Approval for Material Sample 1

OUTGOING Rev. Title Attachment Date


Date Required INCOMINGDat Author/Copy delivered
Date Issued Status
Reply e Issued Delivered to

BBVN-FIVE-S2-SC- Anti Termite Treatment Product - LENFOS 50EC [Pesticide (Hop TriLENFOS
company)] leaflet, Certificate for Pesticide
AMASA-0001-14 registration (official), Certificate of quality
14/02/28 14/03/10 control for import pesticide (official), Tung
certificates of analysis (4 pages)

Anti-Termite Product LENFOS - 50EC Certificates for Pesticide 14/03/04


14/03/03 Mr. Tung C
BBVN-FIVE-S2-SC- Anti Termite Treatment: Termimesh Rev.1 Certificate of Quality, Certificate of Origin,
AMASA-0001-14/R1 14/03/14 14/03/21 Ocean Bill of Lading, Company Profile, Tung
Catalogue, Sample
Anti Termite Treatment Termimesh Rev.1 14/03/17
14/03/17 C
BBVN-FIVE-S2-SC- Anti Termite Treatment: Termimesh. Rev.2 Certificate of Analysis, Certificate of Quality
AMASA-0001/R2 Control for Import Pesticide, Certificate for
14/03/18 Pesticide registration (official) Tung

Anti Termite Treatment: Termimesh. Rev.2 14/03/28


14/03/27 B
BBVN-FIVE-S2-SC- Geotextile ARITEX ART20 Specification of Non-Woven Geotextile, Result 14/03/11
AMASA-0002-14 14/03/05 14/03/10 of Geotextile official, Sample Tung

14/03/10 B
Additional document Teinco Company Profile (in English) + 8 contracts as reference experience
Profile in English + 8 contracts
Tung
BBVN-FIVE-S2-SC- Geotextile ARITEX ART20 Re-submit sample
AMASA-0002-14/R2
14/05/02 14/05/08 14/05/07 Tung A/B

BBVN-FIVE-S2-SC- Concrete grade & Slump 14/03/10


AMASA-0003-14 14/03/07 Mrs. Lan
Concrete grade & Slump
14/03/10 C
BBVN-FIVE-S2-SC- Concrete grade & Slump (Rev.1) 1 A3 paper
AMASA-0003-14/R1 14/03/13 Mrs. Lan
Concrete Grade & Slump Rev.1 14/03/13
14/03/13 A
BBVN-FIVE-S2-SC- Steel (Kyoei Steel Vietnam Co., Ltd) Company profile, Brochure, Inspection
AMASA-0004 certificate of raw material, Transportation
14/03/17 capacity of company in Vietnamese Hoang

Steel (Kyoei Steel Vietnam Co., LtdO 14/03/19


14/03/19 B
BBVN-FIVE-S2-SC- Marubeni Itochu Steel Letter of Guaranty for Transportation of Dbar
AMASA-0004 (ADD) to B.Braun Project; Letter of Guaranty for
14/04/15 14/04/18 Quality of Billets Using for Production of Steel Hoang
Dbar Supplied to B. Braun Project

Marubeni Itochu Steel


14/04/16 A
BBVN-FIVE-S2-SC- Purlin Sample, Mill Test certificate, Inspection
AMASA-0005 14/03/17 certificate, 1 A3 size drawing Hoang
Purlin 14/03/24
14/03/24 C
Approval for Material Sample 2
OUTGOING Rev. Title Attachment Date
Date Required INCOMINGDat Author/Copy delivered
Date Issued Status
Reply e Issued Delivered to

BBVN-FIVE-S2-SC- Purlin Rev1 (revised based on comments in AMASA-0005 dated 24- Sample
AMASA-0005/R1 14/04/07 14/04/10 Mar-2014) Hoang
Purlin_rev1
14/04/21 B

BBVN-FIVE-S2-SC- Sample for Material Sticker


AMASA-0006 14/03/24 14/03/25 Hoang
Sample for Material Sticker 14/03/24
14/03/24 A
BBVN-FIVE-S2-SC- Sand for Backfill
AMASA-0007 14/03/24 14/03/25 Hoang
Sand for Backfill
14/03/28 C
BBVN-FIVE-S2-SC- Sand for Backfill Rev.1 Test report by VIBM (Vietnam Institute for
AMASA-0007/R1 14/04/03 14/04/07 Building Materials) Hoang
Sand for Backfill Rev.1
10-Apr-14 A

BBVN-FIVE-S2-SC- Crush rock range 2-10mm, less than 10% passing the 2.36mm sieve for Backfill
AMASA-0008 14/03/24 14/03/25 Hoang
Crush rock range 2-10mm, less than 10% passing the 2.36mm sieve for Backfill
14/03/28 C
BBVN-FIVE-S2-SC- Crush rock range 2-10mm, less than 10% passing the 2.36mm sieve for
Test
Backfill
result by
Rev.1
VIBM (Vietnam Institute for
AMASA-0008/R1 14/04/03 14/04/07 Building Materials)
Crush rock range 2-10mm, less than 10% passing the 2.36mm sieve for Backfill Rev.2
14/04/05 C
BBVN-FIVE-S2-SC- Crush rock range 2-10mm, less than 10% passing the 2.36mm sieve for Backfill Rev.2
AMASA-0008/R2 14/04/14 14/04/17
Crush rock range 2-10mm, less than 10% passing the 2.36mm sieve for Backfill Rev.2
14/04/17 A
BBVN-FIVE-S2-SC- List of FM Approval Materials
AMASA-0009 14/03/25 14/03/28 Tung
List of FM Approval Materials
14/03/29 C
BBVN-FIVE-S2-SC- List of FM Approval Materials_Rev.1 (Revised based on comments in AMASA_0009 dated 11-Apr-2014)
AMASA-0009/R1 14/04/25 14/04/25 Tung
List of EM Approval material _ Rev1
14/04/25 B

BBVN-FIVE-S2-SC- Steel plate for steel structure (Thickness 6mm, 8mm, 10mm, 12mm,
AMASA-0010 14/04/02 14/04/05 16mm, 20mm, 30mm, 40mm) Hoang
Steel plate for steel structure (Thickness 6mm, 8mm, 10mm, 12mm,
14/04/05 16mm, 20mm, 30mm, 40mm) B
BBVN-FIVE-S2-SC- Steel plate for steel structure (Thickness 6mm, 8mm, 10mm, 12mm, Test Result
AMASA-0010 14/05/17 14/05/20 16mm, 20mm, 30mm, 40mm)_Additional Documents for AMASA- Hoang QC
(ADD.01) 0010 dated 2-Apr-201

BBVN-FIVE-S2-SC- Color Paint Catalogue for Steel structure


AMASA-0011 14/04/02 14/04/05 Hoang
Color Paint Catalogue for Steel structure
14/04/17 C
BBVN-FIVE-S2-SC- Color Paint Catalogue for Steel structure_Rev.1
AMASA-0011/R1 14/05/19 14/05/13 14/05/15 Hoang QC C
Approval for Material Sample 3
OUTGOING Rev. Title Attachment Date
Date Required INCOMINGDat Author/Copy delivered
Date Issued Status
Reply e Issued Delivered to

BBVN-FIVE-S2-SC- Color Paint Catalogue for Steel Structure_Rev.1_Additional ISO 12944 for lifetime of paint
AMASA-0011/R1 14/05/12 14/05/15 14/05/15 Documents Hoang QC
(ADD.01)
BBVN-FIVE-S2-SC- Color Paint for Steel structure_Rev.2 revised based on comments in Sample (INTERLAC-645)
AMASA-0011/R2 14/05/23 14/05/28 14/05/29 AMASA-0011_Rev.1 dated 15-May-2014 Hoang QC C
BBVN-FIVE-S2-SC- Color Paint for Steel structure_Rev.3 revised based on comments in Sample (INTERLAC-645)
AMASA-0011/R3 14/05/29 14/06/5 14/05/31 AMASA-0011_Rev.2 dated 28-May-2014 Hoang QC A

BBVN-FIVE-S2-SC- XYPEX (Crystalline Waterproof Coating system) Introduction, Spec Data, Xypex Concentrate,
AMASA-0012 Vietnam Projects references, Vinh Hiep Hung-
Xypex-Method Statement, Material safety data
14/04/03 14/04/07 sheet, Selected Projects & SAMPLE Tung
(powder&plate)

XYPEX (Crystalline Waterproof Coating system)


12-Apr-14 B
BBVN-FIVE-S2-SC- XYPEX (Crystalline Waterproof Coating system)_Additional C/O & C/Q
AMASA-0012 (ADD) 14/04/17 14/04/21 Documents Tung

Tung B+C
BBVN-FIVE-S2-SC- XYPEX (Crystalline Waterproof Coating system)_Sample
AMASA-0012 14/05/13 14/05/16 14/05/14 B
(ADD.02)/R1

BBVN-FIVE-S2-SC- Hight intension Bolts (D16, D20, D24) hot dip galvanized Certificate of Origin (C/O), Certificate of
AMASA-0013 14/04/07 14/04/10 Qualtiy (C/Q) Hoang
Hight intension Bolts (D16, D20, D24) hot dip galvanized
14/04/14 C
BBVN-FIVE-S2-SC- High Tension Bolts (D16, D20, D24) hot dip galvanized_Rev.1
AMASA-0013/R1 14/04/24 14/04/28 14/06/17 (Revised based on comments in AMASA_0013 dated 14-Apr-2014) Hoang A

BBVN-FIVE-S2-SC- Wall Tile for Wet area (Toilet & Changing room) 01 Sample
AMASA-0014 10-Apr-14 14-Apr-14 Tung
Wall Tile for Wet area (Toilet & Changing room)
14/04/14 C
BBVN-FIVE-S2-SC- Ceramic Tile for Black Corridor (CR1), Wet Areas (CR2), Exterior 2 company catalogues, Test report, Techinical
AMASA-0014/R1 14/04/18 14/04/23 Terrace (CR3), Toilet Wall (CR4) supplied by Viet Ceramic & Bach Specifications, Samples Tung
Ma Ceramic
Ceramic Tile for Black Corridor (CR1), Wet Areas (CR2), Exterior
14/04/24 Terrace (CR3), Toilet Wall (CR4) supplied by Viet Ceramic & Bach C
Ma Ceramic
Approval for Mechanical, Electrical Plumbing 4
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
14/04/16 Lighting Protection C

14/04/07 MV Cable & MV Terminal kit A

14/04/04 Steel conduit (Smartube) C

14/03/26 AHU-2units Rev.1 C 14/03/26

14/03/24 Air Conditioning C 14/03/24

14/03/17 Air Cooled Chiller C 14/03/17

14/03/17 AHU-2units C 14/03/17

Plumbing System u.PVC Pipe&Fitting B


11-Apr-14 12-Apr-14
Plumbing system-PPR pipe & fitting B
12-Apr-14
Air Cooled Chiller Rev.1 based on comments AMEP-0001 dated 17Mar2014 B
12-Apr-14
AHU-2units Rev.2 B
12-Apr-14
VRV III Air Conditioning Rev.1 B
11-Apr-14 12-Apr-14

08-Apr-14 Transformer & LV busduct (feeder) B 08-Apr-14


Plumbing system-HDPE pipe & fitting
04-Apr-14 C 04-Apr-14

08-Apr-14 LV Busway Production B 08-Apr-14


BBVN-FIVE-S2-SC- 14/03/17 14/03/22 Air Cooled Chiller Specification, chiller selection Trung
AMEP-0001 software, 2 A4 size drawings

BBVN-FIVE-S2-SC- 14/03/31 14/04/05 Air Cooled Chiller Rev.1 based on comments AMEP-0001 dated Trung
AMEP-0001/R1 17Mar2014

BBVN-FIVE-S2-SC- 14/03/17 14/03/22 AHU (AIR HANDLING UNIT w/VSD) - 2 units Specification, 2 A4size Trung
AMEP-0002 drawings, AL-KO AHU AT6
brochure, Form Material &
Equipment Approval record
signed by Sub-contractor dated
10-Mar-2014

BBVN-FIVE-S2-SC- 14/03/24 14/03/31 AHU - 2 units Rev.1


AMEP-0002/R1
BBVN-FIVE-S2-SC- 14/04/01 14/04/08 AHU-2units Rev.2 AHU No.3&4 Data sheet,
AMEP-0002/R2 AHU AT6 Catalogue, Supply
fan curve diagram, Exhaust fan
curve diagram, fan motor
catalogue, damper actuator
catalogues, heat wheel
catalogues

BBVN-FIVE-S2-SC- 14/03/17 14/03/22 VRVIII Air Conditioning Specification, VRV brochure, Quang
AMEP-0003
BBVN-FIVE-S2-SC- 14/03/29 14/04/04 VRV III Air Conditioning Rev.1 VRV Tabulation list, 15
AMEP-0003/R1 catalogues of CDU 1 to 5 and
Indoor Cooling/Heating

BBVN-FIVE-S2-SC- 14/03/31 14/04/04 LV Busway Production Canalis KSC, 630A Canalis, Mr. Quang
AMEP-0004 630A End Feed-end cover,
Plug in

BBVN-FIVE-S2-SC- 14/03/31 14/04/03 MV Cable & MV Terminal kit Mr. Quang


AMEP-0005
BBVN-FIVE-S2-SC- 14/08/08 14/08/13 14/08/12 MV Cable & MV Terminal kit 36kV Technical Description Details Quang/Ujiie B/A
AMEP-0005 (A)

BBVN-FIVE-S2-SC- 14/03/31 14/04/08 Transformer & LV busduct (feeder) Relays, Thermo meter, Feeder Mr. Quang
AMEP-0006 busway copper contact,
Flexible LinkEdgewise

BBVN-FIVE-S2-SC- 14/04/01 14/04/05 Plumbing System u.PVC Pipe&Fitting


AMEP-0007

BBVN-FIVE-S2-SC- 14/04/02 14/04/06 Plumbing system-PPR pipe & fitting Mr. Quang
AMEP-0008

BBVN-FIVE-S2-SC- 14/04/02 14/04/06 Plumbing system-HDPE pipe & fitting Mr. Quang
AMEP-0009
BBVN-FIVE-S2-SC- 10-Apr-14 14-Apr-14 Plumbing system-HDPE pipe & fitting_Rev.1
AMEP-0009/R1
14/04/11 Plumbing system-HDPE pipe & fitting_Rev.1 C

BBVN-FIVE-S2-SC- 14/04/19 14/04/23 Plumbing system-HDPE pipe & fitting_Rev.2 Mr. Quang
AMEP-0009/R2
14/04/24 Plumging system - HDPE pipe & Fittings _ Rev.2 A/B

BBVN-FIVE-S2-SC- 10-Apr-14 14-Apr-14 HVAC system/ u.PVC pipe & Fitting (Condensate Drain Pipe) Mr.Ujiie
AMEP-0010
14/04/23 HVAC system/ u.PVC pipe & Fitting (Condensate Drain Pipe) B

BBVN-FIVE-S2-SC- 14/04/28 14/05/02 14/05/07 Diesel Generating Sets Technical Detail Desciption, Mr. Quang N/A
AMEP-0011 Drawing, Catalogue

BBVN-FIVE-S2-SC- 14/03/31 14/04/04 PVC conduit and fitting (SP) Brochure & Certificate Mr. Quang
AMEP-0012
14/04/04 PVC conduit and fitting (SP) C

BBVN-FIVE-S2-SC- 14/04/14 14/04/19 PVC conduit and fitting (SP)_Rev.1 Certificate & Brochure Mr. Quang/Mr.Diem
AMEP-0012/R1
14/04/17 PVC conduit and fitting (SP)_Rev.1 C

BBVN-FIVE-S2-SC- 14/03/31 14/04/04 Steel conduit (Smartube) Brochure & Certificate Mr. Quang
AMEP-0013
BBVN-FIVE-S2-SC- 14/04/14 14/04/19 Steel conduit (Smartube).Rev1 Company Profile & Brochure Mr. Quang/Mr. Diem
AMEP-0013/R1
14/04/17 Steel conduit (Smartube).Rev1 C

BBVN-FIVE-S2-SC- 14/05/06 14/05/10 14/05/28 Steel Conduit and Fittings_Rev2 Catalogue & Supplier Profile Mr. Quang/Diem B/B/A
AMEP-0013/R2
BBVN-FIVE-S2-SC- 14/07/14 14/07/19 14/07/18 Steel Conduit & Fittings _Rev.2 (Additional Document) Catalogue B/A
AMEP-0013/R2 (ADD.01)

BBVN-FIVE-S2-SC- 14/03/31 14/04/04 Flexible conduit for underground (Baan) Brochure & Certificate Mr. Quang
AMEP-0014
14/04/04 Flexible conduit for underground (BAAN) C

BBVN-FIVE-S2-SC- 14/04/14 14/04/19 Flexible conduit for underground (Baan)_Rev.1 Cerfiticate, Capacity & Mr. Quang/Mr. Diem
AMEP-0014/R1 Experience Report
BBVN-FIVE-S2-SC- 14/04/23 Flexible conduit for Underground (BAAN)_Rev.1 B/A
AMEP-0014/R2
14/06/02 B

BBVN-FIVE-S2-SC- 12-Apr-14 19-Apr-14 LV Cable Mr.Quang


AMEP-0015
14/04/16 LV Cable C

BBVN-FIVE-S2-SC- 14/04/25 14/05/02 14/05/09 LV Cable_Rev.1 (Revised based on comments in AMEP_0015 dated Mr. Quang C
AMEP-0015/R1 16/J64-Apr-2014)
BBVN-FIVE-S2-SC- 14/05/23 14/06/3 14/06/09 LV Cable_Rev.1 (Revised based on comments in AMEP_0015 dated Mr. Quang B
AMEP-0015/R1 16/J64-Apr-2014)

BBVN-FIVE-S2-SC- 12-Apr-14 16-Apr-14 Lighting Protection Mr.Quang


AMEP-0016
BBVN-FIVE-S2-SC- 14/04/28 14/05/2 14/06/05 Lighting Protection_Rev.1 Revised based on comments AMEP_0016 Quang/Diem B
AMEP-0016/R1 dated 16-APR-2014

BBVN-FIVE-S2-SC- 14/04/15 14/04/18 VAV for Circulation Corridor VariTrane VAV Terminal Mr. Quang
AMEP-0017 Catalogue
14/04/24 VAV for Circulation Corridor A/B

BBVN-FIVE-S2-SC- 14/05/06 14/05/13 14/05/28 Process Chilled Water Insulation Technical Detail Description, Mr. Quang B
AMEP-0018 Catalogue

BBVN-FIVE-S2-SC- 14/04/15 14/014/18 14/04/17 RO Water System (Pipe & Fitting and Valve) Pipe & Fitting for RO Mr. Quang C
AMEP-0019 Catalogue, Valve for RO
Catalogue
BBVN-FIVE-S2-SC- 14/05/24 14/06/06 RO Water System (Pipe & Fitting and Valve)_Rev.1 Revised based on Tabulation, Technical Detail Randy/Quang
AMEP-0019/R1 comments in AMEP-0019 dated 17-April-2014 Description. Catalogue

BBVN-FIVE-S2-SC- 14/04/22 14/04/28 14/05/07 Fire Alarm System Intelligent Fire Control Panel, smoke Quang, Diem C
detector, heat detector, alarm bell,
AMEP-0020 manual call point, deam detector, duct
smoke detector, laser smoke detector,
telephone jack, relay control module,
monitor module, control module, fault
isolator, horn trobe, phone
communication module, lamp driver
module (for renovation of MIMIC
panel)

BBVN-FIVE-S2-SC- 14/05/15 14/05/22 14/05/31 (15 items) Fire Alarm System Catalogue & Supplier Profile Quang/ Trung B
AMEP-0020/R1 [FM Approval] Intelligent Fire Control Panel IFC 302(E), smoke
detector 2951J, heat detector 5951J, alarm bell SSM24-6, manual call
point JBG-12LX, beam detector FSB-200/FSB-200s, duct smoke
detector D4240, laser smoke detector 7351J, telephone jack FPJ, relay
control module M300RJ, monitor module M301MJ, fault isolator
M500XJ, horn trobe CHSR, phone communication module M500FPJ,
lamp driver module LDM-32

BBVN-FIVE-S2-SC- 14/04/23 14/04/26 Flexible Thermelly Insulation Duct Connection Catalogue Mr. Quang
AMEP-0021
14/05/05 Flexible Thermelly Insulation Duct Connection B

BBVN-FIVE-S2-SC- 14/04/23 14/04/26 14/05/14 Glasswool Insulation for Cleanroom Ducts Certificate of Compliance FM Mr. Quang B/B/A
AMEP-0022 Approval Class 4924,
Catalogue

BBVN-FIVE-S2-SC- 14/04/24 14/04/26 Galvanized Pipe Medium Grade SCHED 40 for Fire Fighting Tabulation & Catalogue Mr. Quang
AMEP-0023
14/04/25 Galvanized Pipe Medium Grade SCHED 40 for Fire Fighting C

BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/29 Galvanized Pipe Medium Grade SCHED 40 for Fire Fighting (FM 200 FM 200 Piping, Tabulation & Quang/Trung A
AMEP-0023/R1 (A) System)_Rev.1 Revised based on comments in AMEP_0023 dated 25- Catalogue
Apr-2014
BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/28 Galvanized Pipe Medium Grade SCHED 40 for Fire Fighting (above Tabulation & Catalogue Quang/Trung A/B
AMEP-0023/R1 (B) Ground Floor) _Rev.1 Revised based on comments in AMEP_0023
dated 25-Apr-2014
BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/15 Galvanized Pipe Medium Grade SCHED 40 for Fire Fighting Tabulation & Catalogue Quang/Trung C
AMEP-0023/R1 (C) (Underground)_Rev.1 Revised based on comments in AMEP_0023
dated 25-Apr-2014
BBVN-FIVE-S2-SC- 14/05/31 14/06/12 14/06/03 Galvanized Pipe Medium Grade SCHED 40 for Fire Fighting Tabulation, Technical Detail Quang/Trung B
AMEP-0023/R2 (C) (Underground)_Rev.2 Revised based on comments in AMEP_0023/R1 Description & Catalogue
(C) dated 15-May-2014
Denso Tape
Pipe Fittings (JIS)

BBVN-FIVE-S2-SC- 14/04/28 14/05/2 14/05/19 FM 200 C/W Control Panel and Accessories FIKE Technical detail Quang/Trung C
AMEP-0024 description, drawing and
catalogue
BBVN-FIVE-S2-SC- 14/06/02 14/06/13 14/06/25 FM 200 C/W Control Panel and Accessories_Rev.1 Revised upon Tabulation, Calculation, Quang/Trung B
AMEP-0024/R1 AMEP 0024 dated 19-May-2014 Catalogue
Approval for Mechanical, Electrical Plumbing 5
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
BBVN-FIVE-S2-SC- 14/09/17 14/09/22 14/09/22 FM 200 C/W Accessories_Rev.2 (Superseded the approved FM 200 c/w Technical Data Sheet Quang/Trung B
AMEP-0024/R2 Accessories_Rev.1 in AMEP24/R1 dated 25-June-2014)

BBVN-FIVE-S2-SC- 14/04/28 14/05/02 14/05/21 Sprinkler Head System Preaction Sprinkers (Quick Quang C
AMEP-0025 Response Upright), Quick
Response Sprinkler heads,
Standard Sprinkler Heads
VIKING Technical Detail
desciption, Catalogue

BBVN-FIVE-S2-SC- 14/06/02 14/06/12 14/07/03 Sprinkler Head System (Preaction Sprinkers (Quick Response Upright Tabulation, Catalogue Quang B
AMEP-0025/R1 and Pendant), Quick Response, Sprinkler heads, Standard Sprinkler
Heads, Sprinkler Guard )_Rev.1 Revised upon AMEP-0025 dated 21-
May-2014
BBVN-FIVE-S2-SC- 14/10/02 14/10/06 14/10/07 ESPR Upright Sprinkler for Warehouse Under Duct- VIKING VK520 Technical Data Sheet Quang A
AMEP-0025/R1(ADD.01) K14.0 (Additional Material for approved in AMEP_0025 dated 03-July-
2014)

BBVN-FIVE-S2-SC- 14/04/29 14/05/05 HVAC_Hepa Filter (AAF)_Size 1060x460x69mm Technical Detail Description, Quang/Trung
AMEP-0026 Drawing, Catalogue

BBVN-FIVE-S2-SC- 14/04/29 14/05/05 14/05/28 HVAC_Hepa Filter (AAF)_Size 1060x1060x69mm Technical Detail Description, Quang/Trung B/B/A
AMEP-0027 Drawing, Catalogue

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 Drawings Quang/Vuong


AMEP-0028 Hepa Filter Box (INOCHI)_Top Open&Dimension 1145x1145x400mm;
Top Open&Dimension 11145x1145x400; Bottom Open&Dimension
1145x545x400mm; Bottom Open&Dimension 1145x1145x400mm

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/20 HVAC_ Chilled Water Pipe (Tread Seal for Screw type) for Compressor Catalogue Quang B/A
AMEP-0029 Chilled Water and Instrument on Piping

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/20 Compressor System_Compressor Pipe Tread Seal for Screw type piping Catalogue Quang A
AMEP-0030 tread seal

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/22 HVAC System_VRV Indoor and Refrigerant Pipe Support Technical Detail Description Quang C
AMEP-0031 & Catalogue

BBVN-FIVE-S2-SC- 14/04/29 14/05/05 14/05/07 Galvanized Ducts and Fittings for Low Pressure (SSSC) Catalogue Quang/Vuong C
AMEP-0032
BBVN-FIVE-S2-SC- 14/05/23 14/06/02 14/05/28 HVAC System_Galvanized Ducts and Fittings for Low Pressure _Rev.1 Tabulation, Technical Data Quang A/B
AMEP-0032/R1 Revised based on comments in AMEP-0032 dated 7-May-2014

BBVN-FIVE-S2-SC- 14/04/29 14/05/05 14/05/07 Galvanized Duct and Fittings for Medium Pressure Catalogue Quang/Vuong C
AMEP-0033
BBVN-FIVE-S2-SC- 14/05/19 14/06/02 14/05/28 Galvanized Duct and Fittings for Medium Pressure_Rev.1 A
AMEP-0033/R1

BBVN-FIVE-S2-SC- 14/04/29 14/05/05 14/05/07 Spiral Duct and Fittings Catalogue Quang/Vuong C
AMEP-0034
BBVN-FIVE-S2-SC- 14/05/19 14/06/02 14/05/28 Spiral Duct and Fittings_Rev.1 A/B
AMEP-0034/R1

BBVN-FIVE-S2-SC- 14/05/02 14/05/08 14/05/09 Butterfly valve and OS&Y gate valves for fire fighting Catalogue Trung C
AMEP-0035
BBVN-FIVE-S2-SC- 14/05/21 14/06/03 14/05/26 Fire fighting system_OS&Y Gate valves for FF System Hose reel -18 Tabulation, Catalogue Randy B/B/A
AMEP-0035/R1 gate valve, tamper switch (supervisory switch) - OSYSU-1, Automatic
air vent - AV-0100, Butterfly valve - HPW Series

BBVN-FIVE-S2-SC- 14/06/05 14/06/11 14/06/11 Fire fighting system_OS&Y Gate valves for FF System _ Rev.1 Tabulation, Catalogue Trung A
AMEP-0035/R1 (ADD.01) (ADD.01) _ Revised based on comments in AMEP-0035/R1 dated 26-
May-2014

BBVN-FIVE-S2-SC- 14/06/03 14/06/09 14/06/27 Balancing Valve (PCW, AHU and Compressor) and Motorized Valve Tabulation, Catalogue Mr. Quang B
AMEP-0036 for Chiller and AHU

BBVN-FIVE-S2-SC- 14/10/14 14/10/18 14/10/18 Motorized Valve for AHU (Johnson Control) Catalogue, Technical Data Quang/Ujiie C
AMEP-0036 A
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 Motorized Valve for AHU (Johnson Control) Catalogue, Technical Data, Quang/Ujiie
AMEP-0036 A/R1 BBVN-S2-SC-LTR-0087

BBVN-FIVE-S2-SC- 14/05/02 14/05/08 14/05/22 Alarm valve and Pre-action valve for fire fighting system Catalogue Trung A/B/B
AMEP-0037

BBVN-FIVE-S2-SC- 14/07/28 14/08/02 14/08/04 Pre-action valve double interlock type (Superseded the pre-action valve Catalogue, Technical detail Quang B
AMEP-0037 A single interlock in AMEP-37 dated 19-May-2014 following designer description
comments)

BBVN-FIVE-S2-SC- 14/05/02 14/05/08 14/05/09 Lighting system Catalogue Quang/Diem C


AMEP-0038
BBVN-FIVE-S2-SC- 14/05/14 14/05/21 14/05/29 Lighting system_Rev.1 Revised based on comments in AMEP-0038 Tabulation, Lighting -1x18W, B/B/A
AMEP-0038/R1 dated 9-May-2014 2x13W, Exits, High bay
150W, Road pole lamp,
3x36W, 2x28W
(Weatherproof), 2x28W,
3x14W, Road Pole Lamp,
3x14W

BBVN-FIVE-S2-SC- 14/06/05 14/06/09 14/06/25 Lighting system_Rev.1 (Add.01)_ Revised based on comments in Catalogue B/A+C
AMEP-0038/R1 (ADD.01) AMEP-0038/R1 dated 29-May-2014

BBVN-FIVE-S2-SC- 14/06/26 14/07/01 14/06/27 Lighting System_(Additional) Exit Light for exit road (revised based on Tabulation, Catalogue B
AMEP-0038 (A) comments in AMEP-38/R1 (ADD) dated 25-June-2014

BBVN-FIVE-S2-SC- 14/05/02 14/05/08 14/05/28 BMS system Catalogue Diem B


AMEP-0039
BBVN-FIVE-S2-SC- 14/07/09 BMS system B
AMEP-0039 (ADD)

BBVN-FIVE-S2-SC- 14/05/03 14/05/09 14/05/28 Copper pipe & Fitting Catalogue Quang B/B/A
AMEP-0040

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/20 Water Supply System_Water Heater (ARISTON) Techinical detail description & Quang B/A
AMEP-0041 Catalogue

BBVN-FIVE-S2-SC- 14/05/06 14/05/13 14/05/28 Chiller Pipe Insulation Technical Detail Description, Mr. Quang B/B/A
AMEP-0042 Catalogue, FM Certificate

BBVN-FIVE-S2-SC- 14/05/06 14/05/13 14/05/28 VRV Insulation (Refrigirant Pipe and Condensate Drain) Catalogue, Technical Detail Mr. Quang B/B/A
AMEP-0043 Description, FM certificate

BBVN-FIVE-S2-SC- 14/05/06 14/05/13 14/05/14 Flexible Joint Model Z-3000 & Flexible Joint Model Z-9000 Technical Detail Description, Mr. Quang C
AMEP-0044 Catalogue
BBVN-FIVE-S2-SC- 14/05/31 14/06/13 14/06/02 HVAC&CDA_Flexible Joint for Chiller Piping and CDA Piping - SF- Technical Detail Description, Quang/Ujiie A
AMEP-0044/R1 600_Rev.1 (Revised based on comments in AMEP-0044 dated 14-May- Catalogue
2014)

BBVN-FIVE-S2-SC- 14/05/07 14/05/10 14/05/23 Air Compressor Technical Detail Description, Mr. Quang B
AMEP-0045 Catalogue

BBVN-FIVE-S2-SC- 14/05/09 14/05/15 14/05/15 Sanitary Wares Sanitary Ware Tabulation, Quang/ Khoa C/A+B+C
AMEP-0046 Under Counter Top Basin,
Wall Hung Basin, Auto Sensor
Basin Tap, Water Closet, Wall
Hung Urinal w Automatic
Flush Valve, Automatic Flush
Valve, Shower Mixer
Complete, Pantry Sink, Faucet
for Pantry Sink, Accessories

BBVN-FIVE-S2-SC- 14/06/03 14/06/10 14/06/10 Sanitary Wares_Rev.1 Revised based on comments in AMEP-0046 Tabulation, faucet automatic, Quang/ Khoa A
AMEP-0046/R1 dated 15-May-2015 shower

BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/28 Supply Fan Catalogues of Ventilation Fan Quang/Diem C
AMEP-0047 Equipment No. OAF-PII-01

BBVN-FIVE-S2-SC- 14/06/03 14/06/09 14/06/05 Supply Fan_Rev.1 (revised based on comments in AMEP-0047 dated Catalogue of Supply Fan Mr. Quang B
AMEP-0047/R1 28-May-2014) Equipment No. OAF-PII-01

BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/28 Smoke Exhaust Fan Catalogues of Smoke Exhaust C
AMEP-0048 Equipment No. FSFE-PII-01;
PAEF-PII-01
BBVN-FIVE-S2-SC- 14/06/02 14/06/09 14/06/13 Smoke Exhaust Fan_Rev.1 Revised based on comments in AMEP-0048 Catalogue of smoke exhaust Quang/Ujiie C/C/B
AMEP-0048/R1 dated 28-May-2014 (RFC submitted paralelly for this AMEP) fan Equipment No.FSFE-PII-
01; PAEF-PII-01

BBVN-FIVE-S2-SC- 14/06/26 14/07/01 14/07/05 B


AMEP-0048/R2
Approval for Mechanical, Electrical Plumbing 6
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/28 Exhaust Fan Catalogues of Ventilation Fan C
AMEP-0049 Equipment No. EAFG-PII-01,
EAFG-PII-02; EAF1-PII-01,
EAF1-PII-02
BBVN-FIVE-S2-SC- 14/06/03 14/06/09 14/06/05 Exhaust Fan_Rev.1 revised based on comments in AMEP-0049 dated Catalogue of Supply Fan Mr. Quang B
AMEP-0049/R1 28-May-2014) RFC submitted paralelly for this AMEP Equpment No. EAFG-PII-01;
EAFG-PII-02; EAF1-PII-01;
EAF1-PII-02

BBVN-FIVE-S2-SC- 14/05/10 14/05/17 14/05/31 CCTV System (Indoor PTZ IP dome camera, outdoor PTZ IP dome C
AMEP-0050 camera, Indoor fixed camera, FOC (fiber optic converter)
BBVN-FIVE-S2-SC- 14/06/13 C
AMEP-0050/R1
BBVN-FIVE-S2-SC- 14/06/18 14/06/23 14/06/25 CCTV System_Indoor PTZ dome camera, Outdoor PTZ IP dome Tabulation, technical detail Diem B
AMEP-0050/R2 Camera, IP indoor fixed dome camera, FOC (fiber optic desciption, catalogue
converter)_Rev.2 Revised based on comments in AMEP-0050/R1 dated
13-June-2014

BBVN-FIVE-S2-SC- 14/05/10 14/05/17 14/05/19 HVAC System: Black carbon steel pipe SCHED 40 for chilled water Technical detail description, Quang/Ujiie C
AMEP-0051 Catalogue
BBVN-FIVE-S2-SC- 14/05/31 14/06/14 14/06/02 HVAC System: Black carbon steel pipe SCHED 40 for chilled Technical detail description, Quang/Ujiie B
AMEP-0051/R1 water_Rev.1 Revised based on comments in AMEP-0051 dated 16- Catalogue
May-2014

BBVN-FIVE-S2-SC- 14/05/10 14/05/15 14/05/19 HVAC System: Black carbon steel pipe fittings for chilled water Technical detail description, C
AMEP-0052 Catalogue
BBVN-FIVE-S2-SC- 14/05/31 14/06/14 14/06/02 HVAC System: Black carbon steel pipe fittings for chilled water_Rev.1 Technical detail description, B
AMEP-0052/R1 Revised based on comments in AMEP-0052 dated 19-May-2014 Catalogue

BBVN-FIVE-S2-SC- 14/05/16 14/05/20 14/05/22 HVAC System_Chilled Water Pipe Support Catalogue Quang C
AMEP-0053

BBVN-FIVE-S2-SC- 14/05/15 14/05/19 14/06/05 HVAC_Buffer Tank & Buffer Tank Insulation Location of installation Technical detail description, Quang B/B+C
AMEP-0054 AHU room (Buffer tank capacity 5m3) (NAM AN) Catalogue

BBVN-FIVE-S2-SC- 14/11/05 14/11/12 Buffer Tank Insulation - BASF Elastopor MH 2149 (Superseded the Technical Data Sheet Quang/Ujiie
AMEP-0054 A approved buffer tank insulation in AMEP-54 dated 5-June-2014

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/20 Fire Fighting System_Fire Fighting Tread Seal for Screw type Piping Catalogue Quang A
AMEP-0055 Tread Seal (TOMBO)

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/21 Fire Fighting System (Fire Extinguisher CO2&ABC, Fire Hydrant Catalogue Quang C
AMEP-0056 Pillar, Hosereel cabinet (indoor type), Fire Hose reel (Indoor with
Accessories), Fire Hydrant cabinet outdoor & Fire hydrant (outdoor with
accessories))
BBVN-FIVE-S2-SC- 14/06/18 14/06/23 14/07/04 Fire Hose Reel & Extinguisher; Drum Hose Reel for Clean Room, Tabulation, Catalogue, Quang/Ujiie B/A+B+C
AMEP-0056/R1 Circulation Corridor, Office Ground Floor, Warehouse, above Ceiling Drawings
Clean Room, Office 1st Floor, External and Transformer Room 1,2,3,
Stage 1_Rev.1 Revised based on comments in AMEP-0056 dated 21-
May-2014

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/21 Process Cooling Water System_SUS 304 Pipe Use for Process Cooling Tabulation, Technical Detail Quang C
AMEP-0057 Water Description & Catalogue

BBVN-FIVE-S2-SC- …… …….. 14/06/02 Process Cooling Water System_SUS 304 Pipe Use for Process Cooling B
AMEP-0057/R1 Water_Rev.1

BBVN-FIVE-S2-SC- 14/05/14 14/05/17 14/05/20 Process Cooling Water System_SUS 304 Pipe Fittings Use for Process Tabulation, Technical Detail Quang B
AMEP-0058 Cooling Water & Fittings Description & Catalogue

BBVN-FIVE-S2-SC- 14/05/15 14/05/17 14/05/21 Compressed Air System_Copper Pipe Fittings for Compressed Air (Use Catalogue Quang C
AMEP-0059 for Compressor air Piping inside production area and above walkable
ceiling connected on GI pipe)
BBVN-FIVE-S2-SC- 14/05/31 14/06/13 14/06/23 Compressed Air System_Copper Pipe Fittings for Compressed Air (Use Technical Detail Description, Quang A
AMEP-0059/R1 for Compressor air Piping inside production area and above walkable Catalogue
ceiling connected on GI pipe)_Rev.1 Revised based on comments in
AMEP-0059 dated 21-May-2014

BBVN-FIVE-S2-SC- 14/05/15 14/05/19 14/05/21 Compressed Air System_Copper Pipe for Compressed Air (Use for Catalogue Quang C
AMEP-060 Compressor air Piping inside production area and above walkable
ceiling connected on GI pipe)
BBVN-FIVE-S2-SC- 14/05/30 14/06/13 14/06/03 Compressed Air System_Copper Pipe for Compressed Air (Use for Technical Detail Description, Quang/Randy/Ujiie A
AMEP-060/R1 Compressor air Piping inside production area and above walkable Catalogue
ceiling connected on GI pipe)_Rev.1 Revised based on comment in
AMEP-60 dated 21-May-2014

BBVN-FIVE-S2-SC- 14/05/15 14/05/29 14/06/13 (1) Network Video Recorder; (2) Reader Controller & Card Reader Catalogue, Tabulation Quang/Randy B
AMEP-061 Interface Module-Lenel LNL-1320 Series, LNL-2220; (3) nput Control
Module-Lenel LNL1100 Series 2; (4) Door Contact-Position Sensor
1078C-N; (5)Door Holder-YLI YD-602; (6) Door Alarm - AV Gad Eye
spy II pro; (7) Card Reader & Card Reader w/Time Tracking - HID R10;
(8) Pir Sensor - AV Gad Eye spy II pro; (9) Emergency Door Release
Break Glass - YLI ABK-900A, Fire Proofl (10) Exit Push Button - YLI
ABK-802

BBVN-FIVE-S2-SC- 14/07/14 14/07/19 14/07/18 Card Reader & Card Reader with Time Tracking_Rev.1 - HID-R10- catalogue Quang/Randy B
AMEP-061/R1 900N (Superseded the Card Reader & Card Reader with time tracking-
HID-R10-6100B, 6108B, 6109B in AMEP-61 dated 13-June-2014)

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/06/05 HVAC System _ Non-Clean room Duct Sealant (APOLLO A100) Catalogue Quang B
AMEP-062

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/06/05 HVAC System_Cleanroom Duct Sealant (Terostat MS930) Catalogue Quang B
AMEP-063

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/06/05 Compressed Air System_GI Black Steel Pipe Medium Grade Schedule Tabulation. Catalogue Quang A/B
AMEP-064 40

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/05/21 Compressed Air System_GI Black Steel Pipe Fittings (DN50, DN80) Tabulation, Catalogue Quang C
AMEP-065
BBVN-FIVE-S2-SC- 14/05/31 14/06/12 14/06/03 Compressed Air System_GI Black Steel Pipe Fittings (DN50, Tabulation, Catalogue Quang B
AMEP-065/R1 DN80)_Rev.1 Revised based on Comments in AMEP-0065 dated 21-
May-2014

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/06/05 Water Supply System_Water Pump & Water Pump Control Panel Catalogue, Manufacturer Quang B SUPERSEEDED
AMEP-066 Letter, Technical Data & booster pump Grund
Drawing Fos Hydro Multi -
B/E 2CME 25-41

BBVN-FIVE-S2-SC- 14/06/14 14/06/20 14/06/20 Water Supply System_Water Pump & Water Pump Control Catalogue, Manufacturer Quang/Khoa B
AMEP-066/R1 Panel_Rev.1 Revised based on Approval RFC-023 dated 6-June-2014 Letter, Technical Data &
(SMZ-140606/D147) Drawing

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/06/05 Sewage Pump_SP-01 to SP-02 Pump pit, SP-03 to SP-04 Pump pit Catalogue, Manufacturer Quang B/B/A
AMEP-067 (external) Letter

BBVN-FIVE-S2-SC- 14/05/16 14/05/30 14/06/06 MVAC System_Primary Chilled Water Pump CHWP Manufacturer Letter, Technical Quang B
AMEP-068 03(200x150CNHA), Secondary Chilled Water Pump SCHWP-01-03 Data
150x125 FS4KA5 37

BBVN-FIVE-S2-SC- 14/05/19 14/06/02 Electrical Cable & Accessories for Control System: (1) 12C MM Fiber Tabulation, Technical Detail Randy/Quang
AMEP-069 Optic Cable (Indoor) - B9B042, (2) 4C Multimode Outside Plant Fiber Description, Catalogue
Optic Cable - B9A171, (3) 14AWG Twisted Pair Cable - 5120UL, (4)
Shielded 6-core AWG22 Cable - 5504FE, (5) Shield 2-core AWG18
Cable - 5300FE, (6) Shield 4-core AWG22 Cable - 5502FE, (7) UTP
Category 6 Network Cable - 2413, (8) Faceplate Kit Shutter - 2111036-
1, (9) Category 6 SL Series Jacks -1375055-1

BBVN-FIVE-S2-SC- 14/06/14 14/06/21 14/06/25 Electrical Cable & Accessories for Control System: (1) 12C MM Fiber Tabulation, Technical Detail Quang B/B+C
AMEP-069/R1 Optic Cable (Indoor) - B9B042, (2) 4C Multimode Outside Plant Fiber Description, Catalogue
Optic Cable - B9A171, (3) 14AWG Twisted Pair Cable - 5120UL, (4)
Shielded 6-core AWG22 Cable - 5504FE, (5) Shield 2-cor_Rev.1

BBVN-FIVE-S2-SC- 14/10/31 14/11/06 14/11/03 Faceplate Kit Shutter - AMP (Model: 2-1427030-1, 2-1427030-2), Technical Detail Quang/Ujiie B
AMEP-069/R2 Suppersed the approved faceplate kit shutter in AMEP-69/R1 dated 25-
June-2014

BBVN-FIVE-S2-SC- 14/06/27 14/07/03 14/07/09 Electrical Cable & Accessories for Control System: 14AWG pair cable; Technical Detail Description, Quang/Diem A (SUPERSEDED)
AMEP-069 (A) 14AWG Twisted pair cable; TCVN 5738:2001 Catalogue
BBVN-FIVE-S2-SC- 14/08/09 14/08/14 14/08/15 Fiber Optic Cable Technical Detail Description, Quang B
AMEP-069 [B] Catalogue
BBVN-FIVE-S2-SC- 14/08/18 14/08/23 14/08/22 Fire Alarm Cable 14AWG Twisted Pair Cable-5100FZE & 14AWG Manufacturer Letter, Technical Quang B
AMEP-069 [C] Pair Cable-5100UZE (Superseded AMEP-69 [A] dated 9-July-2014) Data Sheet

BBVN-FIVE-S2-SC- 14/08/23 14/08/27 14/08/28 Catelogy 6 UTP Cable Cut Sheet - AMP (Superseded the UTP Catelogy Manufacturer Letter, Catalog Quang/Ujiie B
AMEP-069 [D] 6 inn approved AMEP_069/R1 dated 25 June 2014)

BBVN-FIVE-S2-SC- 14/05/19 14/06/02 14/05/28 Bare Copper Wire - 70mm2 Quang/Ujiie B/A
AMEP-070
Approval for Mechanical, Electrical Plumbing 7
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
BBVN-FIVE-S2-SC- 14/05/19 14/05/30 14/05/29 (A) LV Panel & LCP: (1,2,3) DB-1A-1, 2,3; (4) DB-CDU2, (5,6) DB- Tabulation, Technical Data, Randy, Ujiie, Quang C
AMEP-071 MCC2,3; (7) DB-SCHWP; (8,9) DB-M/C-1,2; (10) DB-IT2; (11) LCP- Drawing, catalogue
TK-01-04-TC, LCP-TK-04-04-MC, LCP-ASS-03&04, LCP-MD-05-22;
(12) LCP-ASS-01,02,05,06,07; (13) LCP-P2-F-1&2; (14) LCP-P2-F-
3&4; (15) LCP-P2-F-MD-1,2,3,4,5,6; (16,17,18) LCP-P2-G-1&2,3,4;
(19) LCP-P2-G-MD-1; (20) PCHWP; (21) DB-CH-03; (22) VSD-RF;
(23) 02 New MCCB in MSB-A Bus-2 (for DB-MCC3-1); (24) DB-CW;
(25,26,27) DB-1C,1D,1E Modification; (28) DB-CDA Modification;
(29) DB-GC-Modification; (30) ATS Panel; (31) DB-M/C-3
Modification; (32) CLP-EXT-03

BBVN-FIVE-S2-SC- 14/06/11 14/06/18 14/06/27 LV Panel: (1,2,3) DB-1A-1, 2,3; (4) DB-CDU2, (5,6) DB-MCC2,3; (7) Tabulation, Technical Data, Ujiie, Quang, Diem B
AMEP-071/R1 DB-SCHWP; (8,9) DB-M/C-1,2; (10) DB-IT2; (11) Local Panel LCP: Drawing, catalogue
LCP-TK-01~04-TC, LCP-TK-01~04-MC, LCP-ASS-03&04, LCP-MD-
05~22; (12) Local Panel: LCP-ASS-01,02,05,06,07; (13) Local Panel
LCP: LCP-P2-F-1&2 (new); (14) Local Panel LCP: LCP-P2-F-3&4
(new); (15) Local Panel LCP: LCP-P2-F-MD-1,2,3,4,5,6; (16,17,18)
Local Panel LCP: LCP-P2-G-1&2,3,4; (19) Local Panel LCP: LCP-P2-
G-MD-1; (20) PCHWP; (21) DB-CH-03; (22) 02 New MCCB in MSB-
A Bus-No.2; MSB-ABUS 2 for DB-MCC3-1&2; (23, 24, 25) DB-
1C,1D,1E Modification; (26) DB-CDA Modification; (27) DB-GC-
Modification; (28) ATS Panel; (29) DB-M/C-3 Modification; (30) CLP-
EXT-03 New; (31) DB-CW

BBVN-FIVE-S2-SC- 14/05/23 14/06/05 14/06/27 HVAC_Volume Control Damper (Rectangular Type), Volume Control Tabulation, Technical Detail Quang/Ujiie B/B+C
AMEP-072 Damper (Round Type), Access Door for Duct description, Catalogue

BBVN-FIVE-S2-SC- 14/05/23 14/06/05 14/06/02 Cable Ladder & Trunking for Power, Data & BMS - E.Nhat Tabulation, Technical Detail Quang/ Ujiie B
AMEP-073 Description, Catalogue

BBVN-FIVE-S2-SC- 14/05/23 14/05/30 14/06/02 Compressor Valve System Ball Valve, Check Valve, Auto Trung/Quang B
AMEP-074 drain, Relief Valve
BBVN-FIVE-S2-SC- 14/08/28 14/08/30 14/09/02 Compressor Valve System (SUS Ball Valve _ Flange Type) TOYO, Data sheet Trung / Quang C
AMEP-074 (FINAL) Model: 3011L

BBVN-FIVE-S2-SC- 14/05/24 14/06/06 14/06/27 HVAC_Exhaust and Return Air Grille, Air Grille for Production Tabulation, Technical Detail Quang/Ujiie A
AMEP-075 Cleanroom Plenum Description, Catalogue

BBVN-FIVE-S2-SC- 14/05/24 14/05/28 14/06/27 Damper for Air Duct Tabulation, Volume Control Quang/Ujiie B/B/A
AMEP-076 Damper, Motorized Damper,
Smoke Fire Damper, Non-
Return Damper Model BDD-
A-R & BDD-A3-R

BBVN-FIVE-S2-SC- 14/05/29 14/06/05 14/06/27 HVAC_BACnet Interface for VRV III Quang/Ujiie B/B/A
AMEP-077

BBVN-FIVE-S2-SC- 14/05/31 14/06/13 14/06/10 HVAC_Wafer Check Valve, Butterfly Valve size up to DN200 lever, Technical Detail Description, Quang/Randy/Ujiie B/A+B+C
AMEP-078 Butterfly Valve Gear Type, Y Strainer for DN65 and Above (Flange end Catalogue
type), Y strainer for CDA chilled water supply piping, Thermometer,
Pressure Guage, Ball valve for Pressure gauge and temperature gauge,
Flow switch for chiller return pipe

BBVN-FIVE-S2-SC- 14/06/25 14/06/30 14/07/04 HVAC_Butterfly Valve Gear Type, Butterfly valve Lener Type, Lug Technical Detail Description Quang/Randy/Ujiie B/A+B+C
AMEP-078 (A) Type, Wafer Cheeck valve, Y Strainer, Ball balce for Y-Strainer Drain

BBVN-FIVE-S2-SC- 14/05/30 14/06/11 14/06/02 HVAC_VRV Refrigerant Piping (REFNET PIPING) Technical Detail Description, Quang/Ujiie A
AMEP-079 Catalogue

BBVN-FIVE-S2-SC- 14/05/31 14/06/13 14/06/27 Production Exhaust, Production exhaust filter and Housing Catalogue Quang/Ujiie B/B/A
AMEP-0080

BBVN-FIVE-S2-SC- 14/06/03 14/06/09 14/06/10 Drainage and Water Supply Valve (PPR Shut Off Valve, Check valve Catalogue, Tabulation Quang/Ujiie C
AMEP-0081 Flange Type, Check Valve Swing Brass Type, Ball Valve Flange Type,
Ball Valve Screw Type, Gate Valve Flange Type)
BBVN-FIVE-S2-SC- 14/06/16 14/06/20 14/06/20 Water Supply System_Gate Valve PPR Technical Detail Description Quang/Ujiie B/A+C
AMEP-0081 (A)
BBVN-FIVE-S2-SC- 14/06/16 14/06/20 14/06/20 Drainage System_Ball Valve (SUS), Check Valve (SUS) Technical Detail Description Quang/Ujiie B/B
AMEP-0081 (B)
BBVN-FIVE-S2-SC- 14/07/05 14/07/11 14/07/08 Gate Valve (Flange Type)_(For Water Supply Pipe in Pump Room), Technical Detail Description Quang/Ujiie B/A+C
AMEP-0081 ( C ) Gate Valve PPR, Gate Valve
BBVN-FIVE-S2-SC- 14/08/07 14/08/13 14/08/18 Brass Gate Valve for Hot Water Supply_Rev.1 Revised based on Catalogue Quang/Ujiie B/A
AMEP-0081/R1 ( C ) comments in AMEP-81 (C ) dated 8-July-2014) Refer to RFC-85

BBVN-FIVE-S2-SC- 14/08/01 14/08/07 14/08/26 PVC Ball Check Valve (Manufacturer: FIP)_Model: SXENV Technical Detail Description Quang/Ujiie/Khoa B
AMEP-0081 (D) (Superseded AMEP-81 (B) refer to RFC-71 subjected "Submersible
Pump Pit 1 & 2" dated 17-July -2014 Rejected)
BBVN-FIVE-S2-SC- 14/08/01 14/08/07 14/08/26 PVC Ball Check Valve (Manufacturer: FIP)_Model: VEENV Technical Detail Description Quang/Ujiie/Khoa B
AMEP-0081 (E) (Superseded AMEP-81 (B) refer to RFC-71 subjected "Submersible
Pump Pit 1 & 2" dated 17-July -2014 Rejected)
BBVN-FIVE-S2-SC- 14/08/01 14/08/07 14/08/26 PVC Ball Check Valve (Manufacturer: FIP)_Model: VXENV Technical Detail Description Quang/Ujiie/Khoa B
AMEP-0081 (F) (Superseded AMEP-81 (B) refer to RFC-71 subjected "Submersible
Pump Pit 1 & 2" dated 17-July -2014 Rejected)
BBVN-FIVE-S2-SC- 14/06/05 14/06/09 14/06/10 Lighting Switch (1way, 2way, 4way) & Plate (1gang-1divice, Tabulation, Catalogue Quang/Ujiie B
AMEP-0082 1gang-2divices, 1gang-3divices)
BBVN-FIVE-S2-SC- 14/08/23 14/08/27 14/08/28 Lighting Switch 1way & 2way (Superseded the lighting swich 1 way & Catalog, Manufacturers Letter B
AMEP-0082(A) 2 way in approved AMEP_082 dated 10 June 2014)

BBVN-FIVE-S2-SC- 14/06/05 14/06/09 14/06/10 Socket Outlet_Single Socket, Double Socket, Divice Plate, Tabulation, Catalogue Quang/Ujiie B/A+B+C
AMEP-0083 Weatherproof Socket, Industrial Socket & Plug, 1gang 16A 1Pole/N/E
Switch Socket Outlet, Floor Box 2x16A Double Socket Outlet w/ 2
Data, Isolators for VRV, Camera, Heater
BBVN-FIVE-S2-SC- 14/07/17 14/07/22 14/07/21 Weatherproof Socket - MK Masterseal Compact 86893 GRY IP66, 15A Technical Detail Description Quang/Ujiie/Diem B
AMEP-0083 (A) 3Pin (Superseded the weatherproof socket in AMEP-83 dated 10-June-
2014)
BBVN-FIVE-S2-SC- 14/08/23 14/08/27 14/08/28 Socket Outlet_Single Outlet, Double Socket & Plates (Superseded the Catalog, Manufacturers Letter Quang/Ujiie B
AMEP-0083 (B) single socket, double docket & plate in approved AMEP_083 dated 10
June 2014)
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 14/11/03 Raised Floor Box w/ 2x16A Double Socket Outlet & 2 data Revised Sample Material Picture, MK Quang/Ujiie B
AMEP-0083 (C ) based on comments in AMEP-83 dated 10-June-2014 Catalogue

BBVN-FIVE-S2-SC- 14/06/06 14/06/09 14/06/27 Fire fighting System_Vane Type Waterflow Alarm Switch with Retard Catalogue Quang/Ujiie A/B/A
AMEP-0084

BBVN-FIVE-S2-SC- 14/06/06 14/06/09 14/06/27 Fire fighting System_Pressure relief Valve Catalogue Quang/Ujiie A/B/A
AMEP-0085

BBVN-FIVE-S2-SC- 14/06/06 14/06/09 14/06/10 Fire fighting System_Denso Tape for Underground Catalogue Quang/Ujiie C
AMEP-0086
BBVN-FIVE-S2-SC- 14/06/14 14/06/18 14/06/20 Fire fighting System_Denso Tape for Underground_Rev.1 Revised Catalogue Quang/Ujiie A
AMEP-0086/R1 based on comments in AMEP-0086 dated 10-June-2014

BBVN-FIVE-S2-SC- 14/06/06 14/06/10 14/06/18 Fire Stop Mortar Technical Detail Description Quang/Ujiie A
AMEP-0087

BBVN-FIVE-S2-SC- 14/06/06 14/06/10 14/06/18 Fire Stop Sealant Technical Detail Description Quang/Ujiie A
AMEP-0088

BBVN-FIVE-S2-SC- 14/06/07 14/06/16 14/06/27 Fire Fighting System_Flexible Hose for Sprinkler Head (K5.6 & K14.0) Tabulation, Catalogue Quang/Ujiie B/B/A
AMEP-0089

BBVN-FIVE-S2-SC- 14/06/12 14/06/16 14/06/12 Safety Valve Catalogue Quang/Ujiie/Khoa C


AMEP-0090

BBVN-FIVE-S2-SC- 14/06/12 14/06/16 14/06/12 Welding Rod Catalogue Quang/Ujiie/Trung C


AMEP-0091
BBVN-FIVE-S2-SC- 14/06/18 14/06/24 14/06/23 Welding Rod_Rev.1 Revised based on comments in AMEP-91 dated Product Data Sheet Quang/Ujiie/Trung C
AMEP-0091/R1 12-June-2014
BBVN-FIVE-S2-SC- 14/06/26 14/06/30 14/07/04 Welding Rod_Rev.2 Revised based on comments in AMEP-91/R1 dated Catalogue Quang/Ujiie/Trung B
AMEP-0091/R2 23-June-2014

BBVN-FIVE-S2-SC- 14/06/12 14/06/16 14/06/12 Sub Welding Rod Catalogue Quang/Ujiie/Trung C


AMEP-0092
BBVN-FIVE-S2-SC- 14/06/18 14/06/24 14/06/25 SUS Welding Rod_Rev.1 Revised based on comments in AMEP-0092 Product Data Sheet Quang/Ujiie / ung C
AMEP-0092/R1 dated 12-June-2014
BBVN-FIVE-S2-SC- 14/06/26 14/06/30 14/07/04 GAS Metal Arc Welding (KIM TIN)_Rev.2 Revised based on Catalogue, Techinical Detail Quang/Ujiie / ung C
AMEP-0092/R2 comments in AMEP-92/R1 dated 25-June-2014 Description
BBVN-FIVE-S2-SC- 14/07/08 GAS Metal Arc Welding (KIM TIN)_Rev.3 Revised based on A
AMEP-0092/R3 comments in AMEP-92/R2 dated 4-July-2014

BBVN-FIVE-S2-SC- 14/06/12 14/06/16 14/06/12 Hot Water Pipe Insulation Catalogue Quang/Ujiie/Khoa B
AMEP-0093

BBVN-FIVE-S2-SC- 14/06/12 14/06/16 14/06/12 Copper Pipe for Hot Water Catalogue Quang/Ujiie/Khoa B/A
AMEP-0094

BBVN-FIVE-S2-SC- 14/06/12 14/06/16 14/06/12 Copper Pipe Fittings for Hot Water Piping Catalogue Quang/Ujiie/Khoa A
AMEP-0095

BBVN-FIVE-S2-SC- 14/06/16 14/06/20 14/06/20 Pipe Fittings_Flange Slip on Type (For Valve Flange Technical Detail Description, Quang/ Ujiie A/B
AMEP-0096 Connection)_Refer to comments in AMEP-0078 dated 10-June-2014 Catalogue
Approval for Mechanical, Electrical Plumbing 8
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply

BBVN-FIVE-S2-SC- 14/06/17 14/06/21 14/06/20 Copper Pipe for AHU connection (Use for AHU coil connection) & Technical Detail Description, Quang/ Ujiie A
AMEP-0097 Copper Pipe Fittings for AHU connection (Use for AHU coil Catalogue
connection)

BBVN-FIVE-S2-SC- 14/06/17 14/06/21 14/06/20 Exposed Chiller Pipe Insulation Cladding Technical detail description, Quang/ Ujiie C
AMEP-0098 Catalogue
BBVN-FIVE-S2-SC- 14/06/25 14/07/01 14/06/27 Exposed Chiller Pipe Insulation Cladding_Rev.1 Revised based on Technical detail description A
AMEP-0098/R1 comments in AMEP-98 dated 20-June-2014

BBVN-FIVE-S2-SC- 14/06/18 14/06/25 14/06/23 Anchor Bolt (SANKO) for Pipe Support on Trench Pit and Underground Catalogue Quang./Ujiie C
AMEP-0099 Toilet

BBVN-FIVE-S2-SC- 14/06/18 14/06/24 14/06/23 Support Materials (Tisco) Catalogue Quang/Ujiie B


AMEP-100

BBVN-FIVE-S2-SC- 14/06/18 14/06/25 14/06/23 Treaded Rod, Bolt, Nuts, Washer, Pipe Clamp (Tanco/Zhapu) Certificate/Test of Quality and Quang/Ujiie C
AMEP-101 Quantity, Product Data Sheet

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/11 Treaded Rod, Bolt, Nuts, Washer, Pipe Clamp (Tanco/Zhapu)_Rev.1 Technical Detail Description Quang/Ujiie B/A+B+C
AMEP-101/R1 Revised based on comments in AMEP-101 dated 23-June-2014

BBVN-FIVE-S2-SC- 14/08/06 14/08/13 14/08/18 Treaded Rod for Indoor Support - TANCO Class 4.8 DIN975 Submitted Catalogue Quang/Ujiie B/A+B+C
AMEP-101 (A) based on comments in AMEP-101/R1 dated 11-July-2014

BBVN-FIVE-S2-SC- 14/06/18 14/06/25 14/06/23 Buffer Tank (NAM AN) 1A3size drawing Quang/Ujiie B
AMEP-102

BBVN-FIVE-S2-SC- 14/06/21 14/06/25 14/06/25 Galvanized Anchor Bolt (HILTI) Technical Detail Description Quang/Ujiie B
AMEP-103

BBVN-FIVE-S2-SC- 14/06/21 14/06/25 14/06/25 U Bolt (For Support above ground) Technical Detail Description Quang/Ujiie B
AMEP-104

BBVN-FIVE-S2-SC- 14/06/21 14/06/25 14/06/25 SUS Anchor Bolt (HILTI) Technical Detail Description Quang/Ujiie B
AMEP-105

BBVN-FIVE-S2-SC- 14/06/21 14/06/25 14/06/25 Spring Isolator For 7 items, Technical Detail Quang/Ujiie B/A+C
AMEP-106 Description
BBVN-FIVE-S2-SC- 14/07/21 SPRING ISOLATOR_Rev.1 C
AMEP-106/R1
BBVN-FIVE-S2-SC- 14/08/04 14/08/09 14/08/25 Spring Isolator (Floor Mounted)_Manufacturer: MASON_Model" Technical Detail Description Quang/Ujiie B/A+C
AMEP-106/R2 SLFH_Rev.2 Revised based on comments in AMEP-106/R1 dated 21- (for 8 items)
July-2014
BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/18 Spring Isolator (Floor Mounted) for Primary & Secondary Pump - Catalogue Quang/Ujiie C
AMEP-106 (A) MASON SLFH1350 & SLFH1750 (Revised based on comment in
AMEP-106/R2 dated 25-August-2014)
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 14/11/08 Spring Isolator (Floor Mounted) for Primary & Secondary Pump - Catalogue Quang/Ujiie C
AMEP-106 (A)/R1 MASON SLFH1350 & SLFH1750 (Revised based on comment in
AMEP-106(A) dated 18-Oct-2014)
BBVN-FIVE-S2-SC- 14/11/06 14/11/13 14/11/08 Spring Isolator (Floor Mounted) for Primary & Secondary Pump - Catalogue, Shop Drawing Quang/Ujiie B
AMEP-106 (A)/R2 MASON SLFH1350 & SLFH1750_Rev.2 (Revised based on comment
in AMEP-106(A) dated 18-Oct-2014)

BBVN-FIVE-S2-SC- 14/06/23 14/06/28 14/06/26 VAV for Circulation Corridor Communication Controller - DVC-V304 Catalogue Quang/Ujiie B
AMEP-107

BBVN-FIVE-S2-SC- 14/06/25 14/07/01 14/06/27 Galvanized Repair Compound Technical Detail Description Quang/Ujiie B/A
AMEP-108

BBVN-FIVE-S2-SC- 14/06/25 14/07/01 14/06/27 Fire Fighting Paint (Vinilex Primer) Technical Detail Description Quang/Ujiie C
AMEP-109
BBVN-FIVE-S2-SC- 14/07/09 14/07/14 Fire Fighting Paint (Vinilex Primer)_Nippon Paint (Model: VINILEX Technical Detail Description Quang/Ujiie
AMEP-109/R1 120 ACTIVE Primier)_rev.1 Revised based on comments in AMEP-109
dated 27-June-2014

BBVN-FIVE-S2-SC- 14/06/25 14/07/01 14/06/27 Fire Fighting Paint (Primer for Welded Location) Technical Detail Description Quang/Ujiie C
AMEP-110
BBVN-FIVE-S2-SC- 14/07/05 14/07/11 14/07/08 Fire Fighting Paint (Primer for Welded Location)_Rev.1 (Revised based Technical Detail Description Quang/Ujiie C
AMEP-110/R1 on comments in AMEP_110 dated 27-June-2014

BBVN-FIVE-S2-SC- 14/06/25 14/07/01 14/06/27 Fire Fighting Paint (Sprinkler, Hydrant and Hose Reel top Coat paint) Technical Detail Description Quang/Ujiie C
AMEP-111
BBVN-FIVE-S2-SC- 14/07/09 14/07/14 Fire Fighting Paint (Sprinkler, Hydrant and Hose Reel top Coat Technical Detail Description Quang/Ujiie
AMEP-111/R1 paint)_Nippon Paint (Model: Bilac B9004 Vermillion)_Rev.1 Revised
based on comments in AMEP-111 dated 27-June-2014

BBVN-FIVE-S2-SC- 14/06/26 14/07/03 14/07/29 Access Control System_Passive Infrared Sensor Tabulation, Catalogue Quang/Ujiie B
AMEP-112

BBVN-FIVE-S2-SC- 14/06/26 14/07/02 14/07/09 DDC for Compressor Chiller Water Valve, Motorized Valve for Tabulation, Catalogue Quang/ Ujiie B
AMEP-113 compressor chilled water pipe, temperature sensor for compressor
chilled water pipe, Solenoid valve for compressor

BBVN-FIVE-S2-SC- 14/08/27 14/09/01 14/09/04 Solenoid valve for compressor (ASCA) for Compressor Chilled Water Technical Description and Quang/Ujiie/Khoa B
AMEP-113 (A) Pipe_Model: SCXE238A005-24017 (Supperseded Solenoid valve for Catalogue
compressor in AMEP-113 dated 26-June-2014) Based on comments in
AMEP-113

BBVN-FIVE-S2-SC- 14/07/01 14/07/05 14/07/07 Process Chilled Water Valve Tabulation, Catalogue Quang/Ujiie B/A+B+C
AMEP-114
BBVN-FIVE-S2-SC- 14/07/15 14/07/21 14/07/25 Process Chilled Water Valve_Rev.1 Revised based on comments in Tabulation, Technical detailed Quang/Ujiie/Trung B/A
AMEP-114 (A) AMEP-114 dated 7-July-2014 description
BBVN-FIVE-S2-SC- 14/08/28 14/08/30 14/09/06 Process Chilled Water Valve_Rev.1 (Additional Document) Gate Valve (TOYO)_DN80 Quang/Ujiie/Trung C
AMEP-114 (A) (FINAL) for water supply Tie-in works;
Ball valve (TOYO) for
Compressor room Tie-in

BBVN-FIVE-S2-SC- 14/07/04 14/07/09 14/07/08 Aluminum Insulation Pin (Al Pin) Technical Detail Description Quang/Ujiie A
AMEP-115

BBVN-FIVE-S2-SC- 14/07/05 14/07/11 14/07/08 Gavanized Black Carbon steel Pipe Medium Grade Schedule 40 (Use Technical Detail Description Quang/Ujiie A
AMEP-116 for Water Supply on Pump Room)

BBVN-FIVE-S2-SC- 14/07/05 14/07/11 14/07/08 Gavanized Black Carbon steel Pipe BS-M (Use for Water Supply DN Technical Detail Description Quang/Ujiie B
AMEP-117 100mm and Below)

BBVN-FIVE-S2-SC- 14/07/05 14/07/11 14/07/08 Gavanized Black Carbon steel Pipe Fittings (Use for Water Supply in Technical Detail Description Quang/Ujiie B
AMEP-118 Pump Room)

BBVN-FIVE-S2-SC- 14/07/07 14/07/12 14/07/10 Auto Drain (for Compressor Auto Drain in Compressor Room) Technical Detail Description Quang/Ujiie A
AMEP-119 (ADCA)_Model FA20

BBVN-FIVE-S2-SC- 14/07/07 14/07/12 14/07/10 Y Strainer (for compressor Chilled Water Supply Piping) Technical Detail Description Quang/Ujiie A
AMEP-120 (ARITA)_Model Brass-Y-Strainer-Screwed End BSPT

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/11 HVAC System_ Aluminum Insulation Tape (Bond Tape) Technical Detail Description Quang/Ujiie B
AMEP-121

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/21 Duct Silencer for AO Fan Duct (Tan Hung) Technical Detail Description Quang/Ujiie C
AMEP-122

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/21 Duct Silencer for AHU Supply Duct (Tan Hung) Technical Detail Description Quang/Ujiie C
AMEP-123 W4200xH2000mmxL3100mm

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/21 Duct Silencer for AHU Supply Duct (Tan Hung) Technical Detail Description Quang/Ujiie C
AMEP-124 W4300xH2000mmxL2800mm

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/11 Fire Fighting Paint Technical Detail Description Quang/Ujiie B/A+B+C
AMEP-125 Fire Fighting Paint (Vinilex Primer)_Nippon Paint (Model: VINILEX
120 ACTIVE Primier)_rev.1 Revised based on comments in AMEP-109
dated 27-June-2014
Fire Fighting Paint (Primer for Welded Location)_Rev.1 (Revised based
on comments in AMEP_110 dated 27-June-2014)
Fire Fighting Paint (Sprinkler, Hydrant and Hose Reel top Coat
paint)_Nippon Paint (Model: Bilac B9004 Vermillion)_Rev.1 Revised
based on comments in AMEP-111 dated 27-June-2014

BBVN-FIVE-S2-SC- 14/07/09 14/07/14 14/07/11 HVAC_Aluminum Insulation Pin Adhesive (TITEBOND)_Model: Technical Detail Description Quang/Ujiie A
AMEP-126 Titebond Heavy Duty Construction Adhesive

BBVN-FIVE-S2-SC- 14/07/14 14/07/19 14/07/18 Ybsguekded 2-Core AWG18 Cable Technical Detail Description Quang/Randy B/A
AMEP-127
Approval for Mechanical, Electrical Plumbing 9
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply

BBVN-FIVE-S2-SC- 14/07/14 14/07/19 14/07/18 Cable Terminal for LV Cable (Big type & Small Type) Tabulation, Catalogue Quang/Randy B/A
AMEP-128

BBVN-FIVE-S2-SC- 14/07/15 14/07/21 14/07/17 Floor Clean Out (1st Floor Toilet)_Model: COB Technical Detail Description Quang/Ujiie C
AMEP-129
BBVN-FIVE-S2-SC- 14/08/01 14/08/06 14/08/12 Floor Clean Out (1st Floor Toilet)_Model: COB Technical Detail Description Quang/Ujiie/Khoa C
AMEP-129/R1 (Ground Floor Toilet)_Model: COA_Rev.1 (Revised based on
comments in AMEP_129 dated 17-July-2014)
BBVN-FIVE-S2-SC- 14/10/27 14/11/01 14/11/04 Cleanout for First Floor Office - K Product CO 810W Type: CW-43 and Catalogue Quang/Ujiie/Khoa B
AMEP-129/R2 CW-25_rev.2 Revised based on comment in AMEP-129/R1 dated 12-
August-2014

BBVN-FIVE-S2-SC- 14/07/15 14/07/21 14/07/17 Floor Clean Out (Ground Floor)_Model: COA Technical Detail Description Quang/Ujiie C
AMEP-130

BBVN-FIVE-S2-SC- 14/07/18 14/07/23 14/07/21 Bitumen For Pipe Protection (Shell Bitumen)_Model: Shell Flintkote 3 Technical Detail Desciption Quang/Ujiie/Trung C
AMEP-131
BBVN-FIVE-S2-SC- 14/08/01 14/08/08 14/08/15 Bitumen For Pipe Protection (Shell Bitumen)_Model: Shell Flintkote Catalogue Quang/Ujiie/Trung C
AMEP-131/R1 3_Rev.1 Revised based on comments in AMEP-131 dated 21-July-2014

BBVN-FIVE-S2-SC- 14/08/01 14/08/08 14/08/15 Bitumen For Pipe Protection (Shell Bitumen)_Model: Shell Flintkote Catalogue Quang/Ujiie/Trung C
AMEP-131 (ADD.01) PF-4_ADD (Additional Document based on EMEP-131 dated 21--July-
2014

BBVN-FIVE-S2-SC- 14/07/18 14/07/23 14/07/21 Copper Pipe Welding Rod (Brazing)_Harris [Model: AWS A5.8, BCuP Technical Detail Desciption Quang/Ujiie/Trung C
AMEP-132 2]
BBVN-FIVE-S2-SC- 14/07/25 Copper Pipe Welding Rod (Brazing)_Harris [Model: AWS A5.8, BCuP B/A
AMEP-132/R1 2]_Rev.1

BBVN-FIVE-S2-SC- 14/07/18 14/07/23 14/07/21 GTAW Welding Rod for Pipe 50mm and Below (Huyndai)_Model: ST- Technical Detail Desciption Quang/Ujiie/Trung C
AMEP-133 50G
BBVN-FIVE-S2-SC- 14/07/25 GTAW Welding Rod for Pipe 50mm and Below (Huyndai)_Model: ST- B
AMEP-133/R1 50G_Rev.1

BBVN-FIVE-S2-SC- 14/07/21 14/07/25 14/07/24 SMAW Welding Rod for Pipe (Chosun Welding Co.,Ltd)_Model: LC- Technical Detail Desciption Quang/Ujiie/Trung B
AMEP-134 300

BBVN-FIVE-S2-SC- 14/07/22 14/04/24 14/07/28 Master Tie-in List, Method Statement List, Material and Tool List, 5A3size pages Master Tie-in Quang/Ujiie C Superseed (Replaced
AMEP-135 Organization Chart for Stage 1 List, Method Statement List of by APD-69)
Tie-in 1A3size page, 8A3size
pages Material and Tool List +
26A3size drawings, 2A3size
pages Organization Chart for
Stage 1 + 2A3pages contact
details

BBVN-FIVE-S2-SC- 14/08/08 14/08/13 Master Tie-in List, Method Statement List, Material and Tool List, Tie-in Comments List Quang/Ujiie
AMEP-135/R1 Organization Chart for Stage 1_Rev.1 Revised based on comments in (2A3sizepages), Master Tie-in
AMEP_135 dated 28-Jul-2014 List for Stage 1 (9S3size pages
+ 1 A0size colored page),
Method Statement List of Tie-
in (1A3size page),
Organizational Chart,
Manpower list (2A3size pages)

BBVN-FIVE-S2-SC- 14/07/25 14/07/31 14/08/04 Bolt, Nuts, Washer for Flange DIN 931, Class 8.8 Technical Detail Desciption Quang/Ujiie C
AMEP-136
BBVN-FIVE-S2-SC- 14/08/06 14/08/13 14/08/18 Bolt, Nuts, Washer for Flange -TANCO DIN931 Class 8.8 _Rev.1 catalogue Quang B
AMEP-136/R1 Revised based on comments in AMEP-136 dated 4-Aug-2014

BBVN-FIVE-S2-SC- 14/07/30 14/08/06 14/08/18 Hose Rack Assembly (Manufacturer: Croker) Technical Detail Desciption Quang/Ujiie B
AMEP-137
BBVN-FIVE-S2-SC- 14/09/03 14/09/05 14/10/20 Hose Rack Assembly (Manufacturer: Croker)_Rev.1 Revised based on Manufacturer Letter, Quang/Ujiie C
AMEP-137/R1 comments in AMEP-137 dated 18-August-2014 Catalogue
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 Hose Rack Assembly (Manufacturer: Croker)_Rev.2 Revised based on Manufacturer Letter, Quang/Ujiie
AMEP-137/R2 comments in AMEP-137/R1 dated 20-October-2014 Catalogue

BBVN-FIVE-S2-SC- 14/07/30 14/08/06 PVC Ball Valve (Manufacturer: FIP)_Model: VXEAV Technical Detail Desciption Quang/Ujiie
AMEP-138

BBVN-FIVE-S2-SC- 14/08/06 14/08/13 14/08/11 Fire Resistance Cable for Fire Alarm Stage 1 Tie-in Connection - Catalogue Quang/ujiie B
AMEP-139 Wilson FR-100

BBVN-FIVE-S2-SC- 14/08/09 14/08/14 14/08/29 Flexible Canvas for Mechanical Equipment_Prodetech Tabulation, Catalogue Quang/ujiie B
AMEP-140
BBVN-FIVE-S2-SC- 14/09/22 Flexible Canvas for Mechanical Equipment_Prodetech _Rev.1 Revised B
AMEP-140/R1 based on comments in AMEP-140 dated 29-August-2014

BBVN-FIVE-S2-SC- 14/10/16 flexible Canvas for Mechanical Equipment_Prodetech _Rev.2 Revised B


AMEP-140/R2 based on comments in AMEP-140/R1 dated 22-September-2014

BBVN-FIVE-S2-SC- 14/08/14 14/08/19 14/10/06 Sikagrout GP (Sika)_Model: Sikagrout GP& SikaFlex-Construction Technical Detail Description Quang/Ujiie B
AMEP-141 (AP)_Model: SikaFlex-Construction (AP) for Toilet Sleeve Sealing

BBVN-FIVE-S2-SC- 14/08/18 14/08/23 14/08/22 Access Control Panel Enclosure W560xH700xD250 & Drawing, Picture of Existing Quang/Ujiie C
AMEP-142 W540xH560xD250 Panel for Panel Color

BBVN-FIVE-S2-SC- 14/08/25 14/08/29 14/08/28 Access Control Panel Enclosure W560xH700xD250 & Drawing Quang/Ujiie B
AMEP-142/R1 W540xH560xD250_Rev.1 Revised based on comments in AMEP-142
dated 22-August-2014

BBVN-FIVE-S2-SC- 14/08/20 14/08/25 MS-24.1: HV Connection for Transformer TX-2 Quang/Ujiie/Diem


AMEP-143

BBVN-FIVE-S2-SC- 14/08/21 14/08/25 14/08/29 Copper Busbar for Modification of LV Panel & Earth Copper Bar- Catalogue Quang/Ujiie B/A
AMEP-144 Oriental Copper

BBVN-FIVE-S2-SC- 14/08/21 14/08/25 14/08/28 Nickel Coated Brass Cable Gland & Nylon Cable Gland (w/Locknut) Tabulation, 1A4size photo, Quang/Ujiie B
AMEP-145 data sheet

BBVN-FIVE-S2-SC- 14/08/21 14/08/25 14/08/28 PV Control Panel for Pre-Action Valve & Schematic Diagram for Drawings Quang/Ujiie/Randy C
AMEP-146 Operation (Additional Document for AMEP-37A Pre-Action Valve for
Fire fighting system double interlock)

BBVN-FIVE-S2-SC- 14/08/23 14/08/27 Hermeseal S-2 for fire fighitng pipe to fittings thear connection (pipe Catalog, Method Application,
AMEP-147 size DN25, DN32, DN40, DN50) Shop drawing Location

BBVN-FIVE-S2-SC- 14/08/28 14/09/02 Sprinkler Pipe Support and Process Exhaust Duct DN250 and Below Sample
AMEP-148

BBVN-FIVE-S2-SC- 14/08/30 14/09/05 14/09/06 Drop in Anchor (SANKO)_Model: CT-1040; CT1250 Use for Concrete Product Data Sheet Quang/Ujiie C
AMEP-149 Slab Anchoring

BBVN-FIVE-S2-SC- 14/08/30 14/09/01 14/09/04 Duct Silencer for AHU Supply Duct (W4200xH2000xL3540 & Drawing & Photos Quang/Ujiie C
AMEP-150 W4300xH2000xL3540) & Duct Silencer for OA Fan Duct
(W800xH600xL1200)_TAN HUNG
BBVN-FIVE-S2-SC- 14/09/30 14/10/07 14/10/08 Duct Silencer for AHU Supply Duct (W4200xH2000xL3540 & Technical Data Quang/Ujiie C
AMEP-150/R1 W4300xH2000xL3540) & Duct Silencer for OA Fan Duct
(W800xH600xL1200)_TAN HUNG_Rev.1
Revised based on comments in AMEP_150 dated 04-September-2014

BBVN-FIVE-S2-SC- 14/10/10 14/10/16 14/10/13 Duct Silencer for AHU 3 & 4 Supply Duct & OA Duct _ Rev.2 Revised Catalogue, Noise Analysis Quang/Ujiie B
AMEP-150/R2 based on comments in AMEP-150/R1 dated 8-Oct-2014 calculation, Drawing

BBVN-FIVE-S2-SC- 14/09/01 14/09/04 SUS Ball valve Flange type (for process chilled water piping Tie-in 6 Quang/Ujiie
AMEP-151 worker, Insolation to Stage 2)

BBVN-FIVE-S2-SC- 14/09/02 14/09/05 14/09/15 HILTI Plastic Anchor for Brick- HRD 10x70mm (Use for anchoring on Technical Data Quang/Ujiie B
AMEP-152 Brick only)

BBVN-FIVE-S2-SC- 14/09/03 14/09/05 14/09/17 Fire Hydrant Hose & Fire Hydrant Nozzle (Supplier: PCCC Hanoi) Manufacturer Letter, Quang/Ujiie C
AMEP-153 Catalogue

BBVN-FIVE-S2-SC- 14/09/05 14/09/10 14/09/18 Chiller Water and PCW Pipe Insulation Support (AEROFLEX) for Technical detail description Quang/Ujiie C
AMEP-154 supply and return_Model: AEROFIT (Product Data Sheet)

BBVN-FIVE-S2-SC- 14/09/09 14/09/11 14/09/22 Pressure Reducing Valve for Fire Hydrant System - Malgorani Catalogue Quang/Ujiie/Trung C
AMEP-155 EUROBRASS 143
BBVN-FIVE-S2-SC- 14/10/13 14/10/18 14/10/20 Pressure Reducing Valve for Fire Hydrant System_Rev.1 GOETZE Catalogue, Technical Data Quang/Ujiie/Trung B/A
AMEP-155/R1 Series 681 (revised based on comment in AMEP-155 dated 22-
September-2014)

BBVN-FIVE-S2-SC- 14/09/10 14/09/17 Gate Valve DN80 - TOYO 420E (For Water Supply Tie-in Works only) Teechnical Data, Drawing for Quang/Ujiie
AMEP-156 (Superseded the gate valve DN80 in approved ANEP-81C dated 8-July- Reference
2014) Tie-in No.20

BBVN-FIVE-S2-SC- 14/09/10 14/09/17 14/09/27 Ball Valve DN25 - TOYO 5026 (for Compressor Tie-in Works only) Teechnical Data, Drawing for Quang/Ujiie C
AMEP-157 Tie-in No.8 Reference

BBVN-FIVE-S2-SC- 14/09/11 14/09/13 14/09/18 Denso Primer D for Underground Firefighting Technical Data Sheet Quang/Ujiie B
AMEP-158
Approval for Mechanical, Electrical Plumbing 10
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
BBVN-FIVE-S2-SC- 14/09/11 14/09/13 14/09/18 Densoclad 40 HT tape for Underground Firefighting Protection Cover Technical Data Sheet Quang/Ujiie B
AMEP-159

BBVN-FIVE-S2-SC- 14/09/12 14/09/17 14/09/18 Floor Drain for Clean Room Area - FUKUNISHI T-5SBGS-50 Technical Data Sheet Quang/Ujiie B
AMEP-160

BBVN-FIVE-S2-SC- 14/09/18 14/09/23 14/09/22 Flexible Canvas for Mechanical Equipment - YEEDAH (Superseded the Tabulation, Catalogue, Test Quang/Ujiie B (refer to
AMEP-161 approved Flexible canvas in AMEP-140 dated 29-August-2014) report 140/R1)

BBVN-FIVE-S2-SC- 14/09/19 14/09/26 14/09/22 Female Anchor for Suspended Slab, Office and Clean Room Area - Catalogue Quang/Ujiie B
AMEP-162 HILTI HKV

BBVN-FIVE-S2-SC- 14/09/22 14/09/25 14/09/27 Quick Response Pendent Sprinkler for Component Production - Technical data Quang/Ujiie B
AMEP-163 VIKING VK352 L=8.0 (Additional material for approval in approved
AMEP-25/R1 dated 3-July-2014)

BBVN-FIVE-S2-SC- 14/09/22 14/09/25 14/09/27 Flexible Hose for Sprinkler Head - TRONFLEX TCR25BR for Technical data sheet Quang/Ujiie B
AMEP-164 Component Production Sprinkler Head K=8.0 (Superseded the approved
flexible hose for component production sprinkler head K=14 3/4''
commection in AMEP-89 dated 27-June-2014)

BBVN-FIVE-S2-SC- 14/09/26 14/10/03 14/10/01 Electromagnetic Lock_ ALGATECH UL275- SMC Catalogue Quang/ Ujiie C
AMEP-165
BBVN-FIVE-S2-SC- 14/10/18 14/10/22 14/10/24 Electromagnetic Lock_ ALGATECH UL275- SMC_Rev.1 Catalogue Quang/Ujiie B/A
AMEP-165/R1 Revised based on comments in AMEP_165 dated 01-Oct-2014

BBVN-FIVE-S2-SC- 14/09/26 14/10/03 14/10/06 Isolators Technical detail description/ Quang/Ujiie B


AMEP-166 Catalogue
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 Isolators- Schneider Clipdsal WHT35: 3P 35A for RF-P2-01, 02 & Catalog Quang/Ujiie
AMEP-166/R1 Legrand 0 226 27: 4P 100A for SCHWP-01, 02, 03 (Revised and
superseded the approval isolator for SCWP in AMEP-166 dated 06-Oct-
2014)

BBVN-FIVE-S2-SC- 14/10/31 14/11/07 Isolators for VRV Outdoor Unit- Schneider/ Clipsal WHT35 3P Catalogue Quang/Ujiie
AMEP-166(A) 35A&WHT20 3P 20A

BBVN-FIVE-S2-SC- 14/09/29 14/10/04 14/10/06 OS&Y Gate Valve for Fire Fighting System (Double Interlock Pre- Catalog Quang/Ujiie C
AMEP-167 Action)- FIREKING OF200F-400F (Superseded the approved butterfly
valve DN100 in AMEP_0035/R1 based on RFC_0024 & RFI_159)

BBVN-FIVE-S2-SC- 14/10/09 OS&Y Gate Valve for Fire Fighting System (Double Interlock Pre- C
AMEP-167/R1 Action)-
BBVN-FIVE-S2-SC- 14/10/28 OS&Y Gate Valve for Fire Fighting System (Double Interlock Pre- B
AMEP-167/R2 Action)_Rev.2

BBVN-FIVE-S2-SC- 14/09/30 14/10/07 14/10/08 Fire Stop Foam- HILTI CP660 Technical Data Quang/Ujiie C
AMEP-168
BBVN-FIVE-S2-SC- 14/10/20 14/10/27 14/10/24 Fire Stop Foam- HILTI CP660_Rev.1 Revised based on comments in Catalogue, Test report Quang/Ujiie B
AMEP-168/R1 AMEP-168 dated 8-October-2014

BBVN-FIVE-S2-SC- 14/09/30 14/10/07 14/10/08 Fire Stop Pipe Wrap- HILTI CP648-E Technical Data Quang/Ujiie B
AMEP-169

BBVN-FIVE-S2-SC- 14/09/30 14/10/07 14/10/08 Fire Stop Collar- HILTI CP643N Technical Data Quang/Ujiie B
AMEP-170

BBVN-FIVE-S2-SC- 14/10/02 14/10/04 AHU Sealant - SIKAFLEX 221 Technical Data Sheet Quang/Ujiie
AMEP-171

BBVN-FIVE-S2-SC- 14/10/06 14/10/13 14/10/16 Pipe and Duct Labelling (Brady) for chilled water and process chilled Quang/Ujiie B
AMEP-172 water pipe (Supply and Return)_Model: B6606 digitally printed plastic

BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/09 Highbay Lighting Emergency Lamp for Warehouse (OSRAM Halostar Catalogue; Technical Data Quang/Ujiie C
AMEP-173 50W 12V GY6.35); Lamp for Downlight in Office & Canopy (OSRAM sheet
Deluxe D/E); Lamp for Flood Light (Exterior) (OSRAM Powerstar
HQI-TS Excellence 150W/NDL); Lamp for Highbay Light (Warehouse)
(OSRAM Powerstar HQI-E 150W/NDL/Clear); 14W Flourescent Lamp
for Office - Phillips TL5 Essential 14W/840; 28W Flourescent Lamp for
Buffer Areas VRV - Phillips TL5 Essential 28W/840; 36W Flourescent
Lamp for Cleanroom - Phillips TL-D 36W/840; Ballast 36W for Clean
Room-TRIDONIC PC T8 Pro IP; Ballast 28W for Buffer Areas & VRV
- THorn Electronic Ballast for Linear T5 FL Lamp; Ballast 14W for
Office - TRIDONIC PC T5 Top IP 3x14W

BBVN-FIVE-S2-SC- 14/10/17 14/10/20 14/10/23 Highbay Lighting Emergency Lamp for Warehouse (OSRAM Halostar Catalogue, Techinical Data Quang/Ujiie B+C/B+C
AMEP-173/R1 50W 12V GY6.35); Lamp for Downlight in Office & Canopy (OSRAM Sheet
Deluxe D/E); Lamp for Flood Light (Exterior) (OSRAM Powerstar
HQI-TS Excellence 150W/NDL); Lamp for Highbay Light (Warehouse)
(OSRA

BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/09 FS-ONE Fire Stop Sealant for Busduct Penetration - HILTI Catalogue, Technical Data Quang/Ujiie B
AMEP-174

BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/13 Fire Smoke Supply Air Fan FSFS0PII-01,02 - Drugger TDA-V900- Technical Data Sheet Quang/Ujiie C
AMEP-175 14AA-7-7/22 (Additional Fan - Refer to RFC26)

BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/20 PVC Butterfly Valve for Drain Office Pit - FIP FEOV/LM Catalogue Quang/Ujiie B/A
AMEP-176

BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/09 Badge Printer - Fargo HDP5000 & Accessories Catalogue, Installation Guide Quang/Ujiie C
AMEP-177
BBVN-FIVE-S2-SC- 14/11/04 14/11/11 14/11/07 Badge Printer - Fargo HDP5000 & Accessories_Rev.1 Revised based on Technical Detail Description; Quang/Ujiie C
AMEP-177/R1 comments in AMEP-177 dated 9-October-2014 Catalogue
BBVN-FIVE-S2-SC- 14/11/08 14/11/13 Badge Printer - Fargo HDP5000 & Accessories_Rev.2 Revised based on Catalog Quang/Ujiie
AMEP-177/R2 comments in AMEP-177/R1 dated 07-Nov-2014

BBVN-FIVE-S2-SC- 14/10/07 14/10/14 14/10/09 Software for Access Control - Lenel S00090 Picture Quang/Ujiie C
AMEP-178

BBVN-FIVE-S2-SC- 14/10/10 14/10/17 14/10/20 Water Pump Tank - GRUNDFOS GT-H-100 PN10 G1V (Superseded Catalogue, Letter, Certificate Quang/Ujiie C
AMEP-179 the approved water pump tank in AMEP-66/R1 dated 20-June-2014)

BBVN-FIVE-S2-SC- 14/11/05 14/11/12 Water Pump Tank - GRUNDFOS GT-H-100 PN10 G1V _Rev.1 Catalogue, Letter Quang/Ujiie
AMEP-179/R1 Revised based on comments in AMEP-179 dated 20-October-2014

BBVN-FIVE-S2-SC- 14/10/14 14/10/21 14/10/17 BTU Meter - ONICON System-10-BAC BTU Meter (Refer to RFC Catalogue Quang/Ujiie C
AMEP-180 Additional BTU Meter for Chilled Water)
BBVN-FIVE-S2-SC- 14/11/07 14/11/10 BTU Meter - ONICON System-10-BAC BTU Meter_Rev.1 Revised Catalogue, Technical Data Quang/Ujiie
AMEP-180/r1 based on comments in AMEP-180 dated 17-October-2014

BBVN-FIVE-S2-SC- 14/10/17 14/10/20 14/10/21 FM 200 Low Pressure Swich and Discharge Pressure Swich- FIKE Catalogue, Data Sheet Quang/ Ujiie A
AMEP-181

BBVN-FIVE-S2-SC- 14/10/18 14/10/22 14/10/24 Control cable for Mechanical Equipment- LS Vina CVV-A Catalogue, Test Report Quang/ Ujiie C
AMEP-182
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 14/11/03 Control cable for Mechanical Equipment- LS Vina CVV-A_Rev.1 Catalogue, Test Report Quang/ Ujiie C
AMEP-182/R1

BBVN-FIVE-S2-SC- 14/10/22 14/10/27 14/10/28 ACP Battery Back-up - Phoenix TS1272 (12V-7.2Ah) Picture Quang/Ujiie C
AMEP-183
BBVN-FIVE-S2-SC- 14/10/31 14/11/06 14/11/03 ACP Battery Back-up - Phoenix TS1272 (12V-7.2Ah)_Rev.1 Technical Data Quang/Ujiie C
AMEP-183/R1 Revised based on comments in AMEP_182 dated 28-Oct-2014
BBVN-FIVE-S2-SC- 14/11/08 14/11/14 ACP Battery Back-up - Phoenix TS1272 (12V-7.2Ah)_Rev.2 Technical detail description, Quang/Ujiie
AMEP-183/R2 Revised based on comments in AMEP_182/R1 dated 03-Nov-2014 Catalogue

BBVN-FIVE-S2-SC- 14/10/22 14/10/27 14/11/03 EPDM Gasket - Tan Thai Binh G-ST-Flange Gasket Catalogue Quang/Ujiie C
AMEP-184

BBVN-FIVE-S2-SC- 14/10/25 14/11/01 14/10/30 MCCB 630AF/630AT 4P 50kA (by Schneider)_Model: NSX630N Product Data Sheet, Quang/Ujiie B+C/B+C
AMEP-185 IN_AMEP-15/R2 dated 9-
June-2014; IN_AMEP-128
dated 18-July-2014;
IN_AMEP-144 dated 29-
August-2014

BBVN-FIVE-S2-SC- 14/10/31 14/11/01 14/11/03 MCCB 630AF/630AT 4P 50kA- Schneider NSX630N_Rev.1 Catalog Quang/Ujiie B
AMEP-185/R1

BBVN-FIVE-S2-SC- 14/10/25 14/11/01 14/10/31 Variable Speed Drive (VSD)_by Hai Nam (Recycling Fan RF-PII-01, Drawings; Catalogue/Product Quang/Ujiie C
AMEP-186 02) & New DB by Hai Nam Sub-Panel in AHU Room for Smoke Fan Data Sheet

BBVN-FIVE-S2-SC- 14/10/27 14/11/01 14/11/04 PVC Fume Exhaust Fan for Production Tool IMM2-5 and IMM2-6- Catalogue, Performance Data Quang/Ujiie C
AMEP-187 Krugger CCD-9-7 245W 3SY
BBVN-FIVE-S2-SC- 14/11/08 14/11/10 PVC Fume Exhaust Fan for Production Tool IMM2-5 and IMM2-6- Catalog, Technical Data Quang/Ujiie
AMEP-187/R1 Krugger CAC 200-4_ Rev.1
Revised based on comment in AMEP_187 dated 04-Nov-2014

BBVN-FIVE-S2-SC- 14/10/31 14/11/06 14/11/03 Office Power Supply Battery-Altronix OLS120 Technical Data Quang/Ujiie C
AMEP-188

BBVN-FIVE-S2-SC- 14/10/31 14/11/07 14/11/03 Pilot Light Unibody Type- IDEC YW1P- 1BUQ3(2) Catalog Quang/Ujiie B
AMEP-189

BBVN-FIVE-S2-SC- 14/11/07 14/11/14 Trunking, Data, Powepoint for Toolshop 2; for IPQC Lab and for White Technical Detail Description; Quang/Ujiie/Diem
AMEP-190 Office Catalogue

BBVN-FIVE-S2-SC-
AMEP-191

BBVN-FIVE-S2-SC-
AMEP-192

BBVN-FIVE-S2-SC-
AMEP-193

BBVN-FIVE-S2-SC-
AMEP-194
Approval for Mechanical, Electrical Plumbing 11
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
BBVN-FIVE-S2-SC-
AMEP-195

BBVN-FIVE-S2-SC-
AMEP-196

BBVN-FIVE-S2-SC-
AMEP-197

BBVN-FIVE-S2-SC-
AMEP-198

BBVN-FIVE-S2-SC-
AMEP-199
Approval for Mechanical, Electrical Plumbing 12
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
Approval for Mechanical, Electrical Plumbing 13
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
Approval for Mechanical, Electrical Plumbing 14
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
Approval for Mechanical, Electrical Plumbing 15
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
Approval for Mechanical, Electrical Plumbing 16
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
Approval for Mechanical, Electrical Plumbing 17
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply
Approval for Mechanical, Electrical Plumbing 18
OUTGOIING Rev. Date Delivered Date INCOMING Title Attachment Author/Delivered to Status Date Delivered to
Required Date Received Author
Reply

45.00
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 19
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0001-14 Pre-condition survey method Phuc
Pre-condition survey method C

BBVN-FIVE-S2-SC-AMS- 14/03/05 Pre-condition survey method Nguyen


0001-14/R1

BBVN-FIVE-S2-SC-AMS-0002-14 Temporary site office method statement Nguyen


14/02/28 Temporary site office method statement C

BBVN-FIVE-S2-SC-AMS- 14/03/03 14/03/03 Temporary site office method statement (Rev.1) Cuong/Toan
0002-14/R1
14/03/05 Temporary site office method statement (Rev.1) B

BBVN-FIVE-S2-SC-AMS- Temporary site office method statement (Rev.2) Nguyen


0002-14/R2
14/03/06 Temporary site office method statement (Rev.2) C

BBVN-FIVE-S2-SC-AMS- 14/03/06 14/03/06 Temporary site office method statement (Rev.3) Nguyen
0002-14/R3
14/03/06 Temporary site office method statement (Rev.3) B

BBVN-FIVE-S2-SC-AMS-0003-14 14/03/04 14/03/04 Temporary Electric Method Statement Risk Assessment (2 A4 pages), 4 A3 size Dam Minh Quang
drawings: E-01, E-02, E-03, E-04

14/03/06 Temporary Electric Method Statement C

BBVN-FIVE-S2-SC-AMS- 14/03/14 Temporary Electric Method Statement (Rev.1) 9 A3 drawings Trung


0003-14/R1
14/03/17 Temporary Electric Method Statement (Rev.1) C

BBVN-FIVE-S2-SC-AMS- 14/03/18 Temporary Electric Method Statement (Rev.2) 7 A3size drawings Diem
0003/R2
14/03/20 Temporary Electric Method Statement (Rev.2) C

BBVN-FIVE-S2-SC-AMS- 14/03/21 Temporary Electric Method Statement (Rev.3) 1 A3 size schedule, 9 A3 size drawings Diem
0003/R3
14/03/21 Temporary Electric Method Statement (Rev.3) A

BBVN-FIVE-S2-SC-AMS-0004-14 14/03/04 14/03/04 Relocation Fire fighting Method Statement Risk Assessment (2 A4 pages), 1 A3 size Dam Minh Quang
drawings: MF-02
14/03/05 Relocation Fire fighting Method Statement C

BBVN-FIVE-S2-SC-AMS- 14/03/21 14/03/28 MS-21. Fire Fighting System_Remove and Modification Existing Hydrant
Remove
Pipe Rev.1
and Modification Existing Hydrant Pipe, Ujiie/D.T . Trung
0004/R1 Details schedule for the remove & modification
existing hydrant pipe, JSA form1 A3 size drawing

14/03/24 MS-21. Fire Fighting System_Remove and Modification Existing Hydrant Pipe Rev.1 C

BBVN-FIVE-S2-SC-AMS- 14/03/27 14/04/03 MS-21. Fire Fighting System_Remove and Modification Existing Hydrant
Remove
Pipe Rev.2
and Modification Existing Hydrant Pipe, Mr. Trung
0004/R2 Details schedule for the remove & modification
existing hydrant pipe

BBVN-FIVE-S2-SC-AMS-0005-14 14/03/03 14/03/04 Temporary Water Supply Method Statement Risk Assessment (2 A4 pages), A3 size drawings: Dam Minh Quang
Option 1: 3 pages, Option 2: 2 pages
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 20
Issued Required Received
Reply
14/03/06 Temporary Water Supply Method Statement C

BBVN-FIVE-S2-SC-AMS- 14/03/12 Water Supply Temporary System Rev.1 1 A3 size schedule, 2 A3 size drawings Trung
0005-14/R1
14/03/14 Water Supply Temporary System Rev.2 B

BBVN-FIVE-S2-SC-AMS-0006-14 14/03/03 14/03/04 Temporary Sewage water Method Statement Risk Assessment (2 A4 pages), 5 A3 size Dam Minh Quang
drawings: Option 1 (M-03, M-04, underground
Combined), Option 2 (M-03, M-04)

14/03/06 Temporary Sewage water Method Statement C

BBVN-FIVE-S2-SC-AMS- 14/03/14 Water Drain Temporary System Rev.1 1 A3 size schedule, 2 A3 size drawings Trung B
0006-14/R1
Water Drain Temporary System Rev1

BBVN-FIVE-S2-SC-AMS-0007-14 14/03/11 Existing pile rectification 17 A3 size drawings, JSA form Cuong
14/03/14 Existing pile rectification C

BBVN-FIVE-S2-SC-AMS- 14/03/18 Existing pile rectification Rev.1 Work Monitoring, HILTI Specification, QPTL- Cuong
0007/R1 D6:1978, 17 A3 size drawings, JSA form

14/03/26 Existing pile rectification Rev.1 B

BBVN-FIVE-S2-SC-AMS-0008-14 14/03/11 List of Method Statement Thanh


14/03/12 List of Method Statement C/A

BBVN-FIVE-S2-SC-AMS- 14/03/18 List of Method Statement Rev.1 Tu


0008/R1
14/03/21 List of Method Statement Rev.1 B

BBVN-FIVE-S2-SC-AMS-0009 14/03/18 MS-BLD.04 Earthwork Schedule of Elevation, Site organization Chart, Nguyen/Tu
Location & Access, Schedule & Manpower, JSA
form
14/03/25 MS-BLD.04 Earthwork C/B

BBVN-FIVE-S2-SC-AMS- 14/03/29 14/04/02 MS-BLD.04 Earthwork Rev.1 Schedule of Elevation, Site organization Chart,
0009/R1 Location & Access, Schedule & Manpower,
Existing Ground Level, JSA form

14/04/03 MS-BLD.04 Earthwork Rev.1 B

BBVN-FIVE-S2-SC-AMS- 14/04/05 14/04/08 Report & Proposal on consulting for soil treatment method (Based on
0009/R1 (ADD) comment SL.16 in General Note Sheet 2 - For Construciton Drawings
(Structural Drawings) Nov 2013)

12-Apr-14 B
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 21
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0010 14/03/18 14/03/19 MS-11 Subcon Temporary Site Office Schedule of Elevation, Site Organisation Chart, A3 Toan
size Drawings Vinaconex 2 4 pages&North Star 17
pages, JSA form
14/03/20 MS-11 Subcon Temporary Site Office C

BBVN-FIVE-S2-SC-AMS- 14/03/21 14/03/22 MS-11 Subcon Temporary Site Office Rev.1 Site Organisation Chart, Schedule of Works - Toan
0010/R1 Vinaconex 2 & North Star, 1 A3 size Drawings
Master Plan of site office building, 4 A3 size
drawings of Vinaconex 2 & 13 pages North Star,
JSA form
14/03/28 MS-11 Sub-con Temporary Site Office _ Rev.1 Toan B

BBVN-FIVE-S2-SC-AMS-0011 14/03/24 14/03/28 MS.BLD-01/Anti-Termite Work Schedule of elevation, Site Organisation Chart, Thanh
JSA form, 6 A3size drawings
14/03/26 MS.BLD-01/Anti-Termite Work C

BBVN-FIVE-S2-SC-AMS- 14/04/03 14/04/05 MS.BLD-01/Anti-Termite Work Rev.1 based on comments AMS-0011Schedule


dated 26-Mar-2014
of elevation, Site Organisation Chart, Tuan Anh
0011/R1 JSA form, 5 A3size drawings, Material Safety
Data Sheet

12-Apr-14 MS.BLD-01/Anti-Termite Work Rev.1 based on comments AMS-0011 dated 26-Mar-2014 B

BBVN-FIVE-S2-SC-AMS-0012 14/03/27 14/03/31 R.C Work Equipment List, Schedule & Manpower, JSA Tuan Anh

08-Apr-14 R.C Work C


BBVN-FIVE-S2-SC-AMS- 14/04/16 Method Statement for Concrete work, Equipment
14/04/19 R.C Work Rev.1 Tuan Anh
0012/R1 list, JSA

14/04/23 RC Work_Rev.1 Tuan Anh B

BBVN-FIVE-S2-SC-AMS-0013 14/04/04 14/04/09 MS-29: Earthing System and Underground System Work Cabling and Details Schedule/Main Power Requirement, Mr. Quang/Mr.
Piping Survey Method, Installation Underground pipe, Diem
Method installation earth rod in earth pit, Detail of
grounding rod in earth pit, detail of earth pit,
connection from test link box to earth rod, details
of HDPE conduit installation

MS-29: Earthing System and Underground System Work Cabling and Piping C
08-Apr-14
BBVN-FIVE-S2-SC-AMS- 14/04/28 14/05/05
0013/R1

BBVN-FIVE-S2-SC-AMS-0014 14/04/14 14/04/21 MS-19 [C]: Air Conditioning & Mechanical Ventilation System Excavation Work, Installaiton pipe work, testing Mr. Quang/Mr.
[C] Condensation Drain Pipe Underground System Work commissioning, Sleeve, Location of the activity, Trung
Details Schedule/Manpower requirement

14/04/18 MS-19: Air Conditioning & Mechanical Ventilation System C


[C] Condensation Drain Pipe Underground System Work
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 22
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/04/26 14/04/29 14/05/19 MS-19: Air Conditioning & Mechanical Ventilation System [C] Quang/Trung C
0014/R1 Condensation Drain Pipe Underground System Work_Rev.1 Revised
based on comments in AMS_0014 dated 18-Apr-2014

BBVN-FIVE-S2-SC-AMS- 14/05/27 14/05/29 14/06/02 MS-19: Air Conditioning & Mechanical Ventilation System [C] Quang/Trung B
0014/R2 Condensation Drain Pipe Underground System Work_Rev.1 Revised
based on comments in AMS_0014 dated 18-Apr-2014

BBVN-FIVE-S2-SC-AMS-0015 14/04/14 14/04/21 MS-20: Water Supply and Drainage Underground System Work Excavation Work, Installaiton pipe work, testing Mr. Quang/Mr.
commissioning, Sleeve, Location of the activity, Trung
Details Schedule/Manpower requirement

14/04/18 MS-20: Water Supply and Drainage Underground System Work C

BBVN-FIVE-S2-SC-AMS- 14/04/26 14/04/29 14/05/09 MS-20: Water Supply and Drainage Underground System Mr. Quang/Trung B
0015/R1 Work_Rev.1 Revised based on comments in AMS_0015 dated 18-
Apr-2014

BBVN-FIVE-S2-SC-AMS-0016 14/04/14 14/04/21 MS-21: Fire Fighting Underground System Work Excavation Work, Installaiton pipe work, testing Mr. Quang/Mr.
commissioning, Sleeve, Location of the activity, Trung
Details Schedule/Manpower requirement

14/04/18 MS-21: Fire Fighting Underground System Work C

BBVN-FIVE-S2-SC-AMS- 14/04/26 14/04/29 14/05/09 MS-21: Fire Fighting Underground System Work_Rev.1 Revised Quang/Trung B
0016/R1 based on comments in AMS_0016 dated 18-Apr-2014

BBVN-FIVE-S2-SC-AMS-0017 14/04/22 14/04/24 MS-44 Protection Method for Door & Window at Grid Line 12 Method Statement, JSA/Risk Analysis, Schedule Tuan Anh

14/04/23 MS-44 Protection Method for Door & Window at Grid Line 12 B/C

BBVN-FIVE-S2-SC-AMS- 14/04/24 14/04/25 MS-44 Protection Method for Door & Window at Grid Line 12_Rev1 Method Statement, JSA/Risk Analysis, Schedule
0017 (Revised based on comment in AMS_0017 dated 23-Apr-2014)

14/04/25 MS-44 Protectin Method for Door & Window at Grid Line 12_Rev.1 Tuan Anh A/B

BBVN-FIVE-S2-SC-AMS-0018 14/04/28 14/05/05 MS-28: External Lighting-Underground Work for Foundation Cabling Survey Method, Installation underground pipe, Quang/Diem C
& Piping installation underground crossing road, concrete
foundation method, JSA, schedule, plan of activity

14/05/07 MS-28: External Lighting-Underground Work for Foundation Cabling C


& Piping
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 23
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/05/12 14/05/16 14/05/19 MS-28: External Lighting-Underground Work for Foundation Cabling Details schedule/Menpower Requirements, Quang/Diem B
0018/R1 & Piping_Rev.1 Revised based on comments in AMS-0018 dated 7- MSE.1: Survey Method, MSE.2: Installation
May-14 underground pipe, MSE.3: Details of HDPE
conduit installation, MSE.4: Method Installation
underground pipe across rain water pipe at
crossroad, MSE.5: Fabrication of pipe cast
foundation, MSE.6: Make concrete foundation
method

BBVN-FIVE-S2-SC-AMS-0019 14/04/29 14/05/05 14/05/09 MS-25: Underground Piping & Cabling for Pumpit Survey Method, Installation underground pipe, Quang/Diem C
detail of installation of HDPE conduit, Connect to
panel, sleeve for pum pit, JSA, schedule, plan of
activity
BBVN-FIVE-S2-SC-AMS- 14/05/28 14/05/28 14/06/04 MS-25: Underground Piping & Cabling for Pumpit_Rev.1 Revised Detailed schedule/Manpower Requirement, Quang/Diem C
0019/R1 based on comments in AMS-19 dated 9-May-2014 MSE.1: Survey Method; MSE.2: Installation
Underground Pipe (HDPE); MSE.3: Details of
HDPE conduit installationl; MSE.4: Connect to
electric panel
BBVN-FIVE-S2-SC-AMS- 14/11/08 14/11/12 MS-25: Underground Piping & Cabling for Pumpit_Rev.2 Revised Detailed schedule/Manpower Requirement, Quang/Diem
0019/R2 based on comments in AMS-19/R1 dated 4-June-2014 MSE.1: Survey Method; MSE.2: Installation
Underground Pipe (HDPE); MSE.3: Details of
HDPE conduit installationl; MSE.4: Connect to
electric panel

BBVN-FIVE-S2-SC-AMS-0020 14/04/29 14/05/05 14/05/09 MS-35: CCTV system-Underground system work cabling and piping Survey Method, Installation underground pipe, Quang/Diem C
detail of installation of HDPE conduit, JSA,
schedule, plan of activity
BBVN-FIVE-S2-SC-AMS- 14/05/24 14/05/28 14/05/28 MS-35: CCTV system-Underground system work cabling and Detailed schedule/Manpower Requirement, Quang/Diem B
0020/R1 piping_Rev.1 Revised based on comments in AMS-20 dated 9-May- MSE.1: Survey Method; MSE.2: Installation
2014 Underground Pipe (FEP); MSE.3: Details of
HDPE conduit installation; MSE.4: Method
installation underground pipe across rain water
pipe at crossroad

BBVN-FIVE-S2-SC-AMS-0021 14/04/29 14/05/3 14/05/07 MS-BLD.05 Method Statement for Temporary Steel Stage 1.Working Procedure, 2.Material Spec., 3.Platform Tuan Anh
Installation, 4.Schedule & Manpower, 5.Drawing,
6.JSA/Risk Analysis, 7.Crane Spec., 8.Calculation B
Sheet

BBVN-FIVE-S2-SC-AMS-0022 14/04/29 14/05/05 MS-30 Lightning System - Underground Work Cabling and Piping Quang/Diem
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 24
Issued Required Received
Reply
14/05/09 MS-30 Lightning System - Underground Work Cabing and Piping Mr. Quang C

BBVN-FIVE-S2-SC-AMS- 14/05/12 14/05/15 14/05/19 MS-30 Lightning System - Underground Work Cabing and Piping Details schedule/Manpower requirements, MSE.1: Quang/Diem B
0022/R1 _Rev.1 Revised based on comments in AMS_0022 dated 05-May- Survey Method, MSE.2: Installation underground
2014 pipe, MSE.3: details of HDPE conduit installation,
MSE.4.1&4.2: Method installation earth rod in
earth pit, MSE.5: Detail of grounding rod in earth
pit, MSE.6: detail of earth pit, MSE.7&7.1:
Connection from test link box to earth rod,
MSE.8&8.1&8.2&8.3: Sleeve for lightning cable,
MSE.7: Connection from test link box to earth rod

BBVN-FIVE-S2-SC-AMS-0023 14/05/2 14/05/06 14/05/07 MS-BLD.18 Method Statement for Road & Stormwater works 1.General, 2.Reference standards & documents 3. Tuan Anh
Equipment list, 4.Preparation works,
5.Construction for road work, 6.Construction for C
storm works, 7.Quality managemant., 8.Safety
management
BBVN-FIVE-S2-SC-AMS- 14/05/21 14/05/24 MS-BLD.18 Method Statement for Road & Stormwater works_Rev.1 Drawings for road construction, Drawings for Tuan Anh
0023/R1 Revised based on comments in AMS-0023 dated 7-May-2014 storm water construction, Schedule & Manpower,
JSA/Risk Assessment

BBVN-FIVE-S2-SC-AMS-0024 14/05/05 14/05/07 14/05/07 MS-45: Staircase Demolition at Gridline 12 Method Statement, JSA/Risk Assessment, Tuan Anh
B
Schedule
BBVN-FIVE-S2-SC-AMS- 14/05/21 14/05/24 14/06/03 MS-45: Staircase Demolition at Gridline 12_Rev.1 Revised based on
0024/R1 comments in AMEP-24 dated 7-May-2014 B

BBVN-FIVE-S2-SC-AMS-0025 14/06/05 14/06/10 14/06/11 MS-BLD.03 - Scaffolding Installation & Dismantling Works Scaffolding Layout, Section&Details; Schedule; Tuan Anh
Data Sheet/Catalogue; JSA/RA; Calculation Sheet A

BBVN-FIVE-S2-SC-AMS-0026 14/05/07 14/05/10 14/05/13 MS-BLD.06-A: Reinforcement Concrete - Trench Pit Method Statement, Tuan Anh C
JSA/Risk Assessment
BBVN-FIVE-S2-SC-AMS- 14/05/14 14/05/16 14/05/16 MS-BLD.06-A: Reinforcement Concrete - Trench Pit_Rev.1 Revised Method Statement, Equipment List, Tuan Anh B/A
0026/R1 based on comments in AMS-0026 dated 13-May-2014 Schedule&Manpower, JSK/Risk Assessment
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 25
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0027 14/06/11 14/06/16 MS-BLD.10-Roofing & Waterproofing for Roof Waterproofing Guarantee; RA & JSA; Tuan Anh
Introduction Letter from SIKA Ltd Vietnam;
Worker Certification/License; SIKA Products Data
Sheet; Machinery Catalogue; Drawings for
Waterproofing Works; Material Safety Data Sheet
- MSDS; Report for Mock-up Application REP-
MU-01

BBVN-FIVE-S2-SC-AMS-0028 14/05/09 14/05/13 14/05/15 MS-BLD.09_XYPEX Waterproofing for Under Slab Drawings, Specification/Data Sheet, Material Tuan Anh B
Safety Data Sheet, JSA/Risk Assessment

BBVN-FIVE-S2-SC-AMS-0029 (A) 14/05/28 MS-34 [A]: Fire Detection and Alarm System for Stage 1 Details Schedule/Manpower Requirement, MSE.1: Quang/Diem C
Scaffolding setup for existing generator and
MVSG room, MSE.2: Scaffolding setup for AHU
area, MSE.3: Method of installation detector
exposed, MSE.4: Installation for BMS room

BBVN-FIVE-S2-SC-AMS- 14/07/31 14/08/07 14/08/11 MS-34 [A]: Fire Detection and Alarm System for Stage 1_Rev.1 Details Schedule/Manpower Requirement, Quang/Diem C
0029 (A)/R1 Revised based on comments in AMS-29 (A) dated 28-May-2014 Appendix 1: Location of Activity, Appendix 2:
Detail of installation - MV Switchgear room,
Appendix 3: Detail of installation - Generator
room, Appendix 4: AHU room, Appendix 5:
Detail of installation-BMS room, Appendix 6:
Detail of installation - SFACP panels, JSA, Risk
Assessment and management for change system,
RCR services pre-work/task observation sheet,
Pre-task planning worksheet

BBVN-FIVE-S2-SC-AMS- 14/08/22 14/08/25 14/08/28 MS-34 [A]: Fire Detection and Alarm System for Stage 1_Rev.2 Comments response table; Details Quang/Diem B
0029 (A)/R2 Revised based on comments in AMS-29 (A)/R1 dated 11-August- Schedule/Manpower Requirement, Works detail
2014 (Tie-in No. 31) table; Appendix 1: Location of Activity, Appendix
2: Detail of installation - MV Switchgear room,
Appendix 3: Detail of installation - Generator
room, Appendix 4: AHU room, Appendix 5:
Detail of installation-BMS room, Appendix 6:
Connection for BB262B-IFC-320-Z04&BB262-
IFC-320-Z05 panel;Appendix 7: Detail of new
modules connection to FA system, JSA, Risk
Assessment and management for change system,
RCR services pre-work/task observation sheet,
Pre-task planning worksheet
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 26
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0029 (B) 14/05/28 MS-34 [B]: Fire Detection and Alarm System for Stage 2 Details Schedule/Manpower Requirement, MSE.1: Quang/Diem B
Scaffolding setup for existing generator and
MVSG room, MSE.2: Scaffolding setup for AHU
area, MSE.3: Method of installation detector
exposed, MSE.4: Installation for BMS room

BBVN-FIVE-S2-SC-AMS- 14/08/22 14/08/25 MS-34 [B]: Fire Detection and Alarm System for Stage 2_Rev.1 Comments response table; Details Quang/Diem
0029 (B)/R1 Revised based on comments in AMS-29 (B) dated 25-May-2014 Schedule/Manpower Requirement, Work Detail
table; Location of activity; Detail of Installation -
MV Switchgear room/Generator room/AHU
room/BMS Room; Connection for BB262B-IFC-
320-Z04&BB262-IFC-320-Z05 panel; Detail of
new modules connection to FA system; JSA; Risk
assessment and management for change system;
RCR servicers Pre-work/Task observation sheet;
Pre-task planning worksheet

BBVN-FIVE-S2-SC-AMS- 14/10/29 14/11/03 14/11/07 MS-34 [B]: Fire Detection and Alarm System for Stage 2_Rev.2 Details Schedule/Manpower Requirement, Quang/Diem C
0029 (B)/R2 Revised based on comments in AMS-29 (B) /R1 MSE.1: Method Installation Concealed EMC
conduit on the wall; MSE.2: Method of Installation
for expose conduit; MSE.3: Method of Installation
conduit under sub-beam; MSE.4: Method of
Installation detector on ceiling; MSE.5: Method of
Installation detector for office, corridor and
changing room; MSE.6: Method of Installation
equipment for office, corridor and changing room;
MSE.7: Method of Installation detector for
cleaning room; MSE.8: Method of Installation
equipment for cleaning room; MSE.9: Method of
Installation beam detector for warehouse; MSE.10:
Method of Installation beam detector for
warehouse; MSE.11: Cable test form

BBVN-FIVE-S2-SC-AMS-0030 14/05/15 14/05/17 14/05/22 MS-46: Fence Relocation Method Statement, JSK/Risk Assessment, Tuan Anh C
Schedule
BBVN-FIVE-S2-SC-AMS- 14/05/29 14/06/04 14/06/02 MS-46: Fence Relocation_Rev.1 Revised based on comments in Method Statement, JSK/Risk Assessment, Tuan Anh/Ba B
0030/R1 AMS-0030 dated 22-May -2014 Schedule Hoa
BBVN-FIVE-S2-SC-AMS- 14/06/12 14/06/13 14/06/13 MS-46: Fence Relocation_Rev.1 (Additional Document) Ba Hoa/Nguyen B
0030/R1 (ADD.01)

BBVN-FIVE-S2-SC-AMS-0031 14/05/16 14/05/20 14/05/23 MS-21 [A]: Fire Fighting System_Stage 1 Methodology, Location, Site Orgnization Chart, Quang/Trung C
Tool&Equipment List, Detail
Schedule/Manpower, Safety Management, Quality
Control, Appendices
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 27
Issued Required Received
Reply

BBVN-FIVE-S2-SC-AMS-0032 14/05/16 14/05/20 14/05/23 MS-21 [B]: Fire Fighting System_Stage 2 Methodology, Location, Site Orgnization Chart, C
Tool&Equipment List, Detail
Schedule/Manpower, Safety Management, Quality
Control, Appendices
BBVN-FIVE-S2-SC-AMS- 14/07/16 14/07/21 14/07/25 MS-21 [B]: Fire Fighting System_Stage 2_Rev.1 Revised based on Installation Equipment, Installation FM200, Quang/Trung C
0032/R1 comments in AMS-32 dated 23-May-2014 Installation support & pipe, Inspection Document,
Procedure firestop, location of the activity, details
schedule/Manpower requirement, JSA

BBVN-FIVE-S2-SC-AMS- 14/08/01 14/08/07 14/08/16 MS-21 [B]: Fire Fighting System_Stage 2_Rev.2 Revised based on Installation Equipment, Installation FM200, Quang/Trung C
0032/R2 comments in AMS-32/R1 dated 25-July-2014 Installation support & pipe, Inspection Document,
Procedure firestop, location of the activity, details
schedule/Manpower requirement, JSA

BBVN-FIVE-S2-SC-AMS- 14/08/22 14/08/27 14/09/04 MS-21 [B]: Fire Fighting System_Stage 2_Rev.3 Revised based on Comments response table; Installation Equipment, Quang/Trung B
0032/R3 comments in AMS-32/R2 dated 16-August-2014 Installation support & pipe, Inspection Document,
Procedure firestop, location of the activity, details
schedule/Manpower requirement, JSA

BBVN-FIVE-S2-SC-AMS-0033 14/05/19 14/05/24 14/05/28 MS-20 [A]: Water Supply and Drainage System for Stage 1 Quang/Khoa C

BBVN-FIVE-S2-SC-AMS- 14/06/26 14/07/03 14/07/01 MS-20 [A]: Water Supply and Drainage System for Stage 1_Rev.1 Pump &Pipe install works, location of the activity, Quang/Khoa C
0033/R1 Revised based on comments in AMS-33 dated 28-May-2014 Procedure fire stop, Details schedule/Manpower
requirement, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet,
hot work permit, document reference, risk
assessment & management for change system

BBVN-FIVE-S2-SC-AMS- 14/07/09 14/07/16 14/07/11 MS-20 [A]: Water Supply and Drainage System for Stage 1_Rev.2 Pump &Pipe install works, location of the activity, Quang/Khoa C
0033/R2 Revised based on comments in AMS-33 dated 1-July-2014 Procedure fire stop, Welding Procedure, Details
schedule/Manpower requirement, RCR servicer
pre-work/task observation sheet, Pre-task planning
work sheet, hot work permit, document reference,
risk assessment & management for change system

BBVN-FIVE-S2-SC-AMS- 14/07/30 14/08/06 14/08/12 MS-20-A-1: Water Supply System for Stage 1_Rev.3 Revised based Pump &Pipe install works, location of the activity, Quang/Khoa C
0033/R3 (A) on comments in AMS-33/R2 dated 11-July-2014 Procedure fire stop, Welding Procedure, Details
schedule/Manpower requirement & Tie-in List,
RCR servicer pre-work/task observation sheet,
Pre-task planning work sheet, hot work permit,
document referenced, risk assessment &
management for change system

BBVN-FIVE-S2-SC-AMS- 14/08/15 14/08/22 14/08/26 MS-20-A-1: Water Supply System for Stage 1_Rev.4 Revised based Pump &Pipe install works, Location of the Quang/Khoa B
0033/R4 (A) on comments in AMS-33/R3 (A) dated 12-August-2014 activity, Procedure fire stop, Welding Procedure,
Details schedule/Manpower requirement & Tie-in
List, RCR servicer pre-work/task observation
sheet, Pre-task planning work sheet, hot work
permit, document referenced, risk assessment &
management for change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 28
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/07/30 14/08/06 14/08/12 MS-20-A-1: Drainage System for Stage 1_Rev.3 Revised based on Installation works, location of the activity, Details Quang/Khoa C
0033/R3 (B) comments in AMS-33/R2 dated 11-July-2014 schedule/Manpower requirement, RCR servicer
pre-work/task observation sheet, Pre-task planning
work sheet, document referenced, JSA

BBVN-FIVE-S2-SC-AMS- 14/08/15 14/08/22 14/08/27 MS-20-A-2: Drainage System for Stage 1_Rev.4 Revised based on Installation works, location of the activity, Details Quang/Khoa B
0033/R4 (B) comments in AMS-33/R3 (B) dated 12-August-2014 schedule/Manpower requirement, RCR servicer
pre-work/task observation sheet, Pre-task planning
work sheet, document referenced, JSA

BBVN-FIVE-S2-SC-AMS-0034 14/05/19 14/05/24 14/05/28 MS-20 [B]: Water Supply and Drainage System for Stage 2 Quang/Khoa C

BBVN-FIVE-S2-SC-AMS- 14/06/26 14/07/03 14/07/04 MS-20 [B]: Water Supply and Drainage System for Stage 2_Rev.1 Installation Pipe, Procedure firestop, Location of Quang/Khoa B/B+C
0034/R1 Revised based on comments in AMS-34 dated 28-May-2014 the activity, Document referenced

BBVN-FIVE-S2-SC-AMS-0035 14/05/21 14/05/26 14/05/28 MS-23: Equipment for Stage 1 Detailed Schedule/Manpower Requirement, Quang/Diem C
MSE.1: Method Take out louver of transformer,
MSE.2: Method make temporary unloading area,
MSE.3: Method unloading transformer and fix
transformer, MSE.4: Method reinstallation of
louvers for transformer

BBVN-FIVE-S2-SC-AMS- 14/08/09 14/08/14 14/08/15 MS-23: Equipment for Stage 1_Rev.1 Revised based on comments in Details schedule/Manpower Requirements, Quang/Diem B
0035/R1 AMS_0035 dated 28-May-2014 MSE.1: Take out louver menthod, MSE.2: Make
temporary uploading area, MSE.3: Uploading
transformer and fix transformer, MSE.4: Move
transformer to foundation, MSE.5: Fix
Transformer to concrete base, MSE.6: Re-install
louver and finish work

BBVN-FIVE-S2-SC-AMS-0036 14/06/16 14/06/20 14/06/23 MS-24 [A]: Main Feeder, Cable Rack, Busway and Panel System for Detailed Schedule/Manpower Requirements, Quang/Diem C
Stage 1 MSE.1: Method of unloading busway and cable
rack, MSE.2: Method of installation support for
cable rack/busway under sub-beam; MSE.3:
Method of installation cable rack

BBVN-FIVE-S2-SC-AMS- 14/07/23 14/07/26 14/08/01 MS-24 [A]: Main Feeder, Cable Rack, Busway and Panel System for Detailed Schedule/Manpower Requirements, Quang/Diem C
0036/R1 Stage 1_Rev.1 Revised based on comments in AMS-36 dated 23-June- MSE.1: Method of unloading cable rack and
2014 panels, MSE.2: Method of Making wall opening
holes; MSE.3: Method of making floor opening
holes, MSE.4: Method of installation cable rack at
AHU room, MSE.5: Method of installing cable
rack above walkable ceilingl MSE.6L Method of
installing cable rack at utility area, MSE.7:
Method of installing LV panels; JSA, RA and
Management for change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 29
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/08/07 14/08/12 14/08/15 MS-24 [A]: Main Feeder, Cable Rack, Busway and Panel System for Detailed Schedule/Manpower Requirements, Quang/Diem B
0036/R2 Stage 1_Rev.2 Revised based on comments in AMS-36/R1 dated 01- MSE.1: Method of unloading cable rack,
August-2014 scaffoldings; MSE.2: Method of Making wall
opening holes; MSE.3: Method of making floor
opening holes, MSE.4: Method of installation
cable rack at AHU room, MSE.5: Method of
installing cable rack above walkable ceiling;
MSE.6: Method of installing cable racks at utility
area; RCR services pre-work/task observation
sheet; Pre-task planning sheet; Hot work permit;
JSA and Management for change system

BBVN-FIVE-S2-SC-AMS-0037 14/05/22 14/05/29 MS-24 [B]: Main Feeder, Cable Rack, Busway and Panel System for Detailed Schedule/Manpower Requirements, Quang/Diem
Stage 2 MSE.1: Method of unloading busway and cable
rack, MSE.2: Method of installation support for
cable rack/busway under concrete ceiling; MSE.3:
Method of installation support for cable
rack/busway under sub-beam; MSE.4: Method of
installation cable rack; MSE.5: Method of
installation LV Busway for production machine;
MSE.6: Method of installation panel

BBVN-FIVE-S2-SC-AMS-0038 14/05/22 14/05/29 14/05/28 MS-25 [A]: Cable and Trunking for Stage 1 Detailed Schedule/Manpower Requirements, Quang/Diem C
MSE.1: Method of unloading cable drum to AHU
room; MSE.2: Mehtod of installation pulling
cable; MSE.3: Mehtod of installation for
termination connection
BBVN-FIVE-S2-SC-AMS- 14/07/28 14/08/04 14/08/07 MS-25 [A]: Cable and Trunking for Stage 1_Rev.1 Revised based on Detailed Schedule/Manpower Requirements, C
0038/R1 comments in AMS-38 dated 28-May-2014 MSE.1: Method of unloading cable drum to AHU
room; MSE.2: Mehtod of installation pulling
cable; MSE.3: Mehtod of installation for
termination connection
BBVN-FIVE-S2-SC-AMS- 14/08/19 14/08/22 14/08/23 MS-25 [A]: Cable and Trunking for Stage 1_Rev.2 Revised based on MSE.1: Method of unloading cables; MSE.2: Quang/Diem/ B
0038/R2 comments in AMS-38/R1 dated 7-August-2014 Mehtod of unloading trunkings; MSE.3: Method Ujiie
of installation trunkings above walkable ceiling;
MSE.4: Mehtod of installing trunking at AHU
room; MSE.5: Method of cabling works; JSA;
Risk Assessment and Managerment for Change
system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 30
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0039 14/05/22 14/05/29 14/05/28 MS-25 [B]: Cable and Trunking for Stage 2 Detailed Schedule/Manpower Requirements, Quang/Diem C
MSE.1: Method of unloading cable and trunking;
MSE.2: Method of installation trunking under sub-
beam for walkway area; MSE.3: Method of
installation trunking under concrete ceiling for
office area; MSE.4: Method of installation
trunking under purlin for office area: MSE.5:
Method of installation cable pulling: MSE.6:
Method of installation cable pulling for warehouse
and common walkway area: MSE.7: Method of
installation for termination connection

BBVN-FIVE-S2-SC-AMS- 14/07/28 14/08/04 MS-25 [B]: Cable and Trunking for Stage 1_Rev. 1 Revised based on Detailed Schedule/Manpower Requirements, Quang/Diem
0039/R1 comments in AMS-39 dated 28-May-2014 MSE.1: Method of unloading cable; MSE.2:
Method of installation trunkings ; MSE.3: Method
of installation trunkings above walkable ceiling;
MSE.4: Method of installation trunkings at AHU
Room; MSE.5: Method of cabling works; MSE.6:
Method of termination works; JSA; Risk
Assessment and Management for change system

BBVN-FIVE-S2-SC-AMS-0039 ( C ) 14/07/12 14/07/14 14/07/18 MS-39 ( C ): Electrical System Work for Stage 1 Remove Lighting Quang/Ujiie/ B
and Trunking Diem

BBVN-FIVE-S2-SC-AMS-0040 14/05/22 14/05/29 14/05/28 MS-26: Lighting System Detailed Schedule/Manpower Requirements, Quang/Diem C
MSE.1: Method installation concealed EMC
conduit on the wall; MSE.2: Method of installation
for expose conduit: MSE.3: Method of installation
conduit under sub-beam; MSE.4: Method of
installation lighting fixture on ceiling: MSE.5:
Method of installation for cleaning room area:
MSE.6: Method of installation lighting fixture for
warehouse: MSE.7: Method of installation
lighting fixture for common area: MSE.8: Method
of installation lighting fixture for walkway and
outdoor area

BBVN-FIVE-S2-SC-AMS-0041 14/05/23 14/05/28 14/06/02 MS-BLD.07 - Structure Steel Erection Works Sequence for Steel Structure Erection; Tuan Anh B
Organization Chart; Equipment List; JSA/Risk
Assessment
BBVN-FIVE-S2-SC-AMS- 14/08/04 14/08/05 14/08/11 MS-BLD.07 - Structure Steel Erection Works_Additional Drawing 1A3size drawing Tuan C
0041 (ADD.01) Anh/Ngueyn/Phu
c
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 31
Issued Required Received
Reply

BBVN-FIVE-S2-SC-AMS-0042 14/06/16 14/06/20 MS-27: Emergency and Exit Lighting System Details schedule/Man Power Requirements; Diem/Quang
MSE.1 : Method installation concealed EMC
conduit on the wall; MSE.2 : Method of
installation for expose conduit; MSE.3 : Method of
installation conduit under sub-beam; MSE.4 :
Method of installation emergency lighting fixture
on ceiling; MSE.5 : Method of installation
emergency lighting fixture for cleaning room area;
MSE.6 : Method of installation emergency
lighting fixture for ware house; MSE.7 : Method
of installation emergency lighting fixture for
common area; MSE.8 : Method of installation
emergency lighting fixture for walkway and
outdoor area; MSE.9 : Method of installation
exit lighting for common area; JSA for emergency
and exit lighting system stage 2

BBVN-FIVE-S2-SC-AMS-0043 14/05/24 14/05/30 MS-30: Lightning System Details Schedule/Manpower requirement; MSE.1: Quang/Diem
connection from testing link box to lightning bar
on roof; MSE.2: connection from testing link box
to lightning bar on roof; MSE.3: connection from
testing link box to lightning bar on roof; MSE.4:
installation detail of air terminal; MSE.5:
installation detail of connection earthing cable to
tape; JSA analysis for lightning system

BBVN-FIVE-S2-SC-AMS-0044 14/06/16 14/06/20 14/06/23 MS-31: Socket Outlet System Details schedule/Man Power Requirements; B
MSE.1: Method installation concealed EMC
conduit on the wall; MSE.2: Method of installation
trunking under sub-beam; MSE.3: Method of
installation cable and outlet for walkway area;
MSE.4 : M Method of installation socket outlet on
the floor; MSE.5: Method of installation socket
outlet on the wall for cleaning room and office
area; MSE.6 : Method of installation isolator at
walkway area; MSE.7 : Installation socket and
isolator on the wall; MSE.8 : Installation socket
and isolator on the wall; Job safety analysis for
socket outlet
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 32
Issued Required Received
Reply

BBVN-FIVE-S2-SC-AMS-0045 14/05/24 14/05/30 MS-28: External Lighting System Details schedule/ManPower Requirements; MSE.1 Quang/Diem
: Method installation plate fix the lighting fixture
on the wall; MSE.2 : Method of installation
bracket the lighting fixture on the wall; MSE.3:
Method of installation support for flood lighting
fixture on the wall; MSE.4: Method of installation
flood lighting fixture on the wall; MSE.5: Method
of installation fix the lighting pole to precast
foundation; MSE.6: Method of installation lighting
fixture to pole and connection; Job safety analysis
for external lighting

BBVN-FIVE-S2-SC-AMS-0046 14/06/16 14/06/20 14/06/23 MS-32 [A]: BMS System Details schedule/ManPower Requirements; MSE.1 Quang/Diem C
: Method installation water temperature sensor;
MSE.2: Method of installation air temperature
sensor; MSE.3: method of installation modulating
dumper; MSE.4: method of installation level
switch for tank and temperature humidity sensor;
JSA for building management system stage 1

BBVN-FIVE-S2-SC-AMS- 14/09/08 14/09/13 14/09/15 MS-32 [A]: BMS System_Rev.1 Revised based on comments in Details schedule/ManPower Requirements; Quang/Diem C
0046/R1 AMS-46 dated 23-June-2014 Appendix 1: Move in path & location of activity
plan; Appendix 2: Installation cable; Appendix 3:
Installation of devices and panels; Appendix 4:
Cable Termination; JSA for BMS stage 1; Risk
assessment and Management for change system,
RCR services Pre-work/Task observation sheet,
Pre-task planning worksheet

BBVN-FIVE-S2-SC-AMS- 14/09/23 14/09/30 14/10/01 MS-32 [A]: BMS System_Rev.2 Revised based on comments in Comments response table; Details Quang/Diem B
0046/R2 AMS-46/R1 dated 15-September-2014 schedule/ManPower Requirements; Appendix 1:
Move in path & location of activity plan;
Appendix 2: Installation cable; Appendix 3:
Installation of devices and panels; Appendix 4:
Cable Termination; JSA for BMS stage 1; Risk
assessment and Management for change system,
RCR services Pre-work/Task observation sheet,
Pre-task planning worksheet
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 33
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0047 14/06/16 14/06/20 14/06/23 MS-32 [B]: BMS System Details schedule/ManPower Requirements; MSE.1 Quang/Diem B
: Method installation of trunking for walkway
ceiling area; MSE.2: Installation of trunking for
office area; MSE.3: installation sensor for panel
and control FCU; MSE.4: installation temperature,
pressure and humidity sensor; MSE.5: installation
damper, humidity and pressure sensor; JSA

BBVN-FIVE-S2-SC-AMS-0048 14/05/31 14/06/05 14/06/05 MS-19 [A]: Air Conditioning & Mechanical Ventilation System Stage General , Methodology, Location, Site Quang/Ujiie, C
1 Organization Chart, Tools & Equipments list, Randy
Detail schedule/manpower, safety management,
quality control, appendices, JSA, Schedule

BBVN-FIVE-S2-SC-AMS- 14/06/27 14/07/03 14/07/04 MS-19 [A]: Air Conditioning & Mechanical Ventilation System Unload Chiller, Location of the activity, details Quang C
0048/R1 (A) _Rev.1 schedule/Manpower requirement, RCR service
MS-19-A-1: Chiller Area Works_ Revised based on comments in pre-work/task observation sheet, Pre-task planning
AMS-48 dated 5-June-2014 work sheet (requirement form RCR), Hot work
permit, RA and management for change system

BBVN-FIVE-S2-SC-AMS- 14/08/04 14/08/09 14/09/06 MS-19-A-1: Chiller Area Works_Rev.2 Revised based on comments Comments response table, Unload Chiller, Quang C
0048/R2 (A) in AMS-48/R1 dated 4-July-2014 Location of the activity, details
schedule/Manpower requirement, RCR service
pre-work/task observation sheet, Pre-task planning
work sheet (requirement form RCR), Hot work
permit, RA and management for change system

BBVN-FIVE-S2-SC-AMS- 14/09/23 14/09/30 14/10/03 MS-19-A-1: Chiller Area Works_Rev.3 Revised based on omments in Comments response table, Unload Chiller, Quang/Vuong B+C/B+C
0048/R3 (A) AMS-48/R2 dated 6-September-2014 Location of the activity, details
schedule/Manpower requirement, RCR service
pre-work/task observation sheet, Pre-task planning
work sheet (requirement form RCR), Hot work
permit, RA and management for change system

BBVN-FIVE-S2-SC-AMS- 14/06/05 14/07/04 Duct Vuong C


0048/R1 (B)
BBVN-FIVE-S2-SC-AMS- 14/07/14 14/07/19 14/07/21 MS-19 [A]-2: Duct Stage 1 Work on the Ceiling Clean Room Preparation works, installation platform/Duct, Quang/Ujiie/ C
0048/R2 (B) Area_Rev.2 Revised based on comments in AMS-0048/R1 (B) dated Locaiton of the activity, Details Vuong
4-July-2014 schedule/manpower requirement, RCR servicer
pre-work/task observation shet, Pre-task planning
work sheet (requirement from RCR), Document
reference, RA and management for change system

BBVN-FIVE-S2-SC-AMS- 14/09/09 14/09/16 14/09/19 MS-19 [A]-2: Duct Stage 1 Work on the Ceiling Clean Room Comments response table; Preparation works, Quang/Ujiie/ B
0048/R3 (B) Area_Rev.3 Revised based on comments in AMS-0048/R2 (B) dated installation Duct, Locaiton of the activity, Details Vuong
21-July-2014 schedule/manpower requirement &Tie-in list,
RCR servicer pre-work/task observation shet, Pre-
task planning work sheet (requirement from RCR),
Document referenced, RA and management for
change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 34
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/07/02 14/07/07 MS-19 [A]: Air Conditioning & Mechanical Ventilation System Unload AHU, PUMP, BUFFER Tank, details Quang/Ujiie/
0048/R1 (C ) _Rev.1 schedule/Manpower requirement, Location of the Vuong
MS-19-A-3: AHU Area Works activity, Procedure Firestop, RCR servicer pre-
work/task observation sheet, Pre-task planning
work sheet (requirement form RCR), Hot work
permit, Document Referenced, RA and
management for change system

BBVN-FIVE-S2-SC-AMS- 14/09/15 14/09/20 14/09/19 MS-19 [A]: Air Conditioning & Mechanical Ventilation System Comments response table; Unload AHU, Details Quang/Ujiie/ C
0048/R2 (C ) MS-19-A-3: AHU Work Area_Rev.2 _ Revised based on comments in schedule/Manpower requirement, Location of the Vuong
AMS-48/R1 (C ) dated 4-June-2014 activity, RCR servicer pre-work/task observation
sheet, Pre-task planning work sheet (requirement
form RCR), RA and management for change
system

BBVN-FIVE-S2-SC-AMS- 14/09/18 14/09/20 14/09/19 MS-19-A-3: AHU Work Area_Rev.2 _ Revised based on comments in Guidance the transportation and installation AHU Quang/Ujiie/ C
0048/R2 (C ) (ADD.01) AMS-48/R1 (C ) dated 4-June-2014_Additional Document (13A4pages_VNese), sketch/drawings (10A4size) Vuong

BBVN-FIVE-S2-SC-AMS- 14/09/24 14/10/01 14/10/07 MS-19-A-3.1: Assembly AHU Work Drawing AHU assebly work; AHU assembly Quang/Vuong B
0048 (D) instruction manual; List part by part assembly
AHU; Factory issue final QC check; Unload AHU;
Detail crane AVC 1 ton; Location of the activity;
Detail schedule/Manpower requirement; RCR
servicer pre-work/task observation sheet; Pre-task
planning work sheet (requirement from RCR);
Risk assessment and management for change
system

BBVN-FIVE-S2-SC-AMS-0049 14/06/24 14/06/28 14/06/26 MS-48: Temporary Concrete Road Method Statement; JSA/RS, Schedule Tuan Anh/Ba B
Hoa

BBVN-FIVE-S2-SC-AMS-0050 14/06/26 14/07/02 MS-49: Aluminum Panel Removal at Gridline 12 Method Statement, JSA/RA, Schedule Tuan Anh

BBVN-FIVE-S2-SC-AMS-0051 14/06/26 14/07/03 14/07/01 MS-22-A-1: Air Compressor System Installation Works, Procedure Fire Stop, Location Quang/Ujiie/ C
of the activity, Details shcedule/Manpower Trung
Requirement, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet,
document referenced, RA and maangement for
change system

BBVN-FIVE-S2-SC-AMS- 14/07/14 14/07/17 14/07/21 MS-22-A-1: Air Compressor System_Rev.1 Revised based on Installation Works, Procedure Fire Stop, Welding C
0051/R1 comments in AMS-51 dated 1-July-2014 Procedure G.I Pipe, Location of the activity,
Details shcedule/Manpower Requirement, RCR
servicer pre-work/task observation sheet, Pre-task
planning work sheet, document referenced, RA
and maangement for change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 35
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/07/30 14/08/06 14/08/12 MS-22-A-1: Air Compressor System_Rev.2Revised based on CommentIns table, Installation Works, Procedure Quang B
0051/R2 comments in AMS-51/R1 dated 21-July-2014 FireStop, Function test of Air Compressor,
Welding Procedure G.I Pipe & Copper pipe,
Location of the activity, Details
shcedule/Manpower Requirement, RCR servicer
pre-work/task observation sheet, Pre-task planning
work sheet, document referenced, RA and
maangement for change system

BBVN-FIVE-S2-SC-AMS-0052 14/06/27 14/07/03 14/07/03 MS-23: Installation Assembly Area Install Assembly Area, Location of the activity, Quang/Ujiie B
details schedule/manpower requirement, RCR pre-
work/task observation sheet, Pre-task planning
work sheet (requirement from RCR)

BBVN-FIVE-S2-SC-AMS-0053 14/06/30 14/07/04 14/07/03 MS-19-A-5: Installation Platform Install Platform, Install temporary floor, lovation Quang/Ujiie B
of the activit, Detail schedule/manpower
requirement, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet
(Requirement from RCR) & JSA

BBVN-FIVE-S2-SC-AMS-0054 14/06/30 14/07/04 14/07/02 MS-22-A-2: Installation of RO, Process Cooling Water Pipe above Detail installaiton works, Welding procedure PP-H Quang/Ujiie/ C
Ceiling Clean Room pipe, Welding procedure SUS pipe, Procedure Khoa
Firestop, Location of the activity, Details
scheudle/Manpower reuirement, RCR servicer pre-
work/task observation sheet, Pretask planning
work sheet, JSA

BBVN-FIVE-S2-SC-AMS- 14/07/07 14/07/18 14/07/10 MS-22-A-2: Installation of Process Cooling water pipe above ceiling Quang/Ujiie/ C
0054/R1 [A] clean room _ Rev.1 Khoa

BBVN-FIVE-S2-SC-AMS- 14/08/07 14/08/11 14/08/18 MS-22-A-2.1: Installation of Process Cooling water pipe above ceiling Comments response table, Detail installaiton Quang/Ujiie/ C
0054/R2 [A]_1 clean room _ Rev.2_STAGE 1 Revised based on comments in AMS- works, Welding procedure SUS pipe, Procedure Khoa
54/R1 [A] dated 10-July-2014 Firestop, Location of the activity, Details
schedule/Manpower reuirement, RCR servicer pre-
work/task observation sheet, Pre-task planning
work sheet, Risk Assessment and Management for
change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 36
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/09/25 14/10/02 14/10/03 MS-22-A-2.1: Installation of Process Cooling water pipe above ceiling Detail installaiton works, Welding procedure SUS Quang/Ujiie/ B
0054/R3 [A]_1 clean room _ Rev.3_STAGE 1 (Close Loop) Revised based on pipe, Procedure Firestop, Location of the activity, Khoa
comments in AMS-54/R2 [A] _1 dated 18-August-2014 Details schedule/Manpower reuirement, RCR
servicer pre-work/task observation sheet, Pre-task
planning work sheet, Document referenced; Risk
Assessment and Management for change system

BBVN-FIVE-S2-SC-AMS- 14/08/07 14/08/11 14/08/18 MS-22-A-2.2: Installation of Process Cooling water (Open Loop) Comments response table, Detail installaiton Quang/Ujiie/ C
0054/R2 [A]_2 pipe above ceiling clean room _ Rev.2_STAGE 1 Revised based on works, Welding procedure SUS pipe, Procedure Khoa
comments in AMS-57/R1 [A] dated 10-July-2014 Firestop, Location of the activity, Details
schedule/Manpower reuirement, RCR servicer pre-
work/task observation sheet, Pre-task planning
work sheet, Hot work permit, Document
Referenced, Risk Assessment and Management for
change system

BBVN-FIVE-S2-SC-AMS- 14/09/25 14/10/02 14/10/03 MS-22-A-2.2: Installation of Process Cooling water (Open Loop) Comments response table, Detail installaiton Quang/Ujiie/ B
0054/R3 [A]_2 pipe above ceiling clean room _ Rev.3_STAGE 1 Revised based on works, Welding procedure SUS pipe, Procedure Khoa
comments in AMS-57/R2 [A] dated 18-August-2014 Firestop, Location of the activity, Details
schedule/Manpower reuirement, RCR servicer pre-
work/task observation sheet, Pre-task planning
work sheet, Hot work permit, Document
Referenced, Risk Assessment and Management for
change system

BBVN-FIVE-S2-SC-AMS- 14/07/07 14/07/18 14/07/14 MS-22-A-3: Installation of RO Water Pipe above ceiling Clean Room Quang/Ujiie/ C
0054/R1 [B] _ Rev.1 Khoa
BBVN-FIVE-S2-SC-AMS- 14/07/30 14/08/06 MS-22-A-3: Installation of RO Water Pipe above ceiling Clean Room Detail installaiton works, Welding procedure PP-H Quang/Ujiie/
0054/R2 [B] _ Rev.2 Revised based on comments in AMS-54/R1 (B) dated 14- pipe, Procedure Firestop, Location of the activity, Khoa
July-2014 (STAGE 1) Details scheudle/Manpower reuirement, RCR
servicer pre-work/task observation sheet, Pretask
planning work sheet, Hot work permit, Document
reference, JSA

BBVN-FIVE-S2-SC-AMS-0055 14/07/01 14/07/05 14/07/08 MS-BLD.06-B: Reinforcement Concrete Septic Tank Method Statement for Septic tank, Equipment List, Tuan Anh B
Schedule, JSA/Risk Assessent

BBVN-FIVE-S2-SC-AMS-0056 14/07/07 14/07/12 14/07/09 MS-39: Electrical System - Temporary Work for Stage 1 Electrical Method, Equipment list, RCR services Quang/Ujiie/ C
pre-work/task observation sheet, Pre-task planning Diem
worksheet
BBVN-FIVE-S2-SC-AMS- 14/07/10 14/07/12 14/07/15 MS-39: Electrical System - Temporary Work for Stage 1_Rev.1 Electrical Method, Equipment list, Details B
0056/R1 Revised based on comments in AMS-56 dated 9-July-2014 schedule/Manpower requirement, JSA for
electrical system temporary for stage 1, RCR
services pre-work/task observation sheet, Pre-task
planning worksheet, Drawings for installation
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 37
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/07/25 14/07/30 14/07/31 MS-39: Electrical System - Temporary Work for Stage 1_Rev.1 6A3size drawings Quang/Diem/ B/A
0056/R1 (ADD) (Supplimental Shop Drawing) Based on comments in AMS-56 dated Ujiie
15-July-2014

BBVN-FIVE-S2-SC-AMS-0057 14/07/09 14/07/14 14/07/22 MS-BLD.02 - Demolition Works at Grid Line 12 Method Statement, RA/JSA, Internal, External Tuan Anh C
Scaffolding Calculation & Drawings, Clean Panel
Protection, Wall & Column Demolition

BBVN-FIVE-S2-SC-AMS- 14/08/04 14/08/06 14/08/15 MS-BLD.02 - Demolition Works at Grid Line 12_Rev.1 Revised Comments response table, Method Statement, Tuan Anh B
0057/R1 based on commnets in AMS-57 dated 22-July-2014 RA/JSA, Internal/ External Scaffolding
Calculation & Drawings, Clean Panel Protection,
Wall & Column Demolition

BBVN-FIVE-S2-SC-AMS- 14/08/11 14/08/15 MS-BLD.02 - Demolition Works at Grid Line 12_Rev.1 (Additional Hanging Cable Data Sheet & Method for Column Tuan Anh
0057/R1 (ADD.01) document) Revised based on commnets in AMS-57 dated 22-July- Hanging
2014

BBVN-FIVE-S2-SC-AMS-0058 14/07/10 14/07/17 14/07/15 MS-39B: Lighting System Temporary Work for Stage 1 Lighting System Method, MSE-01:Terminal wire Quang/Diem B/B+C
connection, MSE-02: Insulation testing,
Equipment List, JSA
BBVN-FIVE-S2-SC-AMS- 14/07/25 14/07/30 14/07/31 MS-39B: Lighting System Temporary Work for Stage 1 (Supplimental 3A3size drawings Quang/Diem B
0058 (ADD) Shop Drawing) Based on comments in AMS-58 dated 15-July-2014

BBVN-FIVE-S2-SC-AMS-0059 14/07/10 14/07/15 14/07/19 MS-BLD.11 - Masonry & Plastering Works Method Statement, RA/JSA, Schedule Phuc C
BBVN-FIVE-S2-SC-AMS- 14/07/22 14/07/24 14/07/24 MS-BLD.11 - Masonry & Plastering Works_Rev.1 Revised based on Method Statement, RA/JSA, Schedule Phuc C/B
0059/R1 comments in AMS-59 dated 19-July-2014
BBVN-FIVE-S2-SC-AMS- 14/07/25 14/07/30 14/07/28 MS-BLD.11 - Masonry & Plastering Works_Rev.2 Revised based on Method Statement, RA/JSA, Schedule Phuc B
0059/R2 comments in AMS-59/R1 dated 24-July-2014
BBVN-FIVE-S2-SC-AMS- 14/08/06 14/08/09 14/08/18 MS-BLD.11 - Masonry & Plastering Works_Rev.2 (Additional 1A3size drawing (Execution Method for Brick Phuc/Nguyen C
0059/R2 (ADD.01) Drawing) Revised based on comments in AMS-59/R1 dated 24-July- Wall)
2014

BBVN-FIVE-S2-SC-AMS-0060 14/07/15 14/07/21 14/07/21 Method Statement for Welding Procedure Plan Welding Procedure Specification (WPS), Welder Quang/Ujiie C
list & Certificates, Welding Report, JSA

BBVN-FIVE-S2-SC-AMS- 14/08/07 14/08/12 14/08/18 Method Statement for Welding Procedure Plan_Rev.1 Revised based Welding Procedure Specification (WPS), Welder Quang/Ujiie B
0060/R1 on comments in AMS-60 dated 21-July-2014 list & Certificates, Welding Report, JSA

BBVN-FIVE-S2-SC-AMS-0061 14/07/16 14/07/21 14/07/25 MS-22-B-1: Air Compressor System Installation works, Welding Procedure G.I pipe, Quang/Ujiie/ C
Location of the activity, Details Trung
schedule/Manpower requirement, Document
referenced, JSA
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 38
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS- 14/08/22 14/08/25 14/08/27 MS-22-B-1: Air Compressor System_Rev.1 Revised based on Comments response table; Installation works, Quang/Ujiie/ B
0061/R1 comments in AMS-61 dated 25-July-2014 Welding Procedure, Location of the activity, Trung
Details schedule/Manpower requirement,
Document referenced, JSA

BBVN-FIVE-S2-SC-AMS-0062 14/07/17 14/07/21 14/07/25 MS-22-B-2: Installation of Process Cooling Water Pipe above Ceiling Detail installation works, welding procedure SUS quang/ujiie C
Clean Room (Stage 2) pipe, Location of the activity, details
schedule/Manpower requirement, document
reference, JSA
BBVN-FIVE-S2-SC-AMS- 14/08/27 14/09/01 MS-22-B-2: Installation of Process Cooling Water Pipe above Ceiling Comments response table; Detail installation quang/ujiie
0062/R1 Clean Room (Stage 2)_Rev.1 Revised based on comments in AMS-62 works, welding procedure SUS pipe (GTAW),
dated 25-July-2014 ITP, Location of the activity, details
schedule/Manpower requirement, document
reference, JSA

BBVN-FIVE-S2-SC-AMS-0063 14/07/17 14/07/21 14/07/28 MS-22-B-3: Installation of R.O Water Pipe above Ceiling Clean Detail installation works, welding procedure PP-H Quang/Ujiie/ C
Room_Stage 2 pipe, Location of the activity, details Khoa
schedule/Manpower requirement, document
reference, JSA
BBVN-FIVE-S2-SC-AMS- 14/09/15 14/09/21 14/09/22 MS-22-B-3: Installation of R.O Water Pipe above Ceiling Clean Detail installation works, welding procedure PP-H Quang/Ujiie/ B
0063/R1 Room_Stage 2_Rev.1 Revised based on comments in AMS_0063 pipe, Location of the activity, details Khoa
dated 28-Jul-2014 schedule/Manpower requirement, document
reference, JSA

BBVN-FIVE-S2-SC-AMS-0064 14/07/18 14/07/23 14/08/18 MS-50: Honeycomb Treatment Product Datasheet Tuan Anh B

BBVN-FIVE-S2-SC-AMS-0065 14/07/25 14/07/30 14/08/07 MS-BLD.51- Demolition Work for Office Area & Column A12 Method Statement for Demolition Works; Method Tuan Anh C
Statement for Temporary Panel; Risk Assessment
and JSA, , Drawings
BBVN-FIVE-S2-SC-AMS- 14/09/09 14/09/15 14/09/19 MS-BLD.51- Demolition Work for Office Area & Column Method Statement for Demolition Works; Method T. Anh C
0065/R1 A12_Rev.1 Revised based on comments in AMS-65 dated 7-August- Statement for Temporary Panel; Risk Assessment
2014 and JSA, Organizational Chart, Schedule

BBVN-FIVE-S2-SC-AMS- 14/09/25 14/10/02 14/10/09 MS-BLD.51- Demolition Work for Office Area & Column Appendix 1: Method Statement for Demolition T. Anh B
0065/R2 A12_Rev.2 Revised based on comments in AMS-65/R1 dated 19- Works; Appendix 2: Method Statement for
September-2014 Temporary Panel; Appendix 3: Risk Assessment
and JSA; Appendix 4: Organization Chart,
Appendix 5: Schedule

BBVN-FIVE-S2-SC-AMS-0066 14/07/30 14/08/06 14/08/04 MS-19-C: Remove Equipment No Used inside AHU Room Remove Works, Location of the Activity, Details Ujiie, Quang B
schedule/Manpower requirement, RCR servicer
pre-work/task observation sheet, Pre-task planning
work sheet (requirement from RCR), Hot work
permit
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 39
Issued Required Received
Reply

BBVN-FIVE-S2-SC-AMS-0067 14/07/30 14/08/06 14/07/31 MS-19-A-6: Method Statement for Tie-in No.: 2.1, 2.2, 2.3 Schedule Material List, Tie-in List, Drawing, RCR Quang C
servicer pre-work/ task observation sheet, pre-task
planning work sheet (requirement from RCR),
Document referenced, Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS- 14/08/05 14/08/09 14/08/07 MS-19-A-6: Method Statement for Tie-in No.: 2.1, 2.2, 2.3_Rev.1 Comments response table, Schedule Material List, Quang B
0067/R1 Revised based on comments in AMS-67 dated 31-July-2014 Tie-in List, Drawing, RCR servicer pre-work/ task
observation sheet, pre-task planning work sheet
(requirement from RCR), Document referenced,
Risk assessment and management for change
system

BBVN-FIVE-S2-SC-AMS- 14/08/09 Additional document (refer to TS 179 dated 12-Aug-2014)


0067/R1 (ADD01)

BBVN-FIVE-S2-SC-AMS-0068 14/07/30 14/08/06 14/08/06 MS-19-A-7: Method Statement for Tie-in No.: 3.1, 3.2, 3.3 Schedule Material List, Tie-in List, Drawing, RCR Quang C
servicer pre-work/ task observation sheet, pre-task
planning work sheet (requirement from RCR),
Document referenced, Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS- 14/08/08 14/08/13 14/08/11 MS-19-A-7: Method Statement for Tie-in No.: 3.1, 3.2, 3.3_Rev.1 Comments response table, Schedule Material List, Quang B
0068/R1 Revised based on comments in AMS-68 dated 6-Aug-2014 Tie-in List, Drawing, RCR servicer pre-work/ task
observation sheet, Pre-task planning work sheet
(requirement from RCR), Document Referenced,
Risk assessment and management for change
system

BBVN-FIVE-S2-SC-AMS-0069 14/08/06 14/08/09 14/08/14 MS-BLD.53_Wall Penetration on Grid 3 MS for Scaffolding; MS for Wall Penetration on Nguyen/Tuan B
Grid 3; Risk Assessment and JSA Anh

BBVN-FIVE-S2-SC-AMS-0070 14/08/08 14/08/13 14/08/14 MS-21-A-2: Method Statement for Tie-in No.: 15.1, 15.2, 15.3, 15.4, Schedule Material List, Tie-in List, Drawing, Quang B
15.5 Installation Work, Fire Stop mortar, RCR servicer
pre-work/ task observation sheet, Pre-task
planning work sheet (requirement from RCR), Hot
work permit, Red tag permit, Risk assessment and
management for change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 40
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0071 14/08/07 14/08/13 14/08/18 MS-19-D: Relocation Duct Inside Electric Room (Tie-In 22) Relocation Works; Location of the activity; Details Quang/Diem B
schedule/Manpower requirement; RCR servicer
pre-work/task observation sheet; Pre-task planning
work sheet (requirement from RCR), JSA

BBVN-FIVE-S2-SC-AMS-0072 14/08/07 14/08/13 14/08/12 MS-19-A-8: Method Statement for Tie-in No.: 1.1, 1.2 Schedule Material List, Tie-in List, Drawing, RCR Quang/Trung B
servicer pre-work/ task observation sheet, Pre-task
planning work sheet (requirement from RCR),
Document Referenced, Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS-0073 14/08/08 14/08/13 14/08/14 MS-19-A-9: Method Statement for Tie-in No.: 9.1, 9.2, 9.3 Schedule Material List, Tie-in List, Drawing, RCR Quang/Ujiie B
servicer pre-work/ task observation sheet, Pre-task
planning work sheet (requirement from RCR),
Document Referenced, Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS-0074 14/08/09 14/08/14 14/08/14 MS-19-A-11: Method Statement for Tie-in No: 11.1, 11.2 Schedule Material List, Tie-in List, Drawing, RCR Quang/Ujiie B
servicer pre-work/ task observation sheet, Pre-task
planning work sheet (requirement from RCR),
Document Referenced, Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS-0075 14/08/09 14/08/14 MS-24.1 HV Connection for transformer TX-2 Detail schedule/ Main Power Requirements, Quang/Ujiie
MSE.1: Marking location at site, MSE.2: Method
of cutting-off the main power, MSE.3: Method of
re-opening the existing holes, MSE.4: Method of
cabling works, MSE.5: Method of cable and
termination works, Job safety analysis, Risk
Assessment and Management for Change System

BBVN-FIVE-S2-SC-AMS-0076 14/08/09 14/08/14 14/08/14 MS-21-A-3: Method Statement for Tie-in No: 16.1, 16.2 Schedule Material List, Tie-in List, Drawing, Quang/Ujiie B
Installation work, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet
(Requirement from RCR), Hot work permit, Red
tag permit, Risk assessment and management for
change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 41
Issued Required Received
Reply

BBVN-FIVE-S2-SC-AMS-0077 14/08/11 14/08/16 14/08/23 MS-19-B-2: Duct Works_Stage 2 Method Duct Works; Installation Works; Location Quang/Vuong C
of the activity; Details schedule/Manpower
requirement; Document referencedl JSA

BBVN-FIVE-S2-SC-AMS- 14/08/29 14/09/05 14/09/16 MS-19-B-2: Duct Works_Stage 2_Rev.1 Revised based on comments Comments response table; Method Duct Works; Quang/Vuong C
0077/R1 in AMS-77 dated 23-August-2014 Installation Works; Location of the activity;
Details schedule/Manpower requirement;
Document referenced; JSA

BBVN-FIVE-S2-SC-AMS-0078 14/08/12 14/08/16 14/08/20 MS-21-A-4: Method Statement for Tie-in No.: 17.1, 17.2 Schedule Material List, Tie-in List, Drawing, Quang/Tuan/ C
Installation work, RCR servicer pre-work/task Trung
observation sheet, Pre-task planning work sheet
(Requirement from RCR), Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS- 14/08/21 14/08/23 14/08/21 MS-21-A-4: Method Statement for Tie-in No.: 17.1, 17.2_Rev.1 Appendix4. Plug Sprinkler Head for roof above Quang/Tuan/ B/A
0078/R1 Revised based on comments in AMS-78 dated 20-August-2014 clean room, JSA Trung

BBVN-FIVE-S2-SC-AMS-0079 14/08/12 14/08/16 14/08/19 MS-31: Tie-in List of Fire Detection and Alarm System Details Schedule/Manpower Requirements; Tie-in Quang/Ujiie B
works detail table; Plan of Tie-in List; Detail of
installation for tie-in list; detail of cable
termination; JSA; Risk assessment and
management for change system; RCR services pre-
work/task observation sheet; pre-task planning
worksheet; Red tag permit

BBVN-FIVE-S2-SC-AMS-0080 14/08/14 14/08/16 14/08/21 MS-BLD.54: Plinth Construction MS for Temporary Canvas protection; MS for Nguyen B
Installing rebar and formwork; MS for casting
concrete; JSA and Risk Assessment

BBVN-FIVE-S2-SC-AMS-0081 14/08/15 14/08/22 14/08/28 MS-19-A-10: Method Statement for Tie-in No.: 4.1, 4.2, 4.3 Schedule Material List, Tie-in List, Drawing, RCR Quang/Khoa B
servicer pre-work/task observation sheet, Pre-task
planning work sheet (Requirement from RCR),
Document Referenced, Risk assessment and
management for change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 42
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0082 14/08/18 14/08/22 14/08/26 MS-20-A-3: Method Statement for Tie-in No. 20.1, 20.2, 20.3 Schedule Material List, Tie-in List, Drawing, RCR Quang/Ujiie B
servicer pre-work/task observation sheet, Pre-task
planning work sheet (Requirement from RCR),
Hot work permit, Document Referenced, Risk
assessment and management for change system

BBVN-FIVE-S2-SC-AMS-0083 14/08/18 14/08/19 14/08/26 MS-19-A-13:Method Statement for Tie-in No.: 5.1, 5.2, 5.3, 5.4, 5.5, Schedule Material List, Tie-in List/Details Quang/Ujiie B
5.6 schedule, Drawing, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet
(Requirement from RCR), Document Referenced,
Risk assessment and management for change
system, Hot Work Permit, Red Tag permit

BBVN-FIVE-S2-SC-AMS-0084 14/08/18 14/08/19 14/09/02 MS-19-A-13: Method Statement for Tie-in No.: 21.1 (R.O Water Tie-in List/Detaila Schedule; Schedule Material Quang/Ujiie N/A
System) List, Drawing, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet,
Hot work permit, Document Referenced, Risk
assessment and management for change system

BBVN-FIVE-S2-SC-AMS-0085 14/08/18 14/08/23 MS-22-A-4: Method Statement for Tie-in No.: 7.1, 7.2 Tie-in List/Details Schedule; Schedule Material Quang/Ujiie
List, Drawing, RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet,
Document Referenced, Risk assessment and
management for change system

BBVN-FIVE-S2-SC-AMS-0086 14/08/18 14/08/20 14/08/19 MS-21-A-5: Method Statement for Tie-in No.: 18.1, 18.2 Schedule Material List, Tie-in List, Drawing, Quang/Ujiie B
Installation work; RCR servicer pre-work/task
observation sheet, Pre-task planning work sheet
(Requirement from RCR), Hot Work Permit, Red
Tag permit; Risk assessment and management for
change system

BBVN-FIVE-S2-SC-AMS- 14/08/21 14/08/23 MS-21-A-5: Method Statement for Tie-in No.: 18.1, 18.2 (FINAL Comments Response table; Schedule Material List, Quang/Ujiie
0086 (FINAL) Document) Tie-in List, Drawing, Installation work; RCR
servicer pre-work/task observation sheet, Pre-task
planning work sheet (Requirement from RCR),
Hot Work Permit, Red Tag permit; Risk
assessment and management for change system
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 43
Issued Required Received
Reply

BBVN-FIVE-S2-SC-AMS-0087 14/08/18 14/08/20 14/08/29 MS-22-A-5: Method Statement for Tie-in No.: 6.1, 6.2 Tie-in List/Details Schedule; Schedule Material Quang/Ujiie B
List, Welding Procedure SUS Pipe; Drawing, RCR
servicer pre-work/task observation sheet, Pre-task
planning work sheet, Hot work permit; Document
Referenced, Risk assessment and management for
change system

BBVN-FIVE-S2-SC-AMS-0088 14/08/19 14/08/22 14/08/22 MS-36-2: LV Busway 3200A Installation MSE.1: Method of unloading LV Busway; MSE.2: Quang/Diem/ B
Mehtod of making wall opening hole; MSE.3: Ujiie
Method of busway installation; JSA; Risk
Assessment and management for change system

BBVN-FIVE-S2-SC-AMS-0089 14/08/19 14/08/22 14/08/23 MS-24.2: LV Busway 3200A Connection from Transformer TX-2 to Site organization chart; Detailed Quang/Ujiie/ C
MSB-A/BUS_2 schedule/Manpower requirement; Material list; Diem
MSE.1: Location plan of work; MSE.2: Method of
cutting-off the main power; MSE.3: Method of
installing the flanged-end units; MSE.4: Detail of
busway connection; JSA; Risk Assessment and
Management for Change system

BBVN-FIVE-S2-SC-AMS- 14/08/26 14/08/30 14/08/28 MS-24.2: LV Busway 3200A Connection from Transformer TX-2 to Comments response table; Site organization chart; Quang/Ujiie/ B
0089/R1 MSB-A/BUS_2_Rev.1 Revised based on comments in AMS-89 dated Detailed schedule/Manpower requirement; Diem
23-August-2014 Material list; MSE.1: Location plan of work;
MSE.2: Method of cutting-off the main power;
MSE.3: Method of installing the flanged-end units;
MSE.4: Detail of busway connection; JSA; Risk
Assessment and Management for Change system

BBVN-FIVE-S2-SC-AMS-0090 14/08/20 14/08/27 14/09/04 MS-BLD.20: Clean Room - Finishing Works Ceiling & Partition Wall Drawing for ceiling & Partition Wall; Products Tuan Anh C
Data sheet; Risk Assessment and JSA

BBVN-FIVE-S2-SC-AMS- 14/09/11 14/09/17 14/09/26 MS-BLD.20: Clean Room - Finishing Works Ceiling & Partition Appendix 1: Drawing for Ceiling & Partition Tuan Anh B
0090/R1 Wall_Rev.1 Revised based on comments in AMS-90 dated 4- Wall; Appendix 2: Products Data Sheet; Appendix
September-2014 3: Risk Assessment and JSA
OUTGOING Rev. Date Date INCOMING Date Title Statement
Approval for Method Attachment Prepared by Status 44
Issued Required Received
Reply
BBVN-FIVE-S2-SC-AMS-0091 14/08/20 14/08/25 14/08/26 MS-19-A-12: Method Statement for Tie-in No.: 8.1,8.2,8.3 Tie-in List/Details Schedule; Schedule Material Quang/Ujiie/ B
List, Drawing, RCR servicer pre-work/task Khoa
observation sheet, Pre-task planning work sheet,
Document Referenced, Hot work permit, Risk
assessment and management for change system

BBVN-FIVE-S2-SC-AMS-0092 14/08/20 14/08/25 14/08/26 MS-24.1: HV Connection for Transformer TX-2 (Tie-in 24.1) Site organization chart; Detailed Quang/Ujiie/ B
schedule/Manpower requirement; Material list; Diem
MSE.1: Working Location at site; MSE.2: Method
of cutting-off the main power; MSE.3: Method of
re-opening the existing holes; MSE.4: Method of
cabling works; MSE.5: Method of cable and
termination works; JSA; Risk Assessment and
Management for Change system

BBVN-FIVE-S2-SC-AMS-0093 14/08/20 14/08/25 14/08/26 MS-21-B-2: Welding Procedure Plan (GTAW) Welding Procedure Specification (WPS); Welder Quang/Ujiie/ B
list & Certificates; Welding Report Khoa

BBVN-FIVE-S2-SC-AMS-0094 14/08/21 14/08/25 MS-21-A-6: Method Statement for Tie-in No.: 19.1, 19.2 Schedule Material List, Tie-in List, Drawing, Quang/Ujiie/khoa
Installation work, RCR servicer pre-work/task
observation sheet, Pre-task planning work
sheet,Hot work permit, Red tag permit, Risk
assessment and management for change system

BBVN-FIVE-S2-SC-AMS-0095 14/08/22 14/08/25 14/08/29 MS-BLD.52: Warehouse Wall Demolition for Roller Shutter Drawing for Demolition works, Organization T.Anh B
Chart, Risk Assessment and JSA; FRI No.183
Approval for Project Document 45
OUTGOING Rev. Date Issued Date Required INCOMING Title Attachments Author/Delivered Status Date Delivered
Reply Date Issued to to Author

BBVN-FIVE-S2-SC-APD-0013 14/03/18 List of Mock-up Mr. Tung

14/03/20 List of Mock-up C

BBVN-FIVE-S2-SC- 14/03/26 14/04/01 List of Mock-up_rev.1


APD-0013/R1
14/04/02 List of Mock-up_rev.1 B

BBVN-FIVE-S2-SC-APD- 14/09/19 14/09/26 14/10/04 List of Mock-up_Rev.1 Updated based on actual condition 3A4size pages Tung C
0013/R1 (Revised)

BBVN-FIVE-S2-SC-APD- 14/10/11 14/10/18 14/10/28 List of Mock-up_Rev.2 Revised based on comments in APD-13/R1 (Revised) dated 4- 4A4size pages Tung B
0013/R2 (Revised) October-2014

BBVN-FIVE-S2-SC-APD-0014 14/03/20 Procurement Plan Mr. Mark

14/03/25 Procurement Plan C

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 14/05/07 Procurement Plan_Rev.1 Revised based on comments in APD-0014 dated 25-Mar- Tung C
APD-0014/R1 2014
BBVN-FIVE-S2-SC- 14/05/15 14/05/19 14/05/21 Procurement Plan_Rev.2 Revised based on comments in APD-0014/R1 dated 07-May- Tung B
APD-0014/R2 2014

BBVN-FIVE-S2-SC-APD-0015 14/03/24 14/03/26 Signature Flowchart Ms. Hau

Signature Flowchart A

BBVN-FIVE-S2-SC-APD-0016 14/03/19 Company profile for Space Frame and Paint (TOA) Mr. Tung

14/03/25 Company profile for Space Frame and Paint (TOA) B

BBVN-FIVE-S2-SC-APD-0017 14/03/24 14/03/25 Road & Drainage System Level based on Pre-condition Survey Result 4A3 drawings for road, 4A3 drawings for drainage Mr. Le/Mr. Thanh (Superseded
system )

BBVN-FIVE-S2-SC-APD-0018 14/03/25 QCP for Steel Strutural Work (QCP-3) Quality Control Documents of Seico (Steel Structural Mrs. Lan
Manufacture)
14/03/31 QCP for Steel Strutural Work (QCP-3) C

BBVN-FIVE-S2-SC- 14/04/02 14/04/07 Profile of Authority Unit for NDT inspector for steel structural works_Rev.1 (based on
APD-0018/R1
11-Apr-14 Profile of Authority Unit for NDT inspector for steel structural works_Rev.1 (based on C 12-Apr-14

BBVN-FIVE-S2-SC- 14/04/03 14/04/07 QCP for Fabrication Structural Steel in SEICO Factory Welding Procedure Specification, Welder List & Mrs. Lan
APD-0018/R1 (II) Certificatess
11-Apr-14 QCP for Fabrication Structural Steel in SEICO Factory C 12-Apr-14
Approval for Project Document 46
OUTGOING Rev. Date Issued Date Required INCOMING Title Attachments Author/Delivered Status Date Delivered
Reply Date Issued to to Author

BBVN-FIVE-S2-SC- 14/04/19 14/04/25 QCP-3(1): Quality Control Plan for Fabrication structural steel in Seico factory_Rev.2
APD-0018/R2 QCP-3(2): Quality Control Plan for Assembly and Erection Structural steel on
site_Rev.1
NDT Laboratory: THT Technology and Services Engineering JSC (English Version)

14/04/28 QCP-3 (full) Mrs. Lan B

BBVN-FIVE-S2-SC-APD-0019 14/03/27 New Gridline based on Survey Existing Factory 1 A4 photo, 1 A3 drawing, 1A3 page benchmark layout, Mr. Nguyen/Mr.
2 A3 size pages of cordinates, 6 A3size drawings Chien

14/03/29 New Gridline based on Survey Existing Factory C

BBVN-FIVE-S2-SC- 14/03/31 14/04/01 New Gridline 7 A3 size drawings Mr. Nguyen


APD-0019/R1
14/04/02 New Gridline B

BBVN-FIVE-S2-SC-APD-0020 14/03/27 14/03/31 Master Schedule & Manpower 12 A3 size pages Mr. Tu

14/04/15 Master Schedule & Manpower 11A3size pages C

BBVN-FIVE-S2-SC- 14/04/29 14/05/02 14/05/08 Master Schedule & Manpower_Rev.1 Revised based on comments in APD_0021 dated 11A3size pages Mr. Tu/Cuong C
APD-0020/R1 15-APR-2014
BBVN-FIVE-S2-SC- 14/05/12 14/05/15 14/05/15 Master Schedule & Manpower_Rev.2 Revised based on comments in APD_0020/R1 11A3size pages Mr. Tu/Cuong B
APD-0020/R2 dated 8-May-2014

BBVN-FIVE-S2-SC-APD-0021 14/03/31 14/04/01 Cash Flow 1A3 size page Tung/Mr. Nguyen

14/04/03 Cash Flow 1A3 size page

BBVN-FIVE-S2-SC-APD-0022 14/03/31 Additional Documents required in APD-0011 dated 14/03/24 dated 24-Mar-2014: 2 business certificates(Luong Tung
Thanh Dong & Kinh Viet), 2 companies profiles (Vinh
Hiep Hung & Doan Thanh)

14/04/03 Additional Documents required in APD-0011 dated 14/03/24 B

BBVN-FIVE-S2-SC-APD-0023 14/04/01 14/04/04 List of Materials 25 A4 pages Mr. Tung

14/04/25 List of Materials B

BBVN-FIVE-S2-SC-APD-0024 14/04/04 14/04/08 Package List of the Project 1A3 size pages Mr. Tung

11-Apr-14 Package List of the Project C 12-Apr-14

BBVN-FIVE-S2-SC- 14/04/28 14/05/05 14/05/07 Package List of the Project_Rev.1 Reivsed based on comments in APD-0024 dated 11- 1A3 size pages Tung A/B
APD-0024/R1 Apr-2014

BBVN-FIVE-S2-SC-APD-0025 14/04/08 14/04/18 Clean Construction Protocol for Clean Room 1A3size page Mrs. Lan
Approval for Project Document 47
OUTGOING Rev. Date Issued Date Required INCOMING Title Attachments Author/Delivered Status Date Delivered
Reply Date Issued to to Author

11-Apr-14 Clean Construction Protocol for Clean Room C 12-Apr-14

BBVN-FIVE-S2-SC- 14/04/29 14/05/05 14/05/09 Clean Construction Protocol for Clean Room_Rev.1 Revised based on comments in Access Layout 4A3size drawings Mrs. Lan B/C
APD-0025/R1 APD-0025 dated 14-Apr-2014

BBVN-FIVE-S2-SC-APD-0026 14/04/08 14/04/10 Work permit forms: (2 + 2 + 4 + 2 + 2 + 2 + 2) A4size Pages Hoang safety
Forms including (i) Parent Work Permit, (ii) Hot Work Permit, (iii) Work At Height
Permit, (iv) Confined Space Permit, (v) Lifting Permit, (vi) Excavation Permit, (vii)
Demolition Permit
14/04/14 Work permit forms:Forms including (i) Parent Work Permit, (ii) Hot Work Permit, (iii) Work At Height Permit, (iv) Confined Space Permit, (v) Lifting Permit, (vi) Excavation Permit, (vii) Demolition Pe
B

BBVN-FIVE-S2-SC- 14/04/25 14/05/02 14/04/26 Work permit forms: Additional 2 Forms (Based on comments in APD-0026 dated 14- Chemical Registration, Checmical Use Declaration & Hoang safety B/A
APD-0026 (ADD) Apr-2014) Work at Height Permit

BBVN-FIVE-S2-SC-APD-0027 08-Apr-14 11-Apr-14 Report of Taking Photograph and Surveying actual quality of B. Braun Five AP Construction Site Stage No.2 Mr. Tu

11-Apr-14 Report of Taking Photograph and Surveying actual quality of B. Braun Five AP Construction Site Stage No.2 B 12-Apr-14

BBVN-FIVE-S2-SC- 14/04/15 Report of Taking Photograph and Surveying actual quality of B. Braun Five AP Construction Site Stage No.2 Mr. Tu
APD-0027 (ADD)

BBVN-FIVE-S2-SC-APD-0028 11-Apr-14 12-Apr-14 Roofing System for FM Global Approval. Roof Nav Assembly No. 237498-0-0 Mr. Tung

14/04/15 Roofing System for FM Global Approval. Roof Nav Assembly No. 237498-0-0 19A3 size drawings C

BBVN-FIVE-S2-SC- 14/04/28 14/05/02 14/05/14 Roofing System for FM Global Approval. Roof Nav Assembly No. 237498-0-0_Rev1 Hard rock 80 for roof insulation, Sika Membrance, Mr. Tung B
APD-0028/R1 revised based on comments in APD-0028 dated 15-APR-2014 Fastener (Catalogue & Datasheet), V125 Decking +
11A3size drawings

BBVN-FIVE-S2-SC-APD-0029 14/04/15 14/04/17 Inspection Form for Earthwork & RC Work (7 forms) Pre-Concrete Inspection, RC Inspection, Formwork Mr. Hoang
Inspection, Puring Concrete on Site, Inspection, Final
Concrete Inspection, Backfill Inpection Record,
Excavation Inspection Record
14/04/21 Inspection Form for Earthwork & RC Work (7 forms) B

BBVN-FIVE-S2-SC- 14/04/23 14/04/26 Inspection Form for Earthwork & RC Work (9 forms)_Additional & Revised based on Pre-Concrete Inspection, RC Inspection, Formwork Tuan Anh
APD-0029 (ADD) comments in APD_0029 dated 24-Apr-2014 Inspection, Puring Concrete on Site, Inspection, Final
Concrete Inspection, Backfill Inpection Record,
Excavation Inspection Record, Lean Concrete
Inspection, Minutes for Material/Equipment Inspection
& Acceptance Reports
14/04/29 Inspection Form for Earthwork & RC Work (9 forms)_Additional & Revised based on Tuan Anh A
comments in APD_0029 dated 24-Apr-2014
Approval for Project Document 48
OUTGOING Rev. Date Issued Date Required INCOMING Title Attachments Author/Delivered Status Date Delivered
Reply Date Issued to to Author

BBVN-FIVE-S2-SC-APD-0030 14/04/15 14/04/17 Clashing Point Check Duct vs Steel Structure (11 items), Duct vs Fire Fighting Mr. Giang/Mr.
(10 items), Cable Ladder/tray vs Structure (8 items) Thanh

14/04/17 Clashing Point Check C

BBVN-FIVE-S2-SC- 14/04/29 14/05/06 Clashing Point Check_Rev.1 Revised based on comments in APD-0030 dated 14-Apr- Mr. Giang/An
APD-0030/R1 2014

BBVN-FIVE-S2-SC-APD-0031 14/04/18 14/04/22 LAS298 profile for Geotextile Test LAS 298 Profile Mrs. Lan/Hoang

14/04/25 LAS298 profile for Geotextile Test B

BBVN-FIVE-S2-SC-APD-0032 14/04/18 14/04/22 LAS201 profile for Testing thickness of zinc coat for purlin LAS 201 Profile Mrs. Lan/Hoang

14/04/25 LAS201 profile for Testing thickness of zinc coat for purlin B

BBVN-FIVE-S2-SC-APD-0033 14/04/21 14/04/23 Temporary Road for Construction Work A3 size drawing Mr. Ba Hoa

14/04/23 Temporary Road for Construction Work C/B

BBVN-FIVE-S2-SC- 14/04/24 14/05/02 Temporary Road for Construction Work_Rev.1 (Revised based on comments in APD- Mr. Ba Hoa
APD-0033/R1 0033 dated 23/04/2014
14/04/25 Temporary Road for Construction Work_Rev.1 (Revised based on comments in APD- B
0033 dated 23/04/2014

BBVN-FIVE-S2-SC-APD-0034 14/04/21 14/04/26 General JSA & Risk Assessment Shimizu 31 items of work Mr. Hoang Safety

14/04/23 General JSA & Risk Assessment Shimizu C

BBVN-FIVE-S2-SC- 14/05/14 14/05/16 14/05/19 General JSA & Risk Assessment Shimizu_Rev.1 Revised based on comments in APD- 61 Activities Hoang Safety C
APD-0034/R1 0034 dated 23-Apr-2014
BBVN-FIVE-S2-SC- 14/05/28 14/06/02. 14/06/02 General JSA & Risk Assessment Shimizu_Rev.2 Revised based on comments in APD- Additional Document required (9 activities + Fire Hoang Safety B
APD-0034/R2 0034 dated 19-May-2014 extinguisher point location on site - 4A3size drawings)

BBVN-FIVE-S2-SC-APD-0035 14/04/24 14/04/25 Proportion Mix Concrete for Construction (M20 10±2, M30 10±2, M30 14±2, M40 Concrete Testing report, Cement testing report, Fine Hoang
10±2, M40 14±2) aggregate testing report, Coarse aggregate testing report,
Water aggregate testing, Admixture specification for
trial mix

14/04/28 Proportion Mix Concrete for Construction (M20 10±2, M30 10±2, M30 14±2, M40 A
10±2, M40 14±2)
Approval for Shop Drawing 49
OUTGOING Rev. Date Issued Required INCOMING Title Attachment Author/Delivered to Status Date Delivered
Replied Date Issued Date to Author

BBVN-FIVE-S2-SC-ASD-173(ADD.01) 14/10/14 14/10/15 14/10/20 PentHouse Drawings (Additional Drawings No.01) 5A3size drawings Thanh C
Revised based on comments in ASD -173
BBVN-FIVE-S2-SC-ASD-173(ADD.02) 14/10/18 14/10/21 14/10/20 PentHouse Drawings .Revised base on BBVN on 6A3 size drawings Thanh B
ASD.173. Replace the relative details and drawings in
ASD-13R1:ASD-124R1:ASD-173(ADD.01)
BBVN-FIVE-S2-SC-ASD-174 14/10/07 14/10/14 14/10/22 Piping Schedule & Underground Schedule Drawing List, 10A1size drawings Quang/Trung/Ujiie C RCR

BBVN-FIVE-S2-SC-ASD-175 14/10/08 14/10/15 14/10/17 AC Control System Plan Drawing list, 4A1size drawings (Office Quang/Ujiie/Diem C
Ground Floor; Clean Room; First Floor;
Outdoor Area)
BBVN-FIVE-S2-SC-ASD-175/R1 14/11/07 14/11/10 AC Control System Plan_Rev.1 Drawing list, 5A1size drawings Quang/Ujiie/Diem
Revised based on comments in ASD_175 dated 17-Oct-
2014

BBVN-FIVE-S2-SC-ASD-176

BBVN-FIVE-S2-SC-ASD-177 14/10/08 14/10/15 14/10/20 Pass Tray Details 1A3size drawing Cuong C
BBVN-FIVE-S2-SC-ASD-177/R1 14/10/28 14/11/03 Pass Tray Details_Rev.1 Revised based on comments in 1A3size drawing Cuong
ASD-177 dated 20-October-2014
Approval for Shop Drawing 50
REFERENCE Ref. Date Previous Title Drawing NAME Drawing CODE Size Author/Delivered to To/Receivers
(ASD_FOR APPROVAL) Issued

BBVN-FIVE-S2-SC- 14/07/01 Bar Bending for Ground Slab Zone 2, Zone 3 Phuc/Nguyen
ASD-102
14/07/07 Bar Bending for Ground Slab Zone 2, Zone Phuc/Nguyen
3_Rev.1 Revised based on comments in ASD-102
dated 7-July-2014
14/07/10 Bar Bending for Ground Slab Zone 2, Zone Phuc/Nguyen
3_Rev.2 Revised based on comments in ASD-
102/R1 dated 9-July-2014
14/07/18 Bar Bending for Ground Slab Zone 2, Zone Phuc/Nguyen
3_Rev.3_Part 1 (Zone 2) Revised based on
comments in ASD-102/R2 dated 14-July-2014

14/07/21 Bar Bending for Ground Slab Zone 2, Zone Phuc/Nguyen


3_Rev.3_Part 2 (Zone 3) Revised based on
comments in ASD-102/R2 dated 14-July-2014
Approval for Shop Drawing 51
Drawing NAME Drawing CODE Size Author/Delivered to To/Receivers

Phuc/Nguyen

Phuc/Nguyen

Phuc/Nguyen

Phuc/Nguyen

Phuc/Nguyen
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BBVN-FIVE-S2-SC- 14/02/29 14/03/07 Architectual/Roof Insulation 2 As-built Tung
RFI-0001-14 drawings:BB/SEC/G1/00/AARC
H/006,
BB/SEC/G1/00/AARCH/007 (A3
size)
BV-137206/6011/SMZ- 14/03/03
140228/D001

BBVN-FIVE-S2-SC- 14/02/28 14/02/28 Structural/Steel structural Comment 8 items of drawings (12 pages A3 Cuong
RFI-0002-14 size drawings)
BV-137206/6011/SMZ- 14/03/03 Steel Structure Comment
140303/D002
BV-137206/6011/SMZ- 14/03/07 Steel Structure Comment. Designer Reply
140306/D004

BBVN-FIVE-S2-SC- 14/02/28 14/02/28 Structural/Ground Beam level confirm 5 pages A3 size drawings Cuong
RFI-0003-14
BV-137206/6011/SMZ- 14/03/03 Steel Structure Comment
140303/D003
BV-137206/6011/SMZ- 14/03/07 Steel Structure Comment. Designer Reply.
140306/D005

BBVN-FIVE-S2-SC- 14/03/04 14/03/05 Architectual/ Grid Line Survey 1 A3 size drawing No.141-HBP- Cuong
RFI-0004-14 A-CD-MB-001b, 4 A4 sized
photos
BV-137206/6011/SMZ- 14/03/010 Gridline Survey
140308/D007
BV-137206/6011/SMZ- 14/03/12 Gridline Survey
140312/D013

BBVN-FIVE-S2-SC- Structural/ Pile Location & Pile Top Level Survey 2 A4 size pages Starter bar survey Cuong
RFI-0005-14 level, 9 A3 size drawings

BV-137206/6011/SMZ- 14/03/10 Pile Location & Pile Top Level Survey


140308/D008
BV-137206/6011/SMZ- 14/03/12 Pile Location & Pile Top Level Survey
140312/D012

BBVN-FIVE-S2-SC- 14/03/04 14/03/07 Structure, Ardhitecture / Design Queries (maintenance/Floor finishing/drain


7 drawing
pipe/cadding/pile
pages A4 size
shaft) Thanh/Cuong
RFI-0006-14
BV-137206/6011/SMZ- 14/03/10 Design Queries: Maintenance/Floor Finishing/Drain
140308/D009 Pipes/Cladding/Pipe Shaft
BV-137206/6011/SMZ- 14/02/13 Design Queries: Maintenance/Floor Finishing/Drain
140312/D014 Pipes/Cladding/Pipe Shaft
BBVN-FIVE- 14/03/28 14/03/ 2 Additional Drawings for Structure/Architecture/Drain Pipe/
S2-SC-RFI-
0006/R1
BV-137206/6011/SMZ- 14/04/02 Design Queries: Maintenance/Floor Finishing/Drain
140402/D037 Pipes/Cladding/Pipe Shaft

BBVN-FIVE-S2-SC- 14/03/04 14/03/07 Struture, Architecture/ Design Queries (require 1 hard copy A1 size with stamp) Mr. Giang/Thanh
RFI-0007-14
BV-137206/6011/SMZ- 14/03/10 Design Queries: hard Copy - Issued for Construction documents
140310/D010
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BBVN-FIVE-S2-SC- 14/03/07 5 A3 size drawings Mr. An/Mr.Giang
RFI-0008-14 M&E/ Bracing steel structure Clashings points
BV-137206/6011/SMZ- 14/03/10
140310/D011 Bracing Steel Structure Clashing Points
BV-137206/6011/SMZ- 14/03/13
140313/D015 Bracing Steel Structure Clashing Points

BBVN-FIVE-S2-SC- 14/03/12 14/03/12 Structure/Architecture/M&E_Design Queries_Toilet 5 A4 size drawings Mr. Giang/An


RFI-0009-14
BV-137206/6011/SMZ- 14/03/13 Toilet Drain and Structure Beam
140313/D016

BBVN-FIVE-S2-SC- 14/03/13 14/03/14 Pile testing result (Intergrity test, Bearing test) Mr. Tu/Nguyen
RFI-0010-14
BV-137206/6011/SMZ- 14/03/17 Pile Test Result All pipe test result report
140317/D019

BBVN-FIVE-S2-SC- 14/03/17 Rain Water Pipe (RWP) grid line A 1 A3 size drawing. Mr. Cuong/Giang
RFI-0011
BV-137206/6011/SMZ- 14/03/21 Rain Water Pipe - Gridline A
140318/D021
BV-137206/6011/SMZ- 14/03/26 Rain Water Pipe - Gridline A
140326/D023
BV-137206/6011/SMZ- 14/04/02 Rain Water Pipe - Gridline A
140402/D038
BBVN-FIVE-S2-SC- 14/03/28 Rain Water Pipe - Gridline A
RFI-0011/R1

BBVN-FIVE-S2-SC- 14/03/17 14/03/18 Backfill Layer Material & Compaction Mr. Hoang
RFI-0012
BV-137206/6011/SMZ- 14/03/21 Backfill Material & Compaction
140318/D022
BV-137206/6011/SMZ- 14/03/26 Backfill Material & Compaction
140326/D024

BBVN-FIVE-S2-SC- 14/03/24 14/03/25 Road & Drainage System Level 4 A3 size drawings (road), 4A3 Mr. Le/Mr. Thanh
RFI-0013 size drawings (drainage system)

00/01/25
BV-137206/6011/SMZ- 14/04/02 RFI-013 Road & Drainage System Level
140403/D033

BBVN-FIVE-S2-SC- 14/03/24 14/03/26 Survey Report with Different level between design and existing of 1 A3 drawing Mr. Le/Mr. Thanh
RFI-0014 interfacing ground floor

BV-137206/6011/SMZ- 14/04/02 (RFI_014) Interfacing Ground Floor Level


140402/D035

BBVN-FIVE-S2-SC- 14/03/24 14/03/27 Brick for Masonry Hoang


RFI-0015
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BV-137206/6011/SMZ- 14/03/29 Brick for Masonry
140329/D029
14/04/04 14/04/09 Brick for Masonry Rev.1

BBVN-FIVE-S2-SC- 14/03/26 14/03/26 RFI_0016_toilet & Structure Beam 6 A3 size drawings Thanh
RFI-0016
BV-137206/6011/SMZ-14

BBVN-FIVE-S2-SC- 14/03/27 14/03/31 Conflict between beeam and Sewage Pipe 4 A3 size drawings Mr. Giang/Mr.
RFI-0017 Thanh, Mr.
Le/Quang
BV-137206/6011/SMZ- 14/04/02 (RFI_017)_Toilet & Structure Beam
140402/D036

BBVN-FIVE-S2-SC- 14/03/27 14/04/02 Civil / Ground Compaction Photos of Soil Trial Test, Testing Mr. Nguyen/Tu
RFI-0018 Resultfor compacting at the
construction site
BV-137206/6011/SMZ- 14/03/29 RFI-18 Ground Compaction
140329/D031
BV-137206/6011/SMZ- 14/04/02 RFI-018 Ground Compaction
140402/D034

BBVN-FIVE-S2-SC- 14/03/29 14/04/02 Electrical/ Lighting cable specification Specification, 2A3 size drawings Mr. Quang
RFI-0019
BV-137206/6011/SMZ- 14/04/01 Electrical/ Lighting cable specification
140401/D032
BV-137206/6011/SMZ- 14/04/04 Electrical/ Lighting cable specification
140404/D041

BBVN-FIVE-S2-SC- 14/04/01 14/04/04 Design/Internal - Location of floor drain at ground and first floor 12 A3size drawings Mr. Quang
RFI-0020
BV-137206/6011/SMZ- 14/04/03 Design/Internal - Location of floor drain at ground and first floor 12 A3size drawings
140403/D039
BV-137206/6011/SMZ- 14/04/08 Design/Internal - Location of floor drain at ground and first floor
140408/D043 (Designer Comments)

BBVN-FIVE-S2-SC- 14/04/04 14/04/07 Purlin Connection Details 4 A3size drawings Mr. Giang/Mr.
RFI-0021 Thanh
BV-137206/6011/SMZ- 14/04/04 Purlin Connection Details
140404/D040
BV-137206/6011/SMZ- 14/04/07 (RFI-021) Purlin Connection Details (reply by Designer) Mr. Giang/Mr.
140404/D042 Thanh

BBVN-FIVE-S2-SC- 14/04/14 14/04/17 Paint for Steel Structure Mr. Giang/Hoang


RFI-0022
BV-137206/6011/SMZ- 14/04/17 Paint for Steel Structure
140417/D044
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BBVN-FIVE-S2-SC- 14/04/21 14/04/24 Dehumidifier in Granulation Room's Specification Mr. Ujiie/Mr.
RFI-0023 Quang
BV-137206/6011/SMZ- 14/04/23 Dehumidifier Specification
140423/D045

BBVN-FIVE-S2-SC- 14/04/21 14/04/24 Lightning Protection System Mr. Ujiie/Mr.


RFI-0024 Quang, Mr. Trung

BV-137206/6011/SMZ- 14/05/06 Lightning Protection System


140506/D046

BBVN-FIVE-S2-SC- 14/04/22 14/04/25 Vent Pipe for Sanaitation Facilities Mr. Ujiie/Mr.
RFI-0025 Quang, Mr. Trung

BV-137206/6011/SMZ- 14/04/23 Vent Pipe for Sanaitation Facilities


140423/D047

BBVN-FIVE-S2-SC- 14/04/22 14/04/25 Specification Clarification (Pile Cap) Mr. Tuan Anh/Mr.
RFI-0026 Mike-Hoa

BV-137206/6011/SMZ- 14/04/25 RFI-026_ Specification Clarification. Foundation Notes.


140424/D056

BBVN-FIVE-S2-SC- 14/04/22 14/04/25 M&E Outlet Location Mr. Ujiie


RFI-0027
BV-137206/6011/SMZ- 14/04/25 RFI-027_ M&E Outlet Location
140424/D055

BBVN-FIVE-S2-SC- 14/04/25 14/04/29 UPS at Panel DB-IT2 Mr. Ujiie


RFI-0028
BV-137206/6011/SMZ- 14/06/06 UPS at Panel DB-IT2
140606/D145
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BBVN-FIVE-S2-SC- 14/04/25 14/04/29 Production Panel Relocation Mr. Ujiie
RFI-0029
BV-137206/6011/SMZ- 14/06/03 Production Panel Relocation Ujiie/Quang
140602/D126

BBVN-FIVE-S2-SC- 14/04/25 14/05/02 Door Hardware Tung


RFI-0030
BV-137206/6011/SMZ- 14/05/22 Door Hardware
140522/D113
BV-137206/6011/SMZ- 14/06/03 Door Hardware
140603/D122

BBVN-FIVE-S2-SC- 14/04/25 14/05/02 Chair at Laboratory Room Tung


RFI-0031
BV-137206/6011/SMZ- 14/04/29 RFI-031_Chair at White Area
140429/D058

BBVN-FIVE-S2-SC- 14/04/25 14/04/26 Lightning Protection Quang


RFI-0032
BV-137206/6011/SMZ- 14/05/06 Lightning Protection Quang/Diem
140506/D062

BBVN-FIVE-S2-SC- 14/04/28 14/05/03 Smoke Exhaust Fan Randy


RFI-0033
BV-137206/6011/SMZ- 14/05/06 Smoke Exhaust Fan Randy
140506/D061

BBVN-FIVE-S2-SC- 14/04/29 14/05/02 Moterrise Damper Randy


RFI-0034
BV-137206/6011/SMZ- 14/05/16 Moterrise Damper Randy
140516/D072
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/04/28 14/05/03 Process Exhaust Fan Randy


RFI-0035
BV-137206/6011/SMZ- 14/05/16 Process Exhaust Fan 2A3size drawings
140516/D073

BBVN-FIVE-S2-SC- 14/04/28 14/05/03 Exhaust Fan Capacity Randy


RFI-0036
BV-137206/6011/SMZ- 14/05/06 Exhaust Fan Capacity Randy
140506/D060

BBVN-FIVE-S2-SC- 14/04/28 14/05/03 Ele. Room Sprinkler Randy


RFI-0037
BV-137206/6011/SMZ- 14/05/16 Ele. Room Sprinkler 1A3size drawing
140516/D074

BBVN-FIVE-S2-SC- 14/04/28 14/05/03 Switch Box Level Randy


RFI-0038
BV-137206/6011/SMZ- 14/05/07 Switch Box Level
140507/D063

BBVN-FIVE-S2-SC- 14/04/28 14/05/02 Warehouse Lighting Randy


RFI-0039
BV-137206/6011/SMZ- 14/04/29 RFI-039_Warehouse Lighting
140429/D059
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BBVN-FIVE-S2-SC- 14/04/28 14/05/02 Sprinkler inside Air Shaft Randy
RFI-0040
BV-137206/6011/SMZ- 14/05/16 Sprinkler inside Air Shaft 2A3size drawings
140516/D075

BBVN-FIVE-S2-SC- 14/04/29 14/05/02 Spinkler Head under Duct Randy


RFI-0041
BV-137206/6011/SMZ- 14/05/16 Spinkler Head under Duct 1A3size drawing + 1A4size photo
140516/D076

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Conductor for Lightning System Randy


RFI-0042
BV-137206/6011/SMZ- 14/05/16 Conductor for Lightning System 1A3size drawing
140516/D077

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Urinal Sensor Socket Randy


RFI-0043
BV-137206/6011/SMZ- 14/05/16 Urinal Sensor Socket 2A3size drawings
140516/D078

BBVN-FIVE-S2-SC- 14/05/20 14/05/23 Water Chiller Valve Randy


RFI-0044
BV-137206/6011/SMZ- 14/06/05 Water Chiller Valve
140605/D140

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 RO Gasket & O ring Type Randy


RFI-0045
BV-137206/6011/SMZ- 14/05/07 RO Gasket & O ring Type Randy
140507/D064

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Existing Panel Modification Randy


RFI-0046
BV-137206/6011/SMZ- 14/05/16 Existing Panel Modification 1A3size drawing & 1A4size Photo
140516/D079

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Manhole for AC Drain & Compressor Drain Randy
RFI-0047
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BV-137206/6011/SMZ- 14/05/16 Manhole for AC Drain & Compressor Drain 3A3size drawings
140516/D080

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Cable ladder & trinking color code Randy
RFI-0048
BV-137206/6011/SMZ- 14/05/16 Cable ladder & trinking color code
140516/D081

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Earthing System Randy


RFI-0049
BV-137206/6011/SMZ- 14/05/16 Earthing System 2A3size drawings
140516/D082

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Earth Pit Dimension Randy


RFI-0050
BV-137206/6011/SMZ- 14/05/16 Earth Pit Dimension 1A3size drawing
140516/D083

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Earth Ring Conductor Randy


RFI-0051
BV-137206/6011/SMZ- 14/05/19 Earth Ring Conductor Randy
140516/D084

BBVN-FIVE-S2-SC- 14/05/02 14/05/03 Single line diagram Randy


RFI-0052
BV-137206/6011/SMZ- 14/05/16 Single line diagram 2A3zise drawings
140516/D101

BBVN-FIVE-S2-SC- 14/05/14 14/05/16 Chiller Control Randy


RFI-0053
BV-137206/6011/SMZ- 14/06/05 Chiller Control
140605/D139
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 Warehouse Exhaust Air Fan and Smoke Exhaust Damper Randy
RFI-0054
BV-137206/6011/SMZ- 14/05/16 Warehouse Exhaust Air Fan and Smoke Exhaust Damper 1A3size drawing
140516/D085

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 Water Supply System Route Randy


RFI-0055
BV-137206/6011/SMZ- 14/05/16 Water Supply System Route 2A3size drawings
140516/D086

BBVN-FIVE-S2-SC- 14/05/02 14/05/05 Louver Air Velocity Randy


RFI-0056
BV-137206/6011/SMZ- 14/05/16 Louver Air Velocity 1A3size drawing
140516/D087

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 Exhaust fan RF-PII-01 & 02 Operation Control Randy
RFI-0057
BV-137206/6011/SMZ- 14/05/16 Exhaust fan RF-PII-01 & 02 Operation Control 1A3size drawing
140516/D088

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 Humidity and Temperature Control on Component Production & Randy
RFI-0058 Storage
BV-137206/6011/SMZ- 14/05/16 Humidity and Temperature Control on Component Production & 1A3size drawing
1405/16/D089 Storage

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 CCTV Monitor at Guard House and BMS Room Randy
RFI-0059
BV-137206/6011/SMZ- 14/05/16 CCTV Monitor at Guard House and BMS Room 1A3size drawing
140516/D090

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 Access Control System Randy


RFI-0060
BV-137206/6011/SMZ- 14/05/16 Access Control System 2A3size drwings
140516/D091
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/02 14/05/05 AHU Plenum Randy


RFI-0061
BV-137206/6011/SMZ- 14/05/16 AHU Plenum 2A3zise drawings
140516/D092

BBVN-FIVE-S2-SC- 14/05/16 14/05/19 MV&LV Cable Color Code Randy


RFI-0062
BV-137206/6011/SMZ- 14/06/05 MV&LV Cable Color Code
140605/D138

BBVN-FIVE-S2-SC- 14/05/08 14/05/11 BV-137206/6011/SMZ- 14/05/12 Push Putton Switch Randy


RFI-0063 140509/D069

BBVN-FIVE-S2-SC- 14/05/02 14/05/06 AHU Supply Air Duct Silencer Randy


RFI-0064
BV-137206/6011/SMZ- 14/05/16 AHU Supply Air Duct Silencer 1A3zise drawing
140516/D093

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 Fire Hose Cabinet Randy


RFI-0065
BV-137206/6011/SMZ- 14/05/16 Fire Hose Cabinet 1A3zise drawing
140516/D094

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 Pre Filter for Ventillation System Randy


RFI-0066
BV-137206/6011/SMZ- 14/05/16 Pre Filter for Ventillation System 3A3zise drawings
140516/D095

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 VentillationSystem for Toilet: Air Grill W/O Duct Randy
RFI-0067
BV-137206/6011/SMZ- 14/05/16 VentillationSystem for Toilet: Air Grill W/O Duct 1A3zise drawing
140516/D096
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 Provisional Sum Items Information Randy


RFI-0068
BV-137206/6011/SMZ- 14/05/09 Provisional Sum Items Information
140507/D065

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 Stage 1 Clean Room Plenum Randy


RFI-0069
BV-137206/6011/SMZ- 14/05/16 Stage 1 Clean Room Plenum 2A3zise drawings
140516/D097

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 Stage 1 Busbar BB4 400A Relocation Randy


RFI-0070
BV-137206/6011/SMZ- 14/06/03 Stage 1 Busbar BB4 400A Relocation
140602/D125

BBVN-FIVE-S2-SC- 14/05/05 14/05/08 Drain Pipe in IPQC Lab Randy


RFI-0071
BV-137206/6011/SMZ- 14/05/16 Drain Pipe in IPQC Lab 1A3zise drawing
140516/D098

BBVN-FIVE-S2-SC- 14/05/06 14/05/09 Beam & Stair Confliction Thanh/Duong-An


RFI-0072
BV-137206/6011/SMZ- 14/05/16 Beam & Stair Confliction 1A3zise drawings
140516/D103
BBVN-FIVE- 14/05/14 14/05/16 Beam & Stair Confliction 1A3size drawing Thanh
S2-SC-RFI-
0072 (ADD.01)

BBVN-FIVE-S2-SC- 14/05/07 14/05/09 CR4-Wall Type Thanh


RFI-0073
BV-137206/6011/SMZ-140 CR4-Wall Type

BBVN-FIVE- 14/05/13 14/05/16 CR4-Wall Type Thanh


S2-SC-RFI-
0073/R1
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/07 14/05/10 Balancing Valve for Chiller Randy


RFI-0074
BV-137206/6011/SMZ- 14/05/16 Balancing Valve for Chiller 2A3zise drawings
140516/D102

BBVN-FIVE-S2-SC- 14/05/07 14/05/10 AHU Chiller Pipe Connection Randy


RFI-0075
BV-137206/6011/SMZ- 14/05/22 AHU Chiller Pipe Connection
140522/D116

BBVN-FIVE-S2-SC- 14/05/08 14/05/10 C5-1 & Anchor Steel Plate Thanh


RFI-0076
BV-137206/6011/SMZ- 14/05/16 C5-1 & Anchor Steel Plate 3A3zise drawings
140516/D099

BBVN-FIVE-S2-SC- 14/05/08 14/05/11 BV-137206/6011/SMZ- 14/05/12 Accesss Control Module Randy


RFI-0077 140509
BV-137206/6011/SMZ-140

BBVN-FIVE-S2-SC- 14/05/09 14/05/12 SB1 Steel Beam Connection Thanh


RFI-0078
BV-137206/6011/SMZ- 14/05/16 SB1 Steel Beam Connection 1A3zise drawing
140516/D100

BBVN-FIVE-S2-SC- 14/05/12 14/05/15 Smoke Exhaust Static Pressure Calculation D61, 2A3size drawings, tabulation Quang
RFI-0079
BV-137206/6011/SMZ- 14/05/22 Smoke Exhaust Static Pressure Calculation
140522/D114
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/12 14/05/15 Water Tank Outlet and Gate Valve 1A4size photo & 2A3size Randy
RFI-0080 drawings
BV-137206/6011/SMZ- 14/06/06 Water Tank Outlet and Gate Valve
140606/D143

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel DB-1A-2 Modification Load Power Schedule& 2A3size Randy
RFI-0081 drawings
BV-137206/6011/SMZ- 14/05/15 M&E Proposed Change Load Power Schedule& 4A3size
140515/D071 drawings

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel DB-1A-3 Modification Load Power Schedule + Drawings Randy
RFI-0082
BV-137206/6011/SMZ- 14/05/15 LV Panel DB-1A-3 Modification Load Power Schedule
140515/D071

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel DB-MCC2 Modification Schedule + Drawings Randy


RFI-0083
BV-137206/6011/SMZ- 14/05/15 LV Panel DB-MCC2 Modification Schedule + 2A3size Drawings
140515/D071

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel DB-SCHWP-02, 03 Modification Schedule, 2A3size drawings Randy
RFI-0084
BV-137206/6011/SMZ- 14/05/15 LV Panel DB-SCHWP-02, 03 Modification Schedule, 2A3size drawings
140515/D071

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel DB-MCC3-1&DB-MCC3-2 Modification Schedule & 2A3size drawings Randy
RFI-0085
BV-137206/6011/SMZ- 14/05/15 Lv Panel DB-MCC3-1&DB-MCC3-2 Modification Schedule & 2A3size drawings
140515/D071
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel Modification: Analog Type Meter to Digital Multimeter Randy
RFI-0086
BV-137206/6011/SMZ- 14/05/15 LV Panel Modification: Analog Type Meter to Digital Multimeter
140515/D071

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 Main Switchboard A&B Modification 2A3size drawings Randy
RFI-0087
BV-137206/6011/SMZ- 14/05/15 Main Switchboard A&B Modification 2A3size drawings
140515/D071

BBVN-FIVE-S2-SC- 14/05/13 14/05/16 LV Panel DB-M/C-1&2, DB-CH-03 Modification 5A3size drawings Randy
RFI-0088
BV-137206/6011/SMZ- 14/05/15 LV Panel DB-M/C-1&2, DB-CH-03 Modification 5A3size drawings
140515/D071

BBVN-FIVE-S2-SC- 14/05/22 14/05/24 MSB-A New MCCB for AHU-04 Supply & Return Fans 2A4size photos&data sheet, Randy
RFI-0089 1A3size drawing
BV-137206/6011/SMZ- 14/07/04 MSB-A New MCCB for AHU-04 Supply & Return Fans
140704/D233

BBVN-FIVE-S2-SC- 15/05/13 14/05/17 Beam B12 size 2A3size drawings Thanh


RFI-0090
BV-137206/6011/SMZ- 14/05/16 Beam B12 size 2A3size drawings
140515/D104

BBVN-FIVE-S2-SC- 14/05/15 14/05/16 Duct Pressure (Low & Medium) Schedule Randy
RFI-0091
BV-137206/6011/SMZ- 14/06/06 Duct Pressure (Low & Medium)
140606/D144

BBVN-FIVE-S2-SC- 14/05/16 14/05/21 Generator Delivery 1A3size drawing Randy


RFI-0092
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply
BV-137206/6011/SMZ- 14/06/03 Generator Delivery
140602/D127

BBVN-FIVE-S2-SC- 14/05/17 14/05/19 AHU Opening 2A3size drawings Randy


RFI-0093
BV-137206/6011/SMZ- 14/06/10 AHU Opening
140610/D161

BBVN-FIVE-S2-SC- 14/05/17 14/0521 CCTV Connection Module Technical Specification & Randy
RFI-0094 1A3size drawing
BV-137206/6011/SMZ- 14/05/22 CCTV Connection Module
140522/D115

BBVN-FIVE-S2-SC- 14/05/22 14/05/24 Return Air Grille 1A3sze drawing Randy


RFI-0095
BV-137206/6011/SMZ- 14/06/11 Return Air Grille
140610/D168
BV-137206/6011/SMZ- 14/07/09 Return Air Grille
140709/D242

BBVN-FIVE-S2-SC- 14/05/22 14/0525 Water Chiller Valve Size 2A3 size drawings Randy
RFI-0096
BV-137206/6011/SMZ- 14/06/25 Water Chiller Valve Size
140624/D195
BV-137206/6011/SMZ- 14/07/09 Water Chiller Valve Size
140709/D243

BBVN-FIVE-S2-SC- 14/05/22 14/05/25 Motorized Valve for Chiller - 03 Data sheet + Specification Randy
RFI-0097
BV-137206/6011/SMZ- 14/07/04 Motorized Valve for Chiller - 03
140704/D234

BBVN-FIVE-S2-SC- 14/05/22 14/05/24 Fusible Link Temperature Requirement for Smoke Duct Fire Damper 1A3size drawing Randy
RFI-0098
BV-137206/6011/SMZ- 14/05/23
140523/D117
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/22 14/05/25 The Brick Jamb at Door Locations 1A4Aize photo & 13A3size Thanh
RFI-0099 drawings
BV-137206/6011/SMZ- 14/06/16 The Brick Jamb at Door Locations
140616/D176

BBVN-FIVE-S2-SC- 14/05/22 14/05/26 Septic Tank 4A3size drawings Thanh


RFI-0100
BV-137206/6011/SMZ- 14/07/09 Septic Tank
140709/D244

BBVN-FIVE-S2-SC- 14/05/23 14/05/25 Ceiling Frame Connection Detail 6A3size drawings Thanh / Duong
RFI-0101
BV-137206/6011/SMZ- 14/06/05 Ceiling Frame Connection Detail
140604/D129

BBVN-FIVE-S2-SC- 14/05/23 14/05/24 Fastener Securement Deck Lap Tung


RFI-0102
BV-137206/6011/SMZ- 14/05/23
140523/D118

BBVN-FIVE-S2-SC- Sanitary Fixture Randy


RFI-0103
BV-137206/6011/SMZ- 14/06/03 Sanitary Fixture
140602/D128

BBVN-FIVE-S2-SC- 14/05/27 14/05/30 New Production Machine Layout 1A3size drawing Randy
RFI-0104
BV-137206/6011/SMZ- 14/06/06 New Production Machine Layout
140606/D146
BV-137206/6011/SMZ- 14/06/10 New Production Machine Layout
140610/D162
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/05/28 14/05/31 Master Key Schedule Mr. Thanh


RFI-0105
BV-137206/6011/SMZ- 14/06/25 Master Key Schedule
140625/D198

BBVN-FIVE-S2-SC- 14/05/28 14/05/31 Structure & Finishing 1Fl Toilet 1A3size drawing Duong
RFI-0106
BV-137206/6011/SMZ- 14/06/07 Structure & Finishing 1Fl Toilet
140607/D148

BBVN-FIVE-S2-SC- 14/05/30 14/06/03 LCP-P2-G-1 Relocation to Stage 1 Staircase 1A3size drawing Randy
RFI-0107
BV-137206/6011/SMZ- 14/06/03 LCP-P2-G-1 Relocation to Stage 1 Staircase
140602/D123

BBVN-FIVE-S2-SC- 14/05/30 14/06/05 Relocation of utilities from under to above of secondary support 2A3size drawings Randy
RFI-0108
BV-137206/6011/SMZ- 14/06/05 Relocation of utilities from under to above of secondary support
140604/D130

BBVN-FIVE-S2-SC- 14/05/30 14/06/04 C8 Column along GL-E size 4A3size drawings Thanh
RFI-0109
BV-137206/6011/SMZ- 14/06/07 C8 Column along GL-E size
140607/S153

BBVN-FIVE-S2-SC- 14/05/31 14/06/07 Relocation of Existing Pole Light, CCTV, Fire Hydrant Pillar & 2A3size drawings Randy
RFI-0110 Cabinet
BV-137206/6011/SMZ- 14/06/25 Relocation of Existing Pole Light, CCTV, Fire Hydrant Pillar &
140625/D199 Cabinet
Request for Information
OUT-GOING Rev Date Issued Date INCOMING Rev Date Issued Title Attachment Author/Delivered to
Required
Reply

BBVN-FIVE-S2-SC- 14/06/2 14/06/05 Aluminum Cover Details @ GL A&Z 6A3size drawings & 1 A3size Thanh
RFI-0111 drawing for REFERENCE
BV-137206/6011/SMZ- 14/06/05 Aluminum Cover Details @ GL A&Z
140605/D137
BBVN-FIVE- 14/06/19 14/06/24 Aluminum Cover Details @ GL A&Z_Rev.1 SMZ_140605/D137(RFI_111) Thanh
S2-SC-RFI- 7A3size drawings
0111/R1
BV-137206/6011/SMZ- 14/06/26 Aluminum Cover Details @ GL A&Z_Rev.1 SMZ_140605/D137(RFI_111) Thanh
140626/D207 7A3size drawings

BBVN-FIVE-S2-SC- 14/06/02 14/06/07 Steel Lintel for Alu door & window 1A3size drawing Thanh
RFI-0112
BV-137206/6011/SMZ- 14/06/07 Steel Lintel for Alu door & window
140607/D149

BBVN-FIVE-S2-SC- 14/06/02 14/06/05 Top Beam @ Gridline 21 6A3size drawings Thanh


RFI-0113
BV-137206/6011/SMZ- 14/06/07 Top Beam @ Gridline 21
140607/D152
BBVN-FIVE- 14/06/09 14/06/14 Top Beam @ Gridline 21 11A3size drawings included in Thanh
S2-SC-RFI- IN_ASD-0020 dated28-May-2014
0113/R1

BBVN-FIVE-S2-SC- 14/06/02 14/06/05 Wall Type 1b Detail 6A3size drawings Thanh


RFI-0114
BV-137206/6011/SMZ- 14/06/07 Wall Type 1b Detail
140607/D150

BBVN-FIVE-S2-SC- 14/06/02 14/06/07 Double Glass Specification 1A3size drawing Thanh


RFI-0115
BV-137206/6011/SMZ- 14/06/07 Double Glass Specification
140607/D151
BBVN-FIVE- 14/06/09 14/06/14 Double Glass Specification Description of Work Thanh
S2-SC-RFI-
0115/R1
BV-137206/6011/SMZ- 14/06/14 Double Glass Specification Description of Work Thanh
140614/D175

BBVN-FIVE-S2-SC- 14/06/05 14/06/12 Concrete Apron to the Curb for Asphalt Road 1A4size photo, 2A3size drawings Le, Thanh
RFI-0116
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author
BBVN-FIVE-S2- BV-137206/6011/SMZ-140314/D017 14/03/14 Bus duct from Aluminum to Copper RFC form BBVN -FIVE-S2-RFC- Mr. Ujiie
RFC-001 0001
BV-137206/6011/SMZ-140327/D025 14/03/27 Bus duct from Aluminum to Copper. Approval RFC form BBVN -FIVE-S2-RFC-
0001 and Estimsation (VO)

BBVN-FIVE-S2- BV-137206/6011/SMZ-140318/D020 14/03/18 Trench and Backfilling under Ground Slab BBVN-FIVE-S2-RFC-0002, 2 Mr. Hoa
RFC-002 drawings A3
BV-137206/6011/SMZ-140522/D109 14/05/22 Trench and Backfilling under Ground Slab_Approval BBVN-FIVE-S2-RFC-0002, 4
drawings A3

BBVN-FIVE-S2- 14/04/12 BV-137206/6011/SMZ-140314/D018 14/03/14 Fire Fighting Pipe Location BBVN-FIVE-S2-RFC-0003,2


RFC-003 A3size drawings, 1 sketch
BBVN-FIVE- 14/06/03 Fire Fighting Pipe Cost Estimation Tung
S2-RFC-003
BV-137206/6011/SMZ-140627/D217 14/06/27 Fire Fighting Pipe_Approval

BBVN-FIVE-S2- 14/04/12 Design Change: (M&E) Addition Floor drain (FD) at ground and first BBVN - FIVE-S2-RFC-0004, Mr. Ujiie
RFC-004 floor 1A3 size drawing
BV-137206/6011/SMZ-140423/D053 14/04/23 Design Change: (M&E) Addition Floor drain (FD) at ground and first BBVN - FIVE-S2-RFC-0004,
floor. Rejected. 1A3 size drawing
BV-137206/6011/SMZ-

BBVN-FIVE-S2- 14/04/29 14/04/29 Conduit from PVC to GI BBVN - FIVE-S2-RFC-0005, Mr. Ujiie
RFC-005 1A4size page, Comparison Sheet

BV-137206/6011/SMZ-140519/D105 14/05/19 Conduit from PVC to GI

BV-137206/6011/SMZ-

BBVN-FIVE-S2- BV-137206/6011/SMZ-140423/D048 14/04/23 Galvanized Fire Fighting Pipe BBVN - FIVE-S2-RFC-0006 Mr. Mike
RFC-0006
BBVN-FIVE- 14/06/03 Galvanized Fire Fighting Pipe_V.O 2 options Mr. Quang
S2-RFC-0006
BV-137206/6011/SMZ-140627/D218 14/06/27 Galvanized Fire Fighting Pipe_Approval

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- BV-137206/6011/SMZ-140423/D049 14/04/23 Lighting Poles BBVN - FIVE-S2-RFC-07 Mr. Mike


RFC-0007
BBVN-FIVE- 14/05/25 Lighting Poles BBVN - FIVE-S2-RFC-07
S2-RFC-0007
BV-137206/6011/SMZ-140619/D185 14/06/19 Lighting Poles

BBVN-FIVE- 14/06/30 Lighting Poles Arrangment_V.O Estimation


S2-RFC-0007

BBVN-FIVE-S2- BV-137206/6011/SMZ-140423/D050 14/04/23 BBVN - FIVE-S2-RFC-0008, Mr. Mike


RFC-0008 Lighting System at Warehouse 1A4size drawing
BBVN-FIVE- 14/05/25 Estimation, Variation
S2-RFC-0008 Lighting System at Warehouse
BV-137206/6011/SMZ-140715/D259 14/07/15
Lighting System at Warehouse_Approval
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author
BBVN-FIVE-S2- BV-137206/6011/SMZ-140423/D051 14/04/23 BBVN - FIVE-S2-RFC-0009 Mike, Tung
RFC-0009 Roof Insulation Material
BV-137206/6011/SMZ-140

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- BV-137206/6011/SMZ-140423/D052 14/04/23 Clean Room Floor Material BBVN - FIVE-S2-RFC-0010, A- Mike, Tung
RFC-0010 CD-SC-01 Finishing & Material
Schedule
BV-137206/6011/SMZ-140428/D057 14/04/28 RFC-10_ Clean Room Floor Material. Additional Details for Static 2A3size drawings
Conductive Vinyl
BBVN-FIVE- 14/05/19 Static Conductive Vinyl Floor Form RFC-010 by SMZ; Tung
S2-RFC-0010 Estimation & 1A3size drawing

BV-137206/6011/SMZ-140528/D121 14/05/28 Static Conductive Vinyl Floor Tung

BBVN-FIVE-S2- Ladder inside Septic Tank & Pump Pit No.1 & No.2 BBVN - FIVE-S2-RFC-010 Mr. Le
RFC-0011
BV-137206/6011/SMZ-140627/D214 14/06/27 Ladder inside Septic Tank & Pump Pit No.1 & No.2

BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BBVN-FIVE-S2- 14/05/13 Road, Ground slab & Natural Soil BBVN - FIVE-S2-RFC-012 Mr. Ba Hoa
RFC-0012
BV-137206/6011/SMZ-140605/D131 14/06/05 Road, Ground slab & Natural Soil_Approval

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- BV-137206/6011/SMZ-140 Biometric Access Control BBVN - FIVE-S2-RFC- a Thanh/Mike


RFC-0013

BV-137206/6011/SMZ-140627/D216 14/06/27 Biometric Access Control

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/05/13 Moisture barrier at clean room BBVN - FIVE-S2-RFC-014, Mr. Tung
RFC-0014 Product Data Sheet
BV-137206/6011/SMZ-140521/D110 14/05/21 Moisture barrier at clean room_Rejected

BBVN-FIVE-S2- 14/05/16 Lighting Control Swich BBVN - FIVE-S2-AC-RFI-73, Randy/Ujiie


RFC-0015 BV-137206/6011/SMZ-140509/D
069, 2A3size drawings

BV-137206/6011/SMZ-140627/D219 14/06/27 Lighting Control Swich_Approval


Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author
BV-137206/6011/SMZ-140

BBVN-FIVE-S2- '14/05/16 Control Module for Access System BBVN - FIVE-S2-SC-RFI-77, Randy/Ujiie
RFC-0016 BV-137206/6011/SMZ-140509/D
070 dated 9May2014, 1A3soze
drawing
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-

BBVN-FIVE-S2- 14/05/15 Fire Hose Reel Supply Connection BBVN - FIVE-S2-RFC- Randy
RFC-0017
BV-137206/6011/SMZ-140619/D180 14/06/19 Fire Hose Reel Supply Connection_Approval

BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-

BBVN-FIVE-S2- BV-137206/6011/SMZ-140520/D106 14/05/20 Archive door relocation BBVN - FIVE-S2-RFC- BV


RFC-0018

BBVN-FIVE- 14/05/25 Archive door relocation 1A3size drawing


S2-RFC-0018
BV-137206/6011/SMZ-140603/D124 14/06/04 Archive Door Relocation_Approval BBVN - FIVE-S2-RFC-018; BV
2A3size drawings
BV-137206/6011/SMZ-140620/D193 14/06/20 Ante-chamber to toilet-Carpet Tiles_Approval

BBVN-FIVE-S2- BV-137206/6011/SMZ-140520/D107 14/05/20 IT Shop and server room - Floor Vinyl tiles BBVN - FIVE-S2-RFC-19 BV
RFC-0019
BBVN-FIVE- 14/05/25 IT Shop and server room - Floor Vinyl tiles BBVN - FIVE-S2-RFC-19, SMZ
S2-RFC-0019 2A4size drawing
BV-137206/6011/SMZ-140605/D132 14/06/05 IT Shop and server room - Floor Vinyl tiles_Approval

BV-137206/6011/SMZ-
BV-137206/6011/SMZ-

BBVN-FIVE-S2- BV-137206/6011/SMZ-140520/D108 14/05/20 Ante Chamber to toilet - Carpet Tiles BBVN - FIVE-S2-RFC-20; BV
RFC-0020 1A3size drawing
BBVN-FIVE- 14/05/25 Ante Chamber to toilet - Carpet Tiles Estimation, 2A3size drawings SMZ
S2-RFC-0020
BV-137206/6011/SMZ-140605/D136 14/06/05 Ante Chamber to toilet - Carpet Tiles

BBVN-FIVE- 14/06/10 RFC-020 form (signature)


S2-RFC-0020
BV-137206/6011/SMZ-
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author

BBVN-FIVE-S2- BV-137206/6011/SMZ-140522/D111 14/05/22 Temporary Backfilling of Stage 2 area_Approval BBVN - FIVE-S2-RFC- BV


RFC-0021
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140

BBVN-FIVE-S2- BV-137206/6011/SMZ-140522/D112 14/05/22 3D Model_Approval BBVN - FIVE-S2-RFC-22 BV


RFC-0022
BV-137206/6011/SMZ-140
BV-137206/6011/SMZ-140

BBVN - FIVE-S2-RFC-
BBVN-FIVE-S2- Water Supply System _ Change the Pipe size & Pipe route, chang Form RFC-023, Ujiie/Randy/Quang
RFC-0023 pump capacity SMZ-140516/D086 dated 26-
May-2014 (for RFI-055), data
sheet&4A3size drawings
BV-137206/6011/SMZ-140606/D147 14/06/06 Water Supply System _ Approval Form RFC-023;
SMZ-140516/S086 dated 16-May-
2014; Water Supply Calculation;
4A3size drawings; 1A3size
drawings list

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/05/21 Fire Fighting System _ Change model & physical data of OS&Y valve BBVN - FIVE-S2-RFC-0024, Ujiie
RFC-0024 from OF200 to OF200F & from cast iron to ductile iron Viking letter, catalogue, data sheet

BV-137206/6011/SMZ-140609/D156 14/06/09 Fire Fighting System _ Change model & physical data of OS&Y valve Ujiie
from OF200 to OF200F & from cast iron to ductile iron_Approved

BV-137206/6011/SMZ-140

BBVN - FIVE-S2-RFC-
BV-137206/6011/SMZ-140
BBVN-FIVE-S2- 14/05/21 Socket and Data Location at Clean Room Ujiie
RFC-0025
BV-137206/6011/SMZ-140627/D215 14/06/27 Socket and Data Location at Clean Room
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author
BBVN-FIVE-S2- BV-137206/6011/SMZ-14070//D123 Fire Smoke Supply Air Fans BBVN - FIVE-S2-RFC- BB
RFC-0026
BBVN-FIVE- 14/08/02 Fire Smoke Supply Air Fans Cost estimation, D223 (RFC-26), Ujiie
S2-RFC-0026 3A3size drawings
BV-137206/6011/SMZ-140
BBVN-FIVE-
S2-RFC-0026

BBVN-FIVE- 14/10/01 Fire Smoke Supply Air Fans Cost estimation, 1A3size drawing Ujiie
S2-RFC-0026
BBVN-FIVE- 14/10/06 Fire Smoke Supply Air Fans Cost estimation Tung
S2-RFC-0026
BV-137206/6011/SMZ-141010//D391 14/10/10 Fire Smoke Supply Air Fans_APPROVED

BBVN-FIVE-S2- Septic Tank Ladder Casting into Concrete BBVN - FIVE-S2-RFC-


RFC-0027
BV-137206/6011/SMZ-140605/D133 14/06/05 Septic Tank Ladder Casting into Concrete_Rejected

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/05/25 Grafting Filter for rubish BBVN - FIVE-S2-RFC-028;


RFC-0028 Estimation, 2A3size drawings
BV-137206/6011/SMZ-140619/D189 14/06/19 Grafting Filter for rubish

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/05/29 Change of Ground Beam Profile_Warehouse GL Z and 21 BBVN - FIVE-S2-RFC- Thanh
RFC-0029
BV-137206/6011/SMZ-140605/D134 14/06/05 Change of Ground Beam Profile_Warehouse GL Z and 21

BV-137206/6011/SMZ-140626/D203 14/06/26 Change of Ground Beam Profile_Warehouse GL Z and 21_Approval

BBVN-FIVE-S2- BV-137206/6011/SMZ-140529/D120 14/05/29 Pharmaceutical Pipe & Sleeve BBVN - FIVE-S2-RFC-


RFC-0030
BV-137206/6011/SMZ-140530/D122 14/05/31 Pharmaceutical Pipe & Sleeve_Approval

BBVN-FIVE-S2- 14/06/02 Additional Drain for IPQC Room BBVN - FIVE-S2-RFC-


RFC-0031
BV-137206/6011/SMZ-140607/D154 14/06/07 Additional Drain for IPQC Room_Rejected

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/05/31 Compressor Pipe Fittings Brand Name BBVN - FIVE-S2-RFC-32 Ujiie
RFC-0032
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author
BV-137206/6011/SMZ-140605/D135 14/06/05 Compressor Pipe Fittings Brand Name

BV-137206/6011/SMZ-140605/D141 14/06/06 Compressor Pipe Fittings Brand Name_Approved

BBVN-FIVE- 14/06/09 Compressor Pipe Fittings Brand Name


S2-RFC-0032

BBVN-FIVE-S2- 14/06/02 Ventilation Fan Brand (From Fantech replaced by Krugger) BBVN - FIVE-S2-RFC- Ujiie
RFC-0033
BV-137206/6011/SMZ-140605/D142 14/06/06 Ventilation Fan Brand (From Fantech replaced by Krugger)_Approval Form RFC-33, Main Equipment Ujiie
List, Technical Specification

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/06/03 Painting on Brick Wall at Air Shaft BBVN - FIVE-S2-RFC- Tung
RFC-0034
BV-137206/6011/SMZ-140607/D155 14/06/07 Painting on Brick Wall at Air Shaft

BV-137206/6011/SMZ-140627/D220 14/06/27 Painting on Brick Wall at Air Shaft_Approval

BBVN-FIVE-S2- 14/06/09 AC Drain and Compressor Drain 4A43sizedrawings Ujiie/Randy


RFC-0035
BV-137206/6011/SMZ-140612/D171 14/06/12 AC Drain and Compressor Drain_Approved

BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/06/09 Ball Valve for Handspray BBVN - FIVE-S2-RFC-0034; Randy


RFC-0036 Cost Estimation;
SMZ-140602/D128 dated 2nd
June 2014; RFI-103_Sanitary
Fixtures dated 23-May -2014;
IN_AMEP-0046 cover page dated
15-May-2014

BV-137206/6011/SMZ-140619/D181 14/06/19 Ball Valve for Handspray_Approval

BBVN-FIVE-S2- BV-137206/6011/SMZ-140609/D158 14/06/09 Copper Pipe for Water Heater BV


RFC-0037
BV-137206/6011/SMZ-140620/D194 14/06/20 Copper Pipe for Water Heater_Approval
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author

BBVN-FIVE-S2- BV-137206/6011/SMZ-140609/D159 14/06/09 Steel Structure Color BV


RFC-0038

BV-137206/6011/SMZ-140619/D184 14/06/19 Steel Structure Color_Rejected

BBVN-FIVE-S2- Flood Lights BV


RFC-0039
BV-137206/6011/SMZ-140609/D160 14/06/09 Flood Lights

BV-137206/6011/SMZ-140619/D186 14/06/19 Flood Lights

BBVN-FIVE-S2- BV-137206/6011/SMZ-140609/D157 14/06/09 Chilled water system bypass BV


RFC-0040
BBVN-FIVE- 14/06/27 Chilled water system bypass_V.O Estimation, drawing
S2-RFC-0040
BV-137206/6011/SMZ-140702/D226 14/07/02 Chilled water system bypass

BBVN-FIVE-S2- 14/06/10 High Speed Door 2.G.D.42 & 2.G.D.46 change from Horman Door to Horman Confirmation Letter, Tung
RFC-0041 Dynaco Door Dynaco Catalogue, Reference
Projects
BV-137206/6011/SMZ-140626/D205 14/06/26 High Speed Door 2.G.D.42 & 2.G.D.46 change from Horman Door to
Dynaco Door_Approval

BBVN-FIVE-S2- 14/06/10 Waterproofing between brick wall and concrete column Estimation, 4A3size drawings Tung
RFC-0042
BV-137206/6011/SMZ-140612/D172 14/06/12 Waterproofing between brick wall and concrete column_Rejected

BBVN-FIVE-S2- Moisture Barrier at Clean Room Sikafloor 81 Epocem 3mmthick to Tung


RFC-0043 Flowcem 2mm thick

BV-137206/6011/SMZ-140626/D204 14/06/26 Moisture Barrier at Clean Room_Approval

BBVN-FIVE-S2- Earth Pit Dimension Duong


RFC-0044
BV-137206/6011/SMZ-140804/D294 14/08/04 Earth Pit Dimension_Approval
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author

BBVN-FIVE-S2- Raised Floor Outlet Box Ujiie/Quang


RFC-0045
BV-137206/6011/SMZ-140619/D187 14/06/19 Raised Floor Outlet Box

BBVN-FIVE-S2- Drainage System Submersible Pump Ujiie/Quang


RFC-0046
BV-137206/6011/SMZ-140619/D182 14/06/19 Drainage System Submersible Pump_Approval

BBVN-FIVE-S2- 14/06/13 Chiller CH-03 Additional Valve Estimation; SMZ-140602/D127 Ujiie/ Quang
RFC-0047 dated 3-Jun-2014; Product Data
Sheet
BV-137206/6011/SMZ-140619/D188 14/06/19 Chiller CH-03 Additional Valve

BBVN-FIVE- 14/07/10 Chiller CH-03 Additional Valve_Rev.1


S2-RFC-0047/
R1
BV-137206/6011/SMZ-140804/D295 14/08/04 Chiller CH-03 Additional Valve_Rev.1 _Approval

BBVN-FIVE-S2- BV-137206/6011/SMZ-140731/D286 14/07/31 IT Adjustment BB


RFC-0048

BBVN-FIVE- BV-137206/6011/SMZ-140822/D331 14/08/22 IT Adjustment SMZ


S2-RFC-0048/
R1
BV-137206/6011/SMZ-140917/D371 14/09/18 IT Adjustment_APPROVAL

BBVN-FIVE-S2- 14/06/17 Construction Joint on Ground Floor Slab 1A3size drawings, 1 A3 drawing Le/Thanh/nguyen
RFC-0049 141-HBPE-S-CD-MB-214

BV-137206/6011/SMZ-140626/D202 14/06/26 Construction Joint on Ground Floor Slab_Approval

BBVN-FIVE- 14/07/17 Construction Joint on Ground Floor Slab Form, 3A3size drawings Phuc. Thanh
S2-RFC-0049/
R1
BV-137206/6011/SMZ-140722/D280 14/07/22 Construction Joint on Ground Floor Slab _Approved

BBVN-FIVE-S2- 14/06/17 Water Heater Safety Walve Drain Pipe 4A3size drawings Ujiie/Quang
RFC-0050
BV-137206/6011/SMZ-140619/D183 14/06/19 Water Heater Safety Walve Drain Pipe_Approved
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author

BBVN-FIVE-S2- 14/06/17 VRV Room Steel Work Member 3A3size drawings Giang
RFC-0051
BBVN-FIVE- 14/06/25 VRV Room Steel Work Member_Additional Document Comparison for geometric Giang/Duong
S2-RFC-0051 properties of sections, 3A3size
(ADD.01) drawings
BV-137206/6011/SMZ-140630/D122 14/07/01 VRV Room Steel Work Member

BBVN-FIVE- 14/07/02 VRV Room Steel work member_Rev.1 Geometric Properties, 1A3size Tung/Giang
S2-RFC-0051/ drawing
R1
BV-137206/6011/SMZ-140723/D282 14/07/23 VRV Room Steel work member_Rev.1 _ Approval Tung/Giang/
Thanh/Quang

BBVN-FIVE-S2- 14/06/20 Priority Power Supply for DB-SP Connection Point 3A3size drawings Quang/Ujiie
RFC-0052
BV-137206/6011/SMZ-140627/D221 14/06/27 Priority Power Supply for DB-SP Connection Point

BBVN-FIVE-S2- 14/06/24 Pit Support Meterial Change from GI to SUS304 4A3size drawings Quang/Ujiie
RFC-0053
BV-137206/6011/SMZ-140711/D251 14/07/11 Pit Support Meterial Change from GI to SUS304_Rejected Estimation, 4A3size drawings

BBVN-FIVE-S2- 14/07/10 Concrete Apron to the kerbt for the asphalt road 3A3size drawings Thanh
RFC-0054
BV-137206/6011/SMZ-140804/D297 14/08/04 Concrete Apron to the kerbt for the asphalt road_Approval

BBVN-FIVE-S2- 14/07/10 Asphalt road extension 3A3size drawings Thanh


RFC-0055
BV-137206/6011/SMZ-140731/D290 14/07/31 Asphalt road extension_Approved Thanh

BBVN-FIVE-S2- 14/06/24 LV Panel Load Technical Data Meter (from analog to digital) Estimation, SMZ-140515/D71 Quang/Ujiie
RFC-0056 dated 15-May-2014, RFI-86 dated
13-May-2014, Panel List for
Multimeter, Technical
Specification
BV-137206/6011/SMZ-140626/D206 14/06/26 LV Panel Load Technical Data Meter (from analog to digital)_Rejected
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author

BBVN-FIVE-S2- 14/06/24 VAV Communication Control Product Data Sheet, AMEP 17 Quang/Ujiie
RFC-0057 dated 24-Apr-2014, VAV
Terminal Unit Catalogue
BV-137206/6011/SMZ-140805/D299 14/08/06 VAV Communication Control_Approval

BBVN-FIVE-S2- 14/07/15 Ramp Adjustments BB


RFC-0058
BV-137206/6011/SMZ-140731/D287 14/07/31 Ramp Adjustments 4A3size drawings BV

BBVN-FIVE- 14/08/22 Ramp Adjustments Estimation, 4A3size drawings, SMZ/Tung


S2-RFC-0058 2A3size photos, 1A3size sketch

BV-137206/6011/SMZ-140829/D349 14/08/29 Ramp Adjustments_Approval

BBVN-FIVE-S2- 14/06/30 Raised Floor Outlet Box (From 4 nos. to 2 nos.) form + ASD 60, ASD-60/R1
RFC-0059 dated 30-June-2014
BV-137206/6011/SMZ-140918/D375 14/09/19 Raised Floor Outlet Box (From 4 nos. to 2 nos.) Ujiie

BBVN-FIVE-S2- 14/10/04 Clinic House Terrace Renovation Cost estimation, 2A3size SMZ (BB)
RFC-0059 drawings

BBVN-FIVE-S2- 14/07/01 LV Panel Modification - DB-SCHWP-02,03 Estimation, 6A3size drawings Ujiie


RFC-0060
BV-137206/6011/SMZ-140

BBVN-FIVE-S2- 14/07/04 Dike Wall and Water Proofing at the Wet Area 9A3size drawings Thanh
RFC-0061
BV-137206/6011/SMZ-140710/D247 14/07/10 Dike Wall and Water Proofing at the Wet Area

BBVN-FIVE-S2- 14/07/04 Waterproofing for Construction Joint (Casting Concrete for Ground Hoang QC
RFC-0062 Slab)
BV-137206/6011/SMZ-140722/D278 14/07/22 Waterproofing for Construction Joint (Casting Concrete for Ground
Slab)_Approved
Request for Information
OUT-GOING CODE Date Issued INCOMING Date Issued Title Attachment Author/Delivered to Status Date
Deliverd to
Author

BBVN-FIVE-S2- 14/07/07 Pressure gauge on the chilled water pipe for compressor diagram, photo A4size Ujiie
RFC-0063
BV-137206/6011/SMZ-140730/D288 14/07/31 Pressure gauge on the chilled water pipe for compressor_Approved Ujiie

BBVN-FIVE-S2- RC for brickwalls at door/window/louver/opening locations Estimation, D176 (RFI-099), Thanh


RFC-0064 14A4size drawings, 4A3size
drawings

BV-137206/6011/SMZ-140731/D291 14/07/31 RC for brickwalls at door/window/louver/opening locations_Approved Thanh

BBVN-FIVE-S2- 14/07/10 Reinforced Concrete post for intersecting brick wall 14A3size drawings Thanh
RFC-0065
BV-137206/6011/SMZ-140718/D271 14/07/18 Reinforced Concrete post for intersecting brick wall _ Rejected

BBVN-FIVE-S2- 14/07/10 Water Proofing for Septic Tank 3A3size drawings Thanh
RFC-0066
Correspondence submission to PCI 81
No. To CC: Issued Title Attachment Authored by

BBVN-FIVE-S2-SC- BV BB 14/08/08 Confirmation of Pre-Action System Control Panel 2A3size drawings Mr. Ujiie
LTR-ENG-0030
BBVN-FIVE-S2-SC- BV BB 08/11/08 ASD-0076/R2 - Fire Sprinkler FM Approvals Mr. Ujiie
LTR-ENG-0031
BBVN-FIVE-S2-SC- BV BB 14/08/08 Shop Drawing Approvals Mr. Ujiie
LTR-ENG-0032
BBVN-FIVE-S2-SC- BV BB 14/08/08 EVN Confirmation for Shutdown Schedule Ujiie
LTR-ENG-0033
BBVN-FIVE-S2-SC- BV BB 14/08/08 MOM Item 8.5.46 Pipe Connection to Buffer Tank 2A3size drawings Ujiie
LTR-ENG-0034
BBVN-FIVE-S2-SC- BV BB 14/08/09 BV-137206/609/140804/SI044 Pharma Proposed Floor Drain 2A4size drawings, BV- Ujiie
LTR-ENG-0035 Provision at Warehouse 137206/609/140804/SI-44
dated 5-August-2014
BBVN-FIVE-S2-SC- BV BB 14/08/11 Support Fabrication Supporting Finishing table Ujiie
LTR-ENG-0036
BBVN-FIVE-S2-SC- BV BB 14/08/08 Factory Visit/Inspection (Hainam Factory) Ujiie
LTR-ENG-0037
BBVN-FIVE-S2-SC- BV BB 14/08/12 MOM-26 Item 9.42 FM-200 Refilling E-mail from FIKE Aisa Pacific Ujiie
LTR-ENG-0038 (Clean Agent FM-200
Refilling for Fike's
System)&MOM-26 page 9 of
22
BBVN-FIVE-S2-SC- BV BB 14/08/12 BV-137206/6011/SMZ-140811/D308 RFC-088 Comment D308 Ujiie
LTR-ENG-0039
BBVN-FIVE-S2-SC- BV BB 14/08/12 ASD-130 Timber door and glass partition Mike
LTR-ENG-0040
BBVN-FIVE-S2-SC- BV BB 14/08/14 BBVN-FIVE-S2-SC-AMEP-005A Comment BBVN-FIVE-S2-SC-AMEP- Ujiie
LTR-ENG-0041 005A
BBVN-FIVE-S2-SC- BV BB 14/08/14 AMEP Comment Clarification BBVN-FIVE-S2-SC-AMEP-002/R2 BBVN-FIVE-S2-SC-AMEP- Ujiie
LTR-ENG-0042 Air Handing Unit 3&4 002/R2 Air Handing Unit 3&4

BBVN-FIVE-S2-SC- BV BB 14/08/14 AMEP Comment Clarification BBVN-FIVE-S2-SC-AMEP-0045 BBVN-FIVE-S2-SC-AMEP- Ujiie


LTR-ENG-0043 Air Compressor 0045 Air Compressor
BBVN-FIVE-S2-SC- BV BB 14/08/14 AMEP Comment Clarification BBVN-FIVE-S2-SC-AMEP-001/R1 BBVN-FIVE-S2-SC-AMEP- Ujiie
LTR-ENG-0044 Air Cooled Chiller 001/R1 Air Cooled Chiller
BBVN-FIVE-S2-SC- BV BB 14/08/14 AMEP Comment Clarification BBVN-FIVE-S2-SC-AMEP-0015/R2 BBVN-FIVE-S2-SC-AMEP- Ujiie
LTR-ENG-0045 LV Cable 0015/R2 LV Cable
Correspondence submission to PCI 82
No. To CC: Issued Title Attachment Authored by

BBVN-FIVE-S2-SC- BV BB 14/08/14 MOM Item 11.12.11 AHU Coil MOM-26 page 11/22l Alko Ujiie
LTR-ENG-0046 letter (Capacity of Cooling
Coil in AHU of Bbraun Phase
2 Project), sketch, 2A3size
draiwng
BBVN-FIVE-S2-SC- BV BB 14/08/15 BB-FIVE AP-S2 – Ref: BV-137206/609/140805/SI049 Zone 2 M&E Tu
LTR-ENG-0047 Installation Works
BBVN-FIVE-S2-SC- BV BB 14/08/15 Inspection Schedule for Transformer Delivery & Power On Quang
LTR-ENG-0048
BBVN-FIVE-S2-SC- NS 14/08/15 BB-FIVE AP-S2 – Ref: Non Compliance with Approved Quang
LTR-ENG-0049 Documentation
BBVN-FIVE-S2-SC- BV BB 14/08/19 Transformer Factory Test Schedule Factory Acceptance Test Quang/Ujiie
LTR-ENG-0050 procedure for Transformer;
Test report of Transformer

BBVN-FIVE-S2-SC- NS 14/08/21 BB-FIVE-AP-S2-Ref: Re-Organization of Site Staff Sasaki Toru


LTR-ENG-0051
BBVN-FIVE-S2-SC- BB BV 14/08/21 Smoke Exhaust Duct Duct & Fitting Schedule; Ujiie
LTR-ENG-0052 1A3size drawing
BBVN-FIVE-S2-SC- BB BV 14/08/21 Transformer Inspection Ujiie
LTR-ENG-0053
BBVN-FIVE-S2-SC- NS 14/08/22 Working Time Ujiie
LTR-ENG-0054
BBVN-FIVE-S2-SC- BV 14/08/23 Remaining Works at Substation Area Ujiie
LTR-ENG-0055
BBVN-FIVE-S2-SC- Nhat Hoa 14/08/23 Clean Room Vinyl Flooring Installation 1A3szie schedule Tung QS
LTR-ENG-0056
BBVN-FIVE-S2-SC- Dai Vu 14/08/23 Clean Room Moisture Resistant Membrane Contract Award 1A3szie schedule Tung QS
LTR-ENG-0057

BBVN-FIVE-S2-SC- BB BV 14/08/29 Contractors Scope of Work & Responsibilities prior to Transformer 1A3size drawing Tu
LTR-ENG-0058 Installation
BBVN-FIVE-S2-SC- BB BV 14/08/29 EVN Checking 2A4size photos Ujiie
LTR-ENG-0059
BBVN-FIVE-S2-SC- BB BV 14/08/30 BBVN - FIVE-AP-S2-RFI 180 Response - BV-137206/6011/SMZ- 3A4size colored photos Tuan Anh /
LTR-ENG-0060 140821/D324 Mike
Correspondence submission to PCI 83
No. To CC: Issued Title Attachment Authored by

BBVN-FIVE-S2-SC- BB BV 14/09/02 HILTI Female Type Anchor (Drop in Anchor) Ujiie


LTR-ENG-0061

BBVN-FIVE-S2-SC- VNC2 14/09/05 Site works progress and Outstanding Schedule of Works Tu
LTR-ENG-0062
BBVN-FIVE-S2-SC- BB BV 14/09/08 Stage 1 Remaining Works (Interlocking Function Test) ETF-01 sheet (LV Room test Ujiie
LTR-ENG-0063 items_2 sheets)
BBVN-FIVE-S2-SC- VNC2 14/09/08 Site Works Progress and Outstanding Schedule of Works Tu
LTR-ENG-0064
BBVN-FIVE-S2-SC- LS BB, BV 14/09/10 Provisional Sum Item 10.114 Installation of Loose Furniture Fixtures Hoa
LTR-ENG-0065
BBVN-FIVE-S2-SC- NS 14/09/10 Stage 1 Underground Firefighting Works Hoa
LTR-ENG-0066
BBVN-FIVE-S2-SC- BB, BV 14/09/10 Chiller Equipment Delivery Schedule Ujiie
LTR-ENG-0067
BBVN-FIVE-S2-SC- NS 14/09/11 Quality of Welding Work NCR-06 dated 12-June-2014 Ujiie
LTR-ENG-0068
BBVN-FIVE-S2-SC- BB BV 14/09/12 Stage 1 Remaining Works (Interlocking Function Test) (ADD.01) MSB Panel Module Control Ujiie/Tu
LTR-ENG-0069 for … Operation 1A3size
drawing
BBVN-FIVE-S2-SC- BB BV 14/09/13 MOM Item 11.20.18 Cable Spacer MOM No.30 page 21 of 31, Ujiie/Tu
LTR-ENG-0070 Product data sheet, 2A3size
drawings
LTR/VIE-001 BB 14/09/16 muon 02 khoa (1 khoa co, 1 khoa dien) Toan

BBVN-FIVE-S2-SC- BB BV 14/09/18 MOM Item 11.17.6 Pre-Action System Confirmation letter from Ban Ujiie
LTR-ENG-0071 Mai System JSC, Certificates,
1A3size drawings
Correspondence submission to PCI 84
No. To CC: Issued Title Attachment Authored by

BBVN-FIVE-S2-SC- BB BV 14/09/19 Material & Installation Flow Chart Ujiie


LTR-ENG-0072
BBVN-FIVE-S2-SC- BB BV 14/09/19 Update Existing DB-1C, DB-1S; DB-1E 1A3size drawing Ujiie
LTR-ENG-0073
BBVN-FIVE-S2-SC- NS 14/09/20 Air Compressor Delivery Internal Minutes for Ujiie
LTR-ENG-0074 material/Equipment Inspection
& Acceptance, AMEP-45,
C/O&C/Q
BBVN-FIVE-S2-SC- BB BV 14/09/26 Site Management Ujiie
LTR-ENG-0075
BBVN-FIVE-S2-SC- BB BV 14/10/06 AHU Sealant - Sikaflex 221 Confirmation letter from Ujiie
LTR-ENG-0076 manufacturer (AL-KO),
Product Data sheet for One-
component adhesive sealant;
Certificate Hygiene
conformity test

BBVN-FIVE-S2-SC- BB BV 14/10/09 FM 200 Re-Filling Letter FM 200 Filling time; Tu


LTR-ENG-0077 FIKE FIRE Suppression
System Distribution IN
VIETNAM
BBVN-FIVE-S2-SC- BB BV 14/10/09 Electrical Cable Color Tu
LTR-ENG-0078

BBVN-FIVE-S2-SC- BB BV 14/10/13 Grundfos Pump Certificate of Origin Confirmation letter from Tu


LTR-ENG-0079 Grundfos; Certificate of
Origin/Processing; Certificate
of Quality & Quantity; IN-
AMEP-66/R1 dated 20-Jun-
2014

LTR/VIE-002 BB 14/10/02 muon 02 khoa (1 khoa co, 1 khoa dien)_3/10 den 17/10 Toan
BBVN-FIVE-S2-SC- NORTH 14/10/13 Issue for Construction Drawing Tu
LTR-ENG-0080 STAR
BBVN-FIVE-S2-SC- BB BV 14/10/13 Stage 1 Clean Room Thanh
LTR-ENG-0081
BBVN-FIVE-S2-SC- BB BV 14/10/16 AMEP-173 Ballast & Lamp for Lighting Confirmation letter by Ujiie
LTR-ENG-0082 THORN, IN_AMEP-173 dated
9-October-2014
Correspondence submission to PCI 85
No. To CC: Issued Title Attachment Authored by

BBVN-FIVE-S2-SC- BB BV 14/10/17 AMEP-173 Ballast & Lamp for Lighting Confirmation letter by Ujiie
LTR-ENG-0082/R1 THORN, IN_AMEP-173 dated
9-October-2014, Comparison
table Lighting Specification,
Technical Specification,
Product Data Sheet

BBVN-FIVE-S2-SC- BB BV 14/10/17 AMEP-173 Ballast & Lamp for Lighting


LTR-ENG-0083
BBVN-FIVE-S2-SC- BB BV 14/10/20 Badge Printer & Card Sample Ujiie
LTR-ENG-0084
BBVN-FIVE-S2-SC- BB BV 14/10/20 RFC-105 Response - AMS-140910/D361 Hoa
LTR-ENG-0085
BBVN-FIVE-S2-SC- BB BV 14/10/20 AMEP-179 Water Pump Tank Confirmation letter from Ujiie
LTR-ENG-0086 A&M technical equipment;
Certificate authorised
distributorship, IN_AMEP 179
dated 20-October-2014,

BBVN-FIVE-S2-SC- BB BV 14/10/22 Motorized Valve for AHU IN-AMEP-0036(A) dated 18- Ujiie
LTR-ENG-0087 Oct-2014, AMEP-0036 dated
03-Jun-2014
BBVN-FIVE-S2-SC- BB BV 14/10/28 Door Fan Test Ujiie
LTR-ENG-0088
BBVN-FIVE-S2-SC- NS 14/10/27 Clean Room Ceiling Installation Ujiie/Tu
LTR-ENG-0089
BBVN-FIVE-S2-SC- BB BV 14/10/30 BV-137206/6011/SMZ-141027/D417 (RFC-123) Change of Mr. Hoa
LTR-ENG-0090 Location for Louver Opening
BBVN-FIVE-S2-SC- BB BV 14/10/30 FM 200 Refilling Confirmation Letter from Tu
LTR-ENG-0091 European Tech., JSC
BBVN-FIVE-S2-SC- BB BV 14/10/31 Viet Kim Company - VRV Air Conditioning Tu
LTR-ENG-0092
BBVN-FIVE-S2-SC- BB BV 14/11/04 MOM Item 8.5.71 RFC-26 Fire Smoke Supply Air Fans RFC-26 Additional OA Tu
LTR-ENG-0093 Supply Fan for Smoke
Exhaust,2A3size drawings;
List of Pending documents for
Resubmission
BBVN-FIVE-S2-SC- BB BV 14/11/04 MOM Item 8.5.71 RFC-26 Fire Smoke Supply Air Fans Tu
LTR-ENG-0093A
Correspondence submission to PCI 86
No. To CC: Issued Title Attachment Authored by

BBVN-FIVE-S2-SC- BB BV 14/11/10 BBVN-FIVE-S2-SC-AMEP_157: Ball Valve for Compressor Tie-in IN-AMEP-157 Ujiie
LTR-ENG-0094 Work
BBVN-FIVE-S2-SC-
LTR-ENG-0095
BBVN-FIVE-S2-SC-
LTR-ENG-0096
BBVN-FIVE-S2-SC-
LTR-ENG-0097
Correspondence submission to PCI 87
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 88
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 89
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 90
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 91
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 92
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 93
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 94
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 95
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 96
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 97
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 98
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 99
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 100
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 101
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 102
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 103
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 104
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 105
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 106
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 107
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 108
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 109
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 110
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 111
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 112
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 113
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 114
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 115
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 116
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 117
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 118
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 119
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 120
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 121
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 122
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 123
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 124
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 125
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 126
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 127
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 128
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 129
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 130
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 131
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 132
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 133
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 134
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 135
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 136
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 137
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 138
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 139
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 140
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 141
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 142
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 143
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 144
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 145
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 146
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 147
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 148
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 149
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 150
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 151
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 152
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 153
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 154
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 155
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 156
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 157
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 158
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 159
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 160
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 161
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 162
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 163
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 164
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 165
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 166
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 167
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 168
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 169
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 170
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 171
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 172
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 173
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 174
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 175
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 176
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 177
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 178
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 179
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 180
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 181
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 182
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 183
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 184
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 185
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 186
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 187
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 188
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 189
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 190
No. To CC: Issued Title Attachment Authored by
Correspondence submission to PCI 191
No. To CC: Issued Title Attachment Authored by
Quatity BV/SMZ FOR
No. Issued Title
(Copies) CON Chop
BV-140218-01 14/02/18 Standards form for reference Thu
BV-140219-01 14/02/19 Benchmark Handover (Minutes of handover btw TONE, ACC & Thu
BBVN)

BBVN-FIVE-S2-SC-TS-0001-14 14/02/26 CVs & Project Organizational Chart; Quality Management Plan ; Lan
Project Execution Plan
BBVN-FIVE-S2-SC-TS-0002-14 14/02/27 Pile Survey Report (by Shimizu)
BBVN-FIVE-S2-SC-TS-0003-14 14/02/28 1.      BBVN-FIVE-S2-SC-AMS-0002-14 Method statement for temporary office, 2.     
BBVN-FIVE-S2-SC-LET-ENG-0001-14 Pile survey report, 3.      BBVN-FIVE-S2-SC-
4.      BBVN-FIVE-S2-SC-ASD-0003-14 Approval for temporary site office shop
drawingASD-0003-14 Approval for signboard shop drawing, RFI_0002, RFI_0003,
Project Safety Plan, AME_001, AME_0002

BBVN-FIVE-S2-SC-TS-0004-14 14/03/03 Return borrowed documents


BBVN-FIVE-S2-SC-TS-0005-14 14/03/03 4 Method statements AMS-003-006 (water supply, sewage water,
temporary electricity, relocation of fire fighting) ,AMS-0001
(Pesticide), ADP-0006 (QCP-1), APD-0007 (QCP-2), RFI-0004 (Grid
line survey)
BBVN-FIVE-S2-SC-TS-0006-14 14/04/03 2 RFI 0005 & 0006, APD-0008 (ITPs)
BBVN-FIVE-S2-SC-TS-0007-14 14/03/04 Return borrowed documents
BBVN-FIVE-S2-SC-TS-0008-14 14/03/05 AMASA_0002 (geotextile), AMS-0001/R1 Pre-condition survey
method, RFI_0007 (hard copy of drawing with stamp)
BBVN-FIVE-S2-SC-TS-0009-14 14/03/06 ASD Site office _0.002/R3
BBVN-FIVE-S2-SC-TS-00010-14 14/03/07 AMASA_0003 (Concrete grade & Slump), APD_0009 Prj
Environmental Plan; RFI_0008_Brace steel structure
BBVN-FIVE-S2-SC-TS-00011-14 14/03/10 APD-0001/R1_Project Management Plan (Rev.1)
BBVN-FIVE-S2-SC-TS-00012-14 14/03/11 AMS_0007 (Pile rectification), AMS_0008 (AMS list)
BBVN-FIVE-S2-SC-TS-00013-14 14/03/12 AMASA_0003/R1 (concrete grade&slump), RFI_0009 (Design
Queries_M&E/Toilet), ASD_0002/R1 (Signboard Rev.1),

BBVN-FIVE-S2-SC-TS-00014-14 14/03/14 Geotextile additional document (Company profile) + 8 contracts for


reference of experience from TEINCO
BBVN-FIVE-S2-SC-TS-00015-14 14/03/28 Giay Chung nhan kiem dinh Dong ho nuoc Zenner- Comma/
Verification Certificate for Water Meter
BBVN-FIVE-S2-SC-TS-00016 14/03/26 Official Electric Meter Number showing dated 19 Feb 2014
BBVN-FIVE-S2-SC-TS-00017 14/04/01 Cerfiticate basic scaffolding course (Tubular)_Vu Viet Anh
BBVN-FIVE-S2-SC-TS-00018 14/04/02 Certificate for Pesticide Registration, Material Safety Data Sheet (for
AMASA_0002_R1)
BBVN-FIVE-S2-SC-TS-00019 14/04/04 Giay chung nhan dang ky thue (Certificate of tax registration)
(Notarized copy)
BBVN-FIVE-S2-SC-TS-00020 14/04/05 19 A3 size drawings REFERENCE for Space Management (Steel
structure, M&E combine)
BBVN-FIVE-S2-SC-TS-00021 14/04/14 RFC-0003 (M&E) Addition FD at ground and first floor
BBVN-FIVE-S2-SC-TS/M&E-00022 14/04/15 Document, Drawing regarding ceiling, wall (Soft file)
BBVN-FIVE-S2-SC-TS/M&E-00023 14/04/18 IN (ASD: 0008_00, AMEP: 0001/R1, 0002/R2, 0003/R1, 0004-00,
0005-00, 0006-00, 0007-00, 0008-00; AMS: 0003//R3, 0004/R1,
0005/R1, 0006/R1, 0007/R1, 0008/R1, 0009/R1, 0013-00); OUT
(AMS: 0014, 0015, 0016)_ CD (Soft Files)
BBVN-FIVE-S2-SC-TS/M&E-00024 14/04/18 CD_AMEP (full)
BBVN-FIVE-S2-SC-TS-00025 14/04/22 RFI Progress status
BBVN-FIVE-S2-SC-TS-00026 14/04/23 IN_AMEP (0013, 0013/R1, 0014, 0014/R1, 0016, 0019)
BBVN-FIVE-S2-SC-TS-00027 14/04/24 IR FORMS for Earth Work & RC Works (9 Forms in total)
BBVN-FIVE-S2-SC-TS-00028 14/04/26 ASD_0005/R3 copy Pile cap Rev.3 (Revised based on comments in
ASD-0005/R2 dated 03-Apr-2014) dated 12-Apr-2014

BBVN-FIVE-S2-SC-TS-00029 14/04/28 IN _ ASD_0006/R1 dated 15-Apr-2014 titled: Steel Structure_Rev.1


revised based on ASD_0006 dated 31-Mar-2014

BBVN-FIVE-S2-SC-TS-00030 14/04/29 Report of Taking Photograph and Surveying Actual Quality of


B.Braun FIVE AP Construction Site Stage No.2
BBVN-FIVE-S2-SC-TS-00031 14/04/29 Report of Taking Photograph and Surveying Actual Quality of
B.Braun FIVE AP Construction Site Stage No.2 (4 copies)
BBVN-FIVE-S2-SC-TS-00032 14/05/05 MOM_12
BBVN-FIVE-S2-SC-TS-00033 14/05/05 M&E Sample Board No.1 _ PPR for Cold Water System, GI Pipe for
FF and Air Compressor, BS pipe for Chiller system
BBVN-FIVE-S2-SC-TS-00034 14/05/05 M&E Sample Board No. 2 _ u. PVC pipe&fittings for Condensate
drain plumbing & Sanitary system, HDPE flexible for electric system,
HDPE pipe for drainage system (compacted area)

BBVN-FIVE-S2-SC-TS-00035 14/05/05 M&E Sample Board No. 3 _ HVAC System


BBVN-FIVE-S2-SC-TS-00036 14/05/05 M&E Sample Board No. 4 _ Lightning System
BBVN-FIVE-S2-SC-TS-00037 14/05/05 M&E Sample Board No. 5 _ Steel Pipe & Fittings and Support of
M&E Systems
BBVN-FIVE-S2-SC-TS-00038 14/05/05 M&E Sample _ Sleeve
BBVN-FIVE-S2-SC-TS-00039 14/05/05 RFC-0009
BBVN-FIVE-S2-SC-TS-00040 14/05/12 APD-0006/R2, APD-0007/R1, APD-00008/R3 (Tuan Anh to
Vinaconex2)
BBVN-FIVE-S2-SC-TS-00041 14/05/12 XYPEX sample
BBVN-FIVE-S2-SC-TS-00042 14/05/12 MOM_13 to North Star
BBVN-FIVE-S2-SC-TS-00043 14/05/12 IN_ASD_0014/R1 Ground Floor Slab, Beam_Rev.1
BBVN-FIVE-S2-SC-TS-00044 14/05/12 IN_ASD_0005/R5_ Trench Pit (For Con. Chopped) 2A3pages
BBVN-FIVE-S2-SC-TS-00045 14/05/14 M&E
BBVN-FIVE-S2-SC-TS-00046 14/05/15 Sample Board_Duct Equipments for HVAC System
BBVN-FIVE-S2-SC-TS-00047 14/05/20 Official Contract Documents
BBVN-FIVE-S2-SC-TS-00048 14/05/19 MOM_13 & 14
BBVN-FIVE-S2-SC-TS-00049 14/05/20 Sample Board_Air Grille for HVAC system
BBVN-FIVE-S2-SC-TS-00050 14/05/21 Sample Board_GI Conduit & Supports
BBVN-FIVE-S2-SC-TS-00051 14/05/21 Sample Board_MV & LV Cable
BBVN-FIVE-S2-SC-TS-00052 14/05/22 IN_ASD-0015/R2 dated 19-May-2014 & ASD-0026/R1 dated 19-
May-2014, IN_ASD-0038 dated 19-May-2014
BBVN-FIVE-S2-SC-TS-00053 14/05/22 IN_BBVN-FIVE-S2-SC-ASD-0014/R1
BBVN-FIVE-S2-SC-TS-00054 14/05/22 IN_ASD-22/R1 & IN - ASD-23/R1 dated 22-May-2014
BBVN-FIVE-S2-SC-TS-00055 14/05/22 IN_ASD-22/R1 & IN - ASD-23/R1 dated 22-May-2015
BBVN-FIVE-S2-SC-TS-00056 14/05/23 MOM_15
BBVN-FIVE-S2-SC-TS-00057 14/05/24 IN_ASD-0008/R2 (A) M&E Underground Drawings_Rev.2 Sleeve for
pipe underground Revised based on comments in ASD-0008/R1 dated
13-May-2013
BBVN-FIVE-S2-SC-TS-00058 14/05/26 IN_ SI_05 Schedule Recovery Plan
BBVN-FIVE-S2-SC-TS-00059 Tuan Anh

BBVN-FIVE-S2-SC-TS-00060 14/05/27 IN - ASD-0033 Ground Floor Wall Type Layout


BBVN-FIVE-S2-SC-TS-00061 14/05/28 IN_ASD-0035 Crane Beam Layout Plan & Section; IN - ASD-0020
CBP for Mezzanine Floor
BBVN-FIVE-S2-SC-TS-00062 14/05/29 IN- ASD-0021/R3 (A) _ M&E Ground Floor Ceiling Combination for
Clean Room Detail Section _ Rev. 3 (A)
BBVN-FIVE-S2-SC-TS-00063 14/05/29 IN_ ASD-0028 M&E Ground Floor Combination Look down(Clean
room) & 1st Floor Ceiling Combination (office) & IN - ASD-0029
M&E Ground Floor Combination Look up(Clean room)

BBVN-FIVE-S2-SC-TS-00064 14/05/29 Interim Payment No.2 (Draft)


BBVN-FIVE-S2-SC-TS-00065 14/05/29 IN_ ASD-0025/R2 Ground Beam for Zone 2_Rev.2 dated 28-May-
2014
BBVN-FIVE-S2-SC-TS-00066 14/05/30 IN_ASD-0013/R1 Roof & Gutter water proofing _Rev.1 dated 29-
May-2014 (For Con chop)
BBVN-FIVE-S2-SC-TS-00067 14/05/30 IN_Transmittal Sheet (BV)_List of Items to be Dismantled at Vacuum
Pump & AHU area
BBVN-FIVE-S2-SC-TS-00068 14/05/31 IN_ASD-0020 dated 28-May-2014 CBP for Mezzanine Floor &
IN_ASD-0026/R1 dated 19-May-2014 Concrete Body Plan for First
Floor_Rev.1
BBVN-FIVE-S2-SC-TS-00069 14/06/02 IN_ASD-0051 dated 29-May-2014 Gridline A Downspout (Sifon) & BV/SMZ For Con
VRV Room & Gridline Z Downspout (Sifon) Chop
BBVN-FIVE-S2-SC-TS-00070 14/06/02 IN - AMS-0030/R1 _ Fence Relocation _ Rev.1 dated 2-June -2014 For con Chop

BBVN-FIVE-S2-SC-TS-00071 14/06/03 IN_AMS-0041 dated 2-June-2014 MS-BLD.07 - Structure Steel For Con Chop
Erection Works dated 2-June-2014
BBVN-FIVE-S2-SC-TS-00072 14/06/04 CCTV Sytem
BBVN-FIVE-S2-SC-TS-00073 14/06/04 IN_AMS-0024/R1 dated 3-June-2014 MS-BLD.18 Method Statement
for Road & Stormwater works_Rev.1
BBVN-FIVE-S2-SC-TS-00074 14/06/05 IN_ASD-0036 dated 3-June-2014 Dock Level Plan & Section For con Chop
BBVN-FIVE-S2-SC-TS-00075 14/06/05 IN_AMEP (50,20/R1,57/R1, 73,51/R1,19/R1, 74,52/R1, 79, 44, CD
60/R1, 65/R1, 13/R1, 13/R2, 32/R1, 33/R1, 70, 34/R1, 23/R1_B, 49,
48, 47, 18, 42, 27, 40, 43, 71, 39, 38/R1) , AMS (14/R2, 40, 29,
20/R1, 29_A, 35, 39, 38, 34, 33), ASD (50, 58, 62, 21/R3_A, 28, 29)

BBVN-FIVE-S2-SC-TS-00076 14/06/06 Additional Document for AMASA-11 (Based on comments in


AMASA-0011/R3 dated 31-May-2014)_Specification_Interlac 645

BBVN-FIVE-S2-SC-TS-00077 14/06/06 Foundation Pit & Concrete Body Plan (CBP).Rev2( Revised based on
RFI-072)
Drawing Ground Floor Beam Layout Plan (1 of 6)
BBVN-FIVE-S2-SC-TS-00078 14/06/07 IN_MOM_017
BBVN-FIVE-S2-SC-TS-00079 14/06/10 Main Contract
BBVN-FIVE-S2-SC-TS-00080 14/06/10 Tender Submission documents for B. Braun Project from QS Hanoi to
Tùng QS filing in construction site (Commercial Part_Original, Rev.1
& Rev.2)
BBVN-FIVE-S2-SC-TS-00081 14/06/10 Refer to AMASA-0025 dated 28-May-2014 regarding: Wire Mesh
Sl52, SL82_Supplemental documents: (1) Song Hop Luc Weldmesh
Co., Ltd - HLC Catalogue; (2) Song Hop Luc Weldmesh Co., Ltd -
Certification & (3) Song Hop Luc Weldmesh Co., Ltd - List of
Reference Projects
BBVN-FIVE-S2-SC-TS-00082 14/06/10 IN_AMEP (10, 54, 62, 63, 64, 66, 67, 68, 69, 15/R2, 16/R1, 47/R1,
49/R1); IN_AMS (39, 48); IN_ASD (60, 63, 64)
BBVN-FIVE-S2-SC-TS-00083 14/06/11 IN_ASD-0043/R1 & ASD-0044/R1
BBVN-FIVE-S2-SC-TS-00084 14/06/11 List of FM Approved Materials (M&E and Building)
BBVN-FIVE-S2-SC-TS-00085 14/06/11 Loose Furniture Quotation (PC sum) [2A3size pages]
BBVN-FIVE-S2-SC-TS-00086 14/06/12 IN_ASD_0054/R1 dated 11-Jun-2014 Internal Staircase_Rev.1 For con red chop

BBVN-FIVE-S2-SC-TS-00087 14/06/12 IN_ASD-0062/R1 dated 11-Jun-2014 HVAC-Water Chiller Pipe For con red chop
Layout 1st Floor _ Stage 1_Rev.1
BBVN-FIVE-S2-SC-TS-00088 14/06/12 Shop Drawing for Steel Door Installation (90A3size drawings)

BBVN-FIVE-S2-SC-TS-00089 14/06/12 IN_AMEP (35, 46, 78, 81,82,83,86); IN_ASD (49, 62/R1, 69, 76)_CD

BBVN-FIVE-S2-SC-TS-00090 14/06/13 SANITEC System - Product Data Sheet (Refer to RFC-0034: Painting
on Brick Wall at Air Shaft)
BBVN-FIVE-S2-SC-TS-00091 14/06/13 FM Approval Materials (Building Material)_R1
BBVN-FIVE-S2-SC-TS-00092 14/06/13 IN_APD-44/R1 dated 28-May-2014: Quality Control Plan for For con red chop
Masonry & Plastering Works (QCP-6)_Rev.1 ; IN_AMS-30/R1 dated
2-Jun-2014; IN_AMS-30/R1 (ADD.01) dated MS-46: Fence
Relocation_Rev.1 (Additional Document) dated 13-Jun-2014;
IN_AMS-0025 dated 11-Jun-2014: MS-BLD.03 - Scaffolding
Installation & Dismantling Works

BBVN-FIVE-S2-SC-TS-00093 14/06/13 IN_ASD_0047/R1 dated 12-Jun-2014: Office Toilet Drawings_Rev.1; For con red chop
IN_ASD-0030/R2 dated 12-Jun-2014: Ground Floor and First Floor
Ceiling_Rev.2; IN_ASD-0053/R1 dated 12-Jun-2014: External
Staircases_Rev.1; IN_ASD-0031/R1 dated 12-Jun-2014:
Male&Female ground floor toilet&changing room_rev.1

BBVN-FIVE-S2-SC-TS-00094 14/06/13 IN_ASD-0032/R2 dated 11-Jun-2014: General Floor Finish For con red chop
Layout_Rev3; IN_ASD-0056/R1 dated 11-Jun-2014: General First
Floor Finish Floor Layou_Rev.1
BBVN-FIVE-S2-SC-TS-00095 14/06/14 FM Approval Materials (M&E Materials)_Rev.1
BBVN-FIVE-S2-SC-TS-00096 14/06/14 IN_MOM_18
BBVN-FIVE-S2-SC-TS-00097 14/06/14 IN_ASD (76, 10/R1, 75, 28); IN_AMEP (93,94,95,90,91,92,48/R1)

BBVN-FIVE-S2-SC-TS-00098 14/06/16 IN_ASD-0070/R1 dated 14-Jun-2014 1st Floor Beam Rebar


Arrangement_Part 2_Rev.1
BBVN-FIVE-S2-SC-TS-00099 14/06/16 Interim Payment No.2
BBVN-FIVE-S2-SC-TS-00100 14/06/17 IN_ASD-0035 Crane Beam Layout Plan & Section dated 28-May- For con red chop
2014
BBVN-FIVE-S2-SC-TS-00101 14/06/17 Monthly Statement No.2_Interim Payment
BBVN-FIVE-S2-SC-TS-00102 14/06/18 IN_ASD-0077/R1 dated 17-June-2014 1st floor slab rebar For con red chop
arrangement Rev.1
BBVN-FIVE-S2-SC-TS-00103 14/06/18 IN_ASD-0068/R1 dated 16-Jun-2014 1st floor beam rebar For con red chop
arrangement
BBVN-FIVE-S2-SC-TS-00104 14/06/19 Additional Document for TS_91 dated 13/June/2014 regarding FM
Approval Materials for Building (refer to Item No. 13 - Fire Resistant
Door _ 120 minutes)_ English translation
BBVN-FIVE-S2-SC-TS-00105 14/06/19 IN_ASD-0059/R2 dated 19-June-2014 regarding Ground Beam for For con red chop
Zone 3 _ Rev.2
BBVN-FIVE-S2-SC-TS-00106 14/06/20 IN_ASD-57/R2 dated 20-June-2014 First Floor Wall Type_Rev.2 For con red chop

BBVN-FIVE-S2-SC-TS-00107 14/06/21 MOM_19


BBVN-FIVE-S2-SC-TS-00108 14/06/23 IN_ASD-20 (Replaced 1 drawing, A3size) MEZZ Floor Beam Layour For con red chop
Plan (4 of 6)
BBVN-FIVE-S2-SC-TS-00109 14/06/24 IN_ASD-15/R2 dated 19-May-2014 Ground Floor Column For con red chop
layout_rev.2
BBVN-FIVE-S2-SC-TS-00110 14/06/25 IN_ASD-15/R2 dated 19-May-2014 Ground Floor Column For con red chop
layout_Rev.2 (2A3size drawings)
BBVN-FIVE-S2-SC-TS-00111 14/06/25 IN_ASD-83 dated 25-Jun-2014 Rebar Arrangement for Stormwater For con red chop
System (A, B, D), IN_ASD-85 dated 25-Jun-2014 Rebar Arrangement
for Stormwater System ( C )
BBVN-FIVE-S2-SC-TS-00112 14/06/26 2 Minutes of Hand-over Material of Owner (Pole Lighting, Lighting
Fixture, Pole Camera, Dome Camera)_6 items
BBVN-FIVE-S2-SC-TS-00113 14/06/30 IN_ASD-26/R1 dated 19-May-2014 revised 2 A3size drawings For con red chop
following comments
BBVN-FIVE-S2-SC-TS-00114 14/06/30 IN_MOM_20
BBVN-FIVE-S2-SC-TS-00115 14/07/01 Monthly Statement Interim No.3 -Interim Payment
BBVN-FIVE-S2-SC-TS-00116 14/07/02 Refer to AMASA-46 dated 12-June-2014; Clean Room Window -
Tempered Glass Cerfiticate _ Purchase Order (Stage 1) from Channel
Systems
BBVN-FIVE-S2-SC-TS-00117 14/07/02 Refer to MOM 20 (item 11.18.2)_ Factory Acceptance for Compress
Air
BBVN-FIVE-S2-SC-TS-00118 14/07/02 RFC-0026 Fire Smoke Supply Air Fans
BBVN-FIVE-S2-SC-TS-00119 14/07/03 Vinaconex 2 Group Accident Insurance Contract _ Copy
BBVN-FIVE-S2-SC-TS-00120 14/07/03 BV-137206/6011/SMZ-140702/D226 dated 02-7-2014
Chilled water system bypass
BBVN-FIVE-S2-SC-TS-00121 14/07/03 IN_ASD-81/R1 dated 03-July -2014 Mezzanine Floor Beam Rebar For con chop
Arrangement _Rev.1 & IN_ASD-82 (A) dated 3-July -2014 Entrance
Mat & Louver
BBVN-FIVE-S2-SC-TS-00122 14/07/04 Welding Procedure Specification (WPS) and Welding Certificate 6G
Refer to AMS-54 dated 2-July -2014
BBVN-FIVE-S2-SC-TS-00123 14/07/05 IN- ASD-0026R1
FIRST FLOOR BEAM LAYOUT PLAN (1 OF 6) -(R.3) SD-Beam -1FL-141-
HBPE-S-CD-MB-261-1/6
FIRST FLOOR BEAM LAYOUT PLAN (1 OF 6) -(R.3) SD-Beam -1FL-141-
HBPE-S-CD-MB-261-1/6
IN-ASD-0077
1FL SLAB TOP X REINFORCEMENT (R.2) SD-BBS-1FL-141-
HBPE-S-CD-MB-217 - TOP X
1FL SLAB TOP Y REINFORCEMENT (R.2) SD-BBS-1FL-
141-HBPE-S-CD-MB-217 - TOP Y
1FL SLAB TOP X REINFORCEMENT(R.2) SD-BBS-1FL-
141-HBPE-S-CD-MB-218 - BOT X
1FL SLAB TOP Y REINFORCEMENT(R.2) SD-BBS-1FL-141-
HBPE-S-CD-MB-218 - BOT Y
1FL SLAB SECTION AND DETAIL (R.2) SD-BBS-1FL-
141-HBPE-S-CD-MB-217-Detail

BBVN-FIVE-S2-SC-TS-00124 14/07/05 Brick wall Typical detail


Brick wall ground floor plan
Brick wall layout 1st floor & mezzanine
BBVN-FIVE-S2-SC-TS-00125 14/07/05 Refer to Letter BBVN-FIVE-S2-SC-LTR-0016 FM Approval
Materials_Rev.2 based on Letter
BB-137206/6011/SMZ-140703/D228 List of EM Approved
Materials_Rev.2; Catalogue: Automatic air vent c/w gate valve for
Pre-action, Heat Detector, Smoke sampling detection system fire
alarm; Flow switch, Pressure switch

BBVN-FIVE-S2-SC-TS-00126 14/07/07 IN_MOM_21


BBVN-FIVE-S2-SC-TS-00127 14/07/07 Quotation and Furniture Layout
BBVN-FIVE-S2-SC-TS-00128 14/07/08 IN_AMS-28 MS.BLD-09_dated 15-May-2014: XYPEX
Waterproofing for Under Slab
BBVN-FIVE-S2-SC-TS-00129 14/07/08 IN-APD-37 dated 7-july-2014 Quality Control Plan for Road &
Stormwater Works (QCP-9)
BBVN-FIVE-S2-SC-TS-00130 14/07/08 2CVs (Randy & Quyen)
BBVN-FIVE-S2-SC-TS-00131 14/07/09 JSA (Refer to AMS-34/R1 dated 4-July-2014)
BBVN-FIVE-S2-SC-TS-00132 14/07/14 Red bill (VAT) for completed amount No.2 for BB Project dated 22-
May-2014
BBVN-FIVE-S2-SC-TS-00133 14/07/12 IN_MOM No.22
BBVN-FIVE-S2-SC-TS-00134 14/07/12 IN_AMS-55 dated 8-July-2014 MS-BLD 06-B: RC Septic Tank
BBVN-FIVE-S2-SC-TS-00135 14/07/12 IN_NCR-05, 06 dated 11-July-2014: GI Piping Procedure & Welding
Procedure
BBVN-FIVE-S2-SC-TS-00136 14/07/14 IN_D258 dated 14-July-2014: (RFC-069) Relocation of By-pass valve
from Walkable ceiling to inside Toolshop room and additional ball
valve (Process Chilled water system)
BBVN-FIVE-S2-SC-TS-00137 14/07/14 IN-APD-0008/R3 dated 22-Apr-2014 Inspection and Testing Plan
(ITP)_Rev.3
BBVN-FIVE-S2-SC-TS-00138 14/07/14 AS 4100-1998 & Amendment No.1 to AS 4100-1998: Steel Structure

BBVN-FIVE-S2-SC-TS-00139 14/07/15 Embeded Plate (PL8, PL12 Q345B) Test Result & Steel Bar (D12,
D16) Test Result
BBVN-FIVE-S2-SC-TS-00140 14/07/16 Ground Floor Column Layout (2A4size drawings)
BBVN-FIVE-S2-SC-TS-00141 14/07/16 Letter to Ministry of Industry & Trade (Goods and products to be
imported), Ist of goods and products to be imported, Investment
lisence of B. B dated 31-Aug-2011
BBVN-FIVE-S2-SC-TS-00142 14/07/16 BBVN-FIVE-S2-RFC-0073
Modification of Data and Voice System Schematic Diagram
BBVN-FIVE-S2-SC-TS-00143 14/07/16 IN-APD-25/R1 dated 9-May-2014 Clean Construction Protocol for
Clean Room& IN-APD-53 dated 19-June-2014 Access Control Layout
for Clean Room Revised based on comments in APD-0025/R1 dated
9-May-2014
BBVN-FIVE-S2-SC-TS-00144 14/07/17 Monthly Statement No.3_Interim Payment
BBVN-FIVE-S2-SC-TS-00145 14/07/17 IN_ASD-96/R2 dated 17-July-2014 Rebar arrangement for Septic tank For con red chop
rev.2 and IN_ASD-117/R1 dated 17-July-2014 Rebar arrangement for
Pump Pit No.1
BBVN-FIVE-S2-SC-TS-00146 14/07/18 IN_D253 dated 11-July-2014 (RFC-67) IT System Wifi Relocation &
IN_D254 dated 11-July-2014 (RFC-68) Process Exhaust System for
Toolshop Room
BBVN-FIVE-S2-SC-TS-00147 14/07/18 IN_SMZ-140716/D265 dated 16-July-2014 (RFI-159) Pre-action
System
BBVN-FIVE-S2-SC-TS-00148 14/07/21 IN_MOM 23
BBVN-FIVE-S2-SC-TS-00149 14/07/21 IN_AMS-27 dated 20-June-2014 MS-BLD-10 Roofing &
Waterproofing for roof
BBVN-FIVE-S2-SC-TS-00150 14/07/21 IN_SI-34 dated 21-July-2014 Submission of Holiday Tester for FF
System (Underground Pipe)
BBVN-FIVE-S2-SC-TS-00151 14/07/21 IN_ASD-109 dated 21-July-2014 Main Building Phase 2.1 Elevation Red For Conchop

BBVN-FIVE-S2-SC-TS-00152 14/07/22 IN_BV-137206/6011/SMZ-140722/D276 dated 22-July-2014 Minutes


Project walkthrough Stage 1 on 18th & 21st July 2014

BBVN-FIVE-S2-SC-TS-00153 14/07/23 IN_ASD-107/R1 dated 22-July-2014 Crane _ Rev.1 For con red chop

BBVN-FIVE-S2-SC-TS-00154 14/07/23 HSE_Incident_Report (EHS F14 4.13)


BBVN-FIVE-S2-SC-TS-00155 14/07/24 Architecture Drawings Pending List
BBVN-FIVE-S2-SC-TS-00156 14/07/24 Incident Investigation Report No.1
BBVN-FIVE-S2-SC-TS-00157 14/07/25 Test Result of Purlin Strength, Decking Strength, Anchor Bolts (M20,
M24) Strength
BBVN-FIVE-S2-SC-TS-00158 14/07/28 IN_MOM_24
BBVN-FIVE-S2-SC-TS-00159 14/07/30 CD_EVN Document (Soft files)
BBVN-FIVE-S2-SC-TS-00160 14/07/31 IN_ASD-102/R3_ 1& 2 dated 30-July-2014 Bar Bending for Ground For con red chop
Slab Zone 2, Zone 3_Rev.3_Part 1 &@ (Zone 2 & Zone 3) Revised
based on comments in ASD-102/R2 dated 14-July-2014

BBVN-FIVE-S2-SC-TS-00161 14/07/31 IN_AMS-59/R2 dated 25-Jul-2014 MS-BLD.11 Masonry & Plastering


Works_Rev.2
BBVN-FIVE-S2-SC-TS-00162 14/07/31 IN_ASD-110/R1 dated 31-Jul-2014 Ground Floor & 1st Floor Brick For con red chop
Wall Plans and Typical Details (Refer to ASD-90)_Rev.1

BBVN-FIVE-S2-SC-TS-00163 14/07/31 Incident Investigation Report No.1


BBVN-FIVE-S2-SC-TS-00164 14/08/01 IN_MOM 25
BBVN-FIVE-S2-SC-TS-00165 14/08/01 Pending/Remaining Material for Approval
BBVN-FIVE-S2-SC-TS-00166 14/08/02 Purlin Test Result (Zinc coating, Tension strength)
BBVN-FIVE-S2-SC-TS-00167 14/08/02 BV-137206/609/140802/SC/SI-43 dated 2-Aug-2014 "Submission of
Holiday Tester for FF System (Underground Pipe)"

BBVN-FIVE-S2-SC-TS-00168 14/08/04 Cash Flow (end of July) (1A3page)


BBVN-FIVE-S2-SC-TS-00169 14/08/04 Surface water test result (1A4page) & Location of sample (1A3 photo
drawing)
BBVN-FIVE-S2-SC-TS-00170 14/08/04 IN_SI-42 dated 2-Aug-2014 Protection and Proper Covering of Sewer
and rian manhole and stormline and sealing of HDPE pipe sleeve
BBVN-FIVE-S2-SC-TS-00171 14/08/05 IN_SI-46 dated 5-Aug-2014 Pharma Proposed Floor Drain Provision
at Warehouse (2A4size photos)
BBVN-FIVE-S2-SC-TS-00172 14/08/05 Monthly Statement No.4_Interim Payment
BBVN-FIVE-S2-SC-TS-00173 14/08/07 IN_ASD-14 (Replaced 4 drawing, A3size) Ground floor beam layout For con red chop
layout (3&6), 3D model, layout section
BBVN-FIVE-S2-SC-TS-00174 14/08/08 Official (red chop) Payment Certificates No.2 (4A4 pages)
BBVN-FIVE-S2-SC-TS-00175 14/08/11 PV Control Panel for Pre-Action Valve
BBVN-FIVE-S2-SC-TS-00176 14/08/12 IN_SMZ-140811/D308 dated 11-Aug-2014 (RFC-88) Duct
Reinforcement Angle Bar_Approval
BBVN-FIVE-S2-SC-TS-00177 14/08/12 OUT_RFC-76 dated 19-July-2014 Change in Roof connection detail
GL-12_Additional Drawing (1A3size drawing)
BBVN-FIVE-S2-SC-TS-00178 14/08/12 Tie-in
BBVN-FIVE-S2-SC-TS-00179 14/08/12 OUT-AMS-67/R1 (ADD.01) dated 09-Aug-2014
BBVN-FIVE-S2-SC-TS-00180 14/08/12 Tie-in Permit
BBVN-FIVE-S2-SC-TS-00181 14/08/13 BBVN - FIVE-S2-SC/IR/M&E-0246 (3 copies)
BBVN-FIVE-S2-SC-TS-00182 14/08/14 Tie-in Permit
BBVN-FIVE-S2-SC-TS-00183 14/08/14 Tie-in Permit 1
BBVN-FIVE-S2-SC-TS-00184 14/08/14 Confirmation Letter from INOCHI Technology SDN BHD (2 HEPA
BOX samples on 1st August 2014 finished imder Powder Coated
Painting) dated 13 Aug 2014
BBVN-FIVE-S2-SC-TS-00185 14/08/14 IN_ASD-109 dated 21-July-2014 Main Building Phase 2.1 Elevation
& IN_ASD-110/R1 Brick wall
BBVN-FIVE-S2-SC-TS-00186 14/08/15 OUT_ASD-052 (ADD.01) GL Z Downspout Combine w/MEZZ CBP
dated 14-August-2014 (1A3size drawing)
BBVN-FIVE-S2-SC-TS-00187 14/08/15 IN-ASD-110/R1 (39A3size drawings)
BBVN-FIVE-S2-SC-TS-00188 14/08/15
BBVN-FIVE-S2-SC-TS-00189 14/08/15 OUT - AMS-64 Dated 18 July 2014 MS-50: Honeycomb treatment

BBVN-FIVE-S2-SC-TS-00190 14/08/16 Dang ky vao thi cong (MS-23: Equipment for stage 1; MS-24A-1: 2 copies/each
Main Feeder, Cable rack for stage 1; MS-24-A-1: Air Compressor
system)
BBVN-FIVE-S2-SC-TS-00191 14/08/18 Acceptance Order & Acceptance Board Establishment Decision

BBVN-FIVE-S2-SC-TS-00192 14/08/18 IN_ASD-20 MEZZ Floor Beam Layout Plan & IN_ASD-26/R1 First
Floor Beam
BBVN-FIVE-S2-SC-TS-00193 14/08/18 IN_MOM-26&27
BBVN-FIVE-S2-SC-TS-00194 14/08/18 FM Approval Materials (Additional item for FM Approval)
BBVN-FIVE-S2-SC-TS-00195 14/08/18 QC Site Check (16 & 18 August 2014)_9pages
BBVN-FIVE-S2-SC-TS-00196 14/08/18 QC Site Check (18 August 2014)_32pages
BBVN-FIVE-S2-SC-TS-00197 14/08/18 HAND-OVER Sample (Magnetic Holder)_Model: YD602_Full set in
1 box (including door contact)
BBVN-FIVE-S2-SC-TS-00198 14/08/18 Tie-in Work No.17 & Tie-in Work No. 18
BBVN-FIVE-S2-SC-TS-00199 14/08/19 Tie-in Work No.22 & Extending the Temporary storage for the
assembly AHU
BBVN-FIVE-S2-SC-TS-00200 14/08/19 IN_ASD-127 dated 16-AUG-2014 Pantry Details; IN_ASD-16A dated For con red chop
16-AUG-2014 Drainage System; IN_ASD-119/R3 dated 14-AUG-
2014 Ramp Enlarge CBP&Finishing Details_Rev.3; .IN_ASD-124/R1
dated 18-AUG-2014 Aluminum Composite Cladding SD_Rev.1

BBVN-FIVE-S2-SC-TS-00201 14/08/19 IN_ASD-132/R1 dated 19-AUG-2014 Chiller Plinth; IN_ASD-128/R1 For con red chop
dated 19-AUG-2014 AHU CBP Extension_Stage 1_Rev.1

BBVN-FIVE-S2-SC-TS-00202 14/08/19 Application for Work Permit (MS-36-2) LV Busway 3200A 2 sets
Installation
BBVN-FIVE-S2-SC-TS-00203 14/08/19 Cable Gland Material Sample (Tabulation for Cable Gland Sample) 1 copy

BBVN-FIVE-S2-SC-TS-00204 14/08/19 AMEP-37A _ Shop drawing of PV Control panel for Pre-action valve, 1 copy
Pre-action system operation & instruciton manual

BBVN-FIVE-S2-SC-TS-00205 14/08/20 BBVN-FIVE-S2-SC-AMEP-0039 Designers' Comment (Attachment: 1 copy


Tabulation of UPS for Building Managerment System; IN_AMEP-39
dated 29-May-2014)
BBVN-FIVE-S2-SC-TS-00206 14/08/20 Honeycomb Treatment (IN_BBVN - FIVE-S2-SC-AMS-64 dated 18- 1 copy
Aug-2014)
BBVN-FIVE-S2-SC-TS-00207 14/08/21 IN_ASD-119 dated
BBVN-FIVE-S2-SC-TS-00208 14/08/21 IN_ASD-140 dated 21-Aug-2014 Framing Elevation; 1 For con red chop
IN_ASD-006/R2(ADD.02) dated 21-Aug-2014 Steel Structure rev.2
BBVN-FIVE-S2-SC-TS-00209 14/08/21 IN_SMZ-140820/D321 dated 20-Aug-2014 (RFI-173) Fire pump 1 copy + CD
room and clinic drawing
BBVN-FIVE-S2-SC-TS-00210 14/08/21 IR-275, 276, 277 2 Copies (signed+
Stamped)
BBVN-FIVE-S2-SC-TS-00211 14/08/22 INOCHI Technology SDN BHD Confirmation letter 1 copy
BBVN-FIVE-S2-SC-TS-00212 14/08/22 Mock-up inspection report 1 copy
BBVN-FIVE-S2-SC-TS-00213 14/08/22 QC Site Check on 22nd August 2014 (21 pages photos) 1 copy
BBVN-FIVE-S2-SC-TS-00214 14/08/23 AMEP-147 Hermeseal Material Submission (Clear Soft Copy) for FM 1 copy
Approval
BBVN-FIVE-S2-SC-TS-00215 14/08/25 Contract on Compensation Insurance for Labor (HUNG TRANG); (ii) 1 copy (Vnese)
Certificate for Construction Machines and Equipment Insurance &
Certificate for Personal Accident Insurance (HUNG TRANG); (iii)
Construction Machines and Equipment Insurance (SEICO); (iv)
Certificate for Personal Accident 24/24 Insurance (VIEN DONG); (v)
Contract on Compensation Insurance for Labor (North Star)

BBVN-FIVE-S2-SC-TS-00216 14/08/25 Bien ban nghiem thu giai doan hoan thanh (Minutes of Inspection & 6 Official Original
Acceptance of Stage Completion: Preliminary inspection for (Red chop)
substation & MV)
BBVN-FIVE-S2-SC-TS-00217 14/08/25 Package of Main Contractor (Monthly Statement No.4)_Interim 1 Copy
payment
BBVN-FIVE-S2-SC-TS-00218 14/08/25 Loose Furniture Quotation (PC sum) [2A3size pages] (Refer to 1 Copy
AMASA_0028); Labor Insurance for Dang Minh (SEICO)
BBVN-FIVE-S2-SC-TS-00219 14/08/25 QC Site Patrol dated 25-August-2014 by Mr. Duong (07 pages) 1 Copy

BBVN-FIVE-S2-SC-TS-00220 14/08/26 IR-268, 279, 291 & 292 2 Copy (with


signature)
BBVN-FIVE-S2-SC-TS-00221 14/08/26 FM Approval Materials (Additional item for FM Approval)_FM plan 1
review No. 191722
BBVN-FIVE-S2-SC-TS-00222 14/08/26 IN_ASD-129/R1 dated 26-August-2014 AHU Plenum 1 For con red chop
Extension_Stage 1_Rev.1 (1A3size drawing)
BBVN-FIVE-S2-SC-TS-00223 14/08/27 IR-250 & 287 with signature 2 with signature
BBVN-FIVE-S2-SC-TS-00224 14/08/27 IN_ASD-127 dated 16-AUG-2014 Pantry Details revised (1A3size 1 For con red chop
drawing)
BBVN-FIVE-S2-SC-TS-00225 14/08/27 IN_Minutes of Inspection & Acceptance of Tie-in Works: Sub-station 06; 06; 02; 02 Original (red chop)
& MV Inspection record (cable 35kV)
Transformer 2000kVA 35(22)/0.4 kV
Panel, cable LV, out going (dated 25/08/2014); Minutes of Inspection
& Acceptance of Completion and Put into Use (dated 27/08/2014):
Correspondence No.01/140826 pertaining Signing of Electrical
Contract (dated 25/08/2014); EVN Contract (14/190002)

BBVN-FIVE-S2-SC-TS-00226 14/08/28 IN_ASD-144/R1 dated 28-August-2014 Brick Wall Details - Rebar 1 copy (for con red
Details_Rev.1 (1A3size drawing) chop)
BBVN-FIVE-S2-SC-TS-00227 14/08/28 IN-ASD-128 AHU Concrete Body Plan Extension _ Stage 1_Rev.1 1 COPPY
Revised based on comments in ASD-128 dated 7-Aug-2014
BBVN-FIVE-S2-SC-TS-00228 14/08/29 Comments on Site Instructions (28-August-2014)_2A1size photos 1 Color copy

BBVN-FIVE-S2-SC-TS-00229 14/08/30 Result of Checking Slab Level (2A3size pages) 1 Copy


BBVN-FIVE-S2-SC-TS-00230 14/09/01 Bảo lãnh thực hiện hợp đồng số 709BG01400357 1 Original (red chop)

BBVN-FIVE-S2-SC-TS-00231 14/09/02 IN_SMZ-140829/D343 dated 29-AUG (RFC-72) IT Adjustments - 1 Copy


Additional Data Points; IN_SMZ-140829/D344 dated 29-AUG (RFC-
75) New DB Panel for Smoke Extraction Fan; IN_SMZ-140829/D346
dated 29-AUG (RFC-99) C-Channel Support for Duct 2401 and
above_Approval; IN_SMZ-14829 dated 29-AUG (RFC-100) DB-1D
Panel Modification_Approval; IN_SMZ-140829/D348 dated 29-AUG
(RFC-103) DB-1E Panel Modification_Approval

BBVN-FIVE-S2-SC-TS-00232 14/09/03 Monthly Statement No.4_Interim Payment (OFFICIAL) 4 Original Copy (red
chop)
BBVN-FIVE-S2-SC-TS-00233 14/09/03 IN_AMS-100 dated 2-SEP-2014 MS-BLD.12-A: Aluminum Door &
Window
BBVN-FIVE-S2-SC-TS-00234 14/09/03 Minutes of Acceptance and Hand-Over after 72 hours electricity
connection (6 Original copies); 2 Electricity Contract (14/190002)

BBVN-FIVE-S2-SC-TS-00235 14/09/04 IN_AMS90 dated 4-September-2014 MS-BLD.20: Clean Room - 1 copy


Finishing Works Ceiling & Partition Wall
BBVN-FIVE-S2-SC-TS-00236 14/09/04 IN_ASD-110/R1 (ADD) dated 4-September-2014 Brick wall elevation 1 copy (for con red
axis U (3A3size drawings) chop)
BBVN-FIVE-S2-SC-TS-00237 14/09/05 Contract Implementation Bank Guarantee (Deutsche Bank for
Electricity Sale/Consumption), 2 copies of Electricity
Sale/Consumption Contract & 2 original official copies; Minutes of
Meeting Checking the electricity sale rate determination

BBVN-FIVE-S2-SC-TS-00238 14/09/05 IN_SMZ-140905/D352 dated 5-September-2014 (TS-221) 1 copy


Clarification Required
BBVN-FIVE-S2-SC-TS-00239 14/09/05 IN_SI-59 dated 5-September-2014 M&E Items at Stage 1 area / 1 copy
Preparation for Saturday 6th power off
BBVN-FIVE-S2-SC-TS-00240 14/09/05 IN_SMZ-140905/D353 dated 5-September-2014 (RFI-190) Weight 1 copy
Capacity Suspended on Purlin
BBVN-FIVE-S2-SC-TS-00241 14/09/08 6 Original Minutes of handover after 72hour Power on dated 1 ORG (set)
3-Sep-/2014; 2 original EVN Contract (14/190002) dated 5-Sep-2014;
2 original of Electrical Selling Rate (dated 5-Sep-2014)
BBVN-FIVE-S2-SC-TS-00242 14/09/09 IN_ASD_0030 dated 19-August-2014 Ground floor and 1st floor 1 copy
ceiling_Rev.3
BBVN-FIVE-S2-SC-TS-00243 14/09/09 As-Built Roof Decking Level (1A4page) 1 copy
BBVN-FIVE-S2-SC-TS-00244 14/09/09 IN_AMS-95 dated 29-August -2014 MS-BLD.52: Warehouse Wall 1 copy
Demolition for Roller Shutter ; IN_APD-58/R1 dated 9-September-
2014 Quality Control Plan for Waterproofing Work (QCP-5)_Rev.1

BBVN-FIVE-S2-SC-TS-00245 14/09/09 IN_AMS-104 dated 9-September-2014 MS-BLD.06-C: 1 copy


Reinforcement Concrete Ramp Extension;
BBVN-FIVE-S2-SC-TS-00246 14/09/09 Incident Investigation Report No.2a, 2b & 2c 1 copy
BBVN-FIVE-S2-SC-TS-00247 14/09/10 Monthly Statement No.5 (Interim Payment) 1 copy
BBVN-FIVE-S2-SC-TS-00248 14/09/10 25A3size As-Built Drawings (prepared by Hoang Ky CTCP TV Xay 1 copy
lap dien luc), checked by North Star
BBVN-FIVE-S2-SC-TS-00249 14/09/11 Red bill (VAT) for completed amount No.3 for BB Project dated 19- 1 Original
August-2014
BBVN-FIVE-S2-SC-TS-00250 14/09/11 Monthly Statement No.4 (Interim Payment) 4 Original
BBVN-FIVE-S2-SC-TS-00251 14/09/11 Cable Arrangement (1A3size drawing) 1 copy
BBVN-FIVE-S2-SC-TS-00252 14/09/13 IN_ASD-160 dated 13-September-2014 Clean room ceiling shop 1 copy
drawings
BBVN-FIVE-S2-SC-TS-00253 14/09/13 MOM Item No. 11.32.4 1
Flushing method for Ro, PCW Open loop & Close Loop Tie-in Work

BBVN-FIVE-S2-SC-TS-00254 14/09/13 Brick wall elevation axis U (opening locations_design)_1A3size 1 copy


drawing
BBVN-FIVE-S2-SC-TS-00255 14/09/15 Integrity Report BBVN-FIVE-S2-SC-New Building Project. 1 copy
Warehouse Area- Water Leakage 20140813- Occurrence, Suspected
cause of occurrence, Rectification Procedure, Integrity Checking,
Appendix
BBVN-FIVE-S2-SC-TS-00256 14/09/16 MOM No.31 Item No.11.30.8 (Production Area 1 copy
Illumination_Calculation)
BBVN-FIVE-S2-SC-TS-00257 14/09/16 Quality Control Document (Buffer/Chiller Tank) 1 copy
BBVN-FIVE-S2-SC-TS-00258 14/09/16 Monthly Statement No.4 (Interim Payment) 4 ORG (set)

BBVN-FIVE-S2-SC-TS-00259 14/09/16 HEPA Box confirmation letter from INOCHI Technology SDN BHD; 1 copy
Document hand-over for construction finalization
BBVN-FIVE-S2-SC-TS-00260 14/09/16 HAFELE lock document (23A4 pages); OUT_ASD-80/R4 dated 6- 1 copy
September-2014 Shop Drawing for Steel Door Installation with Mr.
Hoa's signature
BBVN-FIVE-S2-SC-TS-00261 14/09/16 IN_ASD-110/R1 dated 31-Jul-2014 Ground Floor & 1st Floor Brick 1 copy
Wall Plans and Typical Details (Refer to ASD-90)_Rev.1; IN_ASD-
145 dated 11-September-2014 Brick Wall Elevation Axis 21

BBVN-FIVE-S2-SC-TS-00262 14/09/16 QC Patrol_Site Inspection Comments (16-September-2014)-4A3size 1 colored copy


pages with 22 items
BBVN-FIVE-S2-SC-TS-00263 14/09/18 OUT_ASD-110/R1 (revised) Brick wall ground floor plan 1, 2 & 3 1 copy
(3A3size drawings)
BBVN-FIVE-S2-SC-TS-00264 14/09/22 CSA- Internal Quality Issues (18-September-2014)_3A3size pages 1 color copy

BBVN-FIVE-S2-SC-TS-00265 14/09/22 As-built drawing list (Steel structure; As-built list; sub-con) 1 copy
BBVN-FIVE-S2-SC-TS-00266 14/09/22 SMZ-140919/D377 dated 22-SEP-2014 (RFC-111) Fume Exhaust Fan 1 copy
(RFC-111 form, 1A3size drawing)
BBVN-FIVE-S2-SC-TS-00267 14/09/23 IN_ASD-162 dated 23-September-2014 Racking for Warehouse 1 copy red chop

BBVN-FIVE-S2-SC-TS-00268 14/09/25 (MOM Item 16.32)_HILTI load test report 1 copy


BBVN-FIVE-S2-SC-TS-00269 14/09/25 IN_ASD-74/R3 dated 22-September-2014 Dock leveller, dock 1 copy
shelter_Rev.3
BBVN-FIVE-S2-SC-TS-00270 14/09/25 Brick Wall Detail at Axis 19 from E to G Axis (1A3size drawing) 1 copy

BBVN-FIVE-S2-SC-TS-00271 14/09/25 Brick Wall Detail at Axis 19 from E to G Axis (1A3size drawing) 1 copy

BBVN-FIVE-S2-SC-TS-00272 14/09/25 IR/M&E-383 & IR/M&E-385 (signature)_2 copies 2 copy


BBVN-FIVE-S2-SC-TS-00273 14/09/26 As- built lever for decking 1 copy
BBVN-FIVE-S2-SC-TS-00274 14/09/26 Clean Room -Finishing Works Ceiling & Parition Wall 1 copy

BBVN-FIVE-S2-SC-TS-00275 14/09/27 Red Invoice For IPC NO.4 1 ORG (set)


BBVN-FIVE-S2-SC-TS-00276 14/09/29 As-built drawing for DB-1E, 1C, ID, GC 1 copy
BBVN-FIVE-S2-SC-TS-00277 14/09/29 IN_ASD_0058/R1 dated 05-September-2014 Quality control Plan for 1 copy
Waterproofing Work (QCP-5)_Rev.1 (Approval)
BBVN-FIVE-S2-SC-TS-00278 14/09/29 Brick wall elevation axis Z 1 copy
BBVN-FIVE-S2-SC-TS-00279 14/09/29 Clean Room Doors 1 copy
BBVN-FIVE-S2-SC-TS-00280 14/09/30 FM-200 System (for FM submission) 1 copy
BBVN-FIVE-S2-SC-TS-00281 14/09/30 Magnetic Lock 1 sample
BBVN-FIVE-S2-SC-TS-00282 14/10/01 Monthly Statement No.6 Interim Payment (Summary & Building) 1 Book File c
M&E 1St Interim Payment (M&E IPC No.6) 1
BBVN-FIVE-S2-SC-TS-00283 14/10/01 Monthly Statemant No.5 Interim Payment 1 Original
BBVN-FIVE-S2-SC-TS-00284 14/10/01 Underground Fire Fighting Plan Schedule 1 copy
BBVN-FIVE-S2-SC-TS-00285 14/10/01 Clean Room Sprinklers 1 copy

BBVN-FIVE-S2-SC-TS-00286 14/10/01 Atlas Copco Letter ragarding Air Compressor 1 copy


BBVN-FIVE-S2-SC-TS-00287 14/10/01 FIKE Design Information - Ckean Agent System W/Impulse 1 copy
Technology HFC-227EA Agent
BBVN-FIVE-S2-SC-TS-00288 14/10/02 Ho so hoan cong: Nang cong suat tram bien ap (As-Built document: 1 copy (Vietnamese)
Improve the transformer capacity) 2000kVA-35(22)/0.4kV

BBVN-FIVE-S2-SC-TS-00289 14/10/03 Monthly Statement No.5 (Interim Payment) 4 Original copy

BBVN-FIVE-S2-SC-TS-00290 14/10/03 NCR-23 dated 1-October-2014 Unsatisfactory welding quality on 1 copy


sarnafil layer gridline (L-N&20-21) and CSA3-OCT-2014
BBVN-FIVE-S2-SC-TS-00291 14/10/06 IN_APD-0008/R3 dated 22-April-2014 ITP rev.3 and IN_APD-68/R1 1 copy
dated 22-September-2014 Quality Control Plan for Floor Finishing
Works_QCP-8 (1)_Rev.1

BBVN-FIVE-S2-SC-TS-00292 14/10/07 Monthly Payment No.5 4 Original


BBVN-FIVE-S2-SC-TS-00293 14/10/09 DKE comments on drawings for PCCC Resubmission (7A3size 1 Copy
drawings) (refer to DT119 dated 8-Oct-2014 from BB); DIA Lux
Thorn 96 535 724 DUOPRF 3x36W T26 HF IP65 L840 [STD]
Luminaire Data Sheet
BBVN-FIVE-S2-SC-TS-00294 14/10/09 Monthly Payment No.5 Original
BBVN-FIVE-S2-SC-TS-00295 14/10/09 IN-AMS-65/R1 dated 19-September-2014: MS-BLD.51- Demolition 1 Copy
Work for Office Area & Column A12_Rev.1 Revised based on
comments in AMS-65 dated 7-August-2014

BBVN-FIVE-S2-SC-TS-00296 14/10/09 IN-AMS-110(A)/R1 datd 9-Oct-2014 MS-BLD.14-C-1: Finishing 1 Copy


Works- (Flooring Epoxy Floor)
Revised based on comments in AMS_110 dated 18- Sep- 2014 and
IN-AMS-110 (C )/R1 dated 9-Oct-2014 MS-BLD.14-C-3: Finishing
Works- (Moisture Barrier)
Revised based on comments in AMS_110 dated 18- Sep- 2014

BBVN-FIVE-S2-SC-TS-00297 14/10/10 Drawings: 1 Copy


Clean Room Key Plan
14/10/10

CLEAN ROOM SECTION DETAIL - SHEET 1


CLEAN ROOM SECTION DETAIL - SHEET 2
CLEAN ROOM SECTION DETAIL - SHEET 3
CLEAN ROOM TYPICAL DETAILS - SHEET 1
CLEAN ROOM TYPICAL DETAILS - SHEET 2
HANGER WITH OFFSET 65MM
CEILING LAYOUT H=4000MM
HANGER POINT PLAN
WALL LAYOUT
WALL ELEVATION (1 OF 3)
WALL ELEVATION (2 OF 3)
WALL ELEVATION (3 OF 3)
BBVN-FIVE-S2-SC-TS-00298 14/10/10 Calculation and Report for PCCC re-submission: Fire services report - 1 copy
PCCC; Report-Heating, ventilation & cooling system; Report-Fire
fighting system; Hydraulic calculation (Production) CD

BBVN-FIVE-S2-SC-TS-00299 14/10/13 Toilet Perspective (8A3size drawings) 1 copy


BBVN-FIVE-S2-SC-TS-00300 14/10/13 CLEAN ROOM SECTION KEY PLAN 1 copy
CLEAN ROOM SECTION DETAIL - SHEET 1
CLEAN ROOM SECTION DETAIL - SHEET 2
CLEAN ROOM SECTION DETAIL - SHEET 3
CLEAN ROOM SECTION DETAIL - SHEET 4

BBVN-FIVE-S2-SC-TS-00301
BBVN-FIVE-S2-SC-TS-00302 14/10/14 IN-ASD-159 date 13-Oct-2014 1 copy
BBVN-FIVE-S2-SC-TS-00303 14/10/14 IN-ASD_0031/R1 dated 12-June-2014 Male & Female Ground Floor 1 copy
Toilet & Changing Room.
IN-ASD_0047/R1 dated 12-June-2014 Office Toilet Drawings
BBVN-FIVE-S2-SC-TS-00304 14/10/14 IN-AASD-124/R1 dated 18-Aug-2014 Aluminum Composite 1 copy
Cladding Shop Drawings
BBVN-FIVE-S2-SC-TS-00305 14/10/15 IN_AMS-120 dated 14-October-2014 MS-55 Waterproofing for 1 copy
bathrooms & Others Wet Areas
BBVN-FIVE-S2-SC-TS-00306 14/10/15 IN_AMS-120 dated 14-October-2014 MS-55 Waterproofing for 1 copy
bathrooms & Others Wet Areas; IN_APD-77/R1 dated 14-October-
2014 Quality Control Plan for Finishing Work_Painting for Wall &
Ceiling (QCP-8 (2))_Rev.1; IN_APD-83 dated 14-October-2014
Quality Control Plan for Ceiling Work (QCP-8 (3))

BBVN-FIVE-S2-SC-TS-00307 14/10/15 IN_APD-77/R1 dated 14-October-2014 Quality Control Plan for 1 copy
Finishing Work_Painting for Wall & Ceiling (QCP-8 (2))_Rev.1

BBVN-FIVE-S2-SC-TS-00308 14/10/15 IN_APD-77/R1 dated 14-October-2014 Quality Control Plan for 1 copy
Finishing Work_Painting for Wall & Ceiling (QCP-8 (2))_Rev.1

BBVN-FIVE-S2-SC-TS-00309 14/10/15 IN_APD-77/R1 dated 14-October-2014 Quality Control Plan for 1 copy
Finishing Work_Painting for Wall & Ceiling (QCP-8 (2))_Rev.1;
IN_APD-83 dated 14-October-2014 Quality Control Plan for Ceiling
Work (QCP-8 (3))
BBVN-FIVE-S2-SC-TS-00310 14/10/15 IN_APD-83 dated 14-October-2014 Quality Control Plan for Ceiling 1 copy
Work (QCP-8 (3))
BBVN-FIVE-S2-SC-TS-00311 14/10/17 Updated List of Mock-up, Remaining Material List, Main Equipment 1 copy
List (M&E)
BBVN-FIVE-S2-SC-TS-00312 14/10/17 IN_APD-85 dated 17-October-2014 Quality Control Plan for Partition 1 copy
Work (QCP-8 (4))
BBVN-FIVE-S2-SC-TS-00313 14/10/20 BV-137206/6011/SMZ-141016/D397 (RFC-128 dated 17-OCT-2014) 1 copy
Power Distribution System Modification
BBVN-FIVE-S2-SC-TS-00314 14/10/21 Clean Room Ceiling Mock-up List 1 copy
BBVN-FIVE-S2-SC-TS-00315 14/10/21 Equipment Delivery Schedule for RFC-26 1 copy
BBVN-FIVE-S2-SC-TS-00316 14/10/21 Production Exhaust Filter c/w Housing 1 copy
BBVN-FIVE-S2-SC-TS-00317 14/10/21 Panel Status 1 copy
BBVN-FIVE-S2-SC-TS-00318 14/10/21 NDT Test Report 1 copy
BBVN-FIVE-S2-SC-TS-00319 14/10/21 As-built Roof Level/Elevation (1A3size drawing) 1 copy
BBVN-FIVE-S2-SC-TS-00320 14/10/22 (MOM Item 9.42) FM 200 Refilling Station at Hochiminh city, 1 copy
Vietnam
BBVN-FIVE-S2-SC-TS-00321 14/10/22 1 copy
BBVN-FIVE-S2-SC-TS-00322 14/10/23 IN-ASD-150 -Ground Floor and 1st Floor Ceiling Details 1 copy
BBVN-FIVE-S2-SC-TS-00323 14/10/25
BBVN-FIVE-S2-SC-TS-00324 14/10/25 NDT Test Schedule 1 copy
BBVN-FIVE-S2-SC-TS-00325 14/10/25 Sprinkler Head Inspection (3A3size photos, checklist/check sheet, 1 copy
1A3size drawing)
BBVN-FIVE-S2-SC-TS-00326 14/10/27 IN_AMS-100 (B)/R2 dated 25-October-2014 1 copy
BBVN-FIVE-S2-SC-TS-00327 14/10/27 Lighting calculation for cleanroom 1 copy
BBVN-FIVE-S2-SC-TS-00328 14/10/29 M&E Interim Payment (M&E IPC No.7) [A4size bookfile] and 1 copy
Monthly Statement No.7 Interim Payment [A3size bookfile]

BBVN-FIVE-S2-SC-TS-00329 14/10/31 Monthly Statement No.6_Interim Payment 4 ORIGINAL


BBVN-FIVE-S2-SC-TS-00330 14/11/04 V/O No.30 Asphalt Road Increase Area IN_D290 (RFC-55) dated 31- 1 Copy
July-2014; V/O No. 45 Ramp Adjustment IN_D349dated 29-August-
2014
BBVN-FIVE-S2-SC-TS-00331 14/11/04 As-built Foundation, CBP for First Floor and Trench Pit (26A3size 6 Original
drawings)
BBVN-FIVE-S2-SC-TS-00332 14/11/05 Slab Level before Moisture Barrier Application (3A3size page)_1st 1 Copy
Time
BBVN-FIVE-S2-SC-TS-00333 14/11/07 VAT Red Bill For IPC No.06 1 Original
BBVN-FIVE-S2-SC-TS-00334 14/11/07 Monitoring Panel Table for Power On Schedule 1 copy
BBVN-FIVE-S2-SC-TS-00335
BBVN-FIVE-S2-SC-TS-00336
BBVN-FIVE-S2-SC-TS-00337
BBVN-FIVE-S2-SC-TS-00338
BBVN-FIVE-S2-SC-TS-00339
BBVN-FIVE-S2-SC-TS-00340
BBVN-FIVE-S2-SC-TS-00341
BBVN-FIVE-S2-SC-TS-00342
BBVN-FIVE-S2-SC-TS-00343
BBVN-FIVE-S2-SC-TS-00344
BBVN-FIVE-S2-SC-TS-00345
BBVN-FIVE-S2-SC-TS-00346
BBVN-FIVE-S2-SC-TS-00347
BBVN-FIVE-S2-SC-TS-00348
BBVN-FIVE-S2-SC-TS-00349
BBVN-FIVE-S2-SC-TS-00350
BBVN-FIVE-S2-SC-TS-00351
BBVN-FIVE-S2-SC-TS-00352
BBVN-FIVE-S2-SC-TS-00353
BBVN-FIVE-S2-SC-TS-00354
BBVN-FIVE-S2-SC-TS-00355
BBVN-FIVE-S2-SC-TS-00356
BBVN-FIVE-S2-SC-TS-00357
BBVN-FIVE-S2-SC-TS-00358
BBVN-FIVE-S2-SC-TS-00359
BBVN-FIVE-S2-SC-TS-00360
BBVN-FIVE-S2-SC-TS-00361
BBVN-FIVE-S2-SC-TS-00362
BBVN-FIVE-S2-SC-TS-00363
BBVN-FIVE-S2-SC-TS-00364
BBVN-FIVE-S2-SC-TS-00365
BBVN-FIVE-S2-SC-TS-00366
BBVN-FIVE-S2-SC-TS-00367
BBVN-FIVE-S2-SC-TS-00368
BBVN-FIVE-S2-SC-TS-00369
BBVN-FIVE-S2-SC-TS-00370
BBVN-FIVE-S2-SC-TS-00371
BBVN-FIVE-S2-SC-TS-00372
BBVN-FIVE-S2-SC-TS-00373
BBVN-FIVE-S2-SC-TS-00374
BBVN-FIVE-S2-SC-TS-00375
BBVN-FIVE-S2-SC-TS-00376
BBVN-FIVE-S2-SC-TS-00377
BBVN-FIVE-S2-SC-TS-00378
BBVN-FIVE-S2-SC-TS-00379
BBVN-FIVE-S2-SC-TS-00380
BBVN-FIVE-S2-SC-TS-00381
BBVN-FIVE-S2-SC-TS-00382
BBVN-FIVE-S2-SC-TS-00383
BBVN-FIVE-S2-SC-TS-00384
BBVN-FIVE-S2-SC-TS-00385
BBVN-FIVE-S2-SC-TS-00386
BBVN-FIVE-S2-SC-TS-00387
BBVN-FIVE-S2-SC-TS-00388
BBVN-FIVE-S2-SC-TS-00389
BBVN-FIVE-S2-SC-TS-00390
BBVN-FIVE-S2-SC-TS-00391
BBVN-FIVE-S2-SC-TS-00392
BBVN-FIVE-S2-SC-TS-00393
BBVN-FIVE-S2-SC-TS-00394
BBVN-FIVE-S2-SC-TS-00395
BBVN-FIVE-S2-SC-TS-00396
BBVN-FIVE-S2-SC-TS-00397
BBVN-FIVE-S2-SC-TS-00398
BBVN-FIVE-S2-SC-TS-00399
BBVN-FIVE-S2-SC-TS-00400
BBVN-FIVE-S2-SC-TS-00401
BBVN-FIVE-S2-SC-TS-00402
BBVN-FIVE-S2-SC-TS-00403
BBVN-FIVE-S2-SC-TS-00404
BBVN-FIVE-S2-SC-TS-00405
BBVN-FIVE-S2-SC-TS-00406
BBVN-FIVE-S2-SC-TS-00407
BBVN-FIVE-S2-SC-TS-00408
BBVN-FIVE-S2-SC-TS-00409
BBVN-FIVE-S2-SC-TS-00410
BBVN-FIVE-S2-SC-TS-00411
BBVN-FIVE-S2-SC-TS-00412
BBVN-FIVE-S2-SC-TS-00413
BBVN-FIVE-S2-SC-TS-00414
BBVN-FIVE-S2-SC-TS-00415
BBVN-FIVE-S2-SC-TS-00416
BBVN-FIVE-S2-SC-TS-00417
BBVN-FIVE-S2-SC-TS-00418
14/10/09
Send to/Receiver Author/Remarks File Code Volume
Vol 01
Vol 01

Hard & Soft

Hard
Soft

Mrs. Nguyet BB
Ms. Thu

Mr. Oscar

Thu
Thu
BB, BV

Ngo Duy Ngoc (North Star)


Tam (North Star)

Tam (North Star)


Ms. Hiep, Ms. Thu
Tam (North Star)
a Kien Northstar
a Quang VINACONEX2

a Giang/a Lam Seico

Mr. Ho Tuong Long LS

Ms. Hiep

Ms. Tam
Ms. Hiep

Ms. Hiep

Ms. Hiep
Ms. Hiep
Ms. Hiep

Ms. Hiep
Ms. Hiep
Mr. Binh

Ms. Hiep
Ms. Tam
Mr. Nham
Mr. Nguyen/Mr. Nham
Mr Quang/Ms. Tam
Ms. Hiep
Ms. Thu
Ms. Tam
Ms. Hiep
Ms. Hiep
MS. Hiep
Ms. Tam

Ms. Tam
Ms. Tam
Mr. Bình
Ms. Tam
Ms. Tam

Ms. Tam
Vinaconex_2 (Mr. Bach Quoc
Binh)
North Star
Ms. Tam

Ms. Tam

Ms. Tam

BB, BV, LS
Ms. Tam
Ms. Tam

Ms. Tam

Mr. Binh

Mr. Binh & Ms. Tam

Mr. Nham

Mr. Lam SEICO

BB, BV
Mr. Binh VINACONEX2

Ms. Tam
Ms. Tam

BB, BV

Vinaconex_2 (Mr. Bach Quoc


Binh)

Ms. Tam
Mr. Long_LS
Tung QS

BB, BV
Ms. Tam

Ms. Tam, Mr. Binh


BB, BV
BB, BV
Mr. Binh

Mr. Lam SEICO

Ms. Tam

Ms. Tam

BB, BV

BB
Mr. Binh

NS, Vinaconex2

NS, Vinaconex3

BB, BV
NS
NS

NS, VNC2

LS
HACXO - SEICO

BV
NS, VNC2

NS, VNC2

BB, BV

Vinaconex2, North Star

Vinaconex2, North Star

NS
Vinaconex2, North Star

Vinaconex2, North Star

Vinaconex2, North Star

Vinaconex2

BB, BV

BB, BV, NS, VNC2

NS
LS, BB, BV
BB, BV

BV

NS
BB, BV
NS

NS, VNC2

BB, BV

BV

Vinaconex2

BV

NS
BB, BV
Vinaconex2, Vinh Hiep Hung

VNC2, NS

BB, BV
BB, BV
BB

NS
NS, VNC2
NS

NS

NS

SEICO

BB, BV

BV
BB

NS

NS, VNC2, Hung Trang, Vien


Dong, Nhat Hoa ICT, Dai Vu

Langdon Seah
NS, VNC2

NS

NS

NS
SEICO
NS

NS, VNC2

NS

NS, VNC2

BB, BV
BB, BV
BB, BV
BB (red stamp), BV

NS
NS
VNC2

VNC2

NS, VNC2

BB, BV
NS
BB., BV
BB., BV
NS

BB, BV
BB, BV

NS
NS

BB, BV, LS
NS, VNC2

BV
BB, BV
NS

BB, BV

RCR
BB, BV
RCR (Mr. Thang)
BV
RCR (Mr. Thang)
NS
BB, BV

NS, VNC2

BB, BV, NS, VNC2

BB
NS
VNC2

RCR (Mr. Thang)

BB. BV

VNC2, NS

NS
BB, BV
SEICO
VNC2
VINASANWA (mr. Hung)

RCR
RCR (full set)

NS+ VNC2

NS+ VNC2

RCR (Diem)

BB, BV

BB, BV

BB, BV

VNC2 Tuan Anh

VNC2, NS

NS

BV

BB, BV
NS
VNC2
BB
BB, BV, LS

NS Incoming from BB 23/08/2014

Langdon Seah (MR. Long -


Associate)
BB, BV, LS Tung QS

VNC2 Tuan Anh

BV Trung ME

BB, BV

NS, VNC2

BV Trung ME
BB, Bv, VNC2, NS Cuong

NS

NS, VNC2

NS
VNC2, NS

BB, BV
NS

NS

BB

Viet Chau

BB

Nhat Hoa ITC

VNC2, NS

BB

NS

NS

NS

NS
NS

BB, BV
VNC2, NS

VNC2

BB, BV
BB, BV, LS
BB

BB

BV
BB (Mr. Thanhf)
C-Chanel (Mr. Yoong)

BB

Vinaconex2, NS

BB/BV

BB/BV

BB/BV
Langdon Seah (MR. Long -
Associate)
BB/BV

BB (Mr. Thanhf)
NS, VNC2

SEICO, VNC2

VNC2, NS

VNC2, SEICO

BB, BV
NS

C-Chanel (Mr. Yoong)

BB, BV
NS

BB, BV

VNC2

BV
BV, BB
C-Chanel (Mr. Yoong)
Nhat Hoa ITC
BB(Bernd Plocher)
BB As-built drawing
Hung Trang

Vinaconex(Mr.Phuc)
C-Chanel (Mr. Yoong)
BV
VINASANWA( Mr.Hung)
BB,BV,Langdon Seah(Mr.Long)
BV,Langdon Seah
BV, BB
BV, BB , Langdon Seah(Mr.Long)

BV, BB
BV,BB

BV,BB

Langdon Seah (MR. Long -


Associate)
Hung Trang (Le Xuan Muoi)

1. Đại Vũ ITC
2. Nhật Hoa ITC
3. Vien Dong
4. Vinaconex 2

BB
North Star

BB(Bernd Plocher)
VNC2, Vien Dong

Dai Vu

Chanel System (Yong)


SD-BBVN2-SUB-CHA-CLN-CLG-LAY-01A A3
Chanel System (Yong)

SD-BBVN2-SUB-CHA-CLN-CLG-SEC-01 A3
SD-BBVN2-SUB-CHA-CLN-CLG-SEC-02 A3
SD-BBVN2-SUB-CHA-CLN-CLG-SEC-03 A3
SD-BBVN2-SUB-CHA-CLN-CLG-TYP-01A A3
SD-BBVN2-SUB-CHA-CLN-CLG-TYP-01B A3
SD-BBVN2-SUB-CHA-CLN-CLG-TYP-32 A3
SD-BBVN2-SUB-CHA-CLN-CLG-LAY-01A A1
SD-BBVN2-SUB-CHA-CLN-CLG-LAY-02 A1
SD-BBVN2-SUB-CHA-CLN-PRT-LAY-01 A1
SD-BBVN2-SUB-CHA-CLN-PRT-ELE-01 A1
SD-BBVN2-SUB-CHA-CLN-PRT-ELE-02 A1
SD-BBVN2-SUB-CHA-CLN-PRT-ELE-03 A1
North Star North 14/10/25
Star
return
documen
t & CD

North Star
VINACONEX2, VIEN DONG SD-BBVN2-SUB-CHA-CLN-CLG-LAY-01A
SD-BBVN2-SUB-CHA-CLN-CLG-LAY-SEC-01
SD-BBVN2-SUB-CHA-CLN-CLG-LAY-SEC-02
SD-BBVN2-SUB-CHA-CLN-CLG-LAY-SEC-03
SD-BBVN2-SUB-CHA-CLN-CLG-LAY-SEC-04

Vinaconex2
North Star

North Star

Hung Trang
Vinaconex2

Dai Vu

Doan Thanh

Vien Dong, Nhat Hoa ITC

Channel System

BB, BV APD

Vien Dong (mr. Long)

North Star

BB, BV
BB, BV
BB, BV
BB, BV
BB, BV
BB, BV
BB, BV

BB, BV
Vien Dong(Mr.Long)

BB, BV
BB, BV
Dai Vu
BB, BV
BB, BV, Langdon Seah

BV
BB, BV, Langdon Seah

BV, BB

BB, BV

BB
BB, BV
Correspondence submission to PCI 243
Code/Ref. Issued Date Title Attachment Delivered to

BV-137206-1009-140312/HSI01 14/03/12 Request for Installation electric cabinet and warning sign at live 10A4 photos Toan Safety
cable, stop pumping water at site
BV-137206-1009-140313/HSI02 14/03/13 Request for installation hard barricade for deep hole, provide rubbish 1A4size photo Toan Safety
bin and toilet temporary at site
BV-137206-1009-140321/HSI03 14/03/21 Request for installation drainage system and cover electric wire at Hoang Safety
washing bay
BV-137206-1009-140418/HSI04 14/04/18 Request for checking during night time at project area and bilingual Hoang Safety
permit to work
BV-137206-1009-140428/HSI05 14/04/28 Water Discharge on adjacent Properties Nguyen, Hoang safety
BV-137206-1009-140428/HSI06 14/04/28 Installation for Lightning system (SMZ & Vinaconex Office) Nguyen, Hoang safety
BV-137206-1009-140505/HSI07 14/05/05 Request for Cleaning Up Public road and Drain Stagnant water 4A4size photos Nguyen, Hoang safety
BV-137206-1009-140514/HSI08 14/05/14 Sadety Improvement
BV-137206-1009-140519/HSI09 14/05/19 Request Safety Issue 7A4size photos Nguyen, Hoang safety, Quang
BV-137206-1009-140521/HSI10 14/05/22 Incompliance of minimum HSE Equipments 1A4size photo Nguyen, Hoang safety
BV-137206-1009-142305/HSI11 14/05/23 Improvement of Security entrance post Nguyen, Hoang safety
BV-137206-1009-142405/HSI12 14/05/24 Cable isolation and arrangement 3A4size photos Nguyen, Hoang safety, Quang M&E
BV-137206-1009-143005/HSI13 14/05/30 Control Speed of Heavy Trucks on Site 1A4size photo Nguyen, Hoang safety, Quang M&E
BV-137206-1009-140623/HSI14 14/06/23 Unsafe Access of Ramp 1A4size photo Nguyen, Hoang Safety, Tu
BV-137206-1009-140623/HSI15 14/06/23 Wearing Safety Glass on Site Nguyen, Hoang Safety, Tu
BV-137206-1009-140630/HSI16 14/06/30 Set up life line system for working at height 1A4size photo Nguyen, Hoang Safety, Tu
BV-137206-1009-140702/HSI17 14/07/02 Set up Stable Access for Heavy Crane 2A4size photos Nguyen, Hoang Safety, Tu
BV-137206-1009-140701/HSI18 14/07/03 Working platform for rebar and transfering material 3A4size photos Nguyen, Hoang Safety, Tu
BV-137206-1009-140708/HSI19 14/07/08 Protect web sling 2A4size photos Nguyen, Hoang Safety, Tu
BV-137206-1009-140711/HSI20 14/07/11 Housekeeping at Stage 1 4A4size photos Nguyen, Hoang Safety, Tu
BV-137206-1009-140711/HSI21 14/07/11 Set up safety net system 1A4size photo Nguyen, Hoang Safety, Tu
BV-137206-1009-140717/HSI22 14/07/17 Covering all openings of gridline 12 2A4size photos Nguyen, Hoang Safety, Tu
BV-137206-1009-140718/HSI23 14/07/18 No Smoking at roof of main building 1A4size photo Nguyen, Hoang Safety, Tu
BV-137206-1009-140723/HSI24 14/07/23 Pumping Stagant Water 2A4size photos Nguyen, Hoang Safety, Tu
BV-137206-1009-140723/HSI25 14/07/23 Covering the gap for the cladding of column GL 12-A 1A4size photo Nguyen, Hoang Safety, Tu
BV-137206-1009-140731/HSI26 14/07/31 Sprinkler pipe system protection 1A4size photo Nguyen, Hoang Safety, Tu, Quang
BV-137206-1009-140805/HSI27 14/08/05 Missing PPE 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140805/HSI28 14/08/05 Housekeeping Materials and tools 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140811/HSI29 14/08/11 Washing Bay Improvements 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140806/HSI30 14/08/06 Protection the Floor at Storage area 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140812/HSI31 14/08/12 HSE Supervisor at night shift Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140822/HSI32 14/08/22 Damage Road at Stage 1 1A4size photo Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140909/HSI33 14/09/09 Housekeeping on site 3A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140910/HSI34 14/09/10 Hard Barricade a visitor balcony area 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140910/HSI35 14/09/11 Working with scissor lift 1A4size photo Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140918/HSI36 14/09/18 Concrete beam is impacting the scaffolding 1A4size photo Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140918/HSI37 14/09/18 Housekeeping on site 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140918/HSI38 14/09/18 Unsafe Working Conditions 3A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140922/HSI39 14/09/22 Unsafe Working Condition 1A4size photo Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140922/HSI40 14/09/22 Unsafe Working Condition 6A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140922/HSI41 Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-140930/HSI42 14/09/30 Unsafe Conditioin at 12 Gridline Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141003/HSI43 14/10/03 Lifeline System 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141009/HSI44 14/10/09 Lighting Condition 1A4size photo Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141011/HSI45 14/10/11 Personal Protective Equipment 3A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141011/HSI46 14/10/11 Housekeeping at AHU area 4A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141003/HSI47 14/10/20 Working at height 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141103/HSI48 14/11/03 Unsafe Scaffolding at Gridline Z 5A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141103/HSI49 14/11/03 Concrete on the Top of Column at Gridline 12 2A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141103/HSI50 14/11/03 Dust on Walkable Ceiling 8A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141105/HSI51 14/11/05 Unsafe Activities at Stage 1 10A4 photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141106/HSI52 14/11/06 Training Protocol 1at Clean Stage at Clean Room Area 3A4size photos Nguyen, Hoang Safety, Tu, Mike
BV-137206-1009-141003/HSI53
Correspondence submission to PCI 244
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 245
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 246
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 247
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 248
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 249
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 250
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 251
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 252
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 253
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 254
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 255
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 256
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 257
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 258
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 259
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 260
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 261
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 262
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 263
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 264
Code/Ref. Issued Date Title Attachment Delivered to

45.00
Correspondence submission to PCI 265
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 266
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 267
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 268
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 269
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 270
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 271
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 272
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 273
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 274
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 275
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 276
Code/Ref. Issued Date Title Attachment Delivered to

+
Correspondence submission to PCI 277
Correspondence submission to PCI 278
Correspondence submission to PCI 279
Correspondence submission to PCI 280
Correspondence submission to PCI 281
Correspondence submission to PCI 282
Correspondence submission to PCI 283
Correspondence submission to PCI 284
Correspondence submission to PCI 285
Correspondence submission to PCI 286
Correspondence submission to PCI 287
Correspondence submission to PCI 288
Correspondence submission to PCI 289
Correspondence submission to PCI 290
Correspondence submission to PCI 291
Correspondence submission to PCI 292
Correspondence submission to PCI 293
Correspondence submission to PCI 294
Correspondence submission to PCI 295
Correspondence submission to PCI 296
Correspondence submission to PCI 297
Correspondence submission to PCI 298
Correspondence submission to PCI 299
Correspondence submission to PCI 300
Correspondence submission to PCI 301
Correspondence submission to PCI 302
Correspondence submission to PCI 303
Correspondence submission to PCI 304
Correspondence submission to PCI 305
Correspondence submission to PCI 306
Correspondence submission to PCI 307

1,244,000
Correspondence submission to PCI 308
Correspondence submission to PCI 309
Correspondence submission to PCI 310
Code/Ref. Issued Date Title Attachment Delivered to

BV-137206/609/130826/SC/SI-01 14/03/12 Request for Installation electric cabinet and warning sign at live Mr. Tu, Nguyen, Hoang Safety
cable, stop pumping water at site
BV-137206/609/130826/SC/SI-01 14/07/27 Earthworks. Backfilling of Stage 2 area Mr. Tu, Nguyen, Hoang Safety
BV-137206/609/140516/SC/SI-02 14/05/16 Foundation Works. Improvement for next stages 5A4 photos Mr. Tu, Nguyen, Hoang Safety
BV-137206/609/140521/SC/SI-03 14/05/21 Foundation Works. Waiting bar for ground slad 1A4size photo Mr. Tu, Nguyen, Hoang Safety
BV-137206/609/140526/SC/SI-04 14/05/26 Improvement of Concrete Quality Tu, Nguyen, Tuan Anh/Hoang QC
BV-137206/609/140526/SC/SI-05 14/05/26 Schedule Recovery Plan 1A3size page Tu, Nguyen, Tuan Anh, Quang, Thanh,
Tung QS
BV-137206/609/140529/SC/SI-06 14/05/29 Report after Inspection at SEICO (Steel Structure Supplier) Factory All SMZ members (email)

BV-137206/609/140530/SC/SI-07 14/05/31 Ground Beam Sleeve


BV-137206/609/140609/SC/SI-08 14/06/09 Report after Inspection at SEICO (Steel Structure Supplier) Factory 21A4 size page photos (4 Tu, Nguyen, Tuan Anh
2nd time photos)
BV-137206/609/140609/SC/SI-09 14/06/09 Concrete Curing Progress Tu. Nguyen, Tuan Anh
BV-137206/609/140610/SC/SI-10 14/06/10 Backfilling Method 1A4size photo Tu. Nguyen, Tuan Anh
BV-137206/609/140610/SC/SI-11 14/06/10 Backfilling Material 1A4size photo Tu. Nguyen, Tuan Anh
BV-137206/609/140618/SC/SI-12 14/06/18 Welding Issue on Factory 1A4size photo Tu, Tuan Anh
BV-137206/609/140618/SC/SI-13 14/06/18 Concrete for Footing 1A4size photo Tu, Tuan Anh
BV-137206/609/140619/SC/SI-14 14/06/19 Rain Water pipe position Tu. Nguyen, Tuan Anh
BV-137206/609/140619/SC/SI-15 14/06/19 Embeded steel plate 1A4size photo Tu. Nguyen, Tuan Anh
BV-137206/609/140627/SC/SI-16 14/06/27 Scratch positions during transportation and unloading steel structure 2A4size photos Tu. Nguyen, Tuan Anh

BV-137206/609/140630/SC/SI-17 14/06/30 Rainwater pipe joining fusion welding Works for underground 4A4size photos Tu, Nguyen, Quang
rainwater pipe of Stage 2 area
BV-137206/609/140702/SC/SI-18 14/07/02 Submittal of Shop Drawing for M&E opening and embeded item 1A4size drawing, 1 A4size Tu, Quang, Cuong
schedule
BV-137206/609/140703/SC/SI-19 14/07/03 Scratch positions during transportation and unloading steel structure 3A4size photos Tu. Nguyen, Tuan Anh
2nd time)
BV-137206/609/140703/SC/SI-20 14/07/03 Steel Structure Schedule Tu, Tuan Anh
BV-137206/609/140711/SC/SI-21 14/07/11 Removal of Underground GI piping works at warehouse area 2A4size photos Tu, Nguyen, Quang

BV-137206/609/140703/SC/SI-22 14/07/14 Verticalityof concrete column Tu, Nguyen, Tuan Anh


BV-137206/609/140717/SC/SI-23 14/07/17 Honeycomb of Column GL21Y 2A4size photos Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-24 14/07/14 Surface of concrete column 3A4size photos Tu, Nguyen, Tuan Anh
BV-137206/609/140717/SC/SI-25 14/07/17 Shop Drawing for bar bending for ground slab Zone 2, Xone 3 Tu, Phuc, Nguyen

BV-137206/609/140703/SC/SI-26 14/07/17 Warning of sub-concrete column along axis 21 1A4size photo Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-27 14/07/17 Protection for mezzanine floor 1A4size photo Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-28 14/07/17 Quality of Painting for roof bracing 3A4size photos Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-29 14/07/17 Lean Concrete surface before applying Xypec 2A4size photos Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-30 14/07/19 Notice during loading and unloading progress 1A4size photo Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-31 14/07/19 Aluminum Cladding Material Tu, Nguyen, Tuan Anh
BV-137206/609/140703/SC/SI-32 14/07/19 Testing Results Submission Tu, Nguyen, Tuan Anh
BV-137206/609/140719/SC/SI-33 14/07/19 Technical document of torque wrench Tu, Nguyen, Tuan Anh
BV-137206/609/140721/SC/SI-34 14/07/21 Submission of Holiday Tester for FF System (Underground Pipe) Tu, Nguyen, Quang, (T. Anh), Mike

BV-137206/609/140724/SC/SI-35 14/07/24 Protection and Caring of Installed Rain Water Pipe along GL a and 5A4 photos Tu, Nguyen, T. Anh, Mike
GL Z
BV-137206/609/140724/SC/SI-36 14/07/24 Quality Document Control Tu, Nguyen, T. Anh, Mike
BV-137206/609/140728/SC/SI-37 14/07/28 Brickwork issues 1A4size photo Tu, Nguyen, T. Anh, Mike
BV-137206/609/140731/SC/SI-38 14/07/31 Brickwork issues 2nd time 3A4size photos Tu, Nguyen, T. Anh, Mike
BV-137206/609/140731/SC/SI-39 14/07/31 Heavy Rain during Casting Concrete 3A4size photos Tu, Nguyen, T. Anh, Mike
BV-137206/609/140731/SC/SI-40 14/07/31 Preventive action for Casting Concrete at Ground Slab Tu, Nguyen, T. Anh, Mike
BV-137206/609/140731/SC/SI-41 14/07/31 Correct Damage Rebar at Ground Beam 1A4size photo Tu, Nguyen, T. Anh, Mike
BV-137206/609/140802/SC/SI-42 14/08/02 Protection and Proper Covering of Sewer and rian manhole and 2A4size photos Tu, Nguyen, Mike, Quang
stormline and sealing of HDPE pipe sleeve
BV-137206/609/140802/SC/SI-43 14/08/02 Submission of Holiday Tester for FF System (Underground Pipe) Tu, Nguyen, Mike, Quang

BV-137206/609/140802/SC/SI-44 14/08/02
Correspondence submission to PCI 311
Code/Ref. Issued Date Title Attachment Delivered to

BV-137206/609/140802/SC/SI-45 14/08/02 Road & Stormwater Drainage Issue 2A4size photos Tu, Nguyen, Mike
BV-137206/609/140805/SC/SI-46 14/08/05 Pharma Proposed Floor Drain Provision at Warehouse 2A4size photos Tu, Nguyen, Mike, Quang NS, Tung, Ujiie (To
raise RFC)
BV-137206/609/140805/SC/SI-47 14/08/05 Concrete Beam B3-axis 14A(E-G) bending 1A4size photo Tu, Nguyen, Mike
BV-137206/609/140805/SC/SI-48 14/08/05 Existing roof issues 4A4size photos Tu, Nguyen, Mike
BV-137206/609/140805/SC/SI-49 14/08/05 Zone 2 M&E Installation Works Tu, Nguyen, Mike, Quang
BV-137206/609/140805/SC/SI-50 14/08/05 Backfilling Issue axis G-E 1A4size photo Tu, Nguyen, Mike
BV-137206/609/140805/SC/SI-51 14/08/05 Roof Installation issue 4A4size photos Tu, Nguyen, Mike
BV-137206/609/140807/SC/SI-52 14/08/07 Flatness of ground slab 1A4size photo Tu, Nguyen, Mike
BV-137206/609/140807/SC/SI-53 14/08/07 Delivered and Accepted Rain Water Pipe Material (HDPE) 1A4size photo Tu, Nguyen, Mike, Quang
BV-137206/609/140807/SC/SI-54 14/08/07 Prevent Rain Water Coming to Phase 1-Roof Area 3A4size photos Tu, Nguyen, Mike, Quang
BV-137206/609/140809/SC/SI-55 14/08/11 Installation of Exposed rain water pipe along GL Z at warehouse area 2A4size photos Tu, Nguyen, Mike, Quang

BV-137206/609/140812/SC/SI-56 14/08/13 Quality Document Preparation Before Inspection From Authority

BV-137206/609/140822/SC/SI-57 14/08/22 Delivered AHU at Material Assembly Area at Stage 1 (Parking Area) 1A4size photo Tu, Nguyen/Phuc, Mike, Quang, T.Anh

BV-137206/609/140829/SC/SI-58 14/08/29 Store Material Properly 2A4size photos Tu, Nguyen, T.Anh, Mike
BV-137206/609/140905/SC/SI-59 14/09/05 M&E Items at Stage 1 area / Preparation for Saturday 6th power off Tu, Nguyen, T.Anh, Mike, Quang NS

BV-137206/609/140922/SC/SI-60 14/09/22 Brickwork Defect 3A4size photos Tu, Nguyen, T.Anh, Mike
BV-137206/609/140922/SC/SI-61 14/09/22 Repair water leak on roof before applying insulation layers Tu, Nguyen, T.Anh, Mike
BV-137206/609/140923/SC/SI-62 14/09/23 Stainless Steel Piping Work 1A4size photo Tu, Nguyen, Quang, Mike
BV-137206/609/140924/SC/SI-63 14/09/24 Stage 1 main air duct installation (Handling & moving) 1A4size page Tu, Nguyen, T.Anh, Mike
BV-137206/609/140925/SC/SI-64 14/09/25 Storage material on Site 1A4size photo Tu, Nguyen, T.Anh, Mike
BV-137206/609/140926/SC/SI-65 14/09/26 Air Particle Counting inside Stage 1 Clean Room 6A4size photo
BV-137206/609/140926/SC/SI-66 14/09/26 Damage of underground sevices at Ramp Extension area 5A4 photos
BV-137206/609/141002/SC/SI-67 14/10/02 Underground pipe at technical building stage 1 1A4size photo Tu, Nguyen, Quang, Mike
BV-137206/609/141003/SC/SI-68 14/10/03 Unsatisfactory Frame for Dry Wall at gridline E 1A4size photo Tu, Nguyen, T.Anh, Mike
BV-137206/609/141008/SC/SI-69 14/10/08 Inadequate Protection of AHU Parts and Other Material 1A4size photo Tu, Nguyen, T.Anh, Mike, Quang
BV-137206/609/141104/SC/SI-70 14/11/04 Welding Process Approved Parameters (External Fire Fighting Pipe) 1A4size photo & 1A3size Tu, Nguyen, Mike, Quang
Weld Log/Weld Inspection
Report
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
Correspondence submission to PCI 312
Code/Ref. Issued Date Title Attachment Delivered to

BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
BV-137206/609/140
Correspondence submission to PCI 313
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 314
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 315
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 316
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 317
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 318
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 319
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 320
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 321
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 322
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 323
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 324
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 325
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 326
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 327
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 328
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 329
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 330
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 331
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 332
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 333
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 334
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 335
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 336
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 337
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 338
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 339
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 340
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 341
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 342
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 343
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 344
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 345
Code/Ref. Issued Date Title Attachment Delivered to
Correspondence submission to PCI 346
Code/Ref. Issued Date Title Attachment Delivered to

+
Correspondence submission to PCI 347
Correspondence submission to PCI 348
Correspondence submission to PCI 349
Correspondence submission to PCI 350
Correspondence submission to PCI 351
Correspondence submission to PCI 352
Correspondence submission to PCI 353
Correspondence submission to PCI 354
Correspondence submission to PCI 355
Correspondence submission to PCI 356
Correspondence submission to PCI 357
Correspondence submission to PCI 358
Correspondence submission to PCI 359
Correspondence submission to PCI 360
Correspondence submission to PCI 361
Correspondence submission to PCI 362
Correspondence submission to PCI 363
Correspondence submission to PCI 364
Correspondence submission to PCI 365
Correspondence submission to PCI 366
Correspondence submission to PCI 367
Correspondence submission to PCI 368
Correspondence submission to PCI 369

45.00
Correspondence submission to PCI 370
Correspondence submission to PCI 371
Correspondence submission to PCI 372
Correspondence submission to PCI 373
Correspondence submission to PCI 374
Correspondence submission to PCI 375
Correspondence submission to PCI 376
Correspondence submission to PCI 377
Correspondence submission to PCI 378
Correspondence submission to PCI 379

1,244,000
Correspondence submission to PCI 380
Correspondence submission to PCI 381
Correspondence submission to PCI 382
Correspondence submission to PCI 383
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
BV-13720/802/140520/NCR-01 14/05/20 Ground Beam Rebar: Tie Bar Shape 1A4size photo Tu, Nguyen, Tuan Anh
Reply 14/05/21 Ground Beam Rebar: Tie Bar Shape
BV-13720/802/140520/NCR-01 14/06/03 Ground Beam Rebar: Tie Bar Shape_FINAL_(Confirm Accept for 1A4size photo (2 photos) Tu, Nguyen, Tuan Anh
Payment)

BV-13720/802/140521/NCR-02 14/05/21 Ground Beam Rebar: Waiting Tie Bar 1A4size photo Tu, Nguyen, Tuan Anh
Reply 14/05/21 Ground Beam Rebar: Waiting Tie Bar 2 photos, 1A3size drawing Tuan Anh
BV-13720/802/140521/NCR-02 14/07/08 Ground Beam Rebar: Waiting Tie Bar_FINAL (Confirm Accept for
Payment)

BV-13720/802/140609/NCR-03 14/06/09 Column Footing 1A4size photo Tu, Nguyen, Tuan Anh
Reply 14/06/17 Column Footing Tuan Anh
BV-13720/802/140609/NCR-03 14/06/23 Column Footing_FINAL
BV-13720/802/140621/NCR-04 14/06/21 Column Honeycomb 1A4size photo
Reply 14/07/09 Column Honeycomb 2A4size photos, Sikagrout
214-11 product
specification/data sheet
BV-13720/802/140621/NCR-04 14/07/14 Column Honeycomb_FINAL

