 378.00
f. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
g. Cutting disk pc 3.00 60.00 180.00 72.00 252.00
h. Paint brush pc 4.00 90.00 360.00 144.00 504.00
Sub-total 54,210.00 21,684.00 75,894.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Wall Cladding(Front Portion) m 32.00 600.00 19,200.00 7,680.00 26,880.00
b. Wall cladding (Left side portion) m 36.00 600.00 21,600.00 8,640.00 30,240.00
c. Fixed glass w/ frame Sq ft 35.79 340.00 12,168.60 4,867.44 17,036.04
Sub-total 52,968.60 21,187.44 74,156.04
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. CHB 4" thk Pc. 1,423.00 14.00 19,922.00 7,968.80 27,890.80
b. CHB 6" thk Pc. 1,159.00 19.00 22,021.00 8,808.40 30,829.40
c. Portland Cement Bag 232.00 245.00 56,840.00 22,736.00 79,576.00
d. Washed Sand Cu m 13.00 400.00 5,200.00 2,080.00 7,280.00
e. 10mmØ x 6m RSB Kg. 493.00 52.50 25,882.50 10,353.00 36,235.50
f. G.I Tie Wire Kg. 7.00 80.00 560.00 224.00 784.00
Sub-total 130,425.50 52,170.20 182,595.70
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 199.00 245.00 48,755.00 19,502.00 68,257.00
b. Washed Sand Cu m 7.00 400.00 2,800.00 1,120.00 3,920.00
Sub-total 51,555.00 20,622.00 72,177.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Conc. Neutralizer Gal 16.00 90.00 1,440.00 576.00 2,016.00
b. Paint Primer Gal 16.00 650.00 10,400.00 4,160.00 14,560.00
c. Masonry Putty Gal 23.00 450.00 10,350.00 4,140.00 14,490.00
d. Finishing Paint, Semi-gloss Gal 32.00 714.00 22,848.00 9,139.20 31,987.20
e. Skim coat Bag 12.00 650.00 7,800.00 3,120.00 10,920.00
f. Assorted Paint Brush Pc. 25.00 70.00 1,750.00 700.00 2,450.00
g. Assorted Paint Roller Pc. 15.00 85.00 1,275.00 510.00 1,785.00
h. Roller Pan Pc. 10.00 80.00 800.00 320.00 1,120.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 2,100.00
j. Waterproofing (Flexibond) Gal 36.00 1,700.00 61,200.00 24,480.00 85,680.00
k. Cement Bag 7.00 245.00 1,715.00 686.00 2,401.00
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 2,940.00
Sub-total 123,178.00 49,271.20 172,449.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Polished Floor Tiles 60cm x 60cm Pc. 314.00 250.00 78,500.00 31,400.00 109,900.00
b. Non- Skid Floor Tiles 30cm x 30cm Pc. 448.00 90.00 40,320.00 16,128.00 56,448.00
c. Cement Mortar Bag 17.00 245.00 4,165.00 1,666.00 5,831.00
d. Tile Adhesive Bag 14.00 350.00 4,900.00 1,960.00 6,860.00
e. Tile grout Kg. 63.00 150.00 9,450.00 3,780.00 13,230.00
f. Sand Cu m 6.00 400.00 2,400.00 960.00 3,360.00
Sub-total 139,735.00 55,894.00 195,629.00
1.4.c.2 CR Tiles
Floor Tiles= 3.69 Sq. m.
Wall Tiles= 18.80 Sq. m. Height of wall tiles=2.00m
Qty= 22.49 Sq. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Floor Tiles 20cm x 20cm Pc. 97.00 20.00 1,940.00 776.00 2,716.00
b. Wall Tiles 20cm x 30cm Pc. 329.00 30.00 9,870.00 3,948.00 13,818.00
c. Cement Mortar Bag 3.00 245.00 735.00 294.00 1,029.00
d. Tile Adhesive Bag 3.00 350.00 1,050.00 420.00 1,470.00
e. Tile grout Kg. 12.00 150.00 1,800.00 720.00 2,520.00
f. Sand Cu m 2.00 400.00 800.00 320.00 1,120.00
g. Tile trim Pc. 3.00 199.00 597.00 238.80 835.80
Sub-total 16,792.00 6,716.80 23,508.80
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 4.00 245.00 980.00 392.00 1,372.00
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 560.00
c. Gravel Cu m 1.00 400.00 400.00 160.00 560.00
d. 12mm Dia. RSB Kgs 26.65 43.00 1,145.95 458.38 1,604.33
e. Formworks L.S. 5% of Material cost 146.30 58.52 204.82
Sub-total 3,072.25 1,228.90 4,301.15
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Water closet/Lavatory w/ Acces. Set 1.00 15,500.00 15,500.00 6,200.00 21,700.00
b. Urinal Set 1.00 4,560.00 4,560.00 1,824.00 6,384.00
c. Kitchen sink Set 1.00 3,000.00 3,000.00 1,200.00 4,200.00
Sub-total 23,060.00 9,224.00 32,284.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Fiber Cement Board pc 30.00 485.00 14,550.00 5,820.00 20,370.00
b. Metal double furring Channel pc 36.00 170.00 6,120.00 2,448.00 8,568.00
c. Metal carrying channel pc 18.00 150.00 2,700.00 1,080.00 3,780.00
d. Wall Angle 1'' x 1'' x 10' pc 13.00 75.00 975.00 390.00 1,365.00
e. Blind Rivets pc 116.00 1.50 174.00 69.60 243.60
f. Toks with screw pc 125.00 6.00 750.00 300.00 1,050.00
g. W-clip pc 158.00 5.00 790.00 316.00 1,106.00
Sub-total 26,059.00 10,423.60 36,482.60
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. D1: Main Door (900x2100) pc 2.00 12,500.00 25,000.00 10,000.00 35,000.00
b. D2: Solid Door (800x2100) pc 1.00 9,000.00 9,000.00 3,600.00 12,600.00
c. D3: CR Door (700x2100) pc 1.00 3,750.00 3,750.00 1,500.00 5,250.00
d. D4: Room Door (800x2100) pc 2.00 9,000.00 18,000.00 7,200.00 25,200.00
e. D5: Aluminum Frame (1600x2100) pc 1.00 9,240.00 9,240.00 3,696.00 12,936.00
f. W1: Aluminum Powder Coated (1700x1200) pc 1.00 6,240.00 6,240.00 2,496.00 8,736.00
g. W2: Aluminum Powder Coated (1200x1000) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
h. W3: Aluminum Powder Coated (1000x1200) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
i. W4: Aluminum Powder Coated (1200x2000) pc 2.00 7,280.00 14,560.00 5,824.00 20,384.00
Sub-total 94,110.00 37,644.00 131,754.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,895.00 2,358.00 8,253.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. 2" x 1/4" Flat Bar pc 2.00 580.00 1,160.00 464.00 1,624.00
c. Tempered Glass w/ Clip & bolt sq ft 24.00 750.00 18,000.00 7,200.00 25,200.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 22,450.00 8,980.00 31,430.00
1.4.h.3 Hallway Railings & Sun Buffer at Front Side
Qty= 1.00 Lumpsum
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular pc 29.00 1390.00 40,310.00 16,124.00 56,434.00
b. 1"x2" Tubular pc 2.00 660.00 1,320.00 528.00 1,848.00
c. 2" x 1/4" Flat Bar pc 1.00 580.00 580.00 232.00 812.00
d. Tempered Glass w/ Clip & bolt Sq ft 13.00 750.00 9,750.00 3,900.00 13,650.00
e. Welding rod kg 3.00 90.00 270.00 108.00 378.00
f. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
g. Cutting disk pc 3.00 60.00 180.00 72.00 252.00
h. Paint brush pc 4.00 70.00 280.00 112.00 392.00
Sub-total 54,130.00 21,652.00 75,782.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Wall Cladding(Front Portion) m 32.00 600.00 19,200.00 7,680.00 26,880.00
b. Wall cladding (Left side portion) m 36.00 600.00 21,600.00 8,640.00 30,240.00
c. Fixed glass w/ frame Sq ft 75.79 340.00 25,767.01 10,306.80 36,073.81
Sub-total 66,567.01 26,626.80 93,193.81
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. CHB 4" thk Pc. 469.00 14.00 6,566.00 2,626.40 9,192.40
b. CHB 6" thk Pc. 640.00 19.00 12,160.00 4,864.00 17,024.00
c. Portland Cement Bag 108.00 245.00 26,460.00 10,584.00 37,044.00
d. Washed Sand Cu m 6.00 400.00 2,400.00 960.00 3,360.00
e. 10mmØ x 6m RSB Kg. 212.00 52.50 11,130.00 4,452.00 15,582.00
f. G.I Tie Wire Kg. 3.00 80.00 240.00 96.00 336.00
Sub-total 58,956.00 23,582.40 82,538.40
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 94.00 245.00 23,030.00 9,212.00 32,242.00
b. Washed Sand Cu m 3.00 400.00 1,200.00 480.00 1,680.00
Sub-total 24,230.00 9,692.00 33,922.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 44.00 245.00 10,780.00 4,312.00 15,092.00
b. Washed Sand Cu m 49.00 400.00 19,600.00 7,840.00 27,440.00
c. Sahara Pack 44.00 60.00 2,640.00 1,056.00 3,696.00
Sub-total 30,380.00 12,152.00 42,532.00
1.5.b Painting Works
Wall Area= 124.25 Sq. m.
Beams and Columns= 5.68 Sq. m.
Total= 129.93 Sq. m.
Less: Doors & Windows= 6.26 Sq. m.
Add 5% Contingency for Columns/beams sides, doors & windows conc. jambs= 12.37 Sq. m.
Qty= 259.71 Sq. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Conc. Neutralizer Gal 8.00 90.00 720.00 288.00 1,008.00
b. Paint Primer Gal 8.00 650.00 5,200.00 2,080.00 7,280.00
c. Masonry Putty Gal 11.00 450.00 4,950.00 1,980.00 6,930.00
d. Finishing Paint, Semi-gloss Gal 16.00 714.00 11,424.00 4,569.60 15,993.60
e. Skim coat Bag 6.00 650.00 3,900.00 1,560.00 5,460.00
f. Assorted Paint Brush Pc. 30.00 70.00 2,100.00 840.00 2,940.00
g. Assorted Paint Roller Pc. 25.00 85.00 2,125.00 850.00 2,975.00
h. Roller Pan Pc. 20.00 80.00 1,600.00 640.00 2,240.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 2,100.00
j. Waterproofing (Flexibond) Gal 40.00 1,700.00 68,000.00 27,200.00 95,200.00
k. Cement Bag 7.00 245.00 1,715.00 686.00 2,401.00
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 2,940.00
Sub-total 105,334.00 42,133.60 147,467.60
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Floor Tiles 60cm x 60cm Pc. 275.00 250.00 68,750.00 27,500.00 96,250.00
b. Non- Skid Tiles 30cm x 30cm Pc. 27.00 90.00 2,430.00 972.00 3,402.00
c. Cement Mortar Bag 14.00 245.00 3,430.00 1,372.00 4,802.00
d. Tile Adhesive Bag 11.00 350.00 3,850.00 1,540.00 5,390.00
e. Tile grout Kg. 50.00 150.00 7,500.00 3,000.00 10,500.00
f. Sand Cu m 5.00 400.00 2,000.00 800.00 2,800.00
Sub-total 87,960.00 35,184.00 123,144.00
1.5.c.2 CR Tiles
Floor Tiles= 3.52 Sq. m.
Wall Tiles= 14.80 Sq. m. Height of wall tiles=2.00m
Qty= 18.32 Sq. m.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Floor Tiles 20cm x 20cm Pc. 92.00 20.00 1,840.00 736.00 2,576.00
b. Wall Tiles 20cm x 30cm Pc. 259.00 30.00 7,770.00 3,108.00 10,878.00
c. Cement Mortar Bag 2.00 245.00 490.00 196.00 686.00
d. Tile Adhesive Bag 3.00 350.00 1,050.00 420.00 1,470.00
e. Tile grout Kg. 10.00 150.00 1,500.00 600.00 2,100.00
f. Sand Cu m 1.00 400.00 400.00 160.00 560.00
g. Tile trim Pc. 2.00 199.00 398.00 159.20 557.20
Sub-total 13,448.00 5,379.20 18,827.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 18.00 245.00 4,410.00 1,764.00 6,174.00
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 560.00
c. Gravel Cu m 2.00 400.00 800.00 320.00 1,120.00
d. 12mm Dia. RSB Kgs 15.99 43.00 687.57 275.03 962.60
e. Formworks L.S. 5% of Material cost 314.88 125.95 440.83
Sub-total 6,612.45 2,644.98 9,257.43
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Water closet/Lavatory w/ Acces. Set 1.00 15,500.00 15,500.00 6,200.00 21,700.00
b. Urinal Set 1.00 4,560.00 4,560.00 1,824.00 6,384.00
c. Kitchen sink Set 1.00 3,000.00 3,000.00 1,200.00 4,200.00
Sub-total 23,060.00 9,224.00 32,284.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Fiber Cement Board pc 4.00 485.00 1,940.00 776.00 2,716.00
b. Metal double furring Channel pc 2.00 170.00 340.00 136.00 476.00
c. Metal carrying channel pc 2.00 150.00 300.00 120.00 420.00
d. Wall Angle 1'' x 1'' x 10' pc 2.00 75.00 150.00 60.00 210.00
e. Blind Rivets pc 8.00 1.50 12.00 4.80 16.80
f. Toks with screw pc 15.00 6.00 90.00 36.00 126.00
g. W-clip pc 6.00 5.00 30.00 12.00 42.00
Sub-total 2,862.00 1,144.80 4,006.80
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. D3: CR Door (700x2100) pc 1.00 3,750.00 3,750.00 1,500.00 5,250.00
b. W2: Aluminum Powder Coated (1200x1000) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
Sub-total 7,910.00 3,164.00 11,074.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 1.00 1,390.00 1,390.00 556.00 1,946.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 0.50 90.00 45.00 18.00 63.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 1.00 70.00 70.00 28.00 98.00
Sub-total 3,250.00 1,300.00 4,550.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. Welding rod kg 0.50 90.00 45.00 18.00 63.00
c. Epoxy primer gal 1.00 720.00 720.00 288.00 1,008.00
d. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
e. Paint brush pc 1.00 70.00 70.00 28.00 98.00
Sub-total 3,535.00 1,414.00 4,949.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 7.00 660.00 4,620.00 1,848.00 6,468.00
b. Welding rod kg 3.00 90.00 270.00 108.00 378.00
c. Epoxy primer gal 1.00 720.00 720.00 288.00 1,008.00
d. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
e. Paint brush pc 3.00 70.00 210.00 84.00 294.00
Sub-total 5,940.00 2,376.00 8,316.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Wall cladding (Left side portion) m 49.00 600 29,400.00 11,760.00 41,160.00
b. Fixed glass w/ frame Sq ft 3.08 340 1,047.20 418.88 1,466.08
Sub-total 30,447.20 12,178.88 42,626.08
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. I-Beam for Rafter pc 4.00 16,500.00 66,000.00 26,400.00 92,400.00
50 x 100 x 2.00mm C-Purlin pc 60.00 950.00 57,000.00 22,800.00 79,800.00
Pre-painted Rib-type roofing m 1.00 485.00 485.00 194.00 679.00
12mm x 6m Sag rods pc 18.00 172.00 3,096.00 1,238.40 4,334.40
Roofing insulator roll 2.00 4,500.00 9,000.00 0.00 9,000.00
Chiken wire mesh roll 3.00 500.00 1,500.00 0.00 1,500.00
Pre-painted ridge roll pc 2.00 360.00 720.00 288.00 1,008.00
End Flashing pc 10.00 380.00 3,800.00 1,520.00 5,320.00
Gutter, Pre-painted pc 3.00 380.00 1,140.00 456.00 1,596.00
Welding rod kg 10.00 90.00 900.00 360.00 1,260.00
Teckscrew 2-1/2" pc 851.00 1.50 1,276.50 510.60 1,787.10
Roof Sealant liter 2.00 180.00 360.00 144.00 504.00
Blind Rivets pc 150.00 1.00 150.00 60.00 210.00
Cutting disk pc 4.00 60.00 240.00 96.00 336.00
Epoxy Primer gal 3.00 720.00 2,160.00 864.00 3,024.00
Paint brush pc 5.00 70.00 350.00 140.00 490.00
Sub-total 148,177.50 55,071.00 203,248.50
143,875.20
72,177.00
2,709.00
area
50.84 10.1675 20.335
135,195.20
0.027
37.03703704 0.999
12.34567901
126,322.00
40,874.40
136,438.05
56,168.00
6,715.80
258,636.00
pcs
main 4.6 0.766667 1
vert main 4.8 0.8 1
botom 4.6 0.766667 1
grills 13.8 2.3 3
8,379.00
987,489.65
65.3409091
179,787.30
75,607.00
171,924.20
190,736.00
23,508.80
0.7 4.66666667 5.328
4,301.15
32,284.00
LR BR1 BR2 CR
36.60 21.70 18.90 3.69
131,754.00
8,253.00
5.454545455 1.20
0.55 5.92072855 23.68291
31,430.00
55 2.5 27.5
4 2.60869565 2
5.454545455
12.3797052
75,782.00
4.29 21 31.5
12.25 29.25 30
9.47316568
1,017,556.05
57.4945887
160,958.70
73,206.00
84.63 16.925 33.85
167,346.20
195,629.00
23,508.80
4,301.15
32,284.00
LR BR1 BR2 CR
40.36 21.62 18.89 3.69
131,754.00
8,253.00
5.454545455 1.20
0.55 5.92072855 23.68291
31,430.00
55 2.5 27.5
4 2.60869565 2
5.454545455
12.3797052
75,894.00
4.16 21 31.5
5.30 21 35.7
35.79
74,156.04
1,015,882.49
290,252.14
66.6937229
182,595.70
72,177.00
88.24 17.647 35.294
172,449.20
195,629.00
23,508.80
4,301.15
32,284.00
LR BR1 BR2 CR
40.36 21.62 18.89 3.69
131,754.00
8,253.00
5.454545455 1.20
0.55 5.92072855 23.68291
31,430.00
55 2.5 27.5
4 2.60869565 2
5.454545455
12.3797052
75,782.00
4.16 21 31.5
5.30 21 35.7
75.79
93,193.81
1,059,840.26
28.6796537
82,538.40
33,922.00
48.76 9.752 39.008
147,467.60
123,144.00
18,827.20
9,257.43
32,284.00
LR BR1 BR2 CR
0.00 0.00 0.00 3.52
0 0 0 1.222222
15.66666667 9.16666667 9.166667 2 2.416667
5.352777778 4.20138889 4.201389 2 2.833333
4.766666667 3.16666667 3.166667 1.566667
60 24 24 8
45 31.6666667 31.66667 15.33333
80 36 36 6
4,006.80
11,074.00
4,550.00
5.454545455 1.20
0.55 5.92072855 23.68291
4,949.00
8,316.00
5.24 9.75 49
3.08
42,626.08
203,248.50
768,743.01
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. CHB 4" thk Pc. 402.00 14.00 5,628.00 2,251.20 1,181.88
b. CHB 6" thk Pc. 1,244.00 19.00 23,636.00 9,454.40 4,963.56
c. Portland Cement Bag 178.00 245.00 43,610.00 17,444.00 9,158.10
d. Washed Sand Cu m 10.00 400.00 4,000.00 1,600.00 840.00
e. 10mmØ x 6m RSB Kg. 334.00 52.50 17,535.00 7,014.00 3,682.35
f. G.I Tie Wire Kg. 5.00 80.00 400.00 160.00 84.00
Sub-total 94,809.00 37,923.60 19,909.89
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. 4.5mm Ficem Board pcs 8.00 430.00 3,440.00 1,376.00 722.40
b. 0.5mm Metal Stud pcs 11.00 195.00 2,145.00 858.00 450.45
c. 5/32 x 1/2" Blind Rivet box 7.00 500.00 3,500.00 1,400.00 735.00
d. 1/2" Hardie Screw box 1.00 700.00 700.00 280.00 147.00
e. 1" Concrete Nail kgs 1.00 90.00 90.00 36.00 18.90
f. Hardie Putty gals 2.00 350.00 700.00 280.00 147.00
g. Hardie Perporated Tape pcs 1.00 300.00 300.00 120.00 63.00
h. Sand Paper (#120 & #80) m 1.00 250.00 250.00 100.00 52.50
i. Primer - Flat Latex gals 1.00 900.00 900.00 360.00 189.00
j. Top Coat - Flat Latex gals 1.00 700.00 700.00 280.00 147.00
k. 7" Paint Roller pcs 2.00 180.00 360.00 144.00 75.60
l. 4" Paint Brush pcs 2.00 110.00 220.00 88.00 46.20
m. Paint Tray pcs 2.00 180.00 360.00 144.00 75.60
Sub-total 13,665.00 5,466.00 2,869.65
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Meteorite Glass Blocks pcs 136.00 135.00 18,360.00 7,344.00 3,855.60
b. Portland Cement bags 8.00 290.00 2,320.00 928.00 487.20
c. Washed Sand cu.m. 0.20 800.00 160.00 64.00 33.60
f. Grout bags 3.00 100.00 300.00 120.00 63.00
Sub-total 21,140.00 8,456.00 4,439.40
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 185.00 245.00 45,325.00 73,311.15 17,795.42
b. Washed Sand Cu m 11.00 400.00 4,400.00 1,760.00 924.00
Sub-total 49,725.00 75,071.15 18,719.42
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 3.00 245.00 735.00 294.00 1,029.00
b. Washed Sand Cu m 3.00 400.00 1,200.00 480.00 1,680.00
Sub-total 1,935.00 774.00 2,709.00
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Conc. Neutralizer Gal 13.00 90.00 1,170.00 468.00 245.70
b. Paint Primer Gal 13.00 650.00 8,450.00 3,380.00 1,774.50
c. Masonry Putty Gal 18.00 450.00 8,100.00 3,240.00 1,701.00
d. Finishing Paint, Semi-gloss Gal 26.00 714.00 18,564.00 7,425.60 3,898.44
e. Skim coat Bag 9.00 650.00 5,850.00 2,340.00 1,228.50
f. Assorted Paint Brush Pc. 27.00 70.00 1,890.00 756.00 396.90
g. Assorted Paint Roller Pc. 20.00 85.00 1,700.00 680.00 357.00
h. Roller Pan Pc. 12.00 80.00 960.00 384.00 201.60
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 315.00
j. Waterproofing (Flexibond) Gal 19.00 1,700.00 32,300.00 12,920.00 6,783.00
k. Cement Bag 4.00 245.00 980.00 392.00 205.80
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 441.00
Sub-total 83,564.00 33,425.60 17,548.44
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Polished Floor Tiles 40cm x 40cm Pc. 468.00 159.00 74,412.00 29,764.80 15,626.52
b. Non- Skid Floor Tiles 30cm x 30cm Pc. 174.00 100.00 17,400.00 6,960.00 3,654.00
c. Cement Mortar Bag 67.00 245.00 16,415.00 6,566.00 3,447.15
d. Tile Adhesive Bag 19.00 350.00 6,650.00 2,660.00 1,396.50
e. Tile grout Kg. 23.00 150.00 3,450.00 1,380.00 724.50
f. Sand Cu m 5.00 400.00 2,000.00 800.00 420.00
Sub-total 120,327.00 48,130.80 25,268.67
1.1.c.2 CR Tiles
LS CR Floor Tiles= 2.97 Sq. m.
RS CR Floor Tiles= 3.35 Sq. m.
Qty= 6.32 Sq. m.
