Excavation in Limestone Formation

of KVMRT Conlay Underground


Station, Malaysia

By : Fong-Wah, Chee

1
G&P Professionals Sdn Bhd (www.gnpgroup.com.my)
Please Read Carefully !!!!

Disclaimer
• Unless otherwise indicated, the content of the presentation is the
proprietary property of G&P and all databases, audio, video,
text, photographs and graphics are owned or controlled by G&P.
• Audio or video recording, photo taking, reproduction and
redistribution is strictly NOT permitted.
• All participants shall not share or distribute any of the materials
presented to any other person without consent from G&P.
• By attending the presentation session, you agree to fully abide to
ALL the conditions and requirements stated above.

2
G&P Professionals Sdn Bhd (www.gnpgroup.com.my)
INTRODUCTION

3
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Overview of Project

4
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Overview of Project
• Klang Valley Mass Rapid
Transit (KVMRT) Sungai Buloh-
Serdang- Putrajaya (SSP)
• Total 37 stations
(11 underground stations)
• Total alignment length of
52.2km
(13.5km underground tunnel)

5
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Site Location

Conlay Station

TRX Station

Chan Sow Lin Station

6
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Overview of Project

7
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
SUBSURFACE INVESTIGATION

8
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
General Geology
• Limestone Formation
• Alluvium: very loose sand/
very soft to soft silt.

9
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Subsurface Investigation

Legend:

Existing boreholes (11 nos)


Additional boreholes (16 nos)
10
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Subsurface Investigation

• SPT-N generally less than 10.


• Bedrock level varies.
• Cavities
11
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Bedrock Contour

Localised deep bedrock (37.2m)

Localised deep bedrock

12
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Subsoil information
Overburden Bedrock

Material Alluvium Limestone

Depth Varies; deepest recorded at Varies


37.2m

Unit weight 19 kN/m3 24 kN/m3

RQD - 0 – 100%

SPT-N <10 ; average = 6 -

Average UCS - 50 MPa

Effective shear strength c’ = 1kPa ; c’ = 400kPa ;


φ’ = 29˚ φ’ = 32˚

Elastic modulus, E’ 18,000 kPa 1,000,000 kPa

Hydraulic conductivity, k 1x10-6 m/s 0 – 10 x 10-7 m/s


13
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
EARTH RETAINING STRUCTURE
SYSTEM (ERSS)

14
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
ERSS

Design Consideration:
Configuration of SBP adopted:
- To check the overlapping of
• 1480mm/1180mm (SP/PP) @ 1.92m spacing c/c SBP after considered pile
• 1180mm/880mm (SP/PP) @ 1.66m spacing c/c deviation and verticality such
that the SBP still overlapped
at the bedrock level. (to
prevent water seepage if the
SBP is deviated)
15
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Typical Elevation for Rock Socket

16
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
ERSS

Ground Anchor

Strut

17
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Modelling Input Parameters and
Criteria
Descriptions Modelling Input
Model Type Plain Strain analysis
Soil Model Hardening Soil model
Soil Shear Strength Effective Stress parameters
Soil Material Type Drained
Soil Loading Stiffness 18,000kPa
Soil Unloading Stiffness 54,000kPa
Soil/wall interface factor 0.8
Wall Element Plate element
Wall Bending Stiffness 0.7x EI
Wall Compression Stiffness 0.7x EA
Construction Surcharge 20kPa
Groundwater condition Phreatic
18
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Finite Elements (FE) Model
Bottom-up construction
Temporary ground
anchors (45°) due to
limitation of ROW
Easier for excavation
works due to open space
within excavation pit

19
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Finite Element (FE) Model
Bottom-up construction
Temporary struts due to
site constraint
Contractor not prefer as
the excavation works are
limited by the headroom
available below struts

20
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Finite Element (FE) Model
Wall Estimated Supporting Support Deflection
arrangement Bedrock System Layers
Level
1180mm/880 10m-30m Ground 3-13 0.18% - 0.45%
mm Anchor
1180mm/880 14m-30m Strutting 3-5 0.14% - 0.44%
mm
1480mm/1180 12.5m – 38m Strutting 5-10 0.1% - 0.35%
mm
Ok. < 0.5%

21
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor

Anchor
Head Bearing
Plates

Gusset
Plates

Anchor Walers
Strands Waler
Bracket

22
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Ground Anchor

Ground Anchor
Designed to BS8081:1989

Structural Geotechnical Other Steel


Capacity Capacity Elements

To determine
working load a) Waler
To determine the fixed
of GA length of GA b) Gusset Plates
(in our case is rock socket c) Bearing Plates
To determine length) d) Waler Bracket
how many U-
loops of GA
Designed to BS5950:2000

23
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Ground Anchor Properties
Descriptions Properties

Working loads (kN) 212; 424; 636; 848; 1060

No. of strand 2; 4; 6; 8; 10
Strand diameter (mm) 15.24
Breaking load (kN) 260.7
Factor of safety 1.6

Strand U-loop radius (mm) 47.5

Reduction factor 0.65


Drillhole diameter (mm) 175

Allowable bond stress (kPa) 400

Free length Varies


Bond length (m) 3; 3; 4.5; 6; 7.5
24
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor
GA Installation Procedures

Coring of SBP Wall

Drilling in Soil

Coring in Rock

Installation of GA
strands

Grouting

25
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor
GA Installation Procedures

Coring of SBP Wall

Drilling in Soil

Coring in Rock

Installation of GA
strands

Grouting

26
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor
GA Installation Procedures

