Professional Documents
Culture Documents
WK6 Dra Scheduling PT2
WK6 Dra Scheduling PT2
SCHEDULING PART II
SEM I 2223 DRA2023 Project Management
outcomes
2
DRA2023|SEMI2223|ZZ
Outlines
3
DRA2023|SEMI2223|ZZ
1. Network Analysis : CPM
4
DRA2023|SEMI2223|ZZ
1. Network Analysis : CPM
5
DRA2023|SEMI2223|ZZ
1. Network Analysis : CPM
6
DRA2023|SEMI2223|ZZ
1. Network Analysis : CPM
7
DRA2023|SEMI2223|ZZ
2. Network : AOA
8
DRA2023|SEMI2223|ZZ
2. Network : AOA
9
DRA2023|SEMI2223|ZZ
2. Network : AOA
10
Activities, Duration
1 2
DRA2023|SEMI2223|ZZ
2. Network : AOA
11
DRA2023|SEMI2223|ZZ
2. Network : AOA
12
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
13
Activities Predecessor
A -
B A
C B
A B C
1 2 3 4
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
14
Activities Predecessor
A -
B -
C A,B
A C
1 2 4
B Dummy
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
15
Activities Predecessor
A -
B A
C A
A C
1 2 4
B
Dummy
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
16
Activities Predecessor
A -
B -
C A
D B
A 2 C
1 4
B D
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
17
Activities Predecessor
A -
B A
C A
D B,C
A C D
1 2 4 5
B
Dummy
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
18
Table 2
Activity Predecessors
A -
B -
C A,B
D C
E C
F D
G D,E
DRA2023|SEMI2223|ZZ
3. Developing Network - AOA
19
AOA
2 5
Dummy
F,0
A,0 D,0
E,0
6 G,0
DRA2023|SEMI2223|ZZ
19
4. Network : AON
20
DRA2023|SEMI2223|ZZ
4. Network : AON
21
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
22
Activities Predecessor
A -
B A
C B
ES A EF ES B EF ES C EF
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
23
Activities Predecessor
A -
B -
C A,B
ES A EF
LS Duration LF
Start ES C EF
Day
LS Duration LF
ES B EF
LS Duration LF
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
24
Activities Predecessor
A -
B A
C A
ES B EF
LS Duration LF
ES A EF
LS Duration LF End
Day
ES C EF
LS Duration LF
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
25
Activities Predecessor
A -
B -
C A
D B
ES A EF ES C EF
LS Duration LF LS Duration LF
Start End
Day Day
ES B EF ES D EF
LS Duration LF LS Duration LF
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
26
Activities Predecessor
A -
B A
C A
D B,C
ES B EF
LS Duration LF
ES A EF ES D EF
LS Duration LF LS Duration LF
ES C EF
LS Duration LF
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
27
Table 1
Activity Predecessors
A -
B -
C A,B
D C
E C
F D
G D,E
DRA2023|SEMI2223|ZZ
5. Developing Network - AON
28
AON
Early Start E Early Finish
S
Early Start G Early Finish
t Early Start C Early Finish
r
t E
Early Start B Early Finish
n
Late Start Duration Late Finish Early Start D Early Finish d
Late Start Duration Late Finish
DRA2023|SEMI2223|ZZ
6. Network Analysis
31
Basic Definitions :
Duration (D) – The estimate time required to perform
activities. The time should include all resources that are
assigned to the activities.
Early Start (ES) – The earliest time an activity can be
started
Early Finish (EF) – The earliest time an activity can be
finished and is equal to the early start plus duration
EF = ES + D
Late Finish (LF) – The latest time an activity can be
finished
DRA2023|SEMI2223|ZZ
6. Network Analysis
32
Basic Definitions :
Late Start (LS) – The latest time an activity can be
started without delaying the completion date of the
project
LS = LF – D
TotalFloat (TF) – The amount of time an activity may be
delayed without delaying the completion date of the
project
TF = LF – EF = LS – ES
DRA2023|SEMI2223|ZZ
6. Network Analysis
33
Basic Definitions :
Free Float (FF) – The amount of time an activity may be
delayed without delaying the early start time of the
immediately following activity FFi = ESj – EFi
Critical Path – A series of interconnected activities through
the network diagram, with each activity having zero, free
and total float time. The critical path determines the
maximum time to complete the project
Dummy Activity – An activity (represented by a dotted line
on the arrow network diagram) that indicates that any
activity following the dummy cannot be started until the
activity or activities preceding the dummy are completed.
