Project CPM

A. Acquisition of
place
B. Acquire Software
and team
C. Vendor Selection
D. Procurement
E. Interior Design
F. Wiring and
networking
G. Exterior
Designing
H. Kitchen Setup
I. Software test
J. Staff training
K. Demo/ Test
L. Opening

Activity Predecessor Duration

A - 10
B - 16
C - 6
D C 51

E A 20

F E 16

G A 10

H E 23

I B 10

J B 11

K H, J 10

L K 1
NETWORK:

F
A E H
Start B K
J L
Finish

C I

CPM= A+E+H+K+L = 10+20+23+10+1 = 64 DAYS