LS CR Wall Tiles= 16.21 Sq. m. Height of wall tiles=2.00m
RS CR Wall Tiles= 14.77 Sq. m. Height of wall tiles=2.00m
Qty= 30.98 Sq. m.
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Floor Tiles 20cm x 20cm Pc. 111.00 20.00 2,220.00 888.00 466.20
b. Wall Tiles 20cm x 30cm Pc. 532.00 30.00 15,960.00 6,384.00 3,351.60
c. Cement Mortar Bag 24.00 245.00 5,880.00 2,352.00 1,234.80
d. Tile Adhesive Bag 13.00 350.00 4,550.00 1,820.00 955.50
e. Tile grout Kg. 10.00 150.00 1,500.00 600.00 315.00
f. Sand Cu m 2.00 400.00 800.00 320.00 168.00
g. Tile trim Pc. 4.00 199.00 796.00 318.40 167.16
Sub-total 31,706.00 12,682.40 6,658.26
1.1.d Concrete Works
1.1.d.1 Slab on fill (Parking Area) Area= 31.95 Sq. m.
Thickness= 0.10 m
Qty= 32.05 Cu. M.
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 307.00 245.00 75,215.00 30,086.00 105,301.00
b. Washed Sand Cu m 17.00 400.00 6,800.00 2,720.00 9,520.00
c. Gravel Cu m 27.00 400.00 10,800.00 4,320.00 15,120.00
d. Formwork L.S. 5% of Material cost 4,640.75 1,856.30 6,497.05
Sub-total 97,455.75 38,982.30 136,438.05
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Water closet/Lavatory w/ Acces. Set 2.00 13,000.00 26,000.00 10,400.00 5,460.00
b. Urinal Set 2.00 4,000.00 8,000.00 3,200.00 1,680.00
Sub-total 34,000.00 13,600.00 7,140.00
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Fiber Cement Board pc 9.00 485.00 4,365.00 1,746.00 916.65
b. Metal double furring Channel pc 24.00 170.00 4,080.00 1,632.00 856.80
c. Metal carrying channel pc 23.00 150.00 3,450.00 1,380.00 724.50
d. Wall Angle 1'' x 1'' x 10' pc 37.00 75.00 2,775.00 1,110.00 582.75
e. Blind Rivets pc 79 1.50 118.50 47.40 24.89
f. Toks with screw pc 989 6.00 5,934.00 2,373.60 1,246.14
g. W-clip pc 92 5.00 460.00 184.00 96.60
h. 1" Concrete Nail kgs 3 100.00 300.00 120.00 63.00
i. Primer Paint gals 3 750.00 2,250.00 900.00 472.50
Sub-total 21,182.50 8,473.00 4,448.33
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. D1: Main Door (900x2100) set 1.00 9,500.00 9,500.00 3,800.00 1,995.00
b. Roll-up set 1.00 35,000.00 35,000.00 14,000.00 7,350.00
c. D3: CR Door (700x2100) set 3.00 2,380.00 7,140.00 2,856.00 1,499.40
e. D6: Glass Door w/ Tempered Glass (3200x2400) set 2.00 61,950.00 123,900.00 49,560.00 26,019.00
f. D7: Main Door (1000x2100) set 1.00 12,500.00 12,500.00 5,000.00 2,625.00
g. W5: Aluminum Sliding (600x400) set 2.00 1,600.00 3,200.00 1,280.00 672.00
h. W3: Aluminum Powder Coated (1200x1000 pc 1.00 6,240.00 6,240.00 2,496.00 1,310.40
i. W6: Aluminum Powder Coated (1000x1200 pc 1.00 6,240.00 6,240.00 2,496.00 1,310.40
Sub-total 203,720.00 81,488.00 42,781.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 2.00 90.00 180.00 72.00 252.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,985.00 2,394.00 8,379.00
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. CHB 4" thk Pc. 1,119.00 14.00 15,666.00 6,266.40 3,289.86
b. CHB 6" thk Pc. 1,356.00 19.00 25,764.00 10,305.60 5,410.44
c. Portland Cement Bag 237.00 245.00 58,065.00 23,226.00 12,193.65
d. Washed Sand Cu m 14.00 400.00 5,600.00 2,240.00 1,176.00
e. 10mmØ x 6m RSB Kg. 473.00 52.50 24,832.50 9,933.00 5,214.83
f. G.I Tie Wire Kg. 7.00 80.00 560.00 224.00 117.60
Sub-total 130,487.50 52,195.00 27,402.38
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 161.00 245.00 39,445.00 63,744.00 15,478.35
b. Washed Sand Cu m 9.00 400.00 3,600.00 1,440.00 756.00
Sub-total 43,045.00 65,184.00 16,234.35
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Conc. Neutralizer Gal 13.00 90.00 1,170.00 468.00 245.70
b. Paint Primer Gal 13.00 650.00 8,450.00 3,380.00 1,774.50
c. Masonry Putty Gal 18.00 450.00 8,100.00 3,240.00 1,701.00
d. Finishing Paint, Semi-gloss Gal 26.00 714.00 18,564.00 7,425.60 3,898.44
e. Skim coat Bag 9.00 650.00 5,850.00 2,340.00 1,228.50
f. Assorted Paint Brush Pc. 27.00 70.00 1,890.00 756.00 396.90
g. Assorted Paint Roller Pc. 20.00 85.00 1,700.00 680.00 357.00
h. Roller Pan Pc. 12.00 80.00 960.00 384.00 201.60
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 315.00
j. Waterproofing (Flexibond) Gal 42.00 1,700.00 71,400.00 28,560.00 14,994.00
k. Cement Bag 8.00 245.00 1,960.00 784.00 411.60
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 441.00
Sub-total 123,644.00 49,457.60 25,965.24
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Wooden Accent Floor Tiles 15cm x 60cm Pc. 878.00 79.00 69,362.00 27,744.80 14,566.02
b. Cement Mortar Bag 16.00 245.00 3,920.00 1,568.00 823.20
c. Tile Adhesive Bag 13.00 350.00 4,550.00 1,820.00 955.50
d. Tile grout Kg. 20.00 150.00 3,000.00 1,200.00 630.00
e. Sand Cu m 4.00 400.00 1,600.00 640.00 336.00
Sub-total 82,432.00 32,972.80 17,310.72
1.2.c.2 CR Tiles
Floor Tiles= 3.74 Sq. m.
Wall Tiles= 16.72 Sq. m. Height of wall tiles=2.00m
Qty= 20.46 Sq. m.
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Floor Tiles 20cm x 20cm Pc. 98.00 20.00 1,960.00 784.00 411.60
b. Wall Tiles 20cm x 30cm Pc. 293.00 30.00 8,790.00 3,516.00 1,845.90
c. Cement Mortar Bag 2.00 245.00 490.00 196.00 102.90
d. Tile Adhesive Bag 3.00 350.00 1,050.00 420.00 220.50
e. Tile grout Kg. 11.00 150.00 1,650.00 660.00 346.50
f. Sand Cu m 2.00 400.00 800.00 320.00 168.00
g. Tile trim Pc. 2.00 199.00 398.00 159.20 83.58
Sub-total 15,138.00 6,055.20 3,178.98
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 6.00 245.00 1,470.00 588.00 308.70
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 84.00
c. Gravel Cu m 1.00 400.00 400.00 160.00 84.00
d. 12mm Dia. RSB Kgs 26.65 43.00 1,145.95 458.38 240.65
e. CHB & Plastering Sq.m 3.29 102.30 336.57 134.63 70.68
f. Formworks L.S. 5% of Material cost 130.33 52.13 27.37
Sub-total 3,882.85 1,553.14 815.40
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Water closet/Lavatory w/ Acces. Set 1.00 13,000.00 13,000.00 5,200.00 2,730.00
b. Urinal Set 1.00 4,000.00 4,000.00 1,600.00 840.00
c. Kitchen sink Set 1.00 3,125.00 3,125.00 1,250.00 656.25
Sub-total 20,125.00 8,050.00 4,226.25
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Fiber Cement Board pc 25.00 485.00 12,125.00 4,850.00 2,546.25
b. Metal double furring Channel pc 23.00 155.00 3,565.00 1,426.00 748.65
c. Metal carrying channel pc 16.00 160.00 2,560.00 1,024.00 537.60
d. Wall Angle 1'' x 1'' x 10' pc 41.00 85.00 3,485.00 1,394.00 731.85
e. Blind Rivets pc 95 1.50 142.50 57.00 29.93
f. Toks with screw pc 125 6.00 750.00 300.00 157.50
g. W-clip pc 158 8.00 1,264.00 505.60 265.44
h. 1" Concrete Nail kgs 4 100.00 400.00 160.00 84.00
i. Primer Paint gals 8 750.00 6,000.00 2,400.00 1,260.00
Sub-total 30,291.50 12,116.60 5,017.22
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,895.00 2,358.00 8,253.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. 2" x 1/4" Flat Bar pc 2.00 580.00 1,160.00 464.00 1,624.00
c. Tempered Glass w/ Clip & bolt sq ft 24.00 750.00 18,000.00 7,200.00 25,200.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 22,450.00 8,980.00 31,430.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular pc 29.00 1390 40,310.00 16,124.00 56,434.00
b. 1"x2" Tubular pc 2.00 660.00 1,320.00 528.00 1,848.00
c. 2" x 1/4" Flat Bar pc 1.00 580.00 580.00 232.00 812.00
d. Tempered Glass w/ Clip & bolt Sq ft 13.00 750.00 9,750.00 3,900.00 13,650.00
e. Welding rod kg 3.00 90.00 270.00 108.00 378.00
f. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
g. Cutting disk pc 3.00 60.00 180.00 72.00 252.00
h. Paint brush pc 4.00 70.00 280.00 112.00 392.00
Sub-total 54,130.00 21,652.00 75,782.00
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 4.00 290.00 1,160.00 1,160.00 348.00
b. Sahara Cement Bag 4.00 60.00 240.00 240.00 72.00
c. Sand Cu m 0.23 1,000.00 230.00 230.00 69.00
d. Shera Plank pc 2.00 195.00 390.00 390.00 117.00
a. Conc. Neutralizer Gal 1.00 90.00 90.00 54.00 21.60
b. Paint Primer Gal 2.00 650.00 1,300.00 780.00 312.00
c. Masonry Putty Gal 3.00 450.00 1,350.00 810.00 324.00
d. Finishing Paint, Semi-gloss Gal 2.00 714.00 1,428.00 856.80 342.72
e. Skim coat Bag 3.00 650.00 1,950.00 1,170.00 468.00
f. Assorted Paint Brush Pc. 4.00 85.00 340.00 204.00 81.60
g. Assorted Paint Roller Pc. 4.00 70.00 280.00 168.00 67.20
h. Roller Pan Pc. 3.00 80.00 240.00 144.00 57.60
i. Paint thinner Gal 3.00 120.00 360.00 216.00 86.40
j. Waterproofing (Flexibond) Gal 6.00 900.00 5,400.00 3,240.00 1,296.00
k. Cement Bag 2.00 290.00 580.00 348.00 139.20
l. Assorted Sand Paper M 2.00 250.00 500.00 300.00 120.00
c. Fixed glass w/ frame Sq ft 9.50 340.00 3,230.00 1,292.00 678.30
Sub-total 19,068.00 11,602.80 4,600.62
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. CHB 4" thk Pc. 1,138.00 14.00 15,932.00 6,372.80 3,345.72
b. CHB 6" thk Pc. 1,452.00 19.00 27,588.00 11,035.20 5,793.48
c. Portland Cement Bag 250.00 245.00 61,250.00 24,500.00 12,862.50
d. Washed Sand Cu m 14.00 400.00 5,600.00 2,240.00 1,176.00
e. 10mmØ x 6m RSB Kg. 495.00 52.50 25,987.50 10,395.00 5,457.38
f. G.I Tie Wire Kg. 7.00 80.00 560.00 224.00 117.60
Sub-total 136,917.50 54,767.00 28,752.68
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 163.00 245.00 39,935.00 64,537.50 15,670.88
b. Washed Sand Cu m 10.00 400.00 4,000.00 1,600.00 840.00
Sub-total 43,935.00 66,137.50 16,510.88
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Conc. Neutralizer Gal 13.00 90.00 1,170.00 468.00 245.70
b. Paint Primer Gal 13.00 650.00 8,450.00 3,380.00 1,774.50
c. Masonry Putty Gal 19.00 450.00 8,550.00 3,420.00 1,795.50
d. Finishing Paint, Semi-gloss Gal 26.00 714.00 18,564.00 7,425.60 3,898.44
e. Skim coat Bag 10.00 650.00 6,500.00 2,600.00 1,365.00
f. Assorted Paint Brush Pc. 25.00 70.00 1,750.00 700.00 367.50
g. Assorted Paint Roller Pc. 15.00 85.00 1,275.00 510.00 267.75
h. Roller Pan Pc. 10.00 80.00 800.00 320.00 168.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 315.00
j. Waterproofing (Flexibond) Gal 45.00 1,700.00 76,500.00 30,600.00 16,065.00
k. Cement Bag 8.00 245.00 1,960.00 784.00 411.60
j. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 441.00
Sub-total 129,119.00 51,647.60 27,114.99
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Wooden Accent Floor Tiles 15cm x 60cm Pc. 917.00 79.00 72,443.00 28,977.20 15,213.03
c. Cement Mortar Bag 16.00 245.00 3,920.00 1,568.00 823.20
d. Tile Adhesive Bag 24.00 350.00 8,400.00 3,360.00 1,764.00
e. Tile grout Kg. 30.00 150.00 4,500.00 1,800.00 945.00
f. Sand Cu m 6.00 400.00 2,400.00 960.00 504.00
Sub-total 91,663.00 36,665.20 19,249.23
1.2.c.2 CR Tiles
Floor Tiles= 3.74 Sq. m.
