INDUSTRIAL GASES HUB ABCD

Contract No: FIELD CHANGE NOTICES Date:

PART A – CONTRACTOR:

FCN NO: 12345 FCN TITLE: ABCS

REFERENCE DOCUMENT NO:


Rev No: 03
EXISTING CONDITION:

As per approved drawing UG FWN pipe loop running on Rack, south side of SMR shelter. Support missing.

REASON FOR CHANGE:


UG FWN Rack piping is only mentioned in the drawing. There are no supporting details provided.

GV-03 UG / AG Tie-in Transition Spool dimension was changed due to structure foundation issue.

FM-03 UG pipe dimension changed due to SMR Structure foundation clashing.

FH-17 Near by loop dimension changed due to not possible to install the pipes as per given dimension.
DESCRIPTION OF CHANGE:

Rack piping supports Markup prepared as per site condition.

GV-03 location transition spool modified as per site condition to match the FGL.

FM-03 AG tie-in dimension was 1meter reduced to avoid foundation clashing.

FH-17 loop depth increased to joint pipe & fittings. FSG

Proposed changes marked in Attached Markup drawing.


Disposition Requested Date:
Prepared By: Approved By: Date:

PART B - ENGINEER OF RECORD

Accepted: Approved With changes: Rejected:

List Design Document(s) Affected by FCN (Include documents noted above and additional documents, as required.)

FCN Affects Document Incorporation Required


Document No Rev No
Yes No Yes No

Attached Location blow up drawings

Responsible Design Engineer: Checker

Mechanical/ Process: ✔ Plant Design: Electrical:

Civil/ Structural/ Arch: Control Systems: MET:

SIGNATURE: SIGNATURE:

NAME: NAME: