You are on page 1of 1

A B C D E F G H I J K

GENERAL NOTES DOC # RPEB/ED/02 Rev # 00 Effective Date : 01-06-2020 DRG. DRAWING TITLE DATE REV

N-01 INDEX & NOTES 07.06.22 0

1.1) All dimensions are in millimeters (mm) unless noted otherwise. MS-01 Materials Specifications 17.06.22 0

CR-01 COLUMN REACTIONS 07.06.22 0


8
1.2) Sections & Details are NOT TO SCALE (NTS). 8
E-01 ANCHOR BOLT LAYOUT PLAN , DETAILS & SECTIONS 17.06.22 1
2.1) The structure has been designed as per codes and loads
given in proposal contract. E-02 RIGID FRAME ELEVATION: FRAME LINE 4&5 07.06.22 0

3.1) The Customer (or civil contractor) shall handle: E-03 RIGID FRAME ELEVATION: FRAME LINE 2 ,3 & 6 TO 10 07.06.22 0

E-04 ENDWALL FRAMING & SHEETING: FRAME LINE 1 07.06.22 0


(a) Demarcation of grids.
E-05 ENDWALL FRAMING & SHEETING: FRAME LINE 11 07.06.22 0
(b) Casting the anchor bolts as per critical distances given in Issued for
E-06 SIDEWALL FRAMING & SHEETING: FRAME LINE A 07.06.22 0
Construction (IFC) drawings.
E-07 SIDEWALL FRAMING & SHEETING: FRAME LINE C 07.06.22 0
Customer is requested to NOT follow the "Approval Drawings"
for casting Of anchor bolts. E-08 CRANE LAYOUT PLAN 07.06.22 0

E-09 ROOF FRAMING PLAN 07.06.22 0


7 E-10 0 7
DESIGN & FABRICATION ROOF SHEETING PLAN 07.06.22

TR-01 TRIMS 07.06.22 0

4.1) Fabrication complies with Following codes:


AISC (American Institute of Steel Construction)
manual & AWS (American Welding Society) code.
Fabrication tolerances are adopted from MBMA
(Metal Building Manufacturers Association, USA) code.
LOADING APPLIED AS PER MBMA-06.

6 CRITICAL REQUIREMENTS FOR ERECTION 6

5.1) Before starting erection, the Erector MUST check the followings at site:
(a) Critical distances and level of anchor bolts.
(b) Distances between grid lines.
(c) Diagonals between grid lines.
Erector shall report to Rhino PEB in case of any discrepancy with respect

5
to IFC drawings.
5.2) Safety First! The Erector is FULLY RESPONSIBLE for the followings:
(a) Employing safe erection practices used in PEB industry.
(b) Experienced staff.
APPROVAL DRAWINGS 5

Erection supervisor MUST have the experience of safely


erecting more than 10 PEB buildings.
(c) Proper Equipment.
Steel guy wires (free of joints/knots) Safety harnesses and belts
PROJECT INFORMATION
Safety dress etc. for workers First Aid box.
5.3) Steel guy wires MUST be anchored firmly at ground or floor.
Do NOT remove steel guy wires before complete installation of
4 purlins, girts and bracings. ABSENCE OF GUY WIRES OR POOR
ANCHORING OF GUY WIRES AT GROUND/FLOOR MAY RISK THE
STABILITY OF BUILDING.
JOB NO: RB-A225. QUOTE NO:RB-056-21 4

PEB STRUCTURE.
5.4) Erection MUST start from the 'braced bay.' Bracings MUST
be kept tight all the times. Proceeding towards next bay requires fixing
in-place ALL the purlins, girts and flange braces in previous bay. PROJECT NAME:
5.5) Make sure that right part is installed at right location.

CUSTOMER: CAPITAL BUILDERS.


3
JOBSITE LOCATION: ISLAMABAD-PAKISTAN. 3

DATE 07.06.22 DRAWN BY M.U DESIGNED BY N.M CHECKED BY N.M


2 2

1 17-06-22 ISSUED FOR APPROVAL M.U N.M N.M


FOR APPROVAL 0 07-06-22 ISSUED FOR APPROVAL M.U N.M N.M
REV. DATE DESCRIPTION DRN CHK DSN
TO SCHEDULE THIS PROJECT IN AN EFFICIENT MANNER,KINDLY RETURN THESE DRAWINGS WITH YOUR COMMENTS MARKED IN RED WITH 15 DAYS FROM THE ABOVE DATE.

ANY CHANGES MADE AFTER THE APPROVAL OF THESE DRAWINGS MAY DELAY THE FABRICATION SCHEDULE AND SUBSEQUENTLY THE DELIVERY OF BUILDING.

THESE DRAWINGS ARE NOT FOR CONSTRUCTION


'APPROVED AS IS' 'APPROVED AS NOTED'
JOB No. : RB-A225 QUOTE NO:RB-056-21
PROCEED WITH FABRICATION FABRICATION MAY PROCEED ON THE BASIS OF COMMENTS INDICATED.
PROJECT NAME : PEB STRUCTURE.
1 1
CUSTOMER : CAPITAL BUILDERS.
JOBSITE LOCATION : ISLAMABAD-PAKISTAN.
APPROVER : SIGATURE : DATE : DRAWING TITLE : DWG. No.
INDEX & NOTES
N-01
A B C D E F G H I J K

You might also like