Professional Documents
Culture Documents
Lecturer in Charge:
Index No : 170653T
Module : CE 4482
List of Figures
1.1 Background
level of the proposed building. The dimensions of the proposed sump are 7.0m x 15.0m
with a height of 3.0m. The foundation of the proposed sump will be constructed very
close to already existing wall and column foundations of the building. A photo showing
the area of the proposed sump and existing foundations are presented in Figure 1.0
Under this study, it was proposed to carry out a finite element analysis to investigate the
behavior of the sump foundation and surrounding foundations by using the PLAXIS
Software.
1.2 Subsurface Characteristics
Two boreholes were drilled to identify the subsurface condition beneath the proposed
foundation, and based on those borehole details, the subsurface at the location of
proposed sump and nearby area was conservatively idealized into six layers as presented
in Table 1.0.
Note: Water table was observed at a depth of 0.6m in BH 01 and 0.8m in BH 02. However,
the depth of water table is conservatively assumed as the existing basement level for the
current analysis.
Maximum service load expected due to the construction of the proposed sump
is taken as 35 kN/ m2
The existing wall and column foundations were founded at a depth of about
1.0 m from the existing basement level. Width and the thickness of the wall and
horizontal gap between the wall foundation and sump foundation is 0.5 m.
Similarly the horizontal gap between the column foundation and the sump
foundation is 1.0 m
m2
The foundation for the sump will be placed on the existing basement level.
Elastic modulus of concrete is 26000 MPa and the Poisson’s ratio is 0.15
Cross section of proposed development, that is modelled using PLAXIS software are
presented in Figure 3.
2.0 MAJOR GEOTECHNICAL CONCERNS OF THE CONSTRUCTION
Geometry dimensions
- Left 0 m
- Right 30 m
- Top 0 m
- Bottom -20 m
7m
3.5m
2.5 m
1.5m
3.5m
5.5m
3.5m
30m
1. As the phase one the existing conditions was simulated by activating the column
2. As the second phase, the foundation of sump was activated along with its
corresponding loading
5.0 SETTLEMENT OF THE EXISTING WALL AND COLUMN FOUNDATIONS BEFORE THE
CONSTRUCTION OF THE PROPOSED SUMP
Figure 4: Vertical Displacement profile beneath the column and wall foundations before
the construction of sump
Figure 8: Settlement beneath the wall foundation, after the construction of Sump
Figure 9: Settlement beneath the Column Foundation, after the construction of Sump
According to the analysis results it is obvious that, the construction of sump can affect
the surrounding structures. Cracks can be occur due to the additional settlement of
column and wall foundation. So, the behavior and settlement of column and wall
foundations should be monitored during the construction and operation of the sump,