Wall Tiles= 16.72 Sq. m. Height of wall tiles=2.00m
Qty= 20.46 Sq. m.
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Floor Tiles 20cm x 20cm Pc. 98.00 20.00 1,960.00 784.00 411.60
b. Wall Tiles 20cm x 30cm Pc. 293.00 30.00 8,790.00 3,516.00 1,845.90
c. Cement Mortar Bag 2.00 245.00 490.00 196.00 102.90
d. Tile Adhesive Bag 7.00 350.00 2,450.00 980.00 514.50
e. Tile grout Kg. 6.00 150.00 900.00 360.00 189.00
f. Sand Cu m 2.00 400.00 800.00 320.00 168.00
g. Tile trim Pc. 2.00 199.00 398.00 159.20 83.58
Sub-total 15,788.00 6,315.20 3,315.48
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Water closet/Lavatory w/ Acces. Set 1.00 13,000.00 13,000.00 5,200.00 2,730.00
b. Urinal Set 1.00 4,000.00 4,000.00 1,600.00 840.00
c. Kitchen sink Set 1.00 3,125.00 3,125.00 1,250.00 656.25
Sub-total 20,125.00 8,050.00 4,226.25
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Fiber Cement Board pc 26.00 480.00 12,480.00 4,992.00 2,620.80
b. Metal double furring Channel pc 24.00 155.00 3,720.00 1,488.00 781.20
c. Metal carrying channel pc 17.00 160.00 2,720.00 1,088.00 571.20
d. Wall Angle 1'' x 1'' x 10' pc 45.00 85.00 3,825.00 1,530.00 803.25
e. Blind Rivets pc 109.00 1.50 163.50 65.40 34.34
f. Toks with screw pc 1,068.00 1.50 1,602.00 640.80 336.42
g. W-clip pc 4.00 100.00 400.00 160.00 84.00
h. 1" Concrete Nail kgs 81.00 8.00 648.00 259.20 136.08
i. Primer Paint gals 8.00 750.00 6,000.00 2,400.00 1,260.00
Sub-total 31,558.50 12,623.40 5,231.21
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. D1: Main Door (900x2100) pc 4.00 9,500.00 38,000.00 15,200.00 7,980.00
b. D2: Solid Door (800x2100) pc 1.00 8,700.00 8,700.00 3,480.00 1,827.00
c. D3: CR Door (700x2100) pc 1.00 2,380.00 2,380.00 952.00 499.80
f. W1: Aluminum Powder Coated (1700x1200) pc 1.00 1,600.00 1,600.00 640.00 336.00
g. W3: Aluminum Powder Coated (1200x1000) pc 1.00 6,240.00 6,240.00 2,496.00 1,310.40
h. W6: Aluminum Powder Coated (1000x1200) pc 1.00 6,240.00 6,240.00 2,496.00 1,310.40
i. W4: Aluminum Powder Coated (1200x2000) pc 2.00 7,280.00 14,560.00 5,824.00 3,057.60
Sub-total 77,720.00 31,088.00 16,321.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,895.00 2,358.00 8,253.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. 2" x 1/4" Flat Bar pc 2.00 580.00 1,160.00 464.00 1,624.00
c. Tempered Glass w/ Clip & bolt sq ft 24.00 750.00 18,000.00 7,200.00 25,200.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 22,450.00 8,980.00 31,430.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular pc 29.00 1390.00 40,310.00 16,124.00 56,434.00
b. 1"x2" Tubular pc 2.00 660.00 1,320.00 528.00 1,848.00
c. 2" x 1/4" Flat Bar pc 1.00 580.00 580.00 232.00 812.00
d. Tempered Glass w/ Clip & bolt Sq ft 13.00 750.00 9,750.00 3,900.00 13,650.00
e. Welding rod kg 3.00 90.00 270.00 108.00 378.00
f. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
g. Cutting disk pc 3.00 60.00 180.00 72.00 252.00
h. Paint brush pc 4.00 90.00 360.00 144.00 504.00
Sub-total 54,210.00 21,684.00 75,894.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 4.00 290.00 1,160.00 1,160.00 348.00
b. Sahara Cement Bag 4.00 60.00 240.00 240.00 72.00
c. Sand Cu m 0.23 1,000.00 230.00 230.00 69.00
d. Shera Plank pc 2.00 195.00 390.00 390.00 117.00
a. Conc. Neutralizer Gal 1.00 90.00 90.00 54.00 21.60
b. Paint Primer Gal 2.00 650.00 1,300.00 780.00 312.00
c. Masonry Putty Gal 3.00 450.00 1,350.00 810.00 324.00
d. Finishing Paint, Semi-gloss Gal 2.00 714.00 1,428.00 856.80 342.72
e. Skim coat Bag 3.00 650.00 1,950.00 1,170.00 468.00
f. Assorted Paint Brush Pc. 4.00 85.00 340.00 204.00 81.60
g. Assorted Paint Roller Pc. 4.00 70.00 280.00 168.00 67.20
h. Roller Pan Pc. 3.00 80.00 240.00 144.00 57.60
i. Paint thinner Gal 3.00 120.00 360.00 216.00 86.40
j. Waterproofing (Flexibond) Gal 6.00 900.00 5,400.00 3,240.00 1,296.00
k. Cement Bag 2.00 290.00 580.00 348.00 139.20
l. Assorted Sand Paper M 2.00 250.00 500.00 300.00 120.00
c. Fixed glass w/ frame Sq ft 35.79 340.00 12,168.60 4,867.44 2,555.41
Sub-total 28,006.60 15,178.24 6,477.73
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. CHB 4" thk Pc. 1,138.00 14.00 15,932.00 6,372.80 3,345.72
b. CHB 6" thk Pc. 1,197.00 19.00 22,743.00 9,097.20 4,776.03
c. Portland Cement Bag 219.00 245.00 53,655.00 21,462.00 11,267.55
d. Washed Sand Cu m 13.00 400.00 5,200.00 2,080.00 1,092.00
e. 10mmØ x 6m RSB Kg. 446.00 52.50 23,415.00 9,366.00 4,917.15
f. G.I Tie Wire Kg. 6.00 80.00 480.00 192.00 100.80
Sub-total 121,425.00 48,570.00 25,499.25
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 155.00 245.00 37,975.00 61,474.50 14,917.43
b. Washed Sand Cu m 5.00 400.00 2,000.00 800.00 420.00
Sub-total 39,975.00 62,274.50 15,337.43
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Conc. Neutralizer Gal 11.00 90.00 990.00 396.00 207.90
b. Paint Primer Gal 11.00 650.00 7,150.00 2,860.00 1,501.50
c. Masonry Putty Gal 15.00 450.00 6,750.00 2,700.00 1,417.50
d. Finishing Paint, Semi-gloss Gal 22.00 714.00 15,708.00 6,283.20 3,298.68
e. Skim coat Bag 8.00 650.00 5,200.00 2,080.00 1,092.00
f. Assorted Paint Brush Pc. 25.00 70.00 1,750.00 700.00 367.50
g. Assorted Paint Roller Pc. 15.00 85.00 1,275.00 510.00 267.75
h. Roller Pan Pc. 10.00 80.00 800.00 320.00 168.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 315.00
j. Waterproofing (Flexibond) Gal 37.00 1,700.00 62,900.00 25,160.00 13,209.00
k. Cement Bag 7.00 245.00 1,715.00 686.00 360.15
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 441.00
Sub-total 107,838.00 43,135.20 22,645.98
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Wooden Accent Floor Tiles 15cm x 60cm Pc. 917.00 79.00 72,443.00 28,977.20 15,213.03
c. Cement Mortar Bag 16.00 245.00 3,920.00 1,568.00 823.20
d. Tile Adhesive Bag 17.00 350.00 5,950.00 2,380.00 1,249.50
e. Tile grout Kg. 21.00 150.00 3,150.00 1,260.00 661.50
f. Sand Cu m 6.00 400.00 2,400.00 960.00 504.00
Sub-total 87,863.00 35,145.20 18,451.23
1.4.c.2 CR Tiles
Floor Tiles= 3.74 Sq. m.
Wall Tiles= 16.72 Sq. m. Height of wall tiles=2.00m
Qty= 20.46 Sq. m.
