You are on page 1of 1

BAE Systems Proprietary

GIYS7U-CSJD-8RZ-7O

Observation Notice Standard Form - FM F210

LOCATION: Serial No.


PROJECT:
OBSERVATION NOTICE 017
FACILITY: FILE REF : 017
Contractor's Activity/Data:

Mechanical Engineer Daily Site walk – Record of findings

FM Observation Record No.: 017 Dated 15th December 2022

Observation Description:
1 GF: remove old AC unit and ducts etc from electrical room
2 General: All soil and waste risers in vertical shafts to be provided with ckean out at 1.0m from
floor at each level. Fire rated access panel in riser required
3 General: provide support details for all pipes and ducts within vertical shafts / risers
4 At front RHS and LHS where drain pipes run horizontally through Managers rooms/
bedrooms / offices etc provide acoustic insulation to pipe

NO PHOTOS ATTACHED TO THIS OBSERVATION NOTICE

Signed by (Originator) Christopher Bennett Date 15.12.2022

Authorized by Christopher Bennett Date 15.12.2022

Contractor’s Response:

Signed by (Contractor) Date

Comment/Actions Arising:

Signed by (Originator) Date

Agreed by PM Date
Subsequent Action Taken (date):

Document Reference (if applicable)

Observation Notice Closed (Originator) Date

Programme Engineering Management Plan


Page 1