Mall of Egypt

Concreting Work Risk Assessment JVBO NO: Date: Page: 1 of 2


Risk Assessment: Activity – Concreting Works

Unmitigated
Mitigated Risk
Task Hazards Persons at Risk Risk Proposed Mitigation Measures
L S R L S R

Concreting Contact with Chemical Site Operatives 3 2 6  Suitable PPE to be worn by the workers – 1 2 2
safety helmet, safety boots, gloves
 Materials safety data sheets (MSDS) required
for concrete, shutter oil and curing compound
and other hazardous materials
 Task briefing and toolbox talks for handing of
chemicals
 Proximity of clean water and eyewash station

Concreting Falling objects from Site operatives / 4 4 16  Do not lift loads over personnel 1 4 4
lifted loads plant / visitors
 Trained Banks man to be in charge of all lifting
operations
 Suitable PPE to be worn by the workers –
safety helmet, boots, gloves, high visibility
jacket / vest
 Remove loose objects

Concreting Crush injury Site operatives 4 4 16  Trained banks man to be in charge of all lifting 1 4 4
Banks man operations
 Suitable PPE to be worn by the workers –
safety helmet, boots, gloves, high visibility
jacket/vest
 Safety toolbox for drivers & operators to be
given
Mall of Egypt
Concreting Work Risk Assessment JVBO NO:
Risk Assessment: Activity Date:
– Concreting Works Page: 2 of 2

Persons at Unmitigated Risk Mitigated Risk


Task Hazards Proposed Mitigation Measures
Risk L S R L S R

Final cleaning of Skin burn – concrete Site operatives 4 3 12  Spillage to be collected into tank 2 2 4
tremie pipe & spillage
 Full body to be covered and proper PPE
bucket
(rubber gloves & boots)

Delivery of Traffic (trucks) Operational team 3 4 12  Traffic plan to be established – controlled 2 4 8


materials delivery materials such as backfill
 One way system of traffic wherever possible
 Signs and signals to be established to
control traffic movement
 Traffic management plan to be adhered to
 All operatives to be briefed on the site
mobile plant rules

Night working Slips, trips and falls Operational team 3 3 9  Provide suitable standard of lighting 1 3 3
/ security team

Housekeeping Slips, trips, falls, sharp Operational team 3 3 9  Regular housekeeping to be established. All 2 3 6
objects (nails) nails to be removed from spent timer
assemblies.

Concreting Environmental pollution All site 3 3 9  Weekly toolbox talks 1 3 3


 Weekly inspections
 Leakage from pump to be prevented

If mitigated risk = unmitigated risk contact safety


L (Likelihood) X S (Severity) = R (Risk) manager
1~ 5 X 1~ 5 = 1 ~ 25 Workforce to be briefed with findings before work
1-8 Low Risk – Work can commence
9-12 Medium Risk – Reduce risk further or increase supervision
12-25 High Risk – Must be mitigated