SECTIONAL BENEFICIAL OCCUPATION HANDOVER
1 of 1
The above sub area is hereby accepted by all undersigned company representatives as being
constructed to the design requirements subject to the working off the Phase 3 Punch list or completion
of agreed and documented outstanding works. The Client acknowledges that on signature of this
document by the relevant parties that the risk and responsibilities for the sectional areas reverts to the
Client for any damages that occur, that are not indicated on the agreed punch list or agreed outstanding
work.
(Tick if applicable)
Has sub area been constructed and checked against latest design drawings?
Have all Category A punch listed items been worked off by the Contractor to the satisfaction of
the undersigned?
The defects liability period for these areas will commence on the date of this certificate
Exceptions: