You are on page 1of 12

SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

WORK BELOW GROUND FLOOR LEVEL

Notes:-
1. Hacking of pilehead to final cut-off level by others
2. Bulk earthwork by others

Pilecaps, ground and slab, lift pit base & wall, etc.

Pit / Trench Excavation

Excavate, get out, part return, fill in and ram , remove


surplus excavated materials, deposits, spread and level
where directed within the site:-

A Not exceeding 1.50m deep M3 4,180 -

B Ditto, exceeding 1.50m but not exceeding 3.00m deep M3 600 -

C Ditto, exceeding 3.00m but not exceeding 4.50m deep M3 350 -

D Ditto, exceeding 4.50m but not exceeding 6.00m deep M3 20 -


----------------------------------------

E Extra Over for excavation of rock / boulders M3 300 -

Sub-base & Sundry

Supply and lay:-

F 150mm thick well compacted hardcore blinding, generally M2 2,330 -

G 200mm thick well compacted hardcore blinding, generally M2 500 -


----------------------------------------

H 50mm thick lean concrete Grade 15, generally M2 4,470 -

To Summary Sum -

Page 5B / 1
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

WORK BELOW GROUND FLOOR LEVEL (Cont'd)

Pilecaps, ground and slab, lift pit base & wall, etc. (Cont'd)

Ready Mixed Concrete, generally:-

A Vibrated reinforced concrete, Grade 35 M3 987 -

B Vibrated reinforced concrete, Grade 40 M3 4,280 -

Hot rolled steel deformed reinforcement (High Yield) bars,


generally:-

C Y10mm ~ Y12mm diameter KG 94,300 -

D Y16mm ~ Y32mm diameter KG 449,500 -

Formwork as described in preambles, generally to:-

E Sides and/or soffit of concrete, not exceeding 3.65m H M2 6,790 -

F Edge of concrete, exceeding 150mm but not exceeding M 304 -


225mm high

To Summary Sum -

Page 5B / 2
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

FRAME

Column and Suspended Beam

Ready Mixed Concrete, generally:-

A Vibrated reinforced concrete, Grade 30 M3 15,300 -

B Vibrated reinforced concrete, Grade 40 M3 8,700 -

C Vibrated reinforced concrete, Grade 50 M3

D Vibrated reinforced concrete, Grade 15 M3 70 -


----------------------------------------

Hot rolled steel deformed reinforcement (High Yield) bars,


generally:-

E Y10mm ~ Y12mm diameter KG 878,500 -

F Y16mm ~ Y32mm diameter KG 7,681,100 -

Formwork as described in preambles, generally to:-

G Sides and/or soffit of concrete, not exceeding 3.65m H M2 129,300 -

H Ditto, exceeding 3.65m but not exceeding 4.25m H M2 406 -

I Ditto, exceeding 4.25m but not exceeding 4.85m H M2 406 -

J Ditto, exceeding 4.85m but not exceeding 5.45m H M2 238 -

K Ditto, exceeding 5.45m but not exceeding 6.05 H M2 2,600 -

L Ditto, exceeding 6.05m but not exceeding 6.65m H M2 2,250 -

M Ditto, exceeding 6.65m but not exceeding 7.25 H M2 70 -

N Ditto, exceeding 7.25m but not exceeding 7.85m H M2 65 -

O Ditto, exceeding 7.85m but not exceeding 8.45m H M2 65 -

P Ditto, exceeding 8.45m but not exceeding 9.05m H M2 4,030 -

To Summary Sum -

Page 5B / 3
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

FRAME (Cont'd)

Starter Bars, generally

Planting of starter bar using Hilti Hy 150 epoxy adhesive, to:-

A Y10 / Ø14mm x 100mm depth NO 500 -

B Y12 / Ø16mm x 120mm depth NO 300 -

C Y16 / Ø20mm x 160mm depth NO 200 -

D Y20 / Ø25mm x 200mm depth NO 150 -

E Y25 / Ø32mm x 250mm depth NO 150 -

F Y32 / Ø40mm x 320mm depth NO 150 -

To Summary Sum -

Page 5B / 4
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

UPPER FLOOR SLAB

Suspended Slab, plinths, etc.

Ready Mixed Concrete, generally:-

A Vibrated reinforced concrete, Grade 30 M3 20,200 -

Hot rolled steel deformed reinforcement (High Yield) bars,


generally:-

B Y10mm ~ Y12mm diameter KG 1,917,700 -

C Y16mm ~ Y32mm diameter KG 166,800 -

Formwork as described in preambles, generally to:-

D Sides and/or soffit of concrete, not exceeding 3.65m H M2 100,500 -

E Ditto, exceeding 5.45m but not exceeding 6.05 H M2 2,960 -

F Ditto, exceeding 6.05m but not exceeding 6.65m H M2 2,270 -

G Edge of concrete not exceeding 75mm high M 13,700 -

H Edge of concrete, exceeding 150mm but not exceeding M 36,900 -


225mm high

To Summary Sum -

Page 5B / 5
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

UPPER FLOOR SLAB (Cont'd)

Forming Temporary Boxing

A Overall size 1,500 x 1,200mm opening, in 150mm thick slab NO 89 -

B Overall size 1,200 x 1,200mm opening, in 150mm thick slab NO 45 -

C Overall size 900 x 900mm opening, in 150mm thick slab NO 214 -

D Overall size 600 x 600mm opening, in 150mm thick slab NO 401 -

E Overall size 600 x 300mm opening, in 150mm thick slab NO 45 -

F Overall size 3,000 x 600mm opening, in 150mm thick slab NO 72 -

G Overall size 600 x 900mm opening, in 150mm thick slab NO 1,890 -

H Overall size 300 x 300mm opening, in 150mm thick slab NO 1,890 -

To Summary Sum -

Page 5B / 6
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

ROOF CONSTRUCTION

Roof Beam, Roof Slab, RC Gutter, etc.

Ready Mixed Concrete, generally:-

A Vibrated reinforced concrete, Grade 30 M3 1,490 -

Hot rolled steel deformed reinforcement (High Yield) bars,


generally:-

B Y10mm ~ Y12mm diameter KG 94,600 -

C Y16mm ~ Y32mm diameter KG 109,700 -

Formwork as described in preambles, generally to:-

D Sides and/or soffit of concrete, not exceeding 3.65m H M2 9,200 -

E Edge of concrete, exceeding 150mm but not exceeding M 570 -


225mm high

Temporary Roof & Lift Hoisting Steel Frame

Supply, fabricate, fix and weld structural steelworks, to


engineer's details, including all associated bolts & nuts,
applying coating to bolts heads, projecting bolts shanksm
nuts and all areas of painting work during erection, c/w
one undercoat and two finishing costs of oil paint to all
steel surfaces; to:-

F 254 x 146 x 31mm x 44.64kg/m universal Beam KG 21,000 -


(roof frame)

G 254 x 146 x 31mm x 44.64kg/m universal Beam KG 8,700 -


(Steel frame for hoisting lift car)

H Bondek or equivalent metal deck c/w fixing accessories M2 921 -

I Chipping concrete, Grade 30 M3 92 -

J BRC mesh, A4 M2 921 -

K Formwork to edge of concrete, exceeding 150mm M 272 -


but not exceeding 225mm high

To Summary Sum -

Page 5B / 7
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

STAIRCASE CONSTRUCTION

Staircase, Landing Slab & Beam, Column on Beams, etc.

Ready Mixed Concrete, generally:-

A Vibrated reinforced concrete, Grade 30 M3 723 -

Hot rolled steel deformed reinforcement (High Yield) bars,


generally:-

B Y10mm ~ Y12mm diameter KG 63,500 -

C Y16mm ~ Y32mm diameter KG 7,900 -

Formwork as described in preambles, generally to:-

D Sides and/or soffit of concrete, not exceeding 3.65m H M2 1,610 -

E Sloping soffits of staircase M2 2,060 -

F Raking open edge of staircase, 300mm wide (average), M 2,340 -


cut to profile of treads and risers

G Receding riser, exceeding 150 high but not exceeding M 7,700 -


225m high

To Summary Sum -

Page 5B / 8
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

STRUCTURAL WALL

Retaining Wall, Lift Shaft Wall, Water Tank Wall, etc.

Ready Mixed Concrete, generally:-

A Vibrated reinforced concrete, Grade 30 M3 9,700 -

B Vibrated reinforced concrete, Grade 35 M3 80 -

C Vibrated reinforced concrete, Grade 50 M3


----------------------------------------
D Waterproof concrete, Grade 40, for Water Tank M3 416 -

Hot rolled steel deformed reinforcement (High Yield) bars,


generally:-

E Y10mm ~ Y12mm diameter KG 766,800 -

F Y16mm ~ Y32mm diameter KG 962,200 -

Formwork as described in preambles, generally to:-

G Sides and/or soffit of concrete, not exceeding 3.65m H M2 66,000 -

H Ditto, exceeding 3.65m but not exceeding 4.25m H M2 500 -

To Summary Sum -

Page 5B / 9
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

STRUCTURAL WALL (Cont'd)

Forming Temporary Boxing

A Overall size 1.10 x 2.10m lift door opening, in 300mm thk NO 214 -
to lift core wall

B Overall size 1.45 x 2.10m lift door opening, in 12" thk to NO 415 -
lift core wall

C Overall size 350 x 200mm fireman switch opening, ditto NO 629 -

D Overall size 150 x 300mm opening, generally NO 629 -

E Overall size 75 x 75mm opening, generally NO 50 -


----------------------------------------

F Supply and install "Estopper CJ 250" or equivalent M 500 -


waterstop incl. "Estocell" 25mm thick cork, vertically
and horizontally

G One layer of bituminous waterproofing membrane to side of M2 800 -


lift core wall in contact with soil
----------------------------------------

H Provide the Provisional Sum of RM650,000 for the PS 1 650,000.00


"structural works to link bridge" to be expended as directed
by the Superintending Officer or deducted wholly or partly
if not expended.

To Summary Sum 650,000.00

Page 5B / 10
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

SUNDRY WORKS

Pipe Sleeves

Supply and fix PVC pipe sleeves including trimming


of bars for:

A 50mm diameter NO 1,400 -

B 100mm diameter NO 2,700 -

C 150mm diameter NO 4,100 -

D 200mm diameter NO 1,400 -

E 250mm diameter NO 400 -

To Summary Sum -

Page 5B / 11
SECTION 5B - STRUCTURAL WORKS

TENDER SUM (Phase 1 & Phase 1A)


ITEM DESCRIPTION UNIT
QTY RATE AMOUNT (RM)

ALL PROVISIONAL QUANTITIES

SUMMARY

Page 5B / 1 Sum -

Page 5B / 2 Sum -

Page 5B / 3 Sum -

Page 5B / 4 Sum -

Page 5B / 5 Sum -

Page 5B / 6 Sum -

Page 5B / 7 Sum -

Page 5B / 8 Sum -

Page 5B / 9 Sum -

Page 5B / 10 Sum 650,000.00

Page 5B / 11 Sum -

TOTAL CARRIED TO GRAND SUMMARY (Page GS1/1) Sum 650,000.00

Page 5B / 12

You might also like