Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 1 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 2 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

Risk Rating Residual


Activities (Job Action Party /
S/N Potential Hazards Before Controls / Mitigation Measures Risk/
steps) Remark
Mitigation Rating
1 Work area  Noise P= 3XC (M)  All personnel inside the working area must carry ear muffs P= 1XC (L) MG Supervisor ,
awareness. A= 0XC (NA) at all times. A= 0XC (NA) MG PTW Holder.
E= 2XC (M)  Wear hearing protection at high noise areas. E= 1XC (L)
R= 0XC (NA) R= 0XA(NA)
 H2S and other P= 3XC (M)  All personnel working inside plant/Pipe line corridor shall P= 1XC (L) MG Supervisor ,
toxic gases A= 0XC (NA) have H2S personal gas monitor/Toxic clips. A= 0XC (NA) MG PTW Holder.
E= 2XC (M)  Provide Area Gas Monitor if required by QatarEnergy E= 1XC (L)
R= 2XC (M) PTW. R= 1XC(L)
 Ensure everyone having Escape hood while working in the
plant.
 Ignition sources. P= 3XC (M)  Do not carry mobile phone, smart watch, Lighter, P= 1XC (L) MG Supervisor ,
A= 3XC (M) cigarette, and any kind of ignition sources in the plant. A= 1XC (L) MG PTW Holder.
E= 2XC (M)  Employees to be educated for self-checking prior to enter E= 1XC (L)
R= 3XC(M) into the plant. R= 1XC(L)
 Post Prohibited Items list in all vehicle to refresh
employees.
 Include Prohibited Items Topic in daily TBT for the
awareness of the people
 Emergency P= 3XC (M)  Provide proper access to the area. P= 1XC (L) MG Supervisor ,
condition A= 2XC (M)  In case of any emergency follow MIC emergency Response A= 1XC (L) MG PTW Holder.
E= 0XC (NA) procedures. E= 0XC (NA)
R= 2XC (L)  Each employee should be instructed about safe working R= 1XC(L)
procedure/technique and emergency procedure and
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 3 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

response, in case of emergency.


 Unaware of the P= 2XC (M)  QatarEnergy (9) Lifesaving rules should be discussed with P= 1XC (L) MG Site
QatarEnergy A= 2XC(M) the work crew on daily basis through TBT. A= 1XC (L) Supervisor, MG
Lifesaving rules E= 0XC (NA)  Strict compliance of QatarEnergy (9) LSR should be E= 0XC (NA) PTW Holder
R= 2XC(M) followed(i.e. Gas Hazards, Line of fire etc) R= 1XC(L)
2 Site preparation  Unauthorized P= 3XC (M)  The area identified, confirmed & cleared prior to entry P= 1XC (L) MG Supervisor ,
commencement of A= 0XA(NA) into the work area. A= 0XC (NA) MG PTW Holder.
work E= 0XC (NA)  All personnel shall be trained of all mandatory trainings. E= 0XC (NA)
 Exposing people R= 2XC (L)  Authorized QatarEnergy work permit holders shall R= 1XC(L)
potentially harm ensure obtaining and maintaining of valid work permits
or danger. and associated certificate.
 Lack of safety  The supervisor responsible for this activity has to check
awareness the PPE and tools of his crew to ensure that all required
items are available and properly used.
 Inform all people regarding permit conditions before work
starts.
 Supervisors must conduct daily toolbox talk about nature
of work and associated potential hazards and its control
measures. Discuss possible emergency and response
procedure.
 Comply with all general job requirements mentioned on
PTW.
 Wear all mandatory PPE.
 Slip / Trip / Fall P=3XC (M)  Maintain obstruction free access. P= 1XC (L) MG Supervisor ,
A=0XC (NA)  Beware of ankle breaker stones. A= 0XC (NA) MG PTW Holder.
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 4 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

E=0XC (NA)  Use only designated access. E= 0XC (NA)


R=2XC (M)  Maintain the cable/ hose management R= 1XC(L)
 Manual handling P=3XC (M)  Maintain manual handling technique to avoid stress and P= 1XC (L) MG Supervisor ,
injury A=0XC (NA) strain. A= 0XC (NA) MG PTW Holder.
 Poor ergonomics E=0XC (NA)  Do not lift heavy or oversize load alone. Take assistance E= 0XC (NA)
R=2XC (M) for heavy or awkward loads. R= 1XC(L)
 Provide adequate manpower for manual handling.
 Use mechanical means to lift and carry heavy loads.
 Wrong/ Damaged P=3XC (M)  Use only good condition colour coded tools for the job. P= 1XC (L) MG Supervisor ,
Hand Tools A=0XC (NA)  Remove the damaged tools from the site. A= 0XC (NA) MG PTW Holder.
E=0XC (NA) E= 0XC (NA)
R=2XC (M) R= 1XC(L)
 Pinch Points/ P=3XC (M)  Keep hand and fingers away from trap points and sharp P= 1XC (L) MG Supervisor ,
Sharp edges A=0XC (NA) edges. A= 0XC (NA) MG PTW Holder.
E=0XC (NA)  Wear heavy duty gloves for the task. E= 0XC (NA)
R=2XC (M)  Maintain proper communication between team members. R= 1XC(L)
 Identify sharp edges and trap points prior to start the
task.
 Presence of P= 4XC(M)  Inspect the area before and during the activity for the P= 1XC(L) MG Supervisor ,
Snakes/Insects A= 0XC (NA) presence of any snakes/Insects. A= 0XC (NA) MG PTW Holder.
E= 0XC (NA)  Don’t sit/Stand near Burrow. E= 0XC (NA)
R= 2XC(M)  Emergency standby vehicle to be provided at site. R= 1XC(L)
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 5 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Infected by P=3xC (M)  Any person showing symptoms of infection will be sent to P=1xC (L) MG work crew
Corona virus E=0XC (NA) medical Centre. E=0XC (NA) MG site nurse/
(COVID-19) A=0xB (NA)  Cover your nose and mouth with clean napkin/ or with A=0xB (NA) doctor
 Spread of R=3xC (M) sleeve when coughing or sneezing. R=1xC (L)
infection to others  Inform immediately your supervisor and department
 Dispose-off the tissue with responsibility in a trash bin and
immediately wash your hands
 Avoid any contact with people who show symptoms of
respiratory diseases such as coughing or sneezing.
 If you have flu symptoms, use face mask to avoid infecting
others.
 Wear a mask to limit the respiratory droplets.
 visit the health center or hospital in any flu symptoms.
 Always wash your hands with soap or hand sanitizer.
 Avoid touching your nose, eyes and mouth with unclear
hands.
 Maintain a clean environment & sanitize surfaces.
 Hand washing and sanitizing facility should be provided at
site
 Keep distances (2 M) and avoid close contact to a
minimum
 Avoid contact with stray, sick or dead animals.
 Eat well cooked food.
 Mandatory PPE (Face Mask) should always be worn.
 Ensure your health color code status is always green, if
not it should be immediately reported to health center.
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 6 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Bullying (personal P=3xB (M)  Employee to be reminded in the toolbox talks, to respect P=1xB (L) MG Supervisor ,
injury) E=0XC (NA) people – no bulling is tolerated as per HR-Admin policy. E=0XC (NA) MG PTW Holder.
A=0XC (NA)  Disciplinary action will be imposed if injury incurred A=0XC (NA)
R=1xB (L) horseplay occurs. R=1xB (L)
 Workplace P=3xB (M)  Employee to be reminded in the toolbox talks, that P=1xB (L) MG Supervisor ,
violence (personal E=0XC (NA) horseplay is not allowed. E=0XC (NA) MG PTW Holder.
injury) A=0XC (NA)  No teasing or franking or any kind of horseplay at site as it A=0XC (NA)
R=1xB (L) may lead to undesired event. R=1xB (L)
 Disciplinary action will be imposed if injury incurred
horseplay occurs.
 Workload (stress/ P=3xB (M)  Supervisor to respect what employee or workers feel P=1xB (L) MG Supervisor ,
pressure) from E=0XC (NA) about the job. E=0XC (NA) MG PTW Holder.
Supervision. A=0XC (NA)  Do not push workers to a job out of his scope of duties A=0XC (NA)
R=1xB (L) and responsibilities. R=1xB (L)
 Do not allow workers to excessive workload (single) hand
delegation.
 Always ask worker, how do they feel today, how is their
day or morning so far.
 Engage them into healthy conversation.
 Always listen to their concerns.
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 7 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Working beyond  QatarEnergy PTW Procedure should be followed and MG Supervisor,