BV-13720/802/140711/NCR-05 14/07/11 GI Piping Welding Procedure 7A4size photos


Reply

BV-13720/802/140712/NCR-06 14/07/12 Welding Procedure


Reply

BV-13720/802/140712/NCR-07 14/07/12 Bolts Finishing Length (Steel Structure)


Reply 14/07/21 Bolts Finishing Length (Steel Structure)

BV-13720/802/140621/NCR-08 14/07/14 Main Rebar Deformation 2A4size photos


Reply 14/09/26 Main Rebar Deformation 5A4size photos

BV-13720/802/140621/SC/NCR-09 14/07/16 Column Honeycomb (Axis 21-Y) 1A4size photo Tu, Nguyen, Tuan Anh
Reply 14/08/08 Column Honeycomb (Axis 21-Y)_Solution 1A4size photo, SikaGrout 212- Tu, Nguyen, Tuan Anh
11/214-11 data
sheet/Specification (4A4
pages) 2A4size photos
BV-13720/802/140621/SC/NCR-09 14/08/11 Column Honeycomb (Axis 21-Y)_FINAL 1A4size photo, SikaGrout 212- Tu, Nguyen, Tuan Anh
11/214-11 data
sheet/Specification (4A4
pages) 2A4size photos

BV-13720/802/140721/SC/NCR-10 14/07/21 Damaged Main Rebar & Tie Bar (GL-16 &Q-R) 1A4size photo Tu, Nguyen, Tuan Anh
Reply 14/10/01 Damaged Main Rebar & Tie Bar (GL-16 &Q-R) 1A4size photo Tu, Nguyen, Tuan Anh

BV-13720/802/140721/SC/NCR-11 14/07/21 Unapproved Roof Bracing 1A4size photo Tu, Nguyen, Tuan Anh
Reply 14/07/21 Unapproved Roof Bracing

BV-13720/802/140728/SC/NCR-12 14/07/28 Thickness of masonry motar layer 1A4size photo Tu, Nguyen, Tuan Anh, Mike

Reply
Correspondence submission to PCI 384
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
BV-13720/802/140731/SC/NCR-13 14/07/31 Wrong Position of Concrete Beam at Mezzanine Floor Axis E (16A- 2A2aize photos
19A)

BV-13720/802/140812/SC/NCR-14 14/08/13 Deformed Anchor Bolt at top of Column (A, E-13A, A-E-14A) 2A4size photos Tu, Nguyen, Tuan Anh, Mike

BV-13720/802/140829/SC/NCR-15 14/08/29 Crack on top of column coordinate E-13A 1A4size photo Tu, Nguyen, Tuan Anh, Mike

BV-13720/802/140915/SC/NCR-16 14/09/15 Electrical Earth Wire Insulation Color Tu, Nguyen, Tuan Anh, Mike

BV-13720/802/140922/SC/NCR-17 14/09/22 Wrong Technic in brick work 1A4size photo Tu, Nguyen, Tuan Anh, Mike

14/09/22 Wrong Technic in brick work Tuan Anh


BV-13720/802/140922/SC/NCR-17 14/11/07 wrong Technic in brick work_FINAL (APPROVED) 1A4size photo Mrs. Lan QC

BV-13720/802/140922/SC/NCR-17 (/R1) 14/09/24 Wrong Technic in brick work (not acceptable_Resubmit) Tu, Nguyen, Tuan Anh, Mike

BV-13720/802/140924/SC-NCR-18 14/09/26 Septic tank & Pump pit work 1A4size photo
BV-13720/802/140924/SC-NCR-18 14/10/14 Septic tank & Pump pit work_Repair work 1A4size photo Ba Hoa
BV-13720/802/140924/SC-NCR-18 14/11/05 Septic tank & Pump pit work_Repair work_Rejected 1A4size photo

BV-13720/802/140929/SC-NCR19 14/09/30 Sealant for AHU Cleanroom Grade 7A4size photo

BV-13720/802/140930/SC-NCR-20 14/09/30 Supply Air Duct Method of Fabrication Stage 1 4A4size photo

BV-13720/802/140930/SC/NCR-21 14/09/30 Air Duct Method of Fabrication Stage 2 4A4size photo

BV-13720/802/140930/SC/NCR-22 14/09/30 Air Duct Hanger Support Method 3A4size photo

BV-13720/802/141001/SC/NCR-23 Unsatisfactory welding quality on Sarnafil layer gridline (L-N&20- 3A4size photo
14/10/01 21)

BV-13720/802/140

BV-13720/802/141010/SC/NCR-25 14/10/10 Brickwork defect at gridline 15A (E-G) 1A4size photo Tuan Anh

BV-13720/802/141010/SC/NCR-25 14/11/07 Brickwork defect at gridline 15A (E-G)_REPLY 2A4size photos Mrs. Lan QC
(REPLY)
BV-13720/802/141010/SC/NCR-25 14/11/07 Brickwork defect at gridline 15A (E-G)_FINAL APPROVED 2A4size photos Mrs. Lan QC
Correspondence submission to PCI 385
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)

BV-13720/802/141020/SC/NCR-26 14/10/20 Smoke Extraction Equipment Delivery Inspection 1A4 size photo BV
Reply Method 14/10/22 Smoke Extraction Equipment Delivery Inspection M&E Team

BV-13720/802/141020/SC/NCR-26 14/10/23 Smoke Extraction Equipment Delivery Inspection_Rejected BV

BV-13720/802/140

BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
Correspondence submission to PCI 386
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
BV-13720/802/140
Correspondence submission to PCI 387
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 388
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 389
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 390
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 391
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 392
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 393
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 394
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 395
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 396
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 397
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 398
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 399
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 400
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 401
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 402
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 403
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 404
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 405
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 406
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 407
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 408
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 409
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 410
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 411
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 412
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 413
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 414
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 415
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 416
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 417
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 418
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 419
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 420
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 421
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 422
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 423
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 424
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 425
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 426
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 427
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 428
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 429
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 430
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 431
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 432
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 433
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 434
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 435
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 436
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 437
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 438
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 439
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 440
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 441
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 442
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 443
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 444
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 445
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 446
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 447
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 448
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 449
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 450
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 451
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 452
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 453
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 454
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 455
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 456
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 457
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 458
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 459
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 460
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 461
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 462
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 463
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 464
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 465
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 466
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 467
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 468
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 469
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 470
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 471
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 472
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)
Correspondence submission to PCI 473
Code/Ref. Issued Date OUTGOIN Title Attachment Delivered to
GING
(Reply)
(FINAL)

+
Correspondence submission to PCI 474
Correspondence submission to PCI 475
Correspondence submission to PCI 476
Correspondence submission to PCI 477
Correspondence submission to PCI 478
Correspondence submission to PCI 479
Correspondence submission to PCI 480
Correspondence submission to PCI 481
Correspondence submission to PCI 482
Correspondence submission to PCI 483
Correspondence submission to PCI 484
Correspondence submission to PCI 485
Correspondence submission to PCI 486
Correspondence submission to PCI 487
Correspondence submission to PCI 488
Correspondence submission to PCI 489
Correspondence submission to PCI 490
Correspondence submission to PCI 491
Correspondence submission to PCI 492
Correspondence submission to PCI 493
Correspondence submission to PCI 494
Correspondence submission to PCI 495
Correspondence submission to PCI 496

45.00
Correspondence submission to PCI 497
Correspondence submission to PCI 498
Correspondence submission to PCI 499
Correspondence submission to PCI 500
Correspondence submission to PCI 501
Correspondence submission to PCI 502
Correspondence submission to PCI 503
Correspondence submission to PCI 504
Correspondence submission to PCI 505

1,244,000
Correspondence submission to PCI 506
Correspondence submission to PCI 507
Correspondence submission to PCI 508
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
BBVN-FIVE-S2-SC-SUB-NCR-001 14/08/20 VNC2 Concrete Curve after Removing Formwork for Mezzanine Floor 1A4size drawing, 2A4size Tuan Anh
photos

BBVN-FIVE-S2-SC-SUB-NCR-002 14/08/20 Wrong Position of Concrete Beam at 1st Floor Offcie Area 1A4size drawing, 3A4size Tuan Anh
VNC2 photos

BBVN-FIVE-S2-SC-SUB-NCR-003 14/08/19 SEICO Quan Damaged Anchor Bolts at Office Area 6A4size photos Tuan Anh

BBVN-FIVE-S2-SC-SUB-NCR-004 14/08/29 Crack on top of Column Axis E-16A at Office Area 2A4size photos; 1A3size Tuan Anh
VNC2 Nham drawing

BBVN-FIVE-S2-SC-SUB-NCR-005 14/08/29 C-Channel Yyong Damaged Clean Room Components 3A4size photos Tuan Anh

BBVN-FIVE-S2-SC-SUB-NCR-006 14/09/11 SEICO Quan Finishing length of bolts-anchor bolts 2A4size photos Tuan Anh

BBVN-FIVE-S2-SC-SUB-NCR-007 14/09/17 Concrete Curve at Drainage 1A4size drawing, 2A4size Tuan Anh
VNC2 Nham photos

BBVN-FIVE-S2-SC-SUB-NCR-008 14/09/17 Honeycomb at Concrete Post Axis Z - Warehous 1A4size drawing, Transmittal Tuan Anh
sheet 206 dated 20-August-
VNC2 Nham 2014 (Honeycomb treatment),
2A4size ptotos

BBVN-FIVE-S2-SC-SUB-NCR-009 14/09/23 VNC2 Nham Plaster Cracking at Column 13-U 2A4size photos Tuan Anh

BBVN-FIVE-S2-SC-SUB-NCR-010 14/10/04 VNC2 Nham Water Leak & Wrong Installation Sequence of Septic Tank 3A4size photos Tuan anh

BBVN-FIVE-S2-SC-SUB-NCR-011 14/10/06 Nhat Hoa Wrong Method of Handling and Storage ceiling panel for Clean 4A4size photos Tuan Anh
ITC Room

BBVN-FIVE-S2-SC-SUB-NCR-012 14/10/23 Wrong Frame Installation for Alu. Composite Cladding at Axis 2A4size drawings, 2A4size Tuan Anh
Vien Dong Long/Duy 21/H-Q photos

BBVN-FIVE-S2-SC-SUB-NCR-013 14/10/23 Le Xuan Water Penetrated Rockwool at Axis 20A-21/D-E 3A4size photos Tuan Anh
Hung Trang
Muoi

BBVN-FIVE-S2-SC-SUB-NCR-014
Correspondence submission to PCI 509
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)

BBVN-FIVE-S2-SC-SUB-NCR-015

BBVN-FIVE-S2-SC-SUB-NCR-016

BBVN-FIVE-S2-SC-SUB-NCR-017

BBVN-FIVE-S2-SC-SUB-NCR-018

BBVN-FIVE-S2-SC-SUB-NCR-019
Correspondence submission to PCI 510
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 511
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 512
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 513
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 514
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 515
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 516
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 517
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 518
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 519
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 520
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 521
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 522
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 523
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 524
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 525
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 526
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 527
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 528
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 529
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 530
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 531
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 532
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 533
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 534
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 535
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 536
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 537
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 538
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 539
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 540
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 541
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 542
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 543
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 544
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 545
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 546
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 547
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 548
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 549
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 550
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 551
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 552
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 553
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 554
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 555
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 556
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 557
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 558
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 559
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 560
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 561
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 562
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 563
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 564
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 565
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 566
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 567
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 568
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 569
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 570
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 571
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 572
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 573
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 574
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 575
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 576
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 577
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 578
CODE Issued Date INCOMIN Title/Subject Attachment Author
Name G (Reply&
To
received FINAL)
Correspondence submission to PCI 579
Correspondence submission to PCI 580
Correspondence submission to PCI 581
Correspondence submission to PCI 582
Correspondence submission to PCI 583
Correspondence submission to PCI 584
Correspondence submission to PCI 585
Correspondence submission to PCI 586
Correspondence submission to PCI 587
Correspondence submission to PCI 588
Correspondence submission to PCI 589
Correspondence submission to PCI 590
Correspondence submission to PCI 591
Correspondence submission to PCI 592
Correspondence submission to PCI 593
Correspondence submission to PCI 594
Correspondence submission to PCI 595
Correspondence submission to PCI 596
Correspondence submission to PCI 597
Correspondence submission to PCI 598
Correspondence submission to PCI 599
Correspondence submission to PCI 600
Correspondence submission to PCI 601

45.00
Correspondence submission to PCI 602
Correspondence submission to PCI 603
Correspondence submission to PCI 604
Correspondence submission to PCI 605
Correspondence submission to PCI 606
Correspondence submission to PCI 607
Correspondence submission to PCI 608
Correspondence submission to PCI 609
Correspondence submission to PCI 610

1,244,000
Correspondence submission to PCI 611
Correspondence submission to PCI 612
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position

BV-137206-1009-140312/HSI01 14/03/12 Request for Installation electric cabinet and warning sign at live 10A4 photos Toan Safety
cable, stop pumping water at site
BV-137206-1009-140313/HSI02 14/03/13 Request for installation hard barricade for deep hole, provide rubbish 1A4size photo Toan Safety
bin and toilet temporary at site
BV-137206-1009-140321/HSI03 14/03/21 Request for installation drainage system and cover electric wire at Hoang Safety
washing bay
BV-137206-1009-140418/HSI04 14/04/18 Request for checking during night time at project area and bilingual Hoang Safety
permit to work
BV-137206-1009-140428/HSI05 14/04/28 Water Discharge on adjacent Properties Nguyen, Hoang safety
BV-137206-1009-140428/HSI06 14/04/28 Installation for Lightning system (SMZ & Vinaconex Office) Nguyen, Hoang safety
BV-137206-1009-140505/HSI07 14/05/05 Request for Cleaning Up Public road and Drain Stagnant water 4A4size photos Nguyen, Hoang safety
BV-137206-1009-140514/HSI08 14/05/14 Sadety Improvement
BV-137206-1009-140519/HSI09 14/05/19 Request Safety Issue 7A4size photos Nguyen, Hoang safety, Quang
BV-137206-1009-140521/HSI10 14/05/22 Incompliance of minimum HSE Equipments 1A4size photo Nguyen, Hoang safety
BV-137206-1009-142305/HSI11 14/05/23 Improvement of Security entrance post Nguyen, Hoang safety
BV-137206-1009-142405/HSI12 14/05/24 Cable isolation and arrangement 3A4size photos Nguyen, Hoang safety, Quang M&E
BV-137206-1009-143005/HSI13 14/05/30 Control Speed of Heavy Trucks on Site 1A4size photo Nguyen, Hoang safety, Quang M&E
BV-137206-1009-140623/HSI14 14/06/23 Unsafe Access of Ramp 1A4size photo Nguyen, Hoang Safety, Tu
BV-137206-1009-140623/HSI15 14/06/23 Wearing Safety Glass on Site Nguyen, Hoang Safety, Tu
INCIDENT INVESTIGATION
REPORT
No.001 Set up life line system for working at height 1A4size photo
No.002
No.003
No.004
No.005 14/10/02 Dust on walkable ceiling 14/09/15 2A4size photos Hoang Tuan Anh Site Engineer
No.006 14/10/20 (Packing Area)_Drop steel pipe from the handrail gap at Stage 1 14/10/18 2A4size photos Vuong

No.007
No.008
No.009
No.010
No.011
No.012
No.013
No.014
Correspondence submission to PCI 613
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 614
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 615
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 616
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 617
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 618
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 619
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 620
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 621
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 622
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 623
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 624
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 625
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 626
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 627
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 628
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 629
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 630
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 631
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 632
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 633
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 634
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 635
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 636
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 637
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 638
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 639
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 640
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 641
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 642
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 643
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 644
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 645
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position
Correspondence submission to PCI 646
Code/Ref. Issued Date Title Incident Date Attachment Prepared by Position

+
Correspondence submission to PCI 647
Correspondence submission to PCI 648
Correspondence submission to PCI 649
Correspondence submission to PCI 650
Correspondence submission to PCI 651
Correspondence submission to PCI 652
Correspondence submission to PCI 653
Correspondence submission to PCI 654
Correspondence submission to PCI 655
Correspondence submission to PCI 656
Correspondence submission to PCI 657
Correspondence submission to PCI 658
Correspondence submission to PCI 659
Correspondence submission to PCI 660
Correspondence submission to PCI 661
Correspondence submission to PCI 662
Correspondence submission to PCI 663
Correspondence submission to PCI 664
Correspondence submission to PCI 665
Correspondence submission to PCI 666
Correspondence submission to PCI 667
Correspondence submission to PCI 668
Correspondence submission to PCI 669

45.00
Correspondence submission to PCI 670
Correspondence submission to PCI 671
Correspondence submission to PCI 672
Correspondence submission to PCI 673
Correspondence submission to PCI 674
Correspondence submission to PCI 675
Correspondence submission to PCI 676
Correspondence submission to PCI 677
Correspondence submission to PCI 678
Correspondence submission to PCI 679

1,244,000
Correspondence submission to PCI 680
Correspondence submission to PCI 681
Correspondence submission to PCI 682
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered

Bao Minh insurance Bao 14/03/14 Questionnaire Answer (Contact No. 0977455105) E-
Minh/Mr. mail address:
Thang khacthangvttc@gmail.com
Correspondence submission to PCI 683
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 684
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 685
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 686
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 687
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 688
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 689
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 690
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 691
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 692
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 693
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 694
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 695
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 696
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 697
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 698
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 699
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 700
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 701
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 702
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 703
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered

45.00
Correspondence submission to PCI 704
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 705
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 706
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 707
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 708
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 709
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 710
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 711
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 712
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered

1,244,000
Correspondence submission to PCI 713
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 714
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered
Correspondence submission to PCI 715
No. Rev. To CC: Issued Title Attachment Prepared by DateReplied Delivered to Date Volume
delivered

+
Correspondence submission to PCI 716
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author

DT-77 BB 14/03/25 PCCC documents (CD)

TS-04 14/08/22 Mock up Inspection Report


DT-107 BB 14/09/18 Minutes No.1: Completion of Minutes No.1 (official)_Red
Foundation Work for Main Building signed

DT-109 BB 14/09/22 PCCC, Hydraulic calculation for roof


and warehouse (with sketch); FF
system design report; smoke exhaust
calculation; approved PCCC
documents; drawings, certificate &
technical report, CD

DT-110 BB 14/09/22 BBVN comments on incident


investigation report No.3 - Clean
room wall
DT-116 BB 14/10/08 Approved IPC No.05 for SMZ 01 ORIGINAL Tung
DT-119 BB 14/10/08 DKE comments on drawings for 01 Copy M&E team
PCCC Resubmission (7A3size Transmit to NS
drawings) in TS-293 dated
9-OCT
PCCC 14/10/10 Minutes of Meeting/Inspection in 9- 01 ORIGINAL a Nguyen
October-2014
DT-122 BB 14/10/10 Calculation and Report for PCCC 1 copy M&E North Star on
Re-submission: (i) Fire service report 10-OCT (TS-
- PCCC; (ii) Report-Heating, 298)
ventilation & cooling system; (iii)
Report-Fire fighting system; (iv)
Hydraulic calculation (Production)

DT-123 BB 14/10/23 List of Imported Products (2nd


batch)
DT-124 BB 14/10/24 Letter to DOC (Request for
Inspection of Foundation
Completion)
DT-125 BB 14/10/28 Power of Attorney_from BBVN to 3 original given to Ms.
SMZ to work with PCCC Hau
DT-126 BB 14/10/30 Letter to EVN Thanh Oai pertaining 3 original Quyen keeps
Power Shutdown (1st & 2nd NOV)
for S1 Power Supply Modification

DT-128 BB 14/11/06 Approved IPC No.06 for SMZ 1 Original Tung/Sent to


Mrs. Hieu
Correspondence submission to PCI 717
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 718
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 719
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 720
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 721
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 722
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 723
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 724
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 725
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 726
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 727
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 728
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 729
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 730
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 731
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 732
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 733
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 734
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 735
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 736
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 737
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 738
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 739
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 740
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 741
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 742
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 743
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 744
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 745
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 746
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 747
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 748
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 749
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 750
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 751
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 752
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 753
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 754
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 755
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 756
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 757
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 758
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 759
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 760
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 761
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 762
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 763
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 764
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 765
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 766
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 767
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 768
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 769
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 770
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 771
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 772
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author

45.00
Correspondence submission to PCI 773
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 774
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 775
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 776
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 777
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 778
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 779
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 780
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 781
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 782
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 783
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 784
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 785
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author

1,244,000
Correspondence submission to PCI 786
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 787
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 788
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 789
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 790
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 791
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 792
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 793
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 794
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 795
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 796
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 797
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 798
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 799
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 800
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 801
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 802
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author
Correspondence submission to PCI 803
REV. Received From Date Issued Title Attachment Author/ Status Date Delivered
Delivered to to Author
Author

+
Correspondence submission to PCI 804
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author

BBVN-FIVE-S2-SC-IR 14/03/04 Concrete Mixing trial (7 day - 28 days)_ M30, M40, Slump 14 ±2 ….. Hoang QC
0001
BBVN-FIVE-S2-SC-IR- 14/03/11 Testing Concrete (7 day)_ M30, M40, Slump 14 ±2 Hoang QC
0002
0002-14
BBVN-FIVE-S2-SC-IR- 14/03/13 Concrete Mixing trial Hoang QC
0003 0003
BBVN-FIVE-S2-SC-IR- 14/03/17 Concrete Mixing trial Hoang QC
0004 0004
BBVN-FIVE-S2-SC-IR- 14/03/21 Concrete Mixing trial Hoang QC
0005 0005
BBVN-FIVE-S2-SC-IR- 14/03/24 Trial Mixing Concrete Test (AQH) (7 days) Hoang QC
0006 0006
BBVN-FIVE-S2-SC-IR- 14/03/26 Inspection within the new construction boundary Chu Binh
0007 0007 Nguyen
BBVN-FIVE-S2-SC-IR- Trial Mixing Concrete Test (MHDI9)
0008 0008
BBVN-FIVE-S2-SC-IR- 14/04/02 Inspection the existing soil level at construction site (from 9Am- Nguyen
0009 0009 10AM) dated 3-Apr-2014
BBVN-FIVE-S2-SC-IR- 14/04/04 Trial Mixing Concrete Test (AQH) 14 days Hoang
0010 0010
BBVN-FIVE-S2-SC-IR- 14/04/04 Trial Mixing Concrete Test (MHDI9) 14 days Hoang
0011 0011
BBVN-FIVE-S2-SC-IR- 14/04/07 Anchor Bolts Testing Hoang
0012 0012
BBVN-FIVE-S2-SC-IR- 14/04/07 Rebar Testing for Construction Hoang
0013 0013
BBVN-FIVE-S2-SC-IR- 14/04/11 Actual soil level Check Nguyen
0014 0014
BBVN-FIVE-S2-SC-IR/ 14/04/14 Inspection of Remove and Modification existing fire hydrant pipe Trung
M&E-Site-0015 0015 before & after at construction site
BBVN-FIVE-S2-SC-IR/ 14/04/15 Trial Mixing Concrete Test (AQH) 28 days Hoang
QC-MA-0016 0016
BBVN-FIVE-S2-SC-IR/ 14/04/15 Soft Soil Treatment Ba Hoa
CON-0017 0017
BBVN-FIVE-S2-SC-IR/ 14/04/16 Compact Sand K90-layer1 Ba Hoa
CON-0018 0018
BBVN-FIVE-S2-SC-IR/ 14/04/18 Compact Sand K90_layer 2 Ba Hoa
CON-0019 0019
BBVN-FIVE-S2-SC-IR/ 14/04/18 Concrete Spacer Mixing Grade 30MPa Hoang
CON-0020 0020
BBVN-FIVE-S2-SC-IR/
QC-MA-0021 0021
BBVN-FIVE-S2-SC-IR/ CON 14/04/23 Lean Concrete for Pile Cap (PC 8, PC10, PC11, PC13, PC16, PC18, Phuc
0022 PC31, PC33, PC36, PC40, PC41, C48, C50, C53, C56, C58, C71,
C73, C76, C79, C94, C96, C99, C102, C104, )
BBVN-FIVE-S2-SC-IR/ QC/MA 14/04/23 Sampling Steel Plate for Steel Structure thickness 6mm, 8mm, Hoang
0023 10mm, 12mm, 16mm, 20mm& 40mm
BBVN-FIVE-S2-SC-IR/ CON 14/04/24 Lean Concrete for Foundation PC1C(PC13), PC1C(PC36), Phuc
PC1B(C53), PC1B(C76), PC1B(C99), PC1C(PC15), PC1C(PC34),
PC1B(C51), PC1B(C55), PC1B(C74), PC1B(C78), PC1B(C97),
0024 PC2(PC41), PC1C(PC09), PC1C(PC32), PC1(PC08), PC1(PC31),
PC1A(C58), PC1A(C81), PC1A(C104), PC2(PC40), PC1A(C104),
PC1A(PC40), PC1A(C48), PC1A(C71), PC1A(C94) (24Nos.)

BBVN-FIVE-S2-SC-IR/ 14/04/26 Lean Concrete for Foundation PC1( PC17 ), PC1A ( C49 ), PC1A Toan
( C72 ), PC1A ( C95 ),PC1 ( PC7 ),PC1 ( PC30 ),PC1A
0025 ( C59 ),PC1A ( C82 ),PC1A ( C105 ),PC1 ( PC06 ),PC1
( PC29 ),PC1A ( C60 ),PC1A ( C83 ),PC1A ( C106 ),PC2 ( PC39 )
BBVN-FIVE-S2-SC-IR/ 14/04/26 Formwork, Rebar, Casting concrete for PC1B(C56), Toan
PC1B(C79) ,PC1B(C102), PC1A(C73) , PC1A(C96), PC1A(C57),
0026 PC1A(C80), PC1A(C103), PC1A(C72), PC1A(C95)

BBVN-FIVE-S2-SC-IR/ 14/04/28 Formwork, Rebar, Casting concrete for PC1C(PC11), PC1C(PC10), Toan
PC1C(PC16), PC1B(C56), PC1B(C79), PC1A(C80), PC1B(C97),
0027 PC1A(C96), PC1B(C101), PC1A(C103)

BBVN-FIVE-S2-SC-IR/ 0028
BBVN-FIVE-S2-SC-IR/ 0029
BBVN-FIVE-S2-SC-IR/ 0030
BBVN-FIVE-S2-SC-IR/ 0031
BBVN-FIVE-S2-SC-IR/ 0032
BBVN-FIVE-S2-SC-IR/ 0033
BBVN-FIVE-S2-SC-IR/ 0034
BBVN-FIVE-S2-SC-IR/ 0035
Correspondence submission to PCI 805
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
0035 (B) 14/05/04 Inspection Pile Treatment (higti) Toan
BBVN-FIVE-S2-SC-IR/ 0036
BBVN-FIVE-S2-SC-IR/ 0037
BBVN-FIVE-S2-SC-IR/ 0038
BBVN-FIVE-S2-SC-IR/ 0039
BBVN-FIVE-S2-SC-IR/ 0040
BBVN-FIVE-S2-SC-IR/ 0041
BBVN-FIVE-S2-SC-IR/ 0042
BBVN-FIVE-S2-SC-IR/ 0043
BBVN-FIVE-S2-SC-IR/ 0044
BBVN-FIVE-S2-SC-IR/ 0045
BBVN-FIVE-S2-SC-IR/ 0046
BBVN-FIVE-S2-SC-IR/ 0047
BBVN-FIVE-S2-SC-IR/ 0048
BBVN-FIVE-S2-SC-IR/ 0049
BBVN-FIVE-S2-SC-IR/ 0050
BBVN-FIVE-S2-SC-IR/
0051
BBVN-FIVE-S2-SC-IR/ 0052
BBVN-FIVE-S2-SC-IR/ 0053
BBVN-FIVE-S2-SC-IR/ 0054
BBVN-FIVE-S2-SC-IR/ 0055
BBVN-FIVE-S2-SC-IR/ 0056
BBVN-FIVE-S2-SC-IR/ 0057
BBVN-FIVE-S2-SC-IR/ 0058
BBVN-FIVE-S2-SC-IR/ 0059
BBVN-FIVE-S2-SC-IR/ 0060
BBVN-FIVE-S2-SC-IR/ 14/05/22 Inspection Installation sleeves on trench pit wall at construction site Trung
0061
BBVN-FIVE-S2-SC-IR/ 0062 14/05/22 Inspection of Project Sign Board Nguyen
BBVN-FIVE-S2-SC-IR/ 0063
0064
0065
0066
0067
0068
0069
0070
0071
14/05/28 Rebar, Formwork, Casting Concrete for Ground Beam Axis K - E & Phuc
0072 18 - 21
0073
0074
0075
0076
0077
CON 0078 14/05/31 Lean concrete for external drainage system Toan
0079
0080
0081
0082
0083
0084
0085
0086
0087
Correspondence submission to PCI 806
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 807
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 808
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 809
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 810
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 811
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 812
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 813
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 814
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 815
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 816
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 817
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 818
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 819
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 820
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 821
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 822
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 823
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 824
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 825
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 826
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 827
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 828
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 829
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 830
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 831
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 832
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 833
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 834
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 835
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 836
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 837
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 838
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 839
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 840
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 841
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 842
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 843
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 844
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 845
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 846
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 847
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 848
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 849
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 850
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 851
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 852
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 853
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 854
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 855
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 856
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 857
OUTGOIING Section No. Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 858
Correspondence submission to PCI 859
Correspondence submission to PCI 860
Correspondence submission to PCI 861
Correspondence submission to PCI 862
Correspondence submission to PCI 863
Correspondence submission to PCI 864
Correspondence submission to PCI 865
Correspondence submission to PCI 866
Correspondence submission to PCI 867
Correspondence submission to PCI 868
Correspondence submission to PCI 869
Correspondence submission to PCI 870
Correspondence submission to PCI 871
Correspondence submission to PCI 872
Correspondence submission to PCI 873
Correspondence submission to PCI 874
Correspondence submission to PCI 875
Correspondence submission to PCI 876
Correspondence submission to PCI 877
Correspondence submission to PCI 878
Correspondence submission to PCI 879

45.00
Correspondence submission to PCI 880
Correspondence submission to PCI 881
Correspondence submission to PCI 882
Correspondence submission to PCI 883
Correspondence submission to PCI 884
Correspondence submission to PCI 885
Correspondence submission to PCI 886
Correspondence submission to PCI 887

1,244,000
Correspondence submission to PCI 888
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
MINUTES FOR MATERIAL/EQUIPMENT INSPECTION &
ACCEPTANCE
BBVN-FIVE-S2-SC-ACPT QC-MA-Concrete 14/04/23 Concrete for Construction Proportions Mix Design Result Hoang QC
0001
BBVN-FIVE-S2-SC-ACPT 14/04/23
0002
BBVN-FIVE-S2-SC-ACPT 0003
BBVN-FIVE-S2-SC-ACPT 0004
BBVN-FIVE-S2-SC-ACPT 0005
BBVN-FIVE-S2-SC-ACPT 0006
BBVN-FIVE-S2-SC-ACPT 0007
BBVN-FIVE-S2-SC-ACPT 0008
BBVN-FIVE-S2-SC-ACPT 0009
BBVN-FIVE-S2-SC-ACPT 0010
BBVN-FIVE-S2-SC-ACPT 0011
BBVN-FIVE-S2-SC-ACPT 0012
BBVN-FIVE-S2-SC-ACPT 0013
BBVN-FIVE-S2-SC-ACPT 0014
BBVN-FIVE-S2-SC-ACPT 0015
BBVN-FIVE-S2-SC-ACPT 0016
BBVN-FIVE-S2-SC-ACPT 0017
BBVN-FIVE-S2-SC-ACPT 0018
BBVN-FIVE-S2-SC-ACPT 0019
BBVN-FIVE-S2-SC-ACPT 0020
BBVN-FIVE-S2-SC-ACPT 0021
BBVN-FIVE-S2-SC-ACPT 0022
BBVN-FIVE-S2-SC-ACPT 0023
BBVN-FIVE-S2-SC-ACPT 0024
BBVN-FIVE-S2-SC-ACPT 0025
BBVN-FIVE-S2-SC-ACPT 0026
BBVN-FIVE-S2-SC-ACPT 0027
BBVN-FIVE-S2-SC-ACPT 0028
BBVN-FIVE-S2-SC-ACPT 0029
BBVN-FIVE-S2-SC-ACPT 0030
BBVN-FIVE-S2-SC-ACPT 0031
BBVN-FIVE-S2-SC-ACPT 0032
BBVN-FIVE-S2-SC-ACPT 0033
BBVN-FIVE-S2-SC-ACPT 0034
BBVN-FIVE-S2-SC-ACPT 0035
BBVN-FIVE-S2-SC-ACPT 0036
0037
0038
0039
0040
0041
0042
0043
0044
0045
0046
0047
0048
0049
0050
0051
0052
0053
0054
0055
0056
0057
0058
0059
0060
0061
0062
0063
0064
0065
0066
0067
Correspondence submission to PCI 889
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 890
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 891
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 892
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 893
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 894
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 895
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 896
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 897
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 898
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 899
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 900
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 901
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 902
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 903
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 904
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 905
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 906
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 907
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 908
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 909
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 910
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 911
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 912
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 913
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 914
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 915
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 916
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 917
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 918
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 919
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 920
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 921
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 922
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 923
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 924
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 925
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 926
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 927
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 928
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 929
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 930
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 931
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 932
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 933
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 934
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 935
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 936
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 937
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 938
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 939
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 940
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 941
OUTGOIING Section Date Issued Title Attachment Author/ Status Date Delivered to
Delivered to Author
Correspondence submission to PCI 942
Correspondence submission to PCI 943
Correspondence submission to PCI 944
Correspondence submission to PCI 945
Correspondence submission to PCI 946
Correspondence submission to PCI 947
Correspondence submission to PCI 948
Correspondence submission to PCI 949
Correspondence submission to PCI 950
Correspondence submission to PCI 951
Correspondence submission to PCI 952
Correspondence submission to PCI 953
Correspondence submission to PCI 954
Correspondence submission to PCI 955
Correspondence submission to PCI 956
Correspondence submission to PCI 957
Correspondence submission to PCI 958
Correspondence submission to PCI 959
Correspondence submission to PCI 960
Correspondence submission to PCI 961
Correspondence submission to PCI 962
Correspondence submission to PCI 963
Correspondence submission to PCI 964

45.00
Correspondence submission to PCI 965
Correspondence submission to PCI 966
Correspondence submission to PCI 967
Correspondence submission to PCI 968
Correspondence submission to PCI 969
Correspondence submission to PCI 970
Correspondence submission to PCI 971
Correspondence submission to PCI 972

1,244,000
Correspondence submission to PCI 973
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author

BBVN-FIVE-S2-SC- 14/03/20 17-23 Mar 2014


LMS-0001
BBVN-FIVE-S2-SC- 14/03/21 24-30 Mar 2014 Toan
LMS-0002
BBVN-FIVE-S2-SC- 14/03/24 24-30 Mar 2014 (Rev.1) Toan
LMS-0002/R1
BBVN-FIVE-S2-SC- 14/04/04 7-13 Apr 2014 Toan
LMS-0003
Correspondence submission to PCI 974
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 975
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 976
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 977
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 978
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 979
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 980
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 981
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 982
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 983
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 984
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 985
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 986
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 987
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 988
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 989
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 990
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 991
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 992
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 993
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 994
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 995
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 996
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 997
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 998
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 999
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1000
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1001
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1002
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1003
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1004
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1005
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1006
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1007
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1008
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1009
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1010
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1011
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1012
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1013
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1014
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1015
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1016
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1017
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1018
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1019
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1020
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1021
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1022
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1023
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1024
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1025
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1026
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1027
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1028
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1029
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1030
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1031
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1032
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1033
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1034
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1035
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1036
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1037
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1038
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1039
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1040
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1041
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1042
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1043
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1044
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1045
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1046
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1047
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1048
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1049
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1050
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1051
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1052
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1053
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1054
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1055
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1056
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1057
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1058
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author
Correspondence submission to PCI 1059
No. Rev. Date Issued Date Date INCOMI Rev Date Date Title Attachment Author/ Status Date Delivered
Delivered Required NG Issued Received Delivered to to Author
Reply Author

+
Correspondence submission to PCI 1060
Correspondence submission to PCI 1061
Correspondence submission to PCI 1062
Correspondence submission to PCI 1063
Correspondence submission to PCI 1064
Correspondence submission to PCI 1065
Correspondence submission to PCI 1066
Correspondence submission to PCI 1067
Correspondence submission to PCI 1068
Correspondence submission to PCI 1069
Correspondence submission to PCI 1070
Correspondence submission to PCI 1071
Correspondence submission to PCI 1072
Correspondence submission to PCI 1073
Correspondence submission to PCI 1074
Correspondence submission to PCI 1075
Correspondence submission to PCI 1076
Correspondence submission to PCI 1077
Correspondence submission to PCI 1078
Correspondence submission to PCI 1079
Correspondence submission to PCI 1080
Correspondence submission to PCI 1081
Correspondence submission to PCI 1082
Correspondence submission to PCI 1083

45.00
Correspondence submission to PCI 1084
Correspondence submission to PCI 1085
Correspondence submission to PCI 1086
Correspondence submission to PCI 1087
Correspondence submission to PCI 1088
Correspondence submission to PCI 1089
Correspondence submission to PCI 1090
Correspondence submission to PCI 1091
Correspondence submission to PCI 1092

1,244,000
Correspondence submission to PCI 1093
Correspondence submission to PCI 1094
WEEKLY MEETING
File Issued Title File Code Volume
M-01-001 06/11/23 Weekly MOM at PCI office. No1 -23 November-2006 MOM-03-01 Vol 01
M-01-002 06/11/30 Weekly MOM at PCI office. No1 -30 November-2006 MOM-03-01 Vol 01
M-01-003 06/12/07 Weekly MOM at PCI office. No3 -7 December-2006 MOM-03-01 Vol 01
M-01-004 06/12/15 Weekly MOM at PCI office. No4 -15 December-2006 MOM-03-01 Vol 01
M-01-005 06/12/21 Weekly MOM at PCI office. No 5 -21 December-2006 MOM-03-01 Vol 01
M-01-006 06/12/29 Weekly MOM at PCI office. No 6 -28 December-2006 MOM-03-01 Vol 01
M-01-007 07/01/04 Weekly MOM at PCI office. No 7 -04 January-2007 MOM-03-01 Vol 01
M-01-008 07/01/15 Weekly MOM at PCI office. No 8 -11 January-2007 MOM-03-01 Vol 01
M-01-009 07/01/20 Weekly MOM at PCI office. No 9 -18 January-2007 MOM-03-01 Vol 01
M-01-010 07/01/25 Weekly MOM at PCI office. No 10 -25 January-2007 MOM-03-01 Vol 01
M-01-011 07/02/01 Weekly MOM at PCI office. No 11 -01 February-2007 MOM-03-01 Vol 01
M-01-012 07/02/08 Weekly MOM at PCI office. No 12 -08 February-2007 MOM-03-01 Vol 01
M-01-013 07/02/14 Weekly MOM at PCI office. No 13 -14 February-2007 MOM-03-01 Vol 01
M-01-014 07/03/01 Weekly MOM at PCI office. No 14 -1 March -2007 MOM-03-01 Vol 01
M-01-015 07/03/09 Weekly MOM at PCI office. No 15 -8 March -2007 MOM-03-01 Vol 01
M-01-016 07/03/15 Weekly MOM at PCI office. No 16 -15 March -2007 MOM-03-01 Vol 01
M-01-017 07/03/22 Weekly MOM at PCI office. No 17 -22 March -2007 MOM-03-01 Vol 01
M-01-018 07/03/30 Weekly MOM at PCI office. No 18 -30 March -2007 MOM-03-01 Vol 01
M-01-019 07/04/05 Weekly MOM at PCI office. No 19 -05 April -2007 MOM-03-01 Vol 01
M-01-020 07/04/12 Weekly MOM at PCI office. No 20 -12 April -2007 MOM-03-01 Vol 01
M-01-021 07/04/19 Weekly MOM at PCI office. No 21 -19 April -2007 MOM-03-01 Vol 01
M-01-022 07/05/02 Weekly MOM at PCI office. No 22 -03 May-2007 MOM-03-01 Vol 01
M-01-023 07/05/10 Weekly MOM at PCI office. No 23 -10 May-2007 MOM-03-01 Vol 01
M-01-024 07/05/17 Weekly MOM at PCI office. No 24 -17 May-2007 MOM-03-01 Vol 01
M-01-025 07/05/24 Weekly MOM at PCI office. No 25 -24 May-2007 MOM-03-01 Vol 01
M-01-026 07/05/31 Weekly MOM at PCI office. No 26 -31 May-2007 MOM-03-01 Vol 01
M-01-027 07/06/07 Weekly MOM at PCI office. No 27 -7 June-2007 MOM-03-01 Vol 01
M-01-028 07/06/21 Weekly MOM at PCI office. No 28 -21 June-2007 MOM-03-01 Vol 01
M-01-029 07/06/28 Weekly MOM at PCI office. No 29 -28 June-2007 MOM-03-01 Vol 01
M-01-030 07/07/05 Weekly MOM at PCI office. No 30 -05 July-2007 MOM-03-01 Vol 01
M-01-031 07/07/12 Weekly MOM at PCI office. No 31 -12 July-2007 MOM-03-01 Vol 01
M-01-032 07/07/19 Weekly MOM at PCI office. No 32 -19 July-2007 MOM-03-01 Vol 01
M-01-033 07/07/28 Weekly MOM at PCI office. No 33 -26 July-2007 MOM-03-01 Vol 01
M-01-034 07/08/02 Weekly MOM at PCI office. No 34 -02 August-2007 MOM-03-01 Vol 01
M-01-035 07/08/08 Weekly MOM at PCI office. No 35 -08 August-2007 MOM-03-01 Vol 01
M-01-036 07/08/16 Weekly MOM at PCI office. No 36 -16 August-2007 MOM-03-01 Vol 01
M-01-037 07/08/23 Weekly MOM at PCI office. No 37 -23 August-2007 MOM-03-01 Vol 01
M-01-038 07/08/30 Weekly MOM at PCI office. No 38 -30 August-2007 MOM-03-01 Vol 01
M-01-039 07/09/06 Weekly MOM at PCI office. No 39 -06 Sep-2007 MOM-03-01 Vol 01
M-01-040 07/09/13 Weekly MOM at PCI office. No 40 -13 Sep-2007 MOM-03-01 Vol 01
M-01-041 07/09/20 Weekly MOM at PCI office. No 41 -20 Sep-2007 MOM-03-01 Vol 01
M-01-042 07/09/28 Weekly MOM at PCI office. No 42 -28 Sep-2007 MOM-03-01 Vol 02
M-01-043 07/10/04 Weekly MOM at PCI office. No 43 -04 October-2007 MOM-03-01 Vol 02
M-01-044 07/10/11 Weekly MOM at PCI office. No 44 -11 October-2007 MOM-03-01 Vol 02
M-01-045 07/10/18 Weekly MOM at PCI office. No 45 -18 October-2007 MOM-03-01 Vol 02
M-01-046 07/10/25 Weekly MOM at PCI office. No 46 -25 October-2007 MOM-03-01 Vol 02
M-01-047 07/11/01 Weekly MOM at PCI office. No 47 -01 November-2007 MOM-03-01 Vol 02
M-01-048 07/11/08 Weekly MOM at PCI office. No 48 -08 November-2007 MOM-03-01 Vol 02
M-01-049 07/11/15 Weekly MOM at PCI office. No 49 -15 November-2007 MOM-03-01 Vol 02
M-01-050 07/11/22 Weekly MOM at PCI office. No 50 -22 November-2007 MOM-03-01 Vol 02
M-01-052 07/12/08 Weekly MOM at PCI office. No 52 -06 December-2007 MOM-03-01 Vol 02
M-01-053 07/12/13 Weekly MOM at PCI office. No 53 -13 December-2007 MOM-03-01 Vol 02
M-01-054 07/12/20 Weekly MOM at PCI office. No 54 -20 December-2007 MOM-03-01 Vol 02
M-01-055 07/12/26 Weekly MOM at PCI office. No 55 -26 December-2007 MOM-03-01 Vol 02
M-01-056 08/01/10 Weekly MOM at PCI office. No 56 -10 January -2008 MOM-03-01 Vol 02
M-01-057 08/01/23 Weekly MOM at PCI office. No 57 -23 January -2008 MOM-03-01 Vol 02
M-01-058 08/01/30 Weekly MOM at PCI office. No 58 -30 January -2008 MOM-03-01 Vol 02
M-01-059 08/02/20 Weekly MOM at PCI office. No 59 -20 February -2008 MOM-03-01 Vol 02
M-01-060 08/02/27 Weekly MOM at PCI office. No 60 -27 February -2008 MOM-03-01 Vol 02
M-01-061 08/03/12 Weekly MOM at PCI office. No 61 -12 March -2008 MOM-03-01 Vol 02
M-01-062 08/03/19 Weekly MOM at PCI office. No 62 -19 March -2008 MOM-03-01 Vol 02
M-01-063 08/03/26 Weekly MOM at PCI office. No 63 -26 March -2008 MOM-03-01 Vol 03
M-01-064 08/04/02 Weekly MOM at PCI office. No 64-02 April 2008 MOM-03-01 Vol 03
M-01-065 08/04/23 Weekly MOM at PCI office. No 65-22 April 2008 MOM-03-01 Vol 03
M-01-066 08/05/07 Weekly MOM at PCI office. No 66-7 May 2008 MOM-03-01 Vol 03
M-01-067 08/05/14 Weekly MOM at PCI office. No 67-14 May 2008 MOM-03-01 Vol 03
M-01-068 08/05/21 Weekly MOM at PCI office. No 68-21May 2008 MOM-03-01 Vol 03
M-01-069 08/06/18 Weekly MOM at PCI office. No 69-18 June 2008 MOM-03-01 Vol 03
M-01-070 08/06/25 Weekly MOM at PCI office. No 70-25 June 2008 MOM-03-01 Vol 03
M-01-071 08/07/02 Weekly MOM at PCI office. No 71-02 July 2008 MOM-03-01 Vol 03
M-01-072 08/07/16 Weekly MOM at PCI office. No 72-16 July 2008 MOM-03-01 Vol 03
M-01-074 08/08/06 Weekly MOM at PCI office. No 74-06 August 2008 MOM-03-01 Vol 03
M-01-075 08/08/13 Weekly MOM at PCI office. No 75-13 August 2008 MOM-03-01 Vol 03
M-01-076 08/08/20 Weekly MOM at PCI office. No 76-20 August 2008 MOM-03-01 Vol 03
M-01-077 08/09/03 Weekly MOM at PCI office. No 77-03 Sep 2008 MOM-03-01 Vol 03
M-01-078 08/09/10 Weekly MOM at PCI office. No 78-10 Sep 2008 MOM-03-01 Vol 03
M-01-079 08/09/17 Weekly MOM at PCI office. No 79-17 Sep 2008 MOM-03-01 Vol 03
M-01-080 08/09/24 Weekly MOM at PCI office. No 80-24 Sep 2008 MOM-03-01 Vol 03
M-01-082 08/10/08 Weekly MOM at PCI office. No 82- 8 Oct 2008 MOM-03-01 Vol 03
M-01-083 08/10/15 Weekly MOM at PCI office. No 83-15 Oct 2008 ( No meeting) MOM-03-01 Vol 03

M-01-084 08/10/22 Weekly MOM at PCI office. No 84-22 Oct 2008 ( no meeting) MOM-03-01 Vol 03

M-01-085 08/10/29 Weekly MOM at PMU office. No 85- 29 Oct 2008 MOM-03-01 Vol 03
M-01-086 08/11/19 Weekly MOM at PCI office. No 86-19 Nov 2008 MOM-03-01 Vol 03
M-01-087 09/01/14 Weekly MOM at PMU office. No 87-14 Jan 2009 MOM-03-01 Vol 03
M-01-088 09/04/06 Weekly MOM at PMU office. No 88-06 Apr 2009 MOM-03-01 Vol 03
BI-WEEKLY MEETING
File Issued Title File Code
MB-01-001 06/12/11 Bi-weekly MOM at PMU office on 12/11/06 MOM-03-01
MB-01-002 06/12/25 Bi-weekly MOM at PMU office on 25/12/06 MOM-03-01
MB-01-003 07/01/08 Bi-weekly MOM at PMU office on 8 Jan 2007 MOM-03-01
MB-01-004 07/01/22 Bi-weekly MOM at PMU office on 22 Jan 2007 MOM-03-01
MB-01-005 07/03/06 Bi-weekly MOM at PMU office on 06/03/07 MOM-03-01
MB-01-006 07/03/19 Bi-weekly MOM at PMU office on 19/03/07 MOM-03-01
MB-01-007 07/04/01 Bi-weekly MOM at PMU office on 01/04/07 MOM-03-01
MB-01-008 07/04/16 Bi-weekly MOM at PMU office on 16/04/07 MOM-03-01
MB-01-009 07/05/07 Bi-weekly MOM at PMU office on 07/05/07 MOM-03-01
MB-01-010 07/06/04 Bi-weekly MOM at PMU office on 04 June 2007 MOM-03-01
MB-01-011 07/07/10 Bi-weekly MOM at PMU office on 10/07/07 MOM-03-01
MB-01-012 07/07/23 Bi-weekly MOM at PMU office on 23 July 2007 MOM-03-01
MB-01-013 07/08/13 Bi-weekly MOM at PMU office on 13 August 2007 MOM-03-01
MB-01-014 07/09/10 Bi-weekly MOM at PMU office on 10 September 2007 MOM-03-01

MB-01-015 07/10/01 Bi-weekly MOM at PMU office on 01 October 2007 MOM-03-01


MB-01-016 07/10/22 Bi-weekly MOM at PMU office on 22 October 2007 MOM-03-01
MB-01-016 07/11/12 Bi-weekly MOM at PMU office on 12 November 2007 MOM-03-01
MB-01-017 07/11/26 Bi-weekly MOM at PMU office on 26 November 2007 MOM-03-01
MB-01-018 07/12/24 Bi-weekly MOM at PMU office on 24 December 2007 MOM-03-01
MB-01-019 08/01/14 Bi-weekly MOM at PMU office on 14 January 2008 MOM-03-01
MB-01-020 08/03/03 Bi-weekly MOM at PMU office on 03 March 2008 MOM-03-01
MB-01-021 08/03/31 Bi-weekly MOM at PMU office on 31 March 2008 MOM-03-01
MB-01-022 08/06/02 Bi-weekly MOM at PMU office on 02 June 2008 MOM-03-01
MB-01-023 08/07/07 Bi-weekly MOM at PMU office on 07 July 2008 MOM-03-01
MB-01-024 08/08/25 Bi-weekly MOM at PMU office on 25 August 2008 MOM-03-01
Volume
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01
Vol 01

Vol 02
Vol 02
Vol 02
Vol 02
Vol 02
Vol 02
Vol 02
Vol 03
Vol 03
Vol 03
Vol 03