Professional Documents
Culture Documents
p r e s e n t l y C h a i r m a n of the G e o s y n t h e t i c s T e c h n i c a l C o m m i t.t e e
- 169 -
EPS TOKYO '96 Japan, 29·30 October 1996
ABSTRACT : Since the first use of the EPS blocks for the bridge abutment backfill on the soft
clay ground in 1993, EPS Construction method has been widely used in Korea. The total volume of EPS
3
consumed in Korea reached approximately 190,000m up to May, 1996. However, the major consumption
of EPS blocks was for the backfilling of bridge abutment and for embankment filling on soft ground. To
diversify the application of EPS construction method in Korea, this study performed a series of the full
scale tests for two types of vertical wall using EPS blocks.. Technical aspects of the EPS construction
method for vertical wall were evaluated based on the field performance monitoring data.
INTRODUCTION
EPS(Expanded Polystyrene) is composed of foaming resins. The foaming resin is made through the
process, in which the foaming agent is added to polystyrene resin and soften by heating. EPS blocks
were first used as the construction material in 1972 by NRRL as a means to prevent the settlement of
the embankments on soft ground (Aaboe, 1987). EPS Block has many advantages as a construction
material: light weight, easy construction, high durability, low water absorption, and self-standing
properties, etc.. Therefore it has wide range of application for civil works including soft ground
treatment, retaining wall and bridge abutment backfill, road expansion, and protection of underground
structures, etc ..
In Korea, EPS was first manufactured in early 1970s and has been used for packing and insulation
materials. In 1993, EPS construction method was first introduced in Korea for bridge abutment backfill
3
on soft ground in Seohaean Highway construction project. EPS blocks of 1400 m in volume were used
for the project. Since then the total volume of EPS blocks consumed for construction works were
3
approximately 190,000m up to May 1996, with the predominant application to bridge abutment backfilling
and embankment fills on soft ground (Cho, 1995). Forecasting the increase use of EPS construction
method for the other areas of the application in Korea, the relevant practical research works for
technical confirmation, such as in terms of the reliability of design methodology and construction
efficiency, are required especially through the full scale tests giving realistic evaluation on the behavior
of the structures.
Summarized in this paper are the field performance of the EPS blocks backfilled U-shaped
self-standing retaining wall and vertical wall constructed for the expansion of the existing road. The
advantage aspects of the EPS block backfilled walls, such as decrease of backfill settlement and wall
displacement, enhanced load distribution and decrease of wall pressure are evaluated with field
instrumentation.
Since the EPS construction method was first developed in Norway 1972, it has been widely applied in
- 170 -
many countries, especially in North Europe, North America, and Japan. The usage of EPS blocks has
been dramatically increased with diverse application including soft ground treatment, structural backfill,
foundation supports for underground pipelines, enlargement of platform for railway station, protection
fence against falling rock, and fills for park area near seashore, et:c ..
In Korea, EPS construction method was first introduced in Seohaean Highway construction project in
3.
1993 (Chang, 1994) with the consumption of EPS blocks 1400m Since then, the volume of the EPS
3
blocks used in construction project has been gradually increasing, recording 12,100m in 1994, and
3 3.
lll,800m in 1995, with the total volume of EPS block consumption up to May 1996, is 100,500m (see
Table l(a))
The consumption of EPS blocks with the relation of application type until May, 1996 is shown in
Table l(b)). 55.7% of total volume of EPS blocks that has been used is for bridge abutment, 23.4% for
filling on soft ground, 8.5% for retaining wall backfill, and 9.8% for structure filling. Table l(c) shows
more than 80% of total consumption of EPS blocks was used for road structure, and 12.3% for buildings,
and 6.4% for other type of structures. In Korea, therefore, the EPS construction method will be more
actively used in the future through the application for enlargement of road in the slope area, protection
1993 1 1,400
1994 9 12,100
1995 31 1 1 1 , 8 00
1996.5 17 65,200
Total 58 190,500
Construction of vertical wall using EPS for road enlargement was performed in Yeocheon factory of
Samsung Cheil Industries Inc. in Cheonlanam-Do. The location of construction site is shown in Fig. 1.
