ULTRASONIC TESTING REPORT

Report No-RPY/JWIL/12 Date:-30/11/22

CLIENT : JWIL/MYI
MATERIAL : MS
JOB : Pipe Joint
PROJECT NAME : Chitakhudari Complex Pressurized Irrigation Project

EQUIPMENT : MODSONIC ARJUN 30


PROBE : Angle Probe
SIZE OF PROBE : 8×9, 70 Degree
FREQUENCY OF PROBE : 4 MHZ
TECHNIQUE : Pulse Echo Technique “A”
ACCEPTANCE STANDARD : ASME SEC-V SA 273, SEC VIII DIV-1
COUPLANT : OIL
CALIBRATION RANGE : 0-100mm
GAIN : 45db + 6db
SCANNING : All Over Accessible Area

RESULT
OBSERVATION : Free From Objectionable Flaw
REMARKS : Job Is Acceptable As Per Standard IS 4260
TESTED BY : RAVI SHEKHAR SINGH
(RT,UT,MPT,PT, LEVEL-II)

UT Operator Reviewed By:-


Sr. No. Description Size Date Remarks
1. Dam to pump house J-17 2200×12mm OK- 20/11/22 Accepted
2. Dam to pump house J-16 2200×12mm OK- 20/11/22 Accepted
3. Dam to pump house J-15 2200×12mm OK- 20/11/22 Accepted
4. Dam to pump house J-14 2200×12mm OK- 20/11/22 Accepted
5. Dam to pump house J-13 2200×12mm OK- 20/11/22 Accepted
6. Dam to pump house J-12 2200×12mm OK- 20/11/22 Accepted
7. Dam to pump house J-11 2200×12mm OK- 20/11/22 Accepted
8. Dam to pump house J-10 2200×12mm OK- 25/11/22 Accepted
9. Dam to pump house J-09 2200×12mm OK- 25/11/22 Accepted
10. Dam to pump house J-08 2200×12mm OK- 25/11/22 Accepted
11. Dam to pump house J-07 2200×12mm OK- 25/11/22 Accepted
12. Dam to pump house J-06 2200×12mm OK- 25/11/22 Accepted
13. Dam to pump house J-05 2200×12mm OK- 25/11/22 Accepted
14. Dam to pump house J-04 2200×12mm OK- 25/11/22 Accepted

UT Operator Reviewed By:-