BACKUP VOLUME BOX TAPPING & ASESSORIES

IPA SPAM KSPN MANDALIKA TAHAP I ( KAP. 50L/DETIK)


No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %
1 TAPPINGAN AIR VALVE 250 Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
AIR VALVE 250
Galian Tanah 1.40 1.00 2.22 1.00 3.11 m3 3.11 3.11 100
Sub total 3.11 m3
Pasir urug dipadatkan 1.40 1.00 0.10 1.00 0.14 m3 0.14 0.14 100
Sub total 0.14 m3

Beton lantai kerja , K-125 1.40 1.00 0.05 1.000 0.07 m3 0.07 0.07 100
Sub total 0.07 m3
4

Urugan tanah kembali - m3 - -


Sub total - m3
1 5 3
7 Pemadatan tanah - m3 - -
6
Sub total - m3

Buangan Tanah 3.11 m3 3.11 3.11 100


Sub total 3.11 m3

8 2 8 1
Beton Pondasi Trush Block, K-225 0.20 0.20 0.20 1.00 0.01 m3 0.01 0.01 100
1 5 Sub total 0.01 m3

Beton Penutup, K-225 1.40 1.00 0.10 1.00 0.14 m3 0.14 0.14 100
Sub total 0.14 m3
item kg/m
Tulangan Beton Penutup d10-100, arah x 0.90 14.00 1.00 0.617 7.77 kg 7.77 7.77 100
d10-100, arah y 1.35 10.00 1.00 0.617 8.33 kg 8.33 8.33 100
Sub total 8.33 kg
2 1
Bekistingl Beton Penutup 1.40 1.00 1.00 1.40 m2 1.40 1.40 100
Sub total 1.40 m2
l w h
Pas. Bata Merah 4.80 2.20 1.00 10.56 m2 10.56 10.56 100
Sub total 10.56 m2

Plesteran Dalam 4.80 2.20 1.00 10.56 m2 10.56 10.56 100


Sub total 10.56 m2
dinding
Acian Dalam 3.72 2.20 1.00 8.18 m2 8.18 8.18 100
top w
4.80 0.12 1.00 0.58 m2 0.58 0.58 100
Sub total 8.76 m2
AIR VALVE PIPA 250 ASSESSORIES Size Volume Satuan
1 Stube End Flange ND 250 2.00 bh 2.00 2.00 100
2 Tee Reducer 250x100 ND 250 1.00 bh 1.00 1.00 100
3 Gate Valve ND 100 1.00 bh 1.00 1.00 100
4 Air Valve ND 100 1.00 bh 1.00 1.00 100
5 Dismantling ND 250 1.00 bh 1.00 1.00 100
6 Incian Pipa Gl ND 100 30.00 cm 30.00 30.00 100
7 Flange Las ND 250 2.00 bh 2.00 2.00 100
8 Flange Las ND 100 1.00 bh 1.00 1.00 100
No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %
2 TAPPINGAN CIRCUIT Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
CIRCUIT
Galian Tanah 1.20 1.00 1.02 1.00 1.22 m3 1.22 1.22 100
Sub total 1.22 m3
10 Pasir urug dipadatkan 1.20 1.00 0.10 1.00 0.12 m3 0.12 0.12 100
Sub total 0.12 m3

Beton lantai kerja , K-125 1.20 1.00 0.05 1.000 0.06 m3 0.06 0.06 100
10
Sub total 0.06 m3
8 6

Urugan tanah kembali - m3 - -


Sub total - m3

11 Pemadatan tanah - m3 - -
11 10 9 7 Sub total - m3

Buangan Tanah 1.22 m3 1.22 1.22 100


Sub total 1.22 m3

Beton Pondasi Trush Block, K-225 - m3 - -


Sub total - m3
8 6
Beton Penutup, K-225 1.20 1.00 0.10 1.00 0.12 m3 0.12 0.12 100
Sub total 0.12 m3
item kg/m
Tulangan Beton Penutup d10-100, arah x 0.90 12.00 1.00 0.617 6.66 kg 6.66 6.66 100
d10-100, arah y 1.15 10.00 1.00 0.617 7.09 kg 7.09 7.09 100
Sub total 7.09 kg

Bekistingl Beton Penutup 1.20 1.00 1.00 1.20 m2 1.20 1.20 100
Sub total 1.20 m2
l w h
Pas. Bata Merah 4.40 2.20 1.00 9.68 m2 9.68 9.68 100
Sub total 9.68 m2

Plesteran Dalam 4.40 2.20 1.00 9.68 m2 9.68 9.68 100


Sub total 9.68 m2
dinding w h
Acian Dalam 3.32 2.20 1.00 7.30 m2 7.30 7.30 100
top w h
4.40 0.12 1.00 0.53 m2 0.53 0.53 100
Sub total 7.83 m2

TAPPINGAN CIRCUIT ASSESSORIES Size Volume Satuan


1 Stube End Flange ND 250 2.00 bh 2.00 2.00 100
2 Gate Valve ND 250 1.00 bh 1.00 1.00 100
3 Tee HDPE 250x250 ND 250 1.00 bh 1.00 1.00 100
4 Reducer HDPE 250x100 ND 250 1.00 bh 1.00 1.00 100
5 Pipa HDPE ND 110 12.00 m 12.00 12.00 100
6 Stube End Flange ND 110 1.00 bh 1.00 1.00 100
7 Gate Valve ND 110 1.00 bh 1.00 1.00 100
8 Water Meter ND 110 1.00 bh 1.00 1.00 100
9 Flange Socket ND 110 1.00 bh 1.00 1.00 100
10 Pipa PVC ND 110 12.00 m 12.00 12.00 100
11 Elbow PVC 90⁰ ND 110 2.00 bh 2.00 2.00 100
No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %
3 TAPPING GWT BARAT Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
TAPPING GWT BARAT
Galian Tanah 1.80 1.20 2.22 1.00 4.80 m3 4.80 4.80 100
Sub total 4.80 m3
Pasir urug dipadatkan 1.80 1.20 0.10 1.00 0.22 m3 0.22 0.22 100
Sub total 0.22 m3
7
6 6

5
Beton lantai kerja , K-125 1.80 1.20 0.05 1.000 0.11 m3 0.11 0.11 100
4
8 1 3
Sub total 0.11 m3

Urugan tanah kembali - m3 - -


2 1
12 11 10 9 1 Sub total - m3
12 11 10 9 1
7
6 6
Pemadatan tanah - m3 - -
5
7
Sub total - m3

8
7 2 1 Buangan Tanah 4.80 m3 4.80 4.80 100
Sub total 4.80 m3

Beton Pondasi Trush Block, K-225 1.14 0.20 0.20 1.00 0.05 m3 0.05 0.05 100
Sub total 0.05 m3

Beton Penutup, K-225 1.80 1.20 0.10 1.00 0.22 m3 0.22 0.22 100
Sub total 0.22 m3
item kg/m
Tulangan Beton Penutup d10-100, arah x 1.15 18.00 1.00 0.617 12.77 kg 12.77 12.77 100
d10-100, arah y 1.75 12.00 1.00 0.617 12.95 kg 12.95 12.95 100
Sub total 12.95 kg

Bekistingl Beton Penutup 1.80 1.20 1.00 2.16 m2 2.16 2.16 100
Sub total 2.16 m2
l w h
Pas. Bata Merah 6.00 2.20 1.00 13.20 m2 13.20 13.20 100
Sub total 13.20 m2

Plesteran Dalam 6.00 2.20 1.00 13.20 m2 13.20 13.20 100


Sub total 13.20 m2
dinding
Acian Dalam 4.92 2.20 1.00 10.82 m2 10.82 10.82 100
top w
6.00 0.12 1.00 0.72 m2 0.72 0.72 100
Sub total 11.54 m2

TAPPING GWT BARAT ASSESSORIES Size Volume Satuan


1 Stube End Flange ND 250 3.00 bh 3.00 3.00 100
2 Tee Reducer Gl 250x150 ND 250 1.00 bh 1.00 1.00 100
3 Pipa Incian Gl ND 150 1.00 bh 1.00 1.00 100
4 Flange Las ND 150 3.00 bh 3.00 3.00 100
5 Ben Gl 90⁰ ND 150 1.00 bh 1.00 1.00 100
6 Gate Valve ND 150 1.00 bh 1.00 1.00 100
7 Stube End Flange ND 150 3.00 bh 3.00 3.00 100
8 Tee HDPE ND 150 1.00 bh 1.00 1.00 100
9 Gate Valve ND 250 1.00 bh 1.00 1.00 100
10 Dismanting Joint ND 250 1.00 bh 1.00 1.00 100
11 Water Meter ND 250 1.00 bh 1.00 1.00 100
12 Blind Flange ND 250 1.00 bh 1.00 1.00 100
13 Flange Las ND 250 2.00 bh 2.00 2.00 100
No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %
4 TAPPING PENUNJANG WSBK Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
TAPPING PENUNJANG WSBK
9 Galian Tanah 1.00 0.85 1.02 1.00 0.87 m3 0.87 0.87 100
Sub total 0.87 m3
Pasir urug dipadatkan 1.00 0.85 0.10 1.00 0.09 m3 0.09 0.09 100
Sub total 0.09 m3
10
7 Beton lantai kerja , K-125 1.00 0.85 0.05 1.000 0.04 m3 0.04 0.04 100
Sub total 0.04 m3
3 3
Urugan tanah kembali - m3 - -
Sub total - m3
9 10 8 6
4 Pemadatan tanah - m3 - -
Sub total - m3

3 3 Buangan Tanah 0.87 m3 0.87 0.87 100


10 Sub total 0.87 m3
3
Beton Pondasi Trush Block, K-225 - m3 - -
9
Sub total - m3

Beton Penutup, K-225 1.00 0.85 0.10 1.00 0.09 m3 0.09 0.09 100
Sub total 0.09 m3
10 8 6 5
7 item kg/m
4
Tulangan Beton Penutup d10-100, arah x 0.95 10.00 1.00 0.617 5.86 kg 5.86 5.86 100
d10-100, arah y 0.80 8.00 1.00 0.617 3.95 kg 3.95 3.95 100
Sub total 3.95 kg

Bekistingl Beton Penutup 1.00 0.85 1.00 0.85 m2 0.85 0.85 100
Sub total 0.85 m2
l w h
Pas. Bata Merah 3.70 1.02 1.00 3.77 m2 3.77 3.77 100
Sub total 3.77 m2

Plesteran Dalam 3.70 1.02 1.00 3.77 m2 3.77 3.77 100


Sub total 3.77 m2
dinding
Acian Dalam 2.62 1.02 1.00 2.67 m2 2.67 2.67 100
top w
3.70 0.12 1.00 0.44 m2 0.44 0.44 100
Sub total 3.12 m2

TAPPING PENUNJANG WSBK ASSESSORIES Size Volume Satuan


1 Flange ND 63 1.00 bh 1.00 1.00 100
2 Reducer 110x63 mm ND 100 1.00 bh 1.00 1.00 100
3 Flange Las ND 110 6.00 bh 6.00 6.00 100
4 Stube End Flange ND 110 2.00 bh 2.00 2.00 100
5 Pipa HDPE ND 110 182.00 m 182.00 182.00 100
6 Dismantling Joint ND 110 1.00 bh 1.00 1.00 100
7 Gate Valve ND 110 1.00 bh 1.00 1.00 100
8 Water Meter ND 110 1.00 bh 1.00 1.00 100
9 Ben Gl 90⁰ ND 110 3.00 bh 3.00 3.00 100
10 Pipa Gl ND 110 6.00 m 6.00 6.00 100
No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %
5 TAPPING GRUPUK Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
TAPPING GRUPUK

1 2 4 5 6 6 5 9 8 10
1
2

6
14
10
7 6 5 9
11

12
11 11

8
TAPPING GRUPUK
1 Skal a: 1:30

TAPPING GRUPUK ASSESSORIES Size Volume Satuan


1 Stube End Flange ND 250 1.00 bh 1.00 1.00 100
2 Gate Valve ND 250 1.00 bh 1.00 1.00 100
3 Dismantling Joint ND 250 1.00 bh 1.00 1.00 100
4 Reducer 250x500 ND 250 1.00 bh 1.00 1.00 100
5 Stube End Flange ND 500 1.00 bh 1.00 1.00 100
6 Pipa HDPE ND 500 5.00 m 5.00 5.00 100
7 Ben 45⁰ HDPE ND 500 1.00 bh 1.00 1.00 100
8 Gate Valve ND 150 1.00 bh 1.00 1.00 100
9 Pipa Gl ND 500 80.00 cm 80.00 80.00 100
10 Bling Flange ND 500 1.00 bh 1.00 1.00 100
11 Flange Las ND 500 3.00 bh 3.00 3.00 100
12 Flange Las ND 150 1.00 bh 1.00 1.00 100
13 Pipa Gl ND 150 40.00 cm 40.00 40.00 100
14 Flange Las ND 250 1.00 bh 1.00 1.00 100

No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %


6 AIR VALVE RAMSET Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
AIR VALVE RAMSET
1

4
2
3

AIR VALVE RAMSET ASSESSORIES Size Volume Satuan


1 Air Valve ND 100 1.00 bh 1.00 1.00 100
2 Flange ND 100 1.00 bh 1.00 1.00 100
3 Pipa Incian Gl ND 100 10.00 cm 10.00 10.00 100
4 Pipa GIP ND 250 23.00 m 23.00 23.00 100
No. PEKERJAAN Pekerjaan Uraian Volume Satuan Rencana Realisasi %
7 WASH OUT 250 Pekerjaan Tanah Tulangan L W H Unit Kg/m Volume Satuan Volume
WAHS OUT 250

3 1 2 1

1
9
4
10
5
6
7

8 8

7
WASH OUT 250 ASSESSORIES Size Volume Satuan
1 Stube End Flange ND 250 3.00 bh 3.00 3.00 100
2 Gate Valve ND 250 1.00 bh 1.00 1.00 100
3 Tee PE 250x250 ND 250 1.00 bh 1.00 1.00 100
4 Reducer 250x150 ND 250 1.00 bh 1.00 1.00 100
5 Gate Valve ND 150 1.00 bh 1.00 1.00 100
6 Flange Socket ND 150 1.00 bh 1.00 1.00 100
7 Pipa PVC ND 150 24.00 m 24.00 24.00 100
8 Elbow PVC ND 150 2.00 bh 2.00 2.00 100
9 Flange Las ND 250 1.00 m 1.00 1.00 100
10 Flange Las ND 150 1.00 bh 1.00 1.00 100

TOTAL PERSENTASE 100.00