Professional Documents
Culture Documents
3.
Plots work units completed (vertical axis) against time (horizontal axis)
It will indicate the good visual to show how the work is progressing.
Any deviation in schedule, performance or cost from the plan or from the
set standard to the actual accomplishment is called variance. In the past the
conventional method of control analysis was variance analysis
Planned cost of the total amount of work scheduled to be performed by the milestone date.
Er. Megh Bahadur KC
MSc CM
BCWS
Index (Ratios)
-ve sign indicates time overrun. i.e Project cost of Rs.120 Lakh is behind the schedule.
SPI= 75% which is less than 100 means project is behind the schedule.
Project will be 27-20=7 days late. i.e time lag happen if there is no change in performance.
Why MPS??
1. Ensures not over-extended
2. More efficient use of resources
3. More realistic view of availability
4. Reflections of limitations
Procedure:
1. Obtain estimates of regular and crash times and costs for each activity.
2. Determine the lengths of all paths using regular time for each activity.
3. Identify the critical path(s)
4. Crash activities on the critical path(s) in order of increasing cost as long as crashing costs do not
exceed benefits.
Time-Cost Graph for an Activity
Activity
cost
Crash
Crash cost
Consider the total cost of the project, including the extra cost of crashing activities. The problem
then is to minimize this total cost, subject to the constraint that project duration must be less than
or equal to the time desired by the project manager.
Question: Suppose $1,000 in indirect costs can be saved for each day the
project is shortened. Which activities should be crashed?
Marginal Cost Analysis for House Project
Initial Table
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
Marginal Cost Analysis for House Project
After Crashing 1 Day
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
Marginal Cost Analysis for House Project
After Crashing 2 Days
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
(f) Siding $300 42 39 43
Marginal Cost Analysis for House Project
After Crashing 3 Days
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
(f) Siding $300 42 39 43
(f) Siding $300 42 39 42
Marginal Cost Analysis for House Project
After Crashing 4 Days
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
(f) Siding $300 42 39 43
(f) Siding $300 42 39 42
(b) Framing $400 41 38 41
Marginal Cost Analysis for House Project
After Crashing 5 Days
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
(f) Siding $300 42 39 43
(f) Siding $300 42 39 42
(b) Framing $400 41 38 41
(b) Framing $400 40 37 40
Marginal Cost Analysis for House Project
After Crashing 6 Days
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
(f) Siding $300 42 39 43
(f) Siding $300 42 39 42
(b) Framing $400 41 38 41
(b) Framing $400 40 37 40
(c&f) Plumbing & Siding $500 39 37 39
Marginal Cost Analysis for House Project
Final Table (After Crashing 7 Days)
Length of Path
Activity Crash
to Crash Cost abcegi abdegi abfhi
42 39 45
(f) Siding $300 42 39 44
(f) Siding $300 42 39 43
(f) Siding $300 42 39 42
(b) Framing $400 41 38 41
(b) Framing $400 40 37 40
(c&f) Plumbing & Siding $500 39 37 39
(c&h) Plumbing & Paint Ext. $900 38 37 38
Marginal Cost Analysis for House Project
Seven days have been saved off the length of the project (38 days rather than 45).
$7,000 saved in indirect costs.
The total crashing costs were
$300 + $300 + $300 + $400 + $500 + $900 = $2,700
Total savings = $7,000 – $2,700 = $5,300.