OUTAGE AND STAFF REQUIREMENT

Contract No.: 11031117/00 Date: 17 June 2014


Contractor: AL-BABTAIN CONTRACTING CO. 380KV GIS Section "B" OUTAGE PROGRAM FOR Section "A" High Voltage Test
Contract Description: Construction of New 380/132/13.8kV, S/S 9016 Al-Oraija BSP
Outage Details Required Engineers
SN S/S Job Description Remarks
Circuit Week # Duration Start End Division Start End

1- HV Test for 380KV GIS Section "A" BB - 1B


Circuit # 1 without Surge Arrester of SGT2 DS K214 & K414
(Please refer to attached Test Diagram) on in open position.
20/06/2014 from 7:00 PM to 21/06/2014 Upper bus bar
1 S/S 9016 at 7:00 AM grounded 2 days 6/20/2014 6/21/2014 P, LM, O, T 6/20/2014 6/21/2014
2- HV Test for 380KV GIS Section "A" (please refer to
Circuit # 1 with Surge Arrester of SGT2 attached 380KV
(Please refer to attached Test Diagram) on OSLD For
21/06/2014 from 7:00 PM to 8:00 PM reference)

1- HV Test for 380KV GIS Section "A" BB - 2B


Circuit # 2 without Surge Arrester of SGT1 DS K256 & K456
(Please refer to attached Test Diagram) on in open position.
21/06/2014 from 8:00 PM to 22/06/2014 Lower bus bar
2 S/S 9016 at 7:00 AM grounded 2 days 6/21/2014 6/22/2014 P, LM, O, T 6/21/2014 6/22/2014
2- HV Test for 380KV GIS Section "A" (please refer to
Circuit # 2 with Surge Arrester of SGT1 attached 380KV
(Please refer to attached Test Diagram) on OSLD For
22/06/2014 from 7:00 PM to 8:00 PM reference)