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Floor Tiles 20cm x 20cm Pc. 98.00 20.00 1,960.00 784.00 411.60
b. Wall Tiles 20cm x 30cm Pc. 293.00 30.00 8,790.00 3,516.00 1,845.90
c. Cement Mortar Bag 2.00 245.00 490.00 196.00 102.90
d. Tile Adhesive Bag 7.00 350.00 2,450.00 980.00 514.50
e. Tile grout Kg. 11.00 150.00 1,650.00 660.00 346.50
f. Sand Cu m 2.00 400.00 800.00 320.00 168.00
g. Tile trim Pc. 2.00 199.00 398.00 159.20 83.58
Sub-total 16,538.00 6,615.20 3,472.98
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 4.00 245.00 980.00 392.00 205.80
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 84.00
c. Gravel Cu m 1.00 400.00 400.00 160.00 84.00
d. 12mm Dia. RSB Kgs 26.65 400.00 10,660.00 4,264.00 2,238.60
e. CHB & Plastering Sq.m 3.29 102.30 336.57 134.63 70.68
f. Formworks L.S. 5% of Material cost 105.83 42.33 22.22
Sub-total 12,882.40 5,152.96 2,705.30
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Water closet/Lavatory w/ Acces. Set 1.00 13,000.00 13,000.00 5,200.00 2,730.00
b. Urinal Set 1.00 4,000.00 4,000.00 1,600.00 840.00
c. Kitchen sink Set 1.00 3,125.00 3,125.00 1,250.00 656.25
Sub-total 20,125.00 8,050.00 4,226.25
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Fiber Cement Board pc 26.00 480.00 12,480.00 4,992.00 2,620.80
b. Metal double furring Channel pc 24.00 155.00 3,720.00 1,488.00 781.20
c. Metal carrying channel pc 17.00 160.00 2,720.00 1,088.00 571.20
d. Wall Angle 1'' x 1'' x 10' pc 45.00 85.00 3,825.00 1,530.00 803.25
e. Blind Rivets pc 109.00 1.50 163.50 65.40 34.34
f. Toks with screw pc 1,068.00 1.50 1,602.00 640.80 336.42
g. W-clip pc 4.00 100.00 400.00 160.00 84.00
h. 1" Concrete Nail kgs 81.00 8.00 648.00 259.20 136.08
i. Primer Paint gals 8.00 750.00 6,000.00 2,400.00 1,260.00
Sub-total 31,558.50 12,623.40 6,627.29
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. D1: Main Door (900x2100) pc 4.00 9,500.00 38,000.00 15,200.00 7,980.00
b. D2: Solid Door (800x2100) pc 1.00 8,700.00 8,700.00 3,480.00 1,827.00
c. D3: CR Door (700x2100) pc 1.00 2,380.00 2,380.00 952.00 499.80
f. W1: Aluminum Powder Coated (1700x1200) pc 1.00 1,600.00 1,600.00 640.00 336.00
g. W3: Aluminum Powder Coated (1200x1000) pc 1.00 6,240.00 6,240.00 2,496.00 1,310.40
h. W6: Aluminum Powder Coated (1000x1200) pc 1.00 6,240.00 6,240.00 2,496.00 1,310.40
i. W4: Aluminum Powder Coated (1200x2000) pc 2.00 7,280.00 14,560.00 5,824.00 3,057.60
Sub-total 77,720.00 31,088.00 16,321.20
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 2.00 1,390.00 2,780.00 1,112.00 3,892.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
f. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 5,895.00 2,358.00 8,253.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. 2" x 1/4" Flat Bar pc 2.00 580.00 1,160.00 464.00 1,624.00
c. Tempered Glass w/ Clip & bolt sq ft 24.00 750.00 18,000.00 7,200.00 25,200.00
d. Welding rod kg 1.00 90.00 90.00 36.00 126.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 2.00 70.00 140.00 56.00 196.00
Sub-total 22,450.00 8,980.00 31,430.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular pc 29.00 1390.00 40,310.00 16,124.00 56,434.00
b. 1"x2" Tubular pc 2.00 660.00 1,320.00 528.00 1,848.00
c. 2" x 1/4" Flat Bar pc 1.00 580.00 580.00 232.00 812.00
d. Tempered Glass w/ Clip & bolt Sq ft 13.00 750.00 9,750.00 3,900.00 13,650.00
e. Welding rod kg 3.00 90.00 270.00 108.00 378.00
f. Epoxy primer gal 2.00 720.00 1,440.00 576.00 2,016.00
g. Cutting disk pc 3.00 60.00 180.00 72.00 252.00
h. Paint brush pc 4.00 70.00 280.00 112.00 392.00
Sub-total 54,130.00 21,652.00 75,782.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 4.00 290.00 1,160.00 1,160.00 348.00
b. Sahara Cement Bag 4.00 60.00 240.00 240.00 72.00
c. Sand Cu m 0.23 1,000.00 230.00 230.00 69.00
d. Shera Plank pc 2.00 195.00 390.00 390.00 117.00
a. Conc. Neutralizer Gal 1.00 90.00 90.00 54.00 21.60
b. Paint Primer Gal 2.00 650.00 1,300.00 780.00 312.00
c. Masonry Putty Gal 3.00 450.00 1,350.00 810.00 324.00
d. Finishing Paint, Semi-gloss Gal 2.00 714.00 1,428.00 856.80 342.72
e. Skim coat Bag 3.00 650.00 1,950.00 1,170.00 468.00
f. Assorted Paint Brush Pc. 4.00 85.00 340.00 204.00 81.60
g. Assorted Paint Roller Pc. 4.00 70.00 280.00 168.00 67.20
h. Roller Pan Pc. 3.00 80.00 240.00 144.00 57.60
i. Paint thinner Gal 3.00 120.00 360.00 216.00 86.40
j. Waterproofing (Flexibond) Gal 6.00 900.00 5,400.00 3,240.00 1,296.00
k. Cement Bag 2.00 290.00 580.00 348.00 139.20
l. Assorted Sand Paper M 2.00 250.00 500.00 300.00 120.00
c. Fixed glass w/ frame Sq ft 75.79 340.00 25,767.01 10,306.80 5,411.07
Sub-total 41,605.01 20,617.60 9,333.39
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. CHB 4" thk Pc. 572.00 14.00 8,008.00 3,203.20 1,681.68
b. CHB 6" thk Pc. 834.00 19.00 15,846.00 6,338.40 3,327.66
c. Portland Cement Bag 139.00 245.00 34,055.00 13,622.00 7,151.55
d. Washed Sand Cu m 8.00 400.00 3,200.00 1,280.00 672.00
e. 10mmØ x 6m RSB Kg. 269.00 52.50 14,122.50 5,649.00 2,965.73
f. G.I Tie Wire Kg. 4.00 80.00 320.00 128.00 67.20
Sub-total 75,551.50 30,220.60 15,865.82
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 81.00 245.00 19,845.00 31,946.40 7,768.71
b. Washed Sand Cu m 3.00 400.00 1,200.00 480.00 252.00
Sub-total 21,045.00 32,426.40 8,020.71
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Portland Cement Bag 36.00 290.00 10,440.00 4,176.00 2,192.40
b. Washed Sand Cu m 5.00 1,000.00 5,000.00 2,000.00 1,050.00
c. Sahara Pack 36.00 60.00 2,160.00 864.00 453.60
Sub-total 15,440.00 6,176.00 3,242.40
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Conc. Neutralizer Gal 7.00 90.00 630.00 252.00 132.30
b. Paint Primer Gal 7.00 650.00 4,550.00 1,820.00 955.50
c. Masonry Putty Gal 9.00 450.00 4,050.00 1,620.00 850.50
d. Finishing Paint, Semi-gloss Gal 14.00 714.00 9,996.00 3,998.40 2,099.16
e. Skim coat Bag 5.00 650.00 3,250.00 1,300.00 682.50
f. Assorted Paint Brush Pc. 30.00 70.00 2,100.00 840.00 441.00
g. Assorted Paint Roller Pc. 25.00 85.00 2,125.00 850.00 446.25
h. Roller Pan Pc. 20.00 80.00 1,600.00 640.00 336.00
i. Paint thinner Gal 5.00 300.00 1,500.00 600.00 315.00
j. Waterproofing (Flexibond) Gal 51.00 1,700.00 86,700.00 34,680.00 18,207.00
k. Cement Bag 9.00 245.00 2,205.00 882.00 463.05
l. Assorted Sand Paper M 35.00 60.00 2,100.00 840.00 441.00
Sub-total 120,806.00 48,322.40 25,369.26
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Floor Tiles 30cm x 30cm Pcs 1,252.00 69.00 86,388.00 34,555.20 18,141.48
b. Wooden Accent Floor Tiles 15cm x 60cm Pcs 74.00 79.00 5,846.00 2,338.40 1,227.66
c. Tile Adhesive Bag 24.00 350.00 8,400.00 3,360.00 1,764.00
d. Tile grout Kg. 30.00 150.00 4,500.00 1,800.00 945.00
e. Sand Cu m 6.00 400.00 2,400.00 960.00 504.00
Sub-total 107,534.00 43,013.60 22,582.14
1.5.c.2 CR Tiles
Floor Tiles= 3.69 Sq. m.
Wall Tiles= 16.20 Sq. m. Height of wall tiles=2.00m
Qty= 19.89 Sq. m.
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Floor Tiles 20cm x 20cm Pc. 97.00 20.00 1,940.00 776.00 407.40
b. Wall Tiles 30cm x 20cm Pc. 284.00 30.00 8,520.00 3,408.00 1,789.20
c. Cement Mortar Bag 2.00 245.00 490.00 196.00 102.90
d. Tile Adhesive Bag 7.00 350.00 2,450.00 980.00 514.50
e. Tile grout Kg. 6.00 150.00 900.00 360.00 189.00
f. Sand Cu m 2.00 400.00 800.00 320.00 168.00
g. Tile trim Pc. 2.00 199.00 398.00 159.20 83.58
Sub-total 15,498.00 6,199.20 3,254.58
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 18.00 245.00 4,410.00 1,764.00 6,174.00
b. Washed Sand Cu m 1.00 400.00 400.00 160.00 560.00
c. Gravel Cu m 2.00 400.00 800.00 320.00 1,120.00
d. 12mm Dia. RSB Kgs 15.99 43.00 687.57 275.03 962.60
e. Formworks L.S. 5% of Material cost 314.88 125.95 440.83
Sub-total 6,612.45 2,644.98 9,257.43
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Water closet/Lavatory w/ Acces. Set 1.00 13,000.00 13,000.00 5,200.00 2,730.00
b. Urinal Set 1.00 4,000.00 4,000.00 1,600.00 840.00
c. Kitchen sink Set 1.00 3,125.00 3,125.00 1,250.00 656.25
Sub-total 20,125.00 8,050.00 4,226.25
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Fiber Cement Board pc 4.00 480.00 1,920.00 768.00 403.20
b. Metal double furring Channel pc 3.00 155.00 465.00 186.00 97.65
c. Metal carrying channel pc 3.00 160.00 480.00 192.00 100.80
d. Wall Angle 1'' x 1'' x 10' pc 8.00 85.00 680.00 272.00 142.80
e. Blind Rivets pc 19.00 1.50 28.50 11.40 5.99
f. Toks with screw pc 158.00 1.50 237.00 94.80 49.77
g. W-clip pc 1.00 100.00 100.00 40.00 21.00
h. 1" Concrete Nail kgs 8.00 8.00 64.00 25.60 13.44
i. Primer Paint gals 1.00 750.00 750.00 300.00 157.50
Sub-total 4,724.50 1,889.80 992.15
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. D3: CR Door (700x2100) pc 1.00 3,750.00 3,750.00 1,500.00 5,250.00
b. W2: Aluminum Powder Coated (1200x1000) pc 1.00 4,160.00 4,160.00 1,664.00 5,824.00
Sub-total 7,910.00 3,164.00 11,074.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 2"x4" Tubular Top/vertical frame pc 1.00 1,390.00 1,390.00 556.00 1,946.00
b. 2"x2" Tubular Bottom frame pc 1.00 880.00 880.00 352.00 1,232.00
c. 1"x1" Tubular Railing Grills pc 1.00 445.00 445.00 178.00 623.00
d. Welding rod kg 0.50 90.00 45.00 18.00 63.00
e. Epoxy primer gal 0.50 720.00 360.00 144.00 504.00
f. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
g. Paint brush pc 1.00 70.00 70.00 28.00 98.00
Sub-total 3,250.00 1,300.00 4,550.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 4.00 660.00 2,640.00 1,056.00 3,696.00
b. Welding rod kg 0.50 90.00 45.00 18.00 63.00
c. Epoxy primer gal 1.00 720.00 720.00 288.00 1,008.00
d. Cutting disk pc 1.00 60.00 60.00 24.00 84.00
e. Paint brush pc 1.00 70.00 70.00 28.00 98.00
Sub-total 3,535.00 1,414.00 4,949.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. 1"x2" Tubular pc 7.00 660.00 4,620.00 1,848.00 6,468.00
b. Welding rod kg 3.00 90.00 270.00 108.00 378.00
c. Epoxy primer gal 1.00 720.00 720.00 288.00 1,008.00
d. Cutting disk pc 2.00 60.00 120.00 48.00 168.00
e. Paint brush pc 3.00 70.00 210.00 84.00 294.00
Sub-total 5,940.00 2,376.00 8,316.00
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Total Cost
a. Portland Cement Bag 4.00 290.00 1,160.00 1,160.00 348.00
b. Sahara Cement Bag 4.00 60.00 240.00 240.00 72.00
c. Sand Cu m 0.23 1,000.00 230.00 230.00 69.00
d. Shera Plank pc 2.00 195.00 390.00 390.00 117.00
a. Conc. Neutralizer Gal 1.00 90.00 90.00 54.00 21.60
b. Paint Primer Gal 2.00 650.00 1,300.00 780.00 312.00
c. Masonry Putty Gal 3.00 450.00 1,350.00 810.00 324.00
d. Finishing Paint, Semi-gloss Gal 2.00 714.00 1,428.00 856.80 342.72
e. Skim coat Bag 3.00 650.00 1,950.00 1,170.00 468.00
f. Assorted Paint Brush Pc. 4.00 85.00 340.00 204.00 81.60
g. Assorted Paint Roller Pc. 4.00 70.00 280.00 168.00 67.20
h. Roller Pan Pc. 3.00 80.00 240.00 144.00 57.60
i. Paint thinner Gal 3.00 120.00 360.00 216.00 86.40
j. Waterproofing (Flexibond) Gal 6.00 900.00 5,400.00 3,240.00 1,296.00
k. Cement Bag 2.00 290.00 580.00 348.00 139.20
l. Assorted Sand Paper M 2.00 250.00 500.00 300.00 120.00
b. Fixed glass w/ frame Sq ft 3.08 340 1,047.20 418.88 219.91
Sub-total 16,885.20 10,729.68 4,142.23
RC Rafter
Qty= 2.21 Cu. M
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Ready Mix Concrete(plus 5% loss) Cu m 2.21 4,608.00 10,183.68 4,073.47 2,138.57
b. Misc. Hardwares (3% of materials Cost) lot 1.00 320.79 320.79 128.32 67.37
c. Pumpcrete w/ accessories Cu m 2.21 450.00 994.50 397.80 208.85
d. Reinforcing bars kg 563.27 52.50 29,571.68 11,828.67 6,210.05
Sub-total 41,070.65 16,428.26 8,624.84
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. RC Rafter cu.m. 2.21 29,920.25 16,428.26 8,624.84 8,624.84
b. 50 x 100 x 2.00mm C-Purlin pc 60.00 950.00 57,000.00 22,800.00 11,970.00
c. Pre-painted Rib-type roofing m 1.00 485.00 485.00 194.00 101.85
d. 12mm x 6m Sag rods pc 18.00 172.00 3,096.00 1,238.40 650.16
e. Roofing insulator roll 2.00 4,500.00 9,000.00 0.00 1,350.00
f. Chiken wire mesh roll 3.00 500.00 1,500.00 0.00 225.00
g. Pre-painted ridge roll pc 3.00 550.00 1,650.00 660.00 346.50
h. End Flashing pc 18.00 550.00 9,900.00 3,960.00 2,079.00
i. Gutter, Pre-painted pc 17.00 550.00 9,350.00 3,740.00 1,963.50
j. Welding rod kg 10.00 90.00 900.00 360.00 189.00
k. Teckscrew 2-1/2" pc 851.00 1.50 1,276.50 510.60 268.07
l. Roof Sealant liter 2.00 180.00 360.00 144.00 75.60
m. Blind Rivets pc 150.00 1.00 150.00 60.00 31.50
n. Cutting disk pc 4.00 60.00 240.00 96.00 50.40
o. Epoxy Primer gal 3.00 720.00 2,160.00 864.00 453.60
p. Paint brush pc 5.00 70.00 350.00 140.00 73.50
Sub-total 113,845.76 43,391.84 28,452.51
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. RC Pipe m 13.44 1,800.00 24,192.00 9,676.80 5,080.32
b. Grouting (plus 5% loss) Cu.m 0.16 645.00 101.59 40.64 21.33
c. Backfill, gravel-fill and compaction Cu.m 1.58 450.00 708.75 283.50 148.84
d. Excavation Cu.m 3.60 350.00 52.50
Sub-total 25,002.34 10,350.94 5,302.99
1.6.b Netting & Rope
Qty= 1.00 Lumpsum
Supervision &
Materials Unit Qty. Unit Cost Materials Cost Labor Cost Redesign
a. Net m 63.00 135.00 8,505.00 3,402.00 1,786.05
b. Rope m 73.00 35.00 2,555.00 1,022.00 536.55
c. Tolda pc. 1.00 1,300.00 1,300.00 520.00 273.00
Sub-total 12,360.00 4,944.00 2,595.60
RSB(pcs)
45.1839827
132,732.60
22,000.65
34,035.40
124,796.15
2,709.00
area
94.77 18.954 37.908
116,989.60
0.027
37.03703704 0.999
12.34567901
168,457.80
Total Cost
3,574.20
25,695.60
9,466.80
7,325.50
2,415.00
1,288.00
1,281.56 44,388.40
51,046.66
136,438.05
Plumbing
41,860.00 34,148.10
12,880.00 18,998.00
54,740.00 53,146.10 47,600.00
34,103.83
285,208.00
pcs
main 4.6 0.766667 1
vert main 4.8 0.8 1
botom 4.6 0.766667 1
grills 13.8 2.3 3
8,379.00
1,054,080.10
63.9880952
182,682.50
108,229.00
173,101.60
115,404.80
21,193.20
5,435.99
Total Plumbing
20,930.00 17,074.05
6,440.00 9,499.00
5,031.25 8,050.00
32,401.25 34,623.05 28,175.00
LR BR1 BR2 CR
36.60 21.70 18.90 3.69
42,408.10
108,808.00
8,253.00
5.454545455 1.20
0.55 5.92072855 23.68291
31,430.00
55 2.5 27.5
4 2.60869565 2
5.454545455
12.3797052
75,782.00
4.29 21 31.5
12.25 29.25 30
4.29 21 31.5
12.25 29.25 30
0.00 0 0
9.47316568
931,573.99
66.9642857
220,437.18
294.2088902 110,072.50
180,766.60
128,328.20
22,103.20
28,175.00
LR BR1 BR2 CR
0.00 0.00 0.00 0.00
0 0 0 0
15.66666667 9.16666667 9.166667 2.416667
5.352777778 4.20138889 4.201389 2.833333
4.5 3.16666667 3.166667 1.566667
60 24 24 8
45 31.6666667 31.66667 15.33333
80 36 36 6
44,181.90
108,808.00
8,253.00
5.454545455 1.20
0.55 5.92072855 23.68291
31,430.00
55 2.5 27.5
4 2.60869565 2
5.454545455
12.3797052
75,894.00
4.29 21 31.5
12.25 29.25 30
4.29 21 31.5
12.25 29.25 30
0.00 0 0
35.79
43,184.84
990,917.10
268,108.00
60.3354978
169,995.00
102,249.50
150,973.20
123,008.20
23,153.20
18,035.36
28,175.00
LR BR1 BR2 CR
0.00 0.00 0.00 0.00
0 0 0 0
15.66666667 9.16666667 9.166667 2.416667
5.352777778 4.20138889 4.201389 2.833333
4.5 3.16666667 3.166667 1.566667
60 24 24 8
45 31.6666667 31.66667 15.33333
80 36 36 6
44,181.90
108,808.00
8,253.00
5.454545455 1.20
0.55 5.92072855 23.68291
31,430.00
55 2.5 27.5
4 2.60869565 2
5.454545455
12.3797052
75,782.00
4.29 21 31.5
12.25 29.25 30
4.29 21 31.5
12.25 29.25 30
0.00 0 0
75.79
62,222.61
946,266.97
36.3906926
105,772.10
53,471.40
173,129.74
21,697.20
9,257.43
28,175.00
LR BR1 BR2 CR
0.00 0.00 0.00 0.00
0 0 0 0
15.66666667 9.16666667 9.166667 2.416667
5.352777778 4.20138889 4.201389 2.833333
4.5 3.16666667 3.166667 1.566667
60 24 24 8
45 31.6666667 31.66667 15.33333
80 36 36 6
6,614.30
11,074.00
4,550.00
5.454545455 1.20
0.55 5.92072855 23.68291
4,949.00
8,316.00
4.29 21 31.5
12.25 29.25 30
4.29 21 31.5
12.25 29.25 30
1.00 0.2 0.4
3.08
27,614.88
157,237.60
780,020.91
B ARCHITECTURAL WORKS
1.1 GROUND FLOOR
1.1.a.1 Masonry Walls(includes Cistern Tank) Sq m 164.24 102,768.00 41,107.20 21,581.28 1,007.39 165,456.48 132.95 1,148.12 152,642.49
1.1.a.1.a Dry Wall Sq. m. 13,665.00 5,466.00 2,869.65 0.00 - 30.29 726.33 22,000.65
1.1.a.2 Plastering Works Sq. m. 524.40 51,555.00 20,622.00 10,826.55 158.28 83,003.55 488.74 293.64 143,515.57
1.1.a.3 Concrete Floor Topping Cu. m. 0.26 1,935.00 774.00 406.35 12,193.15 3,115.35 0.26 12,193.15 3,115.35
1.1.b Painting Works Sq. m. 539.03 96,568.00 38,627.20 20,279.28 288.44 155,474.48 449.55 299.27 134,538.04
1.1.c.1 Floor Tiles Sq. m. 80.66 90,230.00 36,092.00 18,948.30 1,801.02 145,270.30 93.95 2,245.58 210,972.55
1.1.c.2 CR Tiles Sq. m. 32.62 29,196.00 11,678.40 6,131.16 1,441.50 47,021.66 37.30 1,368.54 51,046.66
1.1.d.1 Slab on fill (Parking Area) Cu. M. 32.05 97,455.75 38,982.30 20,465.71 4,895.59 156,903.76 32.05 4,895.59 156,903.76
1.1.e Fixtures Lumpsum 1.00 40,120.00 16,048.00 8,425.20 64,593.20 64,593.20 0.00 0.00 -
1.1.f Ceiling Works Sq. M. 5.82 4,797.00 1,918.80 1,007.37 1,327.01 7,723.17 5.82 1,366.34 7,952.09
1.1.g Doors and Windows Lumpsum 1.00 184,740.00 73,896.00 38,795.40 297,431.40 297,431.40 1.00 327,989.20 327,989.20
1.1.h Stair Railings Lin m. 4.60 5,985.00 2,394.00 1,256.85 2,094.75 9,635.85 4.60 2,094.75 9,635.85
1.1.i Glass Blocks Lumpsum 21,140.00 8,456.00 4,439.40 - 1.00 34,035.40 34,035.40
1.1.j Building Signage Lumpsum 16,000.00 0.00 0.00 - 1.00 16,000.00 16,000.00
1.1.k Mezzanine Lumpsum 16,000.00 0.00 0.00 - 1.00 178,008.50 178,008.50
1.1.k.1 Mezzanine Windows Lumpsum 16,000.00 0.00 0.00 - 1.00 29,440.00 29,440.00
1.1.l Ramp Lumpsum 16,000.00 0.00 0.00 - 1.00 21,685.88 21,685.88
Sub-total 719,014.75 287,605.90 150,993.10 1,135,629.20 1,499,481.99
1.2 SECOND FLOOR
1.2.a.1 Masonry Walls Sq. m. 192.52 128,419.50 51,367.80 26,968.10 1,073.96 206,755.40 188.46 1,114.77 210,084.88
1.2.a.2 Plastering Works Sq. m. 550.77 54,005.00 21,602.00 11,341.05 157.87 86,948.05 406.05 292.88 118,924.94
1.2.b Painting Works Sq. m. 533.21 122,803.00 49,121.20 25,788.63 370.80 197,712.83 431.57 461.26 199,066.84
1.2.c.1 Floor Tiles Sq. m. 115.18 136,240.00 54,496.00 28,610.40 1,904.38 219,346.40 108.64 1,221.61 132,715.52
1.2.c.2 CR Tiles Sq. m. 22.49 16,792.00 6,716.80 3,526.32 1,202.81 27,051.22 20.36 1,191.21 24,253.06
1.2.c.3 Pebble Wash Lumpsum 146.30 58.52 30.72 - 1.00 38,306.50 38,306.50
1.2.d.1 Kitchen Pantry Cu. M. 0.40 3,072.25 1,228.90 645.17 12,243.37 4,946.32 0.55 12,243.37 6,733.85
1.2.d.3 Porcelain Slab Sq. m. 0.00 0.00 0.00 0.00 - 3.10 6,760.89 20,958.75
1.2.d.4 Kitchen Cabinet Lumpsum 0.00 0.00 0.00 0.00 - 1.00 20,000.00 20,000.00
1.2.e Fixtures Lumpsum 1.00 23,060.00 9,224.00 4,842.60 37,126.60 37,126.60 0.00 0.00 -
Contract Quantities and Costs Actual Costs
ITEM NO. DESCRIPTION UNIT Contract Material Labor and Supervision Contract Contract Total Actual Actual Unit
Equipment Rental & Re-design Actual Total Cost
Quantity Unit Cost Cost Quantity Cost
1.2.f Ceiling Works Sq. M. 80.89 25,419.00 10,167.60 5,337.99 505.93 40,924.59 71.23 665.81 47,425.32
1.2.g Doors and Windows Lumpsum 1.00 94,110.00 37,644.00 19,763.10 151,517.10 151,517.10 1.00 125,129.20 125,129.20
1.2.h.1 Stair Railings Lin m. 4.60 5,895.00 2,358.00 1,237.95 2,063.25 9,490.95 4.60 2,063.25 9,490.95
1.2.h.2 Hallway Railings at Left Side Lumpsum 1.00 22,450.00 8,980.00 4,714.50 36,144.50 36,144.50 1.00 36,144.50 36,144.50
1.2.h.3 Hallway Railings & Sun Buffer at Front Side Lumpsum 1.00 54,130.00 21,652.00 11,367.30 87,149.30 87,149.30 1.00 87,149.30 87,149.30
1.2.h.4 Wall Cladding & Fixed Glass Lumpsum 1.00 40,430.00 16,172.00 8,490.30 65,092.30 65,092.30 1.00 65,092.30 65,092.30
Sub-total 726,972.05 290,788.82 152,664.13 1,170,205.55 1,141,475.90
1.3 THIRD FLOOR
1.3.a.1 Masonry Walls Sq. m. 169.25 114,970.50 45,988.20 24,143.81 1,093.66 185,102.51 197.22 1,117.75 220,437.18
1.3.a.2 Plastering Works Sq. m. 532.51 52,290.00 20,916.00 10,980.90 158.10 84,186.90 420.65 294.21 123,758.97
1.3.b Painting Works Sq. m. 559.14 119,533.00 47,813.20 25,101.93 344.19 192,448.13 451.76 460.16 207,881.59
1.3.c.1 Floor Tiles Sq. m. 119.27 139,735.00 55,894.00 29,344.35 1,886.25 224,973.35 113.04 1,305.53 147,577.43
1.3.c.2 CR Tiles Sq. m. 22.49 16,792.00 6,716.80 3,526.32 1,202.81 27,051.22 20.46 1,242.36 25,418.68
1.3.c.3 Pebble Wash Lumpsum 5,780.00 2,312.00 1,213.80 - 1.00 38,306.50 38,306.50
1.3.d.1 Kitchen Pantry Cu. M. 0.40 3,072.25 1,228.90 645.17 12,243.37 4,946.32 0.55 12,243.37 6,733.85
1.3.d.2 Porcelain Slab Sq. m. 5,780.00 2,312.00 1,213.80 0.00 - 3.10 6,760.89 20,958.75
1.3.d.3 Kitchen Cabinet Lumpsum 174.00 69.60 36.54 0.00 - 1.00 20,000.00 20,000.00
1.3.e Fixtures Lumpsum 1.00 23,060.00 9,224.00 4,842.60 37,126.60 37,126.60 0.00 0.00 -
1.3.f Ceiling Works Sq. M. 84.56 26,544.00 10,617.60 5,574.24 505.39 42,735.84 74.21 665.86 49,413.11
1.3.g Doors and Windows Lumpsum 1.00 94,110.00 37,644.00 19,763.10 151,517.10 151,517.10 1.00 125,129.20 125,129.20
1.3.h.1 Stair Railings Lin m. 4.60 5,895.00 2,358.00 1,237.95 2,063.25 9,490.95 4.60 2,063.25 9,490.95
1.3.h.2 Hallway Railings at Left Side Lumpsum 1.00 22,450.00 8,980.00 4,714.50 36,144.50 36,144.50 1.00 36,144.50 36,144.50
1.3.h.3 Hallway Railings & Sun Buffer at Front Side Lumpsum 1.00 54,210.00 21,684.00 11,384.10 87,278.10 87,278.10 1.00 87,278.10 87,278.10
1.3.h.4 Wall Cladding & Fixed Glass Lumpsum 1.00 52,968.60 21,187.44 11,123.41 85,279.45 85,279.45 1.00 85,279.45 85,279.45
Sub-total 737,364.35 294,945.74 154,846.51 1,168,280.96 1,203,808.25
1.4 FOURTH FLOOR
1.4.a.1 Masonry Walls Sq. m. 196.63 130,425.50 52,170.20 27,389.36 1,067.93 209,985.06 177.86 1,099.18 195,494.25
1.4.a.2 Plastering Works Sq. m. 526.23 51,555.00 20,622.00 10,826.55 157.73 83,003.55 403.08 286.92 115,650.24
1.4.b Painting Works Sq. m. 552.54 123,178.00 49,271.20 25,867.38 358.92 198,316.58 367.47 472.47 173,619.18
1.4.c.1 Floor Tiles Sq. m. 119.27 139,735.00 55,894.00 29,344.35 1,886.25 224,973.35 113.04 1,251.41 141,459.43
1.4.c.2 CR Tiles Sq. m. 22.49 16,792.00 6,716.80 3,526.32 1,202.81 27,051.22 20.46 1,301.38 26,626.18
1.4.c.3 Pebble Wash Lumpsum 4,160.00 1,664.00 873.60 - 1.00 38,306.50 38,306.50
1.4.d.1 Kitchen Pantry Cu. M. 0.40 3,072.25 1,228.90 645.17 12,243.37 4,946.32 0.55 12,243.37 6,733.85
1.4.d.2 Porcelain Slab Sq. m. 9,240.00 3,696.00 1,940.40 0.00 - 3.10 6,760.89 20,958.75
1.4.d.3 Kitchen Cabinet Lumpsum 14,560.00 5,824.00 3,057.60 0.00 - 1.00 20,000.00 20,000.00
1.4.e Plumbing Works Lumpsum 1.00 23,060.00 9,224.00 4,842.60 37,126.60 37,126.60 0.00 0.00 -
1.4.f Ceiling Works Sq. M. 84.56 26,059.00 10,423.60 5,472.39 496.16 41,954.99 74.21 684.67 50,809.19
1.4.g Doors and Windows Lumpsum 1.00 94,110.00 37,644.00 19,763.10 151,517.10 151,517.10 1.00 125,129.20 125,129.20
1.4.h.1 Stair Railings Lin m. 4.60 5,895.00 2,358.00 1,237.95 2,063.25 9,490.95 4.60 2,063.25 9,490.95
1.4.h.2 Hallway Railings at Left Side Lumpsum 1.00 22,450.00 8,980.00 4,714.50 36,144.50 36,144.50 1.00 36,144.50 36,144.50
1.4.h.3 Hallway Railings & Sun Buffer at Front Side Lumpsum 1.00 54,130.00 21,652.00 11,367.30 87,149.30 87,149.30 1.00 87,149.30 87,149.30
1.4.h.4 Wall Cladding & Fixed Glass Lumpsum 1.00 66,567.01 26,626.80 13,979.07 107,172.88 107,172.88 1.00 107,172.88 107,172.88
1.4.h.5 Grills Lumpsum 2,780.00 1,112.00 583.80 0.00 - 1.00 26,139.16 26,139.16
Sub-total 784,988.76 313,995.50 164,847.64 1,218,832.40 1,180,883.56
Contract Quantities and Costs Actual Costs
ITEM NO. DESCRIPTION UNIT Contract Material Labor and Supervision Contract Contract Total Actual Actual Unit
Equipment Rental & Re-design Actual Total Cost
Quantity Unit Cost Cost Quantity Cost
1.5 ROOF DECK
1.5.a.1 Masonry Walls Sq. m. 84.48 58,956.00 23,582.40 12,380.76 1,123.57 94,919.16 107.07 1,123.57 120,298.35
1.5.a.2 Plastering Works Sq. m. 247.34 24,230.00 9,692.00 5,088.30 157.72 39,010.30 223.62 288.73 64,566.72
1.5.a.3 Concrete Floor Topping Cu. m. 4.60 30,380.00 12,152.00 6,379.80 10,626.07 48,911.80 4.60 10,626.07 48,911.80
1.5.b Painting Works Sq. m. 259.71 105,334.00 42,133.60 22,120.14 652.99 169,587.74 223.63 869.75 194,497.66
1.5.c.1 Floor Tiles Sq. m. 94.38 87,960.00 35,184.00 18,471.60 1,500.48 141,615.60 113.66 1,523.22 173,129.74
1.5.c.2 CR Tiles Sq. m. 18.32 13,448.00 5,379.20 2,824.08 1,182.72 21,667.38 19.89 1,254.49 24,951.78
1.5.c.3 Pebble Wash Lumpsum 0.00 0.00 0.00 - 1.00 38,306.50 38,306.50
1.5.d.1 Kitchen Pantry Cu. M. 1.88 6,612.45 2,644.98 1,388.61 5,662.79 10,646.04 1.88 5,662.79 10,646.04
1.5.d.2 Porcelain Slab Sq. m. 1,440.00 576.00 302.40 0.00 - 2.20 6,760.89 14,873.95
1.5.d.3 Kitchen Cabinet Lumpsum 0.00 0.00 0.00 0.00 - 1.00 10,000.00 10,000.00
1.5.e Fixtures Lumpsum 1.00 23,060.00 9,224.00 4,842.60 37,126.60 37,126.60 0.00 0.00 -
1.5.f Ceiling Works Sq. M. 3.52 2,862.00 1,144.80 601.02 1,309.04 4,607.82 9.22 824.99 7,606.45
1.5.g Doors and Windows Lumpsum 1.00 7,910.00 3,164.00 1,661.10 12,735.10 12,735.10 1.00 12,735.10 12,735.10
1.5.h.1 Stair Railings Lin m. 4.60 3,250.00 1,300.00 682.50 1,137.50 5,232.50 4.60 1,137.50 5,232.50
1.5.h.2 Hallway Railings at Left Side Lumpsum 1.00 3,535.00 1,414.00 742.35 5,691.35 5,691.35 1.00 5,691.35 5,691.35
1.5.h.3 Hallway Railings & Sun Buffer at Front Side Lumpsum 1.00 5,940.00 2,376.00 1,247.40 9,563.40 9,563.40 1.00 9,563.40 9,563.40
