SUMMARY OF BILL OF QUANTITIES (ITEMS OF WORKS)

ITEM NO. DESCRIPTION Qty. Unit Unit Total


Cost Cost
I GENERAL REQUIREMENTS
I-A Preparation of Plans and Professional Fees lot
I-B Permits and Clearances lot
I-C Surety Bond lot
I-D Billboard l.s.
I-E Occupational Safety and Health Program Months
I-F Mobilization/Demobilization l.s.

II SITE WORKS
II - A Clearing & Grubbing sq.m.
II - B Removal of Structures and Obstruction (demolotion) sq.m.
II - C Site Enclosure sq.m.
II - D Staking and lay-out sq.m.
II - E Bunk House / Stock Room sq.m.

III EARTH WORKS


III - A Structure Excavation (Common Soil) cu.m.

III - A Embankment (from Structure Excavation) cu.m.

III - B Gravel Bedding cu.m.

III - C Soil Poisoning li.

IV PLAIN AND REINFORCED CONCRETE WORKS


IV - A Structural Concrete, Class A (28 Days) cu.m.
IV - B Structural Concrete ( Footing and Slab on Fill), Class A (28 days) cu.m.
IV - C Reinforced Steel (Deformed) Grade 40 kgs.
IV - D Reinforced Steel (Deformed) Grade 60 (for two to five storey buildings) kgs.

IV - E Structural Concrete (Columns - Class A, 28 days) cu.m.


IV - F Structural Concrete (Beams/Girder/Roof Beams - Class A, 28 days) cu.m.

IV - G Structural Concrete (Suspended Slab - Class A, 28 days) cu.m.

IV - H Forms and Scaffolding Sq.m.


IV - I Metal Deck Panel l.m.

V MASONRY WORKS
V-A CHB Wall - Non-Load Bearing (Including Reinforcing Steel) 100 mm sq.m.
V-B CHB Wall - Load Bearing (Including Reinforcing Steel) 150mm sq.m.

VI FINISHING WORKS
VI - A Cement Floor Finish (Plain) sq.m.

VI - B Cement Plaster Finish sq.m.


VII WATER PROOFING
VII - A Liquid Waterproofing sq.m.

VIII CARPENTRY AND JOINERY WORKS

VIII - A Ceiling (4.5mm Fiber Cement Board on Metal Framing Ceiling) m

VIII - B 4.5mm Fiber Cement Board on Metal Frame Double Wall Partition sq.m.

IX TILE WORKS
IX - A Glazed Tiles and Trims sq.m.
IX - B Unglazed Tiles and Trims sq.m.

X DOORS AND WINDOWS


X-A Panel Type Door (Solid Core) Painted, with Lever type Door Knob 3 1.89 sq.m.
X-B Sliding Glass Door in Aluminum Framing 2 4.2 sq.m.
X-C Panel Type Door (Solid Core) Painted, with Lever type Door Knob 4 1.68 sq.m.
X-D PVC Type Door Louver with Lever Type Door Knob 4 1.47 sq.m.
X-E Fixed Glass Window in Aluminum Frame w/ Awning Type Window 5.04 sq.m.
1 4.92 sq.m.
X-F Fixed Glass Window in Aluminum Frame w/ Awning Type Window 2.1 sq.m. 2.05
1 sq.m
X-G Fixed Glass Window in Aluminum Frame w/ Awning Type Window
8.28 sq.m.
1
X-H Fixed Glass Window in Aluminum Frame w/ Awning Type Window
8.4 sq.m.
1
X-I Fixed Glass Window in Aluminum Frame w/ Awning Type Window 5.04 sq.m.
1
X-J Fixed Glass Window in Aluminum Frame 2.94 sq.m.
1
X-K Sliding Glass Window in Aluminum Frame 1.8 sq.m.
5
X-L Awning Type Window with 0.60m x 0.80m Transom 0.80 sq.m.
2
X-M Sliding Glass Window in Aluminum Frame 1.08 sq.m.
2
X-N Awning Type Window in Aluminum Frame 0.27 sq.m.
3
XI RAILINGS
XI-A Metal Railings m

XII PAINTING and VARNISHING WORKS


XII-A Painting Works(Masonry/Concrete) sq.m.

XII-B Painting Works (Wood) sq.m.


XII-C Painting Works (Steel) sq.m.

XIII ELECTRICAL WORKS


XIII-A Panel Board with Main and Brach Breaker, Surface Typr set
XIII-B Lighting Fixtures l.s.
XIII-C Wires and Wiring Devices l.s.
XIII-D Conduits ,Boxes and Fittings (Conduit Works/ Conduit Rough-in) l.s.

XIV PLUMBING WORKS


XIV-A Plumbing Fixtures lot
XIV-B Sewer Line lot
XIV-C Cold Water Lines lot
XIV-D Storm Drainage and Sewerage Systems lot

TOTAL CONTRACT COST:


Prepared by: Roarch Angelo Mondido Approved by:
Owner

Checked
by: