This document provides steps for a planned shutdown of a fire system piping network. The key steps are to identify the scope and duration of the shutdown, inspect risks in affected areas, notify relevant parties like the fire department and building owner, tag equipment as out of service, drain water from the piping, and then close valves before work begins. Temporary measures like fire watches may be needed if the shutdown is long-term.
This document provides steps for a planned shutdown of a fire system piping network. The key steps are to identify the scope and duration of the shutdown, inspect risks in affected areas, notify relevant parties like the fire department and building owner, tag equipment as out of service, drain water from the piping, and then close valves before work begins. Temporary measures like fire watches may be needed if the shutdown is long-term.
This document provides steps for a planned shutdown of a fire system piping network. The key steps are to identify the scope and duration of the shutdown, inspect risks in affected areas, notify relevant parties like the fire department and building owner, tag equipment as out of service, drain water from the piping, and then close valves before work begins. Temporary measures like fire watches may be needed if the shutdown is long-term.
If there is a planned shutdown, advise the building owner or authorized
representative to take the following steps:
1. Identify the shutdown's extent and expected duration.
2. Inspect and evaluate the risks in the area(s) affected by the shutdown. 3. Notify the fire department, the insurance carrier, the risk manager, the alarm company, the building owner/manager, and any other person or agency that has jurisdiction. 4. Notify work supervisors in the shutdown area. 5. Place identifying tags (e.g., “Out of Service”) on the system or equipment. 6. Have all repair tools and personnel assembled and ready to perform the work in as short a time as possible. 7. Consider these steps if the shutdown is long term: o Evacuate the portion(s) of the building that is out of service. o Provide a competent fire watch service. o Establish a temporary fire protection water supply.
8. Close all sprinkler control valves.
9.Tag all closed valves. 10.Open the main drain valve and auxiliary drain valves and let the system drain 11. Once the water is done draining, close the main drain valve and auxiliary drain valve. 12.Check for any water trapped at low points in the piping that lack auxiliary drains. 13.Remove that piping so it can drain, then replace it. 14.Remove water from valve pits. 15.Open all the previously tagged closed sprinkler control valves.