You are on page 1of 2

PUNJAB AAB-E-PAK AUTHORITY

4th Floor, EFU House, 6-D Main Gulberg, Jail Road, Lahore
Phone; 042-35786893-94-95-96

Ref: PAPA/D(P&QC)/NZ/1081-1087
Dated: 22nd June, 2022

To,
Director
Brisk International,
111-Y, Commercial, 2nd Floor
Phase-III, DHA, Lahore Cantt,
Lahore.
Subject: SUPPLY, CONSTRUCTION, INSTALLATION AND O&M OF WATER
FILTRATION PLANTS IN SARGODHA & GUJRANWALA DIVISION (PACKAGE-
09)
VARIATION – THREE PHASE MAIN DISTRIBUTION BOARD

(i) Ref: Brisk/PAPA/Guj/Sgd/117 dated 31-05-22


(ii) Ref: JERS-AID JV Letter No. 465-J01-09-CS/60 dated 20-06-22

Reference to above mentioned letter regarding subject variation, M/s JERS-AID JV


has critically examined the variation case of subject item and recommended that three
phase main distribution board (MDB) would be essentially required to operationalize the RO
plants keeping in view of contractor’s plant/equipment as previously single phase (MDB)
was given in the contract.

2. M/s JERS-AID JV duly checked the subject variation based on current market rates
and recommended with following cost impact.

Financial Impact due to Variation of 3 Phase MDB


Amount
Description
(PKR)
Original Contract Cost (Capex + Opex) 421,285,635
Additional cost due to variation of three phase MDB for RO
6,198,465
plants (95 Nos. x Rs. 65,247)
Saving due to dropped Single phase MDB for RO plants
1,528,550
(95 Nos. x Rs. 16,090)
Grand Total Cost 425,955,550

Variation Cost 4,669,915

%age in excess from original cost 1.11%


PUNJAB AAB-E-PAK AUTHORITY
4th Floor, EFU House, 6-D Main Gulberg, Jail Road, Lahore
Phone; 042-35786893-94-95-96

2. Therefore, subject variation of Rs. 4,669,915/- with cost impact 1.11% above is
approved. You are directed to expedite the work for timely completion of the project.

This is being issued with the approval of Chief Engineer / DG Projects, vide
concerned file dated 22-06-2022.

Director Projects & Quality Control


(North Zone)

CC:
• Chief Engineer / DG Projects, Punjab Aab-e-Pak Authority
• Director Planning, Punjab Aab-e-Pak Authority
• Director P&C, Punjab Aab-e-Pak Authority
• Director Finance, Punjab Aab-e-Pak Authority
• Team Leader, JERS-AiD JV
• File