PTW stipulated P= 0XC (NA) implemented. P= 0XC (NA) MG PTW Holder.
timing. A= 0XA(NA)  PTW working conditions should be communicate with A= 0XA(NA)
E= 0XC (NA) work crew. E= 0XC (NA)
R= 3XC (M) R= 1XC (M)

 Heat stress/Heat P= 4XC(M)  Follow heat stress Management procedures. P= 1XC(L) Site Supervisor,
stroke and heat A= 0XA (NA)  Don’t work alone and engage buddy working system. A= 0XA (NA) PTW Holder,
related Illness. E= 0XA (NA)  Adequate Cold drinking water to be provided. E= 0XA (NA) Safety officer
R= 2XC(M)  Follow Flag system. R= 1XC(L)
 Work rest rotation to be followed.
 Provide adequate rest Shelter.
 Heat stress training to be provided to workforce.
 Heat stress Emergency awareness to be discussed through
TBT
3 Adjustment of  Electrical shock P= 0XA (NA)  Authorised person shall involve in the activity. P= 0XA (NA) MG Supervisor,
existing light pole  Improper and A= 0XA(NA)  Obtain the work permit. A= 0XA(NA) MG PTW Holder.
frame wrong isolation E= 0XA (NA)  Follow LOTO procedure E= 0XA (NA)
R= 3XC (M)  Obtain the PRC prior to start the work R= 1XC (M)
 Ensure QatarEnergy Electrical authorisation personnel
 Unsafe acts cause P= 0XA (NA)  Ensure that a worksite supervisor is properly monitoring P= 0XA (NA) MG Supervisor,
of inexperience A= 0XA(NA) the site activity works. A= 0XA(NA) MG PTW Holder.
personnel E= 0XA (NA)  Deploy experienced personnel. E= 0XA (NA)
R= 3XC (M)  QatarEnergy PNP and operation E&I representative R= 1XC (M)
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 8 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Unauthorized Entry P= 0XA (NA)  Area Shall be cordon off P= 0XA (NA) MG Supervisor,
A= 0XA(NA)  Signage’s shall be in place A= 0XA(NA) MG PTW Holder.
E= 0XA (NA) E= 0XA (NA)
R= 3XC (M) R= 1XC (M)
 Pinch point / cut P= 3XC (M)  Keep fingers away from pinch points. P= 1XC (L) MG Supervisor,
injury. A= 2XC (M)  Secure/ Hold the cable lugs during bolting by calibrated A= 1XC(L) MG PTW Holder.
E= 0XA (NA) Torque wrench. E= 0XA (NA)
R= 2XC (M)  Use cut resistance hand gloves. R= 1XC (L)
 Injury due to hand P= 3XC (M)  Check the tools condition and colour code before use. P= 1XC (L) MG Supervisor ,
tools. A= 2XC (M)  Sharp tools to point away from body and not towards A= 1XC(L) MG PTW Holder.
E= 0XA (NA) body. E= 0XA (NA)
R= 2XC (M)  Use right tool for the job. R= 1XC (L)

4 Illumination test  Uncertified testing P=3XC (M)  Use inspected and certified testing devices. P=1XC (L) MG Supervisor ,
by using lux meter devices A=0XA (NA) A=0XA (NA) MG PTW Holder.
E=0XA (NA) E=0XA (NA)
R=2XC (M) R=1XC (L)
5 Working at height  Falling Hazard P= 4XC (M)  All required PPE shall be used. Full body harness with P= 1XC ((L) MG Supervisor,
A= 2XC (M) 100% tie off shall be followed when working 1.8 M A= 1XC ((L) MG PTW Holder.
E= 0XA (NA) E= 0XA (NA)
 3 Point contact to be made while ascending/Descending
R= 3XC (M) R= 1XC((L)
Ladders.
 Full body harness to be inspected and endorsed by BCP.
 Ensure scaffold is inspected and valid tag is available.
 No unauthorized modification of scaffold is allowed.
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 9 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Falling Object P= 4XC (M)  Tool lanyard shall be used P= 1XC ((L) MG Supervisor,
A= 2XC (M)  Area shall be barricaded and signage provided. A= 1XC ((L) MG PTW Holder.
E= 0XA (NA) E= 0XA (NA)
R= 3XC (M)
 Loose items shall be properly contained. R= 1XC((L)

6 Work at night  Poor Illumination P= 3XC(M)  Ensure general lighting and spot lighting are adequate P=1XC (L) MG Supervisor,
 Poor visibility A= 0XA(NA) prior to start the night shift job. A=0XA (NA) MG PTW Holder.
 Trip/Slip/Fall E= 0XA (NA)  Lux level survey to be carried out prior to start night shift E=0XA (NA)
R=2XC(M) R=1XC (L)
 Wrong/ Damaged job.
Equipment  Approval from Operations and MIC to be obtained for the
 Non inspected night shift activities.
equipment’s  Lights to be distributed properly from every side to avoid
shadow at the work area.
 Ensure no obstructions at the walking or Working area.
 Proper cable management to be maintained at site.
 All SIMOPS must be stopped during night shift
 All equipments like tower lights etc used at night to be
inspected and approved by QatarEnergy inspectors.
 Gate pass for the equipment to be ensured at site.
 Use only good condition equipments at site.
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 10 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Working alone P= 3XC(M)  Engage buddy system. Do not work alone. P=1XC (L) MG Supervisor,
 Improper access A= 0XA(NA)  Use only designated access to reach work areas, do not A=0XA (NA) MG PTW Holder.
 Unauthorized E= 0XA (NA) enter any unauthorized areas. E=0XA (NA)
R=2XC(M) R=1XC (L)
entry  Inform site HSE or Supervisor prior to move out from the
work location.
P= 3XC(M)  Wear Clear Safety Goggles at all times. P=1XC (L) MG Supervisor,
 Poor A= 0XA(NA)  High visible reflective vest must be worn at all areas A=0XA (NA) MG PTW Holder.
communication. E= 0XA (NA) where work is ongoing. E=0XA (NA)
 Incorrect PPE R=2XC(M) R=1XC (L)
 Tower lights or other electrical fixtures to be inspected
 Electricity and color coded.
 QP approved tower lights to be used at site.
 Ensure maintenance electricians are available at site
during night shift.
 Proper earthing to be provided for tower lights and other
electrical fixtures.
 Daily inspection of tower lights, electrical fixtures and
cables to be conducted by competent electrician and user
on daily basis prior to use them.
 Ensure ELCB/ MCB provided for all electrical fixtures.
 Communication devices to be available with site
supervisors and HSE team.
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 11 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Biological Hazards P=3xC (M)  Do not sit in the shaded area. P=1xC (M) MG Supervisor,
 Presence of snake, E=0xA (NA)  Do not take rest/sit near trees or bushes. E=0xA (NA) MG PTW Holder.
Scorpion, insect , A=0xB (NA)  Always be vigilant and aware of the work environment. A=0xB (NA)
R=0xB NA) R=0xB NA)
Fox  If encountered with snakes or reptiles do not approach
them and try to kill them, it should be reported to control
room (MIC 135)
 Torch lights to be available with all team to use in case of
emergency.
 Fatigue P=3XC (M)  Supervisor to ask work force if they are rested or fit to P=1XC (L) MG Supervisor,
A=0XA (NA) work. A=0XA (NA) MG PTW Holder.
E=0XA (NA)  Supervisor shall monitor signs of fatigue during TBT. E=0XA (NA)
R=2XC (M) R=1XC (L)
 All personnel shall take proper rest /break time.
 AC stand by bus / vehicle to be available at all night shift
locations

 Collision with P= 3XC(M)  General illumination to be provided at all areas where P=1XC (L) MG Supervisor,
existing pipelines at A= 0XA(NA) congestion/ bend with potential for collision. A=0XA (NA) MG PTW Holder.
pipeline corridor E= 0XA (NA)  Trained banksman assistance to be ensured if required. E=0XA (NA)
R=2XC(M) R=1XC (L)
 Blinking lights to be provided throughout the access until
work location.
 Barricade and warning tapes to be provided at all
locations where bends and congestion at the road.
 Non availability of P=3xC (M)  QPR and other permits to be ensured for night shift P=1xC (M) MG Supervisor,
End user permits E=0xA (NA) activities to cross their asset. E=0xA (NA) MG PTW Holder.
A=0xB (NA) A=0xB (NA)
R=0xB NA) R=0xB NA)
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 12 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

 Improper welfare P=3XC (M)  Ensure proper welfare facilities are available at site for P=1XC (L) MG Supervisor,
facilities A=0XA (NA) night shift activities. A=0XA (NA) MG PTW Holder.
E=0XA (NA) E=0XA (NA)
R=2XC (M) R=1XC (L)
7 Environmental  Lightning P= 3XC (M)  All work shall terminate and each employee shall move to P= 1XC (L) MG Site
Conditions  Rain A= 2XC(M) a safe place when environmental conditions create a A= 1XC (L) Supervisor, MG
 Strong winds E= 0XA (NA) hazard for the employee. E= 0XA (NA) PTW Holder
 Darkness R= 2XC(M)  Provide shelters/Bus to rest in case abnormal weather R= 1XC (L)
conditions
 Ensure dust mask available with all when dust creation
 Wear clear glass during dark/night period.
8 Post activity  Slips, trips and P=3XC (M)  Ensure all equipment / materials removed from area. P=1XC (L) MG Site
checks, falls A=0XA (NA)  Clear the area of any slip, trip or fall hazards. A=0XA (NA) Supervisor, MG
housekeeping. E=0XA (NA)  All equipment’s and tools removed on completion of job. E=0XA (NA) PTW Holder.
R=2XC (M)  Be cautious for the wet slippery surface. R=1XC (L)

 Dust P=3XC (M)  Use Proper PPE for the task. Use dust mask. P=1XC (L) MG Site
A=0XA (NA)  Waste material collected and disposed as per waste A=0XA (NA) Supervisor, MG
E=0XA (NA) management plan. E=0XA (NA) PTW Holder.
R=2XC (M) R=1XC (L)
 Sharp Edges/pinch P=3XC (M)  Wear heavy duty gloves for the task. P=1XC (L) MG Site
points A=0XA (NA)  Keep the body parts away from sharp edges. A=0XA (NA) Supervisor, MG
E=0XA (NA)  Protect the sharp edges with some sort of means if E=1XC (L) PTW Holder.
R=2XC (M) possible. R=1XC (L)
Procedure Ref: IP-OPS-066

JOB HAZARD ANALYSIS


Rev.: A1
Date: Dec. - 2014
Page : 13 of 13

JHA No: 40 Revision No: 0 AREA: MIC JOB LOCATION: STATION S DATE: 01/11/2022
Job Ref (Contract No): GC 22100700 Hazardous Area Classification: Zone 0 , Zone 1 , Zone 2 , Non-Hazardous 
Permit Type & No : SPARK POTENTIAL & 89492
Job Description: TO CARRY OUT ADJUSTMENT OF LIGHT POLE FRAME AND
ILLUMINATION TEST FOR EXISTING LIGHT POLE (S-FL-26)

TEAM MEMBERS & ENDORSEM ENT

Position / Ref Position / Ref Sign


S/N Name Indicator Sign S/N Name Indicator
Avinash Kammili
1 Construction Manager 4
Meethal
Muhammed Hussain
2 Project HSE Lead 5
Latheef
Jojo Escalona /
3 PNE0011C / PNE0002C 6
Aju Kuriakose

JHA Team Leader Authorization: Ref Indicator: Sign:

JHA Approval (Permit Authority/ Asset Holder): Ref Indicator: Sign: