Professional Documents
Culture Documents
Chapter Four
Hydraulic and Hydrologic Design Concept
By Yimam A.
Outline
1 Introduction
3 Measurement of run-off
Learning Objectives
Introduction
Hydrology is the study of the occurrence, movement and distribution of water on, above
and within the earth’s surface.
It is the science which deals with the depletion and replenishment of water resources.
It deals with the surface water as well as the ground water.
It is also concerned with the transportation of water from one place to another, and
from one form to another.
It helps us in determining the occurrence and availability of water.
Cont....
Earlier it was pointed out that the principal parameters necessary in making hydro
power studies are water discharge and hydraulic head.
The measurement and analysis of these parameters is hydrological problem.
Part of the hydrology problem is to identify the vertical distance between the level of
water in the forebay (headwater) of the hydro plant and in the tailrace where the water
issues from the draft tube at the outlet to the turbine.
Determination of head is a surveying problem that identifies elevations of water surface.
Cont....
Cont....
Cont..
Processes involved in the hydrologic cycle are
Precipitation: It includes all the water that falls from atmosphere to earth surface.
Precipitation is of two types
Liquid precipitation(rainfall)
Solid precipitation(snow, hail)
Evaporation: transfer of water from liquid to vapour state is called evaporation
Transpiration: the process by which water is released to the atmosphere by the plants
is called transpiration.
Run-off: includes all the water flowing in the stream channel at any given section.
Cont....
Surface run-off: includes only the water that reaches the stream channel without
first percolating down to the water table.
Hydrologic equation is expressed as follows:
P=R+E
Where P-Precipitation R-Run-Off E-Evaporation
Infiltration: It is is a process by which water enters the surface strata of the soil and
makes its way downwards to the water table.
Precipitation absorbed by the soil seeps or percolates into the ground, forming bodies
of water called the water table or ground storage.
The amount of seepage or infiltration depends on the geological character of the surface
and subsoil.
Cont....
The best way to study the rainfall pattern is with the help of graphical plots.
The hyetographs are the rainfall intensity time curves which indicate the variation of
the rate of rainfall with respect to time.
The cumulative value of rainfall plotted against time represents the mass curve of
rainfall.
Cont....
2. Empirical formula: is only acceptable to a particular site for determining the run
off. But no generalized equation can be developed.
a)Khosla’s formula
R = P − 4.811T
Cont....
c) Lacey’s formula
R = P/(1 + 3084F/P S)
Cont....
3. Run-off curves and tables
Each region has its own catchment area and rainfall characteristics and for the same
region the characteristics mostly remain unchanged.
Based on this fact the run-off coefficients are derived once for all.Then a graph is plotted
in which one axis represents rainfall and the other run-off.
The curves obtained are called run-off curves.
4. Actual measurement: stream gauge is used to measure the stream flow,i.e. run-off.
Hydrograph
A graph showing discharge(run-off) of flowing water with respect to time for a specified
time is called hydrograph.
The time period for discharge hydrograph may be hour,day,week or month.
It indicates the power available from the stream at different times of day, week, month
or year.
Cont....
Cont....
A Hydrograph is used to know:
Rate of flow at any instant during the specific recorded period.
Total volume of flow in a given period, as the area under the hydrograph represents
the volume of water in a given duration.
The mean annual run-off for any of the recorded period.
The maximum and minimum run-off for any selected period.
The maximum rate of run during the floods and duration of frequency of floods(peak
of the curve indicates the flood).
Cont...
Cont...
Use of flow duration curve
1 A flow duration curve allows the evaluation of low level flows.
2 For hydropower studies, the flow duration curve serves to determine the potential for
firm power generation.
The firm power is also known as the primary power.
Secondary power is the power generated at the plant utilizing water other than that used
for the generation of firm power.
3 The flow duration curve also finds use in the design of drainage systems and in flood
control studies.
Cont...
Shortcomings of flow duration curve
It does not present the flows in natural source of occurrence.
It is also not possible to tell from flow duration curve whether the lowest flow occurred
in consecutive periods or were scattered throughout the considered period.
Mass Curve
A mass curve is the graph of the cumulative values of water quantity(run-off) against
time.
It is an integral curve of the hydrograph which expresses the area under the hydrograph
from one time to another.
It is a convenient device to determine storage requirement that is needed to produce a
certain dependable flow from fluctuating discharge of a river by a reservoir.
It is used to solve the reserve problem of determining the maximum demand rate that
can be maintained by a given storage volume.
Cont....
Example
At a particular site the mean monthly discharge is as follows.
a) Draw Hydrograph
b) Draw Flow duration curve
c) Draw Mass curve
d) Find the power in MW available at mean flow if head available is 80 m and overall
efficiency of generation is 85%. Take each month of 30 days
Time(month) Discharge(m3 /s) Time(month) Discharge(m3 /s)
January 100 July 1000
February 225 August 1200
March 300 September 900
April 600 October 600
May 750 November 400
June 800 December 200
a) Hydrograph
Cont....
c) Mass curve
Month Discharge (m3 /s) Total volume( (106 m3 )
January 100 267.84 267.84
February 225 544.32 812.16
March 300 803.52 1615.68
April 600 1555.2 3170.88
May 750 2008.8 5179.68
June 800 2073.6 7253. 28
July 1000 2678.4 9931.68
August 1200 3214.08 13145.76
September 900 2332.8 15478.56
October 600 1607.04 17085.6
November 400 1036.8 18122.4
December 200 535.68 18658.08
By Yimam A. Chapter Four December 11, 2022 31 / 52
Chapter Four
Example
Cont....
D) Power developed
The mean discharge for the given data
100 + 225 + 300 + 600 + 750 + 800 + 1000 + 1200 + 900 + 600 + 400 + 200
=
12
7075
= = 589.583 m3 /month
12
Average power developed is given by
Cont....
A flow duration curve is used to explain discharge capacity, Qc as labeled in the figure
below.
Cont....
This Qc is the discharge at full gate opening of the runner under design head.
Even though to the left of that point on the duration curve the stream discharge is
greater, it is not possible to pass the higher discharge through the plant.
If the reservoir or pondage is full, water must be bypassed by a spillway.
To the right of the runner discharge capacity point, it should be noted that all the water
that can go through the turbine is the amount flowing in the stream at the particular
percent of time point.
If hydraulic head and the expected loss in the penstock are known, it is possible to
generate a power duration curve from the flow duration curve.
Cont....
The Pc value is the full gate discharge value of power and comes from multiplying Qc ,
discharge capacity value by the simultaneous value of head, estimated turbine efficiency
and appropriate conversion constants.
Energy production for a year or a time period is the product of the power ordinate
and time, thus the area under the power duration curve multiplied by appropriate
conversion constants give the energy produced.
It should be noted that to the left of the power capacity point the power tends to
decrease.
This is due to the fact that net head available is decreasing due to the rising of tail
water caused by the higher flows that are occurring during that time interval.
Cont....
Cont...
Average Load or Demand: It is the average of the loads occurring on the power
system or generating station in a given period. The period may be day or month or
year.
kWh supplied in a day
Daily average load =
24 hrs.
kWh supplied in a month
Monthly average load =
720 hrs.
kWh supplied in a year
Yearly average load =
8760 hrs.
Cont...
Load Factor: It is defined as the ratio of average load to the maximum demand during
a given period.
Average Load
Load factor =
Maximum Demand
Units generated in a given period
Load factor =
Maximum Demand × (number of hrs of operation)
Cont...
Capacity Factor or Plant Factor: It is the ratio of average load to the rated
capacity of the power plant.
Average Demand E
Capacity factor = =
Rated capacity of power plant C ×t
Plant capacity factor indicates the reserve capacity of the plant. A power station should
have some reserve capacity for increased load demand in the future. The installed
capacity of the plant is greater than the maximum demand.
Reserve Capacity = Plant Capacity − Maximum demand
Load Factor
Reserve factor =
Capacity Factor
By Yimam A. Chapter Four December 11, 2022 43 / 52
Chapter Four
Electrical Load Study
Cont....
Cont...
Plant use Factor: It is the ratio of units generated (kWh) to the product of plant
capacity and the number of hours for which the plant was in operation.
Station output in kWh
Plant use factor =
plant capacity × hrs of use
This factor is an indication of best possible and effective utilization of generating sta-
tion.
Utilization Factor: It is the ratio of maximum demand to plant capacity.
Maximum Demand
Utilization factor =
Plant capacity
Cont...
Load Curve: A curve showing the load demand variations of consumers with respect
to time is known as load curve.
At certain period of the demand reaches the highest value termed as peak load.
If the time is in hours the load curve is known as daily load curve.
If the time is in days, the load curve is known as monthly load curve and if the time is
in months, the load curve is known as yearly or annual load curve.
Load curves give full information about the incoming load and help to decide the
installed capacity of the power station and to decide the economical sizes of various
generating units.
These curves also help to estimate the generating cost and to decide the operating
schedule of the power station i.e., the sequence in which different units should be run.
Generation companies use this information to plan how much power they will need to
generate at any given time.
By Yimam A. Chapter Four December 11, 2022 46 / 52
Chapter Four
Electrical Load Study
Cont...
Load Duration Curve: When the load elements of a load curve are arranged in
the order of descending magnitudes, the curve thus obtained is called a load duration
curve.
The area under the load duration curve and the corresponding chronological load curve
is equal and represents total energy delivered by the generating station.
Load duration curve gives a clear analysis of generating power economically.
Proper selection of base load power plants and peak load power plants becomes easier.
Cont...
Cont...
Important Terms
Installed capacity: The total of station capacities available to supply the system load
is called the installed capacity.
Firm power (primary power): This is the amount of power that is the minimum pro-
duced by a hydro power plant during a certain period of time. Or It is the power
always available from the stream even at times of lowest flow.
Secondary power: The excess power available over the firm power during the off peak
hours. There is no guarantee for the secondary power.
Dump power: It shows the power in excess of the load requirements and it is made
available by surplus water.
Reading Assignment
Discuss the effect of variable load on power station.
How are load factor, capacity factor and diversity factor interrelated?
Discuss the significance of load factor and diversity factor on generating power stations.
Thank You!