EIGHT DAYS MAINTENANCE JOBS ON UNIT-2 GENERATOR TRANSFORMER.

No Day Activities Materials Needed/man Remark


power
1. Day-1 + Take permit from control room and Permit card / shift Moving
proper isolation of the transformer, + operations and electrical filtration
+ Sample test the oil. Crew. machine to
Lock-off all fain valves. site.

2. Day-2 + Reduce 25 drums of oil from the + Flat and ring Gasket. Check from
transformer. + Three drums of oil store
+ Open up the transformer, change + 2No. Gasket sealants.
gaskets, arrest the leakages and close + 10kg Mounting cloth.
back the openings.
+ Retighten all loose bots and nuts
3. Day-3 + Open all close valves. + 50Litre of vacuum oil. Check from
+ Refill the 25drums of oil. + 20litre of Kerosene. store

4. Day-4 + Start filtration. Chemistry men


+ sample test of oil

5. Day-5 + Filtration continue; Chemistry men


+ Oil test carried out and stop
filtration
6. + Filtration continue
7. + Filtration continue Chemistry men
+ And sample test the oil
8. + shunt-down machine, disconnect Hand-over
and hand-over the transformer the
transformer