Normative Availability
AC: 98% HVDC : 95%
If availability is less than the above norms, reduced recovery of transmission charges
Availability for the purpose of Incentive
AC: 98.5% HVDC : 97.50% Ceiling : 99.75%
If availability is more than the above norms-
Monthly Availability
Annual Fixed Cost X = Tr. Charges
Availability for incentive
Annual Tariff is not dependent upon the quantum of power flow 23
24
Computation of Availability
For AC system
» Transmission availability upto the end of the nth month of the year (TAFMn)=
(o X AVo)+ (p X AVp) + (q X AVq) + (r X AVr) + (u X AVu)
*100
(o + p + q + r + u)
Non switchable line reactors, FSCs and TCSCs are not accounted in availability calculation
26
Computation of Availability
For DC system
» Transmission availability upto the end of the nth month of the year (TAFMn)=
𝑠 𝑡
𝐶𝑥𝑏𝑝 𝑎𝑐𝑡 ∗𝐴𝑉𝑥𝑏𝑝+ 𝑦=1 𝐶𝑦𝑏𝑡𝑏 𝑎𝑐𝑡 ∗𝐴𝑉𝑦𝑏𝑡𝑏
𝑥=1
𝑠 𝑡 *100
𝑥=1 𝐶𝑥𝑏𝑝+ 𝑦=1 𝐶𝑦𝑏𝑡𝑏
Availability Calculation
Penalty on trippings
• After two trippings in a year, additional 12 hours
outage shall be considered in addition to the actual
outage.
• In case of outage of transmission element affecting
evacuation of power from the generating station,
outage hour shall be multiplied by a factor of 2.
Appeal on Disagreement
» In case of any disagreement with the transmission licensee
regarding reason for outage, same may be referred to Chairperson,
CEA within 30 days. The above need to be resolved within two
months.
» Provided further that if there is a difficulty or delay beyond sixty
days, from the incidence in finalizing the recommendation, the
Member Secretary of concerned RPC shall allow the outage hours
on provisional basis till the final view.
34
THINK
» What is the monthly availability for your region/ substation/
transmission line/ profit centre in 2020-21 ?