- 171 -
The rail way is located close to construction site, and a soil slope of the existing road has a dimensions
as follow; length is 145m, slope is 1:1.7, and height is 8- lOm. After EPS construction method
accomplish the road enlargement, customer will have road extension of 20m. The EPS volume of
3
10,000m was used in this construction site. As shown in Table 2, the foundation soils are composed of
sedimentary rock, weathered rock layer, weathered soil layer, alluvium layer (sandy clay or clayey sand)
Concrete foundation of 0.5m thickness x 2.0m width was prepared in order to build the vertical wall.
The H-section steel on the concrete foundation has a dimension of 200 x 200 x 12 x lOmm, and MCB panel
has a dimension of 2.0m x 0.5m. The EPS block has a dimension of l.8m x 0.9m x 0.6m, and the density is
3.
20kg/m Concrete slab of 12cm-15cm thickness is installed above 4 - 5 EPS blocks.
Measurement
The one inclinometer, four settlement gauges, fifteen earth pressure cells, four strain gauges, and one
EL beam sensor were used to measure horizontal earth pressure, vertical pressure, ground settlement and
evaluate effects of proposed EPS construction method. Fig. 2 shows the cross section view of EPS
23 m
I ''\:\
EX02
EX01
Fig. Location of Construction Site Fig. 2 Cross Section View and Location
Fig. 3 shows the horizontal earth pressure variations in the EPS filling layer during construction. The
horizontal pressure was increased suddenly due to the impact loading during construction of concrete
slab and pavement, and the increased pressure decrease gradually with time after the construction of
- 172 -
pavement as shown in Fig. 3. The maximum horizontal earth pressures for each step of construction
with the variation of wall height are shown in Fig. 4. The horizontal earth pressures stabilized after
2
construction of pavement is lower than 0.022kg/cm regardless of wall height as shown in Fig. 4. The
current design method assures that 10% of overburden pressures acts as horizontal pressure. Therefore,
current design method (EDO, 1993) is considered as conservative side from above facts.
0.3 10
"'e ---TP01
-a, - - - TP03
8
� 0.2
• • • • • ·TP04
cu I
:5
.,, .E 6
.,, Cl)
cu 0.1 ·a;
s: J:
4
iij
c �
0 0
2
.!::!
0
J:
0
-0.1
curing of construction
_._. Placing & curing of upper slab
. curing of construction
Fig. 3 Horizontal Earth Pressure Variation Fig. 4 Horizontal Earth Pressure Variation
After the 58 ton trailer truck (rear wheel load : 7.2 ton) and 36 ton dump truck (rear wheel load :
5.3t) were placed on the pavement layer, vertical stresses occurred in the EPS filling layer were
observed as shown in Fig. 5. Table 3 shows increased stresses of pressure cells buried in the EPS
filling layer due to the loading of vehicles. The stress increment indicated by pressure cells buried on
the upper concrete slab drops rapidly as the distance between load cells and vehicle-wheel loading point
increases. However, the maximum value of stress increment (right below wheel loading, JP09) is lower
than stress increment that is calculated assuming that wheel load distributes 45° angle (J:l). Therefore,
load distribution angle in pavement layer is considered larger than 45° . The stress increment in the
EPS filling layer including concrete slab layer is a little bit larger than calculated value. However, from
the overall stress increment distribution, the load distribution angle in the EPS filling layer is considered
approximately 60° . The 45° degree which is being used for EPS design (EDO, 1993) is considered as
conservative side.
Fig. 6 shows the relationship between settlement and time from the beginning of pavement
construction, depending on the location of settlement gauges. The settlements of foundation soil and EPS
filling layer do not show considerable change during pavement construction. The settlements during
pavement construction were 7mm in foundation soil, and 26mm in EPS layer. The settlement of EPS
layer is considered as elastic settlement and tightness between EPS blocks due to pavement loading.
The settlement of EPS layer during pavement construction is about 0.5% of EPS fill height.
