Number Revised Revised Changes Originator Date
RISK AND IMPACT ASSESSMENT CRITERIA For CHH Internal Use Only Page 1 of 3
(FMS-HOS-F-023) ver01_Oct 10, 2017
RISK AND IMPACT ASSESSMENT CRITERIA
FMS-HOS-F-023 ver01
FORM CONTENT
RISK AND IMPACT ASSESSMENT CRITERIA For CHH Internal Use Only Page 2 of 3
(FMS-HOS-F-023) ver01_Oct 10, 2017
RISK AND IMPACT ASSESSMENT CRITERIA
FMS-HOS-F-023 ver01
A. SEVERITY
RATING Risk Description Injury Ill Health
1 First Aid Minor irritation/ discomfort/ First Aid Discomfort/ Temporary illness/ Potential infection
2 Medical Medical Treatment/ Hospitalization/ Non dis-abling Medical Treatment/ Hospitalization/ Mild Infection
Death/ Permanent disability such as; loss of body parts, loss of senses Death/ Permanent disability such as; loss of body parts, loss of senses
3 Fatal
etc. etc./ Severe Infection
Consumption of Water
Electricity (KWh/ day)
Chemical Spillage
Chemicals (L/Day)
Consumption of
Consumption of
Waste Diposal
(cubic meters/day)
(L/Day)
(Liters)
paper (pcs/day)
RATING Impact Description
Minor environmental impact, affects an area(s) within the 5KWh and Non-Hazardous
1 5 and Below 50 and Below 2 and Below 5 and Below Not Regulated Waste
4 and Below
facility, reversible damage Below
B. OCCURRENCE
RATING LEVEL Probability to occur
3 High Occurrence Daily to Monthly/ When accident occurs within the year
C. CONTROLS
I. Hazard
Engineering Administrative Total Control Value
RATING Effectivity Description PPE (10%)
(70%) (20%) (Eng'g+Admin+PPE)
• In-appropriate
Not effective/ No control measure • Not used or applied
3 2.1 0.6 0.3 2.5 to 3
Total Control Value is equal to 2.5 to 3 • No monitoring
• No control measure in- place
II. Aspect
RATING ASPECT CONTROLS
• Daily or Monthly monitoring or maintenance
• Consistently meet DENR requirements or guidelines
1 • Consistently meet company environmental preservation procedure or policy
• Consistent on efficient utilization of resources
• With consistent application of Pollution Control measures
• No monitoring or inspection
• Failed to meet DENR requirements
3 • Not in-line with company environmental preservation procedure or policy
• Inefficient utilization of resources
• No Pollution Control measures
D. RISK/IMPACT CLASSIFICATION
RISK LEVEL Classification Control Measures
1 to 6 Low Risk May require consistent monitoring or regular inspection depending on the extent of controls
Efforts are required to reduce the risk (ie., additional control, monitoring, etc.) Considerable/reasonable resources may have to be allocated to
7 to 12 Medium Risk
reduce the risk.