The dummy does not require any time
DRA2023|SEMI2223|ZZ
6. Network Analysis
34
DRA2023|SEMI2223|ZZ
6. Network Analysis
35
DRA2023|SEMI2223|ZZ
6. Network Analysis
36
LS = LF – D
TF = LF – EF = LS – ES
DRA2023|SEMI2223|ZZ
6. Network Analysis
37
A, 1
1 2
DRA2023|SEMI2223|ZZ
6. Network Analysis
38
ES i Xtvt i EF i ES j Xtvt j EF j
DRA2023|SEMI2223|ZZ
7. Float / Slack
39
DRA2023|SEMI2223|ZZ
7. Float / Slack (cont.)
41
Float
0 10
Activity Float
6 Days
DRA2023|SEMI2223|ZZ
7. Float / Slack (cont.)
42
DRA2023|SEMI2223|ZZ
42
8. Analyzing Network Analysis
43
Determine Free Float (FF) and Total Float (FT) for each
AOA.
Determine the critical path for this project.
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
44
Table 1
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
45
AOA Notation :
3
B,4 Dummy
4 C 3 A
D 6 A
E 2 C
F 4 D
AOA calculation
DRA2023|SEMI2223|ZZ
G 1 B,E,F
8. Analyzing Network Analysis
46
5 11
AOA Notation :
3
7, 6, 1 B,4 Dummy 5, 6, 11
0 0 1 1 4 9 11 11 12 12
A,1 C,3 E,2 G,1
1 2 5 6 7
4 C 3 A
D 6 A
7 7
E 2 C
F 4 D
AOA calculation
DRA2023|SEMI2223|ZZ
G 1 B,E,F
8. Analyzing Network Analysis
47
Activity Duration ES EF LS LF TF FF
A 1 0 1 0 1 0 0
B 4 1 5 7 11 6 6
C 3 1 4 6 9 5 0
D 6 1 7 1 7 0 0
E 2 4 6 9 11 5 5
F 4 7 11 7 11 0 0
G 1 11 12 11 12 0 0
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
48
Table 1
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
49
4 4 8 8 13 13 18 18
1, 0 C, 4 D, 5 F, 4
3 4 5 7
0 0 A,4
1 E, 3 G, 5
B,3
2
6
3 4
13 13
13,11
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
50
Activity Duration ES EF LS LF TF FF
A 4 0 4 0 4 0 0
B 3 0 3 1 4 1 1
C 4 4 8 4 8 0 0
D 5 8 13 8 13 0 0
E 3 8 11 10 13 2 2
F 4 13 17 14 18 1 1
G 5 13 18 13 18 0 0
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
51
A 5 -
B 5 A
C 4 A
D 7 A,B
E 3 B,C
F 3 D,E
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
52
Determine Free Float (FF) and Total Float (FT) for each
AON.
Determine the critical path for this project.
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
53
Table 1
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
54
Activity Duration Predecessor
AON Notation : A 1 -
B 4 A
C 3 A
D 6 A
E 2 C
Early Start B Early Finish F 4 D
Early Start A Early Finish Early Start C Early Finish Early Start E Early Finish Early Start G Early Finish
Late Start 1 Late Finish Late Start 3 Late Finish Late Start 2 Late Finish Late Start 1 Late Finish
AON calculation
Late Start 6 Late Finish Late Start 4 Late Finish
CPM MS Project
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
55
Activity Duration Predecessor
AON Notation : A 1 -
B 4 A
C 3 A
D 6 A
E 2 C
1
Early Start B 5
Early Finish F 4 D
11 G 1 B,E,F
7
Late Start 4 Late Finish
5, 6, 11
0
Early Start A 1
Early Finish 1
Early Start C 4
Early Finish 4
Early Start E 6
Early Finish 11
Early Start G
12
Early Finish
0
Late Start 1
1
Late Finish 6
Late Start 3 9
Late Finish 9
Late Start 2 11
Late Finish 11
Late Start 1 12
Late Finish
7, 6, 1
1
Early Start D 7
Early Finish
7
Early Start F 11
Early Finish
AON calculation
1
Late Start 6 7
Late Finish 7
Late Start 4
11
Late Finish
CPM MS Project
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
56
Activity Duration ES EF LS LF TF FF
A 1 0 1 0 1 0 0
B 4 1 5 7 11 6 6
C 3 1 4 6 9 5 0
D 6 1 7 1 7 0 0
E 2 4 6 9 11 5 5
F 4 7 11 7 11 0 0
G 1 11 12 11 12 0 0
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
57
Table 1
DRA2023|SEMI2223|ZZ
8. Analyzing Network Analysis
58
A 5 -
B 5 A
C 4 A
D 7 A,B
E 3 B,C
F 3 D,E
DRA2023|SEMI2223|ZZ
Planning & scheduling where goes
wrong?
59
DRA2023|SEMI2223|ZZ