Fig. 7 shows measurement results of inclinometer. There is no movement of sliding because horizontal
displacement does not change throughout the before and after pavement construction, and the maximum
horizontal displacement is 5mm. Also, the maximum horizontal displacement which was measured by EL
- 173 -
Table 3 Results of Vehicle Loading Test
Trailer truck (Rear wheel load : 7.2 t) Dump truck (Rear wheel load : 5.3 t)
�
Pressure cells Measured value Calculated value Measured value Calculated value
JPll 0 . 00 5 0.019
Vertical Stress
2
Increase ( k g / c 11 )
Pavement 0.9 m
0.15 m
0.01 ;--
Upper EPS Layer
2.88 m
0.02 � - - - - - - - . . . --�-
J P0 3 : - - - - - - - - · - - ' - 7 - '"": � - - - -.)
...,_
0.12 m
3.36 m
Wheel Load 7 . 2t
0.12 m
Horizontal Displacement ( m m )
-6- E X 0 5 - 1 m
-10 -5 0 5 10
-&-EX04-4m
50
�EX03-6m 0
�EX02-11m
c:
111 30
E 4 , /
Ill
�
�
Cl)
20 I
.s::: 6
• I
c. , ,
10 Ill
c
8
During pa_vement :\
0 construction
' '
construction
Time (hr)
12
I< >I
Pavement construction
- 174 -
CONSTRUCTION OF U-SHAPE SELF-STANDING WALL USING EPS AND
ITS EVALUATION
U-shape self-standing wall using EPS was constructed for Ramp A-2 of Namhaean Highway which
is located in Daejeo-Dong, Kangseogu, Pusan. EPS blocks were employed to fill in U-shape
self-standing wall on the soft ground. The site location is shown in Fig. 8. As shown in Figure 8, the
construction site is located in alluvium zone in the mouth of Nackdong River. The site had been
evaluated as soft ground that needs special soil improvement technique to prevent large settlement and
lateral displacement of foundation soil because N values of foundation soil are lower than 10 and the
average thickness of soft soil layers is about 38m. EPS construction method is selected for this soft
ground site because it can secure stability during and after construction, and save construction time.
The construction procedures are follows ; (1) Construct U-shape of concrete vertical wall (2) Fill the
EPS blocks (D-20) of 4 or 5 (3) Construct concrete slab of 10-15cm thickness on the EPS blocks.
,. I----tt-n;-,:---�:
: �S
P
E�
f'A_'>. I I\ /
\ \ :/'
. .
: 6ex•
9 :
: <? EX-6
00 EX"'
2Brn Jrn
Fig. 8 Location of Construction Site for Fig. 9 Cross Section View and Location
Measurement
The earth pressure cells, settlement gauges, piezometers, and inclinometers are installed to measure
settlement, horizontal displacement, horizontal earth pressure as shown in Fig. 9. The effects of EPS
construction method are evaluated through the measurement results which was performed using above
The earth pressure cells are installed in the depths of lm, 2.lm , 4. 7 m from the p avement. The
measurement results are shown in Fig. 10. H orizontal earth pressures in EPS layer are large at the
beginning of measure by the impacts during construction. A s time passes, the horizontal ea rth pressures
decrease because residual stress caused by heavy construction eq uipment is rearranged. The phenomenon
of residual stress rearrangement has bee n observed in other kind of construction s i te s (K ato, 1994 ).
The horizontal earth pressures caused by overburden pressures in the EPS layer are much lower than
that of R ankine active earth pressures of sandy soils as shown in F g i . 1 1 . At the tim e of 120 d ays after
p ressures. The reason of low horizontal earth pressure are due to self-standing property of EPS bloc k
that has very low poisson's ratio(O .l -0. 1 5) when compared to that of soils.
- 175 -
2)
Lateral Earth Pressure (kg/cm 0.4
"'
"'
9 50 days after
e 0.2
opening of a.
highway (EPS) .c
0.15
t:!