Coring of SBP Wall

Drilling in Soil

Coring in Rock

Installation of GA
strands

Grouting

27
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor
GA Installation Procedures

Coring of SBP Wall

Drilling in Soil

Coring in Rock

Installation of GA
strands

Grouting

28
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor
GA Stressing Procedures
Initial Stressing of Strands
(from longest strands to shortest strands)

On-site Acceptance Test


(for all GA)

Lock-off GA
(normally extra 10% of designed prestressed load )

Lift-off Test
(to check the lock-off load)

Lock-off GA again

29
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor
Type of Test Test Maximum Creep Monitoring Remarks
Frequency Test Load
Proving Test Each GA 160% WL 10 days -
type (80% of fpu) (or longer subjected to loss
of load/displacement)

On-site 1% of total 125% WL 10 days -


Suitability Test working (Temp GA) (or longer subjected to loss
of load/displacement)
GA

On-site ALL 125% WL 50 mins Creep


(or longer subjected to loss monitoring on
Acceptance working (Temp GA) of load/displacement) 10% of total
Test GA working GA only.
Lift-off test after
lock-off of GA.

30
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor

31
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Ground Anchor

32
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut
• Designed to BS5950:2000- Structural Use of Steelwork in Building.
• Check strut force from Finite Elements (FE) and determine working
load.
• Design elements:
a) Strut (lacing, tie-panel) f) Tie-Beam
b) Waler (stiffener) g) Splice Joints
c) Kingpost h) Shear Connector
d) Bracing i) Concrete waler
e) Runner Beam

33
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut

Tie-beam
Kingpost

Splice joint

Tie-panel

Runner Beam Diagonal Strut

Lacing

34
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut
One-Strut Failure shall be considered in the design to ensure the
robustness of the ERSS.

For first layer strut


-designed to FOS=1.05
-waler bending length
increased

Strut fell off

Waler bending
length increased
35
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut
Different waler size
specified for 1st layer

36
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut
One-Strut Failure shall be considered in the design to ensure the
robustness of the ERSS.

For subsequent layer strut


-designed to FOS=1.05
-whole layer of strut is
removed in each excavation
stage to simulate OSF.
-SBP to transfer load to top
and bottom layers struts.

37
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut

38
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Temporary Support
Strut

39
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Grouting

40
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Grout Termination Criteria
a. Surface ground heave >25mm
b. Refusal at pre-determined pressure
Depth, (m) Recommended Holding
Pressure (Bar)
5 – 10 17
10 – 15 18
15 – 20 19
20 – 25 20
25 - 30 21
30 – 35 22
35 - 40 23

c. Volume of grout exceeded 5m3 41


© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Grouting

42
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Typical Section for GA

43
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Typical Section for Struts

44
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Instrumentations
• For excavation of depth 4.0m or deeper:-
a. One type of C1, C2, C3 or C4 array for
every 25m of perimeter wall
b. Average of one type C2 or C3 array for
every 100m of perimeter wall
c. Average of one type C3 or C4 for every
100m of perimeter wall
d. Average of one type C4 array for every
200m of perimeter wall
45
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Typical Array

46
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Instrumentations

© G&P Professionals Sdn Bhd Quality Services - Our Commitment


Instrumentations
• For buildings within monitoring zone:-
a. Min. 4 nos. building settlement markers
for low and medium rise building
b. Min. 8 nos. for high rise building

48
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Instrumentations

© G&P Professionals Sdn Bhd Quality Services - Our Commitment


Monitoring Frequency

50
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Review Level for Movements

51
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Alert Level

52
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Action Level

53
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Alarm Level

54
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
CONSTRUCTION WORKS

55
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
GA loosening

Observed the strand is


not in tension mode.

56
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
GA loosening
Probable cause of loosen strands:
1) Irregular hole diameter of anchor block.
2) Seating of wedges not balance.
3) Rusting of wedges due to weather.

57
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
GA loosening
Remedial works:
1) Inspect all previously installed GA.
2) Replace all wedges.
3) Make sure all 3 pieces of wedges seating evenly and equally
inside the anchor block hole.
4) Apply grease after locked the wedges to prevent rusting.
5) Install additional inclinometers, settlement markers and optical
prisms to monitor.

58
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
GA loosening
Recommendation to use the following tool to lock-off the ground
anchor and ensure all wedges are gripping the strands uniformly.

59
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Rock Mapping
Rock mapping carried out by G&P geologists in every 3m rock excavation.
Kinematic analysis (Stereonet) to check stability of rock slope.
Rock bolts installation if necessary.

60
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Progress Photos

61
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
62
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
63
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
64
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
65
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
66
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
67
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Achievements
• Commencement of work  2017

• Excavation to Final Excavation Level (FEL)


 April 2019

• Max recorded deflection ratio  0.18%

• Vertical rock excavation >> save cost +


time 68
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
CONCLUSIONS

69
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Conclusions
1) Secant bored pile (SBP) supported with temporary support i.e.
temporary strutting / ground anchor and rock strengthening were
successfully implemented for underground station excavation
works.

2) SBP  prevent excessive groundwater drawdown and settlement

70
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
Conclusions
3) Credit to team members G&P Geotechnics Sdn Bhd &
project team of MMC Gamuda

List of team members from G&P


Ir. Dr. Tan Y.C. Ryan Low Y.L.
Ir. Koo K.S. Bonnie Lau
Ir. Lee Y.C. Ang J.S.
Tan P.Y. Desmond Teh Kok Loong

71
© G&P Professionals Sdn Bhd Quality Services - Our Commitment
THANK YOU