1.5.h.4 Wall Cladding & Fixed Glass Lumpsum 1.00 30,447.20 12,178.88 6,393.91 49,019.99 49,019.99 1.00 49,019.99 49,019.99
1.5.h.5 Roofing Works Lumpsum 1.00 148,177.50 55,071.00 30,487.28 233,735.78 233,735.78 1.00 185,690.11 185,690.11
1.5.i Water Proofing Sq. m. 95.58 1,000.11 95,590.86 95.58 1,000.11 95,590.86
Sub-total 553,542.15 217,216.86 115,613.85 979,661.42 1,071,312.30
1.6 WALL CLADDING
1.6.a Rib-type Wall Cladding Lumpsum 10,780.00 4,312.00 2,263.80 0.00 1.00 372,349.53 372,349.53
TOTAL FOR ITEM C. ARCHITECTURAL WORKS 3,521,882.05 1,404,552.82 738,965.23 5,672,609.53 6,469,311.53
C. STRUCTURAL WORKS
2.1 FOOTING Cu. m. 23.60 117,611.83 47,044.74 24,698.49 8,023.52 189,355.06 24.78 8,023.52 198,822.83
Sub-total 189,355.06 198,822.83
2.2 BEAMS
2.2.1 GF Cu. m. 6.89 36,145.31 14,458.12 7,590.51 7,601.53 52,374.55 6.89 7,601.53 52,374.54
2.2.2 2F Cu. m. 11.19 59,290.80 23,716.32 12,451.07 7,677.60 85,912.37 11.19 7,677.60 85,912.34
2.2.3 3F Cu. m. 11.38 60,894.97 24,357.99 12,787.94 7,753.67 88,236.81 11.38 7,753.67 88,236.76
2.2.4 4F Cu. m. 10.62 57,385.72 22,954.28 12,051.00 7,829.75 83,151.90 10.62 7,829.75 83,151.95
2.2.5 RD Cu. m. 6.86 37,428.51 14,971.41 7,859.99 7,905.82 54,233.92 6.05 7,905.82 47,814.40
Sub-total 251,145.31 100,458.12 52,740.51 363,909.55 357,489.99
2.3 COLUMNS
2.3.1 Footing to 2F Cu. m. 14.64 76,802.21 30,720.88 16,128.46 7,601.53 111,286.40 17.86 7,601.53 135,767.13
2.3.2 2F to 3F Cu. m. 6.81 36,083.14 14,433.26 7,577.46 7,677.60 52,284.47 8.16 7,677.60 62,686.07
2.3.3 3F to 4F Cu. m. 6.81 36,440.67 14,576.27 7,652.54 7,753.68 52,802.53 6.90 7,753.68 53,488.76
2.3.4 4F to RD Cu. m. 6.81 36,798.19 14,719.28 7,727.62 7,829.75 53,320.58 6.25 7,829.75 48,916.36
2.3.5 RD to Top of Firewall Cu. m. 3.39 18,496.03 7,398.41 3,884.17 7,905.82 26,800.75 3.57 7,905.82 28,223.78
Sub-total 204,620.24 81,848.10 42,970.25 296,494.73 329,082.10
2.4 GRADE/SUSPENDED SLABS
2.4.1 GF Cu. m. 14.28 76,413.02 30,565.21 16,046.73 7,601.53 108,549.87 13.13 7,601.53 99,770.08
Contract Quantities and Costs Actual Costs
ITEM NO. DESCRIPTION UNIT Contract Material Labor and Supervision Contract Contract Total Actual Actual Unit
Equipment Rental & Re-design Actual Total Cost
Quantity Unit Cost Cost Quantity Cost
2.4.2 2F Cu. m. 12.42 66,460.07 26,584.03 13,956.62 7,677.60 95,355.82 13.73 7,677.60 105,444.16
2.4.3 3F Cu. m. 12.89 68,975.07 27,590.02 14,484.76 7,753.67 99,944.86 11.41 7,753.67 88,496.51
2.4.4 4F Cu. m. 12.91 69,759.85 27,903.94 14,649.57 7,829.75 101,082.02 11.11 7,829.75 86,980.69
2.4.5 RD Cu. m. 11.11 60,616.74 24,246.70 12,729.52 7,905.82 87,833.65 12.13 7,905.82 95,897.60
Sub-total 342,224.75 136,889.90 71,867.20 492,766.21 476,589.04
2.5 SHEAR WALLS Cu. m. 12.32 65,278.16 26,111.27 13,708.41 7,677.60 94,588.06 13.70 7,677.60 105,183.12
2.6 STAIRS Cu. m. 4.38 21,827.96 8,731.19 4,583.87 7,221.17 31,628.72 5.15 7,221.17 37,189.03
2.7 REINFORCING STEEL BARS Kgs. 29,107.50 1,668,212.26 667,284.91 350,324.58 92.27 2,685,821.75 31,261.05 92.27 2,884,457.03
2.8 FORMS AND FORMWORKS
2.8.1 Footing to GF 1.00 51,960.00 20,784.00 10,911.60 83,655.60 83,655.60 1.00 83,655.60 83,655.60
2.8.2 Shear Walls 1.00 37,930.00 15,172.00 7,965.30 61,067.30 61,067.30 1.00 61,067.30 61,067.30
2.8.3 GF To 2F Columns 1.00 74,682.00 29,872.80 15,683.22 120,238.02 120,238.02 1.00 120,238.02 120,238.02
2.8.4 2F Beams to be re-used at 3F 1.00 63,534.00 25,413.60 13,342.14 102,289.74 102,289.74 1.00 102,289.74 102,289.74
2.8.5 2F To 3F Columns Lot 1.00 44,172.00 17,668.80 9,276.12 71,116.92 71,116.92 1.00 71,116.92 71,116.92
2.8.6 4F Beams to be re-used for RD 1.00 61,866.00 24,746.40 12,991.86 99,604.26 99,604.26 1.00 99,604.26 99,604.26
2.8.7 2F and 3F Slabs to be re-used at 4F and RD 1.00 89,775.00 71,820.00 24,239.25 185,834.25 185,834.25 1.00 185,834.25 185,834.25
2.8.8 Stairs from GF to 3F 1.00 10,480.00 6,840.00 2,598.00 19,918.00 19,918.00 1.00 19,918.00 19,918.00
2.8.9 Stairs from 3F to RD 1.00 9,200.00 6,736.00 2,390.40 18,326.40 18,326.40 1.00 18,326.40 18,326.40
Sub-total 443,599.00 219,053.60 99,397.89 762,050.49 762,050.49
2.9 SCAFFOLDINGS Lot 1.00 200,000.00 80,000.00 280,000.00 280,000.00 1.00 280,000.00 280,000.00
2.10 EARTHWORKS
2.10.1 Excavations 179.00 250.00 37.50 287.50 51,462.50 148.22 287.50 42,613.88
2.10.2 Backfill, Gravel-fill and compaction Cu. m. 183.00 300.00 45.00 345.00 63,135.00 159.58 345.00 55,055.50
2.10.3 Gravel Bedding 8.36 450.00 180.00 94.50 724.50 6,054.65 8.77 724.50 6,357.38
Sub-total 450.00 730.00 177.00 120,652.15 104,026.76
2.11 DRAINAGE CANAL REPAIR m. 12.80 39,546.13 15,818.45 8,304.69 2,503.17 32,040.54 12.8 3,176.27 40,656.27
TOTAL FOR ITEM C. STRUCTURAL WORKS 3,292,691.55 1,358,690.64 655,707.33 5,349,307.25 5,575,546.66
Contract Quantities and Costs Actual Costs
ITEM NO. DESCRIPTION UNIT Contract Material Labor and Supervision Contract Contract Total Actual Actual Unit
Equipment Rental & Re-design Actual Total Cost
Quantity Unit Cost Cost Quantity Cost
Discount 29,670.02
ENGINEERS AND CONSULTANTS
Actual Costs
Difference
###
###
###
###
12,813.99
- 22,000.65
- 60,512.02
-
20,936.44
- 65,702.25
- 4,025.00
-
64,593.20
- 228.92
- 30,557.80
-
- 34,035.40
- 16,000.00
- 178,008.50
- 29,440.00
- 21,685.88
- 363,852.80
- 3,329.48
- 31,976.89
- 1,354.01
86,630.88
2,798.16
- 38,306.50
- 1,787.53
- 20,958.75
- 20,000.00
37,126.60
Actual Costs
Difference
- 6,500.73
26,387.90
-
-
-
-
28,729.65
- 35,334.67
- 39,572.07
- 15,433.46
77,395.92
1,632.54
- 38,306.50
- 1,787.53
- 20,958.75
- 20,000.00
37,126.60
- 6,677.27
26,387.90
-
-
-
-
- 35,527.29
14,490.81
- 32,646.69
24,697.40
83,513.92
425.04
- 38,306.50
- 1,787.53
- 20,958.75
- 20,000.00
37,126.60
- 8,854.20
26,387.90
-
-
-
-
- 26,139.16
37,948.84
Actual Costs
Difference
- 25,379.19
- 25,556.42
-
- 24,909.92
- 31,514.14
- 3,284.40
- 38,306.50
-
- 14,873.95
- 10,000.00
37,126.60
- 2,998.63
-
-
-
-
-
48,045.67
-
- 91,650.88
- 372,349.53
- 796,702.00
- 9,467.77
###
-
###
###
###
###
6,419.52
###
-
- 24,480.73
- 10,401.59
- 686.23
4,404.22
- 1,423.03
###
-
8,779.78
Actual Costs
Difference
- 10,088.34
11,448.35
14,101.33
- 8,063.95
###
- 10,595.06
- 5,560.31
- 198,635.28
-
-
-
-
-
-
-
-
-
-
-
-
-
8,848.62
8,079.50
- 302.73
###
- 8,615.73
- 226,239.44
Actual Costs
Difference
###
- 5,095.65
- 3,010.70
- 5,948.95
6,182.40
3,622.50
- 644.00
684.25
5,248.60
708.40
322.00
- 217.35
- 1,875.65
328.44
281.75
202.86
- 6,939.10
3,622.50
- 3,075.10
- 1,152.30
- 1,932.00
- 611.80
- 193.20
- 2,511.60
- 265.65
- 225.40
- 177.10
- 120.75
- 289.80
- 144.90
- 13,227.30
1,932.00
1,207.50
- 18,112.50
1,083.30
3,091.20
2,302.30
1,771.00
322.00
Actual Costs
Difference
547.40
1,618.05
- 1,883.70
- 72.88
- 1,626.26
- 5,255.05
- 1,568.72
- 999.93
- 15,644.30
442.75
1,255.80
8,621.55
- 88.55
- 1,046.50
- 305.90
- 152.95
- 6,440.00
2,286.20
-
-
-
-
-
-
-
-
-
-
-
-
###
- 26,585.40
6,440.00
19,320.00
19,320.00
1,610.00
Actual Costs
Difference
- 805.00
- 732.55
- 24.15
1,468.32
- 805.00
16,905.00
3,542.00
- 14,490.00
11,592.00
- 225.40
- 1,925.56
- 4,508.00
- 805.00
- 837.20
- 1,173.69
4,974.90
1,447.39
- 2,632.35
1,851.50
- 10,384.50
- 7,567.00
- 2,382.80
1,391.04
805.00
- 903.21
- 7,084.00
- 850.08
- 4,347.00
- 128.80
- 386.40
193.20
998.20
273.70
17,212.50
1,851.50
9,660.00
31,994.00
563.50
- 950.00
483.00
- 185.15
- 78.89
635.95
1,078.70
676.20
Actual Costs
Difference
173.88
- 25,760.00
- 4,427.50
- 9,016.00
- 450.80
- 4,282.60
- 241.50
- 56.35
- 80.50
- 708.40
- 3,155.60
- 289.80
- 1,223.60
- 611.80
- 1,932.00
- 410.55
- 115.92
- 152.95
- 305.90
- 201.25
- 998.20
- 2,318.40
- 3,500.00
- 2,898.00
- 289.80
- 644.00
- 1,159.20
- 515.20
- 265.65
- 241.50
- 120.75
- 354.20
- 1,014.30
- 136.85
- 523.25
- 289.80
- 64.40
- 56.35
- 257.60
- 305.90
22,873.38
Actual Costs
Difference
###
###
###
###
###
###
###
Actual Costs
Difference
- 1,397.25
- 8,538.75
- 2,328.75
- 853.88
- 2,654.78
- 1,397.25
- 4,322.16
- 21,492.81
- 1,048,146.27
Actual Percentage
Work Increase Decrease Difference
Architectural - 1,277,622.48 663,586.48 - 614,036.00
Structural - 226,239.44 - 226,239.44
Plumbing - 201,949.55 198,237.53 - 3,712.02
Electrical - 19,164.06 - 19,164.06
Total - 1,724,975.53 861,824.01 - 863,151.52
Contract Quantities a
Material
ITEM NO. DESCRIPTION UNIT Contract
Quantity
Difference SAVE
Actual Accomplishment