· · 0 · · 77 days after
"'
w
0.1
opening of
highway (EPS) �
0.05
- <>- · 120 days after �
.J
opening of
0
highway (EPS)
Fig. 10 Relationship between Horizontal Earth Fig. 11 Horizontal Earth Pressure Variation
Pressure and Time (U-shape Wall) with Wall Height (U-shape Wall)
Fig. 12 shows the relationship between settlement and time after opening of highway in the foundation
soils under the EPS layer of 5m high and soil embankment of 2m high. The consolidation settlement is
not observed even though a little bit of immediate settlement caused by vehicles. When 2 months passed
after opening of highway, settlement of foundation soil under the EPS construction site was lower than
that of common soil embankment that was constructed nearby. Therefore, it can be concluded that EPS
construction method on soft ground is more effective to prevent settlement than other kind of soil fill
method.
Fig. 13 shows the pore water pressure variation in foundation soil with time after opening of highway.
The porewater pressures increase at the time of right after opening of highway, but gradually decreases
with time and converge. This result is correspond to the settlement of foundation soil in Fig. 12. The
decrease of pore water pressure is due to the effect of residual stress caused by heavy construction
8 1.6
-e-EX·2(soll,2D.Bm)
NE
7 1.4
u
-.- e x - 1 ( s o i l , 2 B . 1 m )
- 6 t 1 . 2
-S-EX-6(EPS,13.6m)
E CII
..!:!. 5
s
'E
"' 0.8
E 4 "'
CII
CII ct
... 0.6
� 3
�
"' 2 "'
s 0.4
2
� �
0
0.2
a.
0
0 10 20 30 40 50 60 70 80 0 50 100 150
Time After Opening of Highway (days) Time After Opening of Highway (days)
The measurement results of inclinometer are shown in Fig. 14. The lateral displacement in the front
direction of wall increases from ground surface to the depth of 3.5m, and decreases as depth increase
- 176 .,..-
more than 3.5m. The maximum lateral displacement was 10.57mm right after opening of highway, and
decrease with time. The lateral displacement with time at the depth of 3.5m where maximum lateral
displacement occurred was 10.57mm after 45 days passed since opening of highway. As time passed,
lateral displacement gradually decreases showing 9.25mm at time of 112days. From these measurements,
0 2 4 6 8 10 12 14
_ 10
.§.
; 15
Q.
CD ---7days
o 20
· · · · · · 36 days
- - - · 56 days
25 - · · - 77 days
-=----
-=-- - 11_2 d�
30
Fig. 14 Inclinometer Measurements with Depth CU-shape Wall, After opening of highway)
CONCLUSIONS
Since the first use of the EPS blocks for the bridge abutment backfill on the soft clay gound in
1993 , EPS construction method has been widely used in Korea. The consumption of EPS blocks was
3
about 100,000m at time of 1995 showing dramatic increase. The results of the full scale tests for two
1) The horizontal earth pressures in the EPS filling layer are less than 10% of overburden pressure
2) The load distribution angle is about 60° in the EPS fill layer including concrete slabs. Therefore,
load distribution angle, 45° which is being used for EPS construction design is conservative side.
3) The immediate settlement caused by pavement construction and vehicle loading is due to elastic
settlement of EPS blocks and tightness between EPS blocks. The immediate settlement is roughly
4) There was no sign of sliding and overturning in two vertical wall using EPS blocks. Therefore, the
REFERENCES
Aaboe, R. (1987), "13 Years of Experience with EPS as a Lightweight Fill Material in Road
Chang, Y.C, et al. (1994), "A Study on EPS Construction Method", Report No. 94-15-4, Highway
Cho, S.D. ( 1 995 ) , "Current Practice and Technical Review of EPS Construction Method", Proc. of
International Seminar on the Application of EPS for Embankment Construction, Seoul, 67 - 1 0 1 . (In
Korean)
Kato, T, et al. (1994), "A Case Study on Abutment Backfill Using EPS for Reduction of Earth
Pressure", The Foundation Engineering and Equipment, Vol. 22, No. 10, 37-43. (In Japanese)
- 177 -