Task 3
Manage project scope
BSBPMG530
Student Declaration
To be filled out and submitted with assessment responses
☑ I declare that this task and any attached document related to the task is all my own work and I have
not cheated or plagiarised the work or colluded with any other student(s)
☑ I understand that if I am found to have plagiarised, cheated or colluded, action will be taken against
me according to the process explained to me
☑ I have correctly referenced all resources and reference texts throughout these assessment tasks.
☑ I have read and understood the assessment requirements for this unit
☑ I understand the rights to re-assessment
☑ I understand the right to appeal the decisions made in the assessment
Completed successfully
DNS
Y
N
Did the student satisfactorily:
The student has satisfactorily completed and ☐ ☐ ☐
submitted the following:
Completed successfully
DNS
Y
N
Did the student satisfactorily:
• Addressing the scenarios (monitoring
and control; how the issues were
addressed) – Case Study in Task 3.2A
• Change request form – Case Study in
Task 3.2B
• Email to project sponsor and HR
Manager – Case Study in Task 3.2C
Demonstrated ability to: ☐ ☐ ☐
• Identify and document scope
management issues and recommend
improvements for future projects
See comments.
Assessor Name:
Assessor Signature:
Date:
What is this assessment Task 3.1 builds on Task 2.1 and 2.2.
task about? Task 3.2 builds on Task 2.3
• NA
Assume that the following has happened when executing the project:
Scenarios
A 25% timeline
The project sponsor communicated the decision to disregard the requirement of onsite car
space for staff to one of the project team members who did not document the decision.
B 50% timeline
The project budget is cut by 5%; the project manager has reviewed the expense items and
decided to change the furniture supplier for a more affordable one compromising on the
quality of the furniture for the new campus.
C 50% timeline
The flu season forces 60% of the project team to go on sick leave for three weeks.
D 75% timeline
One of the permits the project team applied for on behalf of MMI is delayed pending
additional information. This may cause a two weeks schedule delay.
Change/s Requested Change the furniture supplier for a more affordable one.
Reason for change/s To reduce the project budget or to decrese the cost.
Impact on the project The budget the of the roject is cut down by 5%
Record
Complete the filing record below to save the project documentation in the project management record
system.
C. Write an email to the HR Manager and the project sponsor to address SCENARIO C.
• Inform the two stakeholders about the issue that the project is experiencing.
• Inform them about your strategy to address the issue and manage the project scope.
• Ask for support and/or resources.
The text of the email should be in grammatically correct English, written in an appropriate (polite,
business-like) style.
(80-120 words)
Write the email using the template below (Template 2).
Template 2 -Email
Email to Project Sponsor and HR Manager
To: TaylorVarin@mmi.edu.au, HRManager
Cc: Rudrateja@gmail.com,
Hi Taylor,
I hope you are doing good sir. I am writing this email to bring a small change request to your notice.
After a long analysis and review, I came to a conclusion to change the furniture supplier to a less
expensive and affordable supplier to cut down on the budget. This budget cut dowm will be good for
the project as with the new supplier we are able to save upto 5% of the budget.
The existing furniture is being used by many of the offices and schools because of te price and
reasonable quality. Therefore, I request you to go through the company details and customer
feedbacks to come to a conclusion,
Thank you
Project Manager
Anupiya Amaraweera
D. Lessons learned
Consider the work performed when developing the scope management plan and its implementation
when addressing Task 3.1 A, B and C.
Consider the following feedback received from the project team.
• The change control process was implemented effectively; however, it could be improved by using
an electronic form
• Some scope changes were not timely communicated, increasing the possibility of scope creep
• The scope management plan was updated every six weeks
Complete a lessons learned report (Template 3) to identify and document scope management issues and
recommend improvements for future projects.
Template 3 -Lessons Learned
Lessons Learned Report
Overview
A brief summary of how scope was managed, to include issues and how they were addressed.
1. The tasks were assigned well among the project 1. Overall communicatin
team improvement
2. Team work was well presented 2. Staff management
3. Budget control 3. Document review process
4. Time management 4. Quality control management
Te am work plays a great role in keeping the tasks and project upto date. Inaddition, reviewing the
document is of paramount importance as the plan to remove parking for the staff not mentioned in
the documentation has resulted in the overall change in the project. Therefore, reviewing projevt
regularly keeps the project on track and up to the requirements. Quality control plays a crucial role
to conduct the project in the future and in the present smoothly.
Record
Complete the filing record below so that the project documentation can be saved in the project
management record system.
Assume that the following has happened when executing the project:
Scenarios
A 25% timeline
The marketing team is extending the invitation to attend the event to education agents
overseas.
B 50% timeline
Reason for change/s Microsoft supprts extra features for team meetings or team cnferences
Impact on the project Change Dcumentation, train the staff to the technology
Record
Complete the filing record below to save the project documentation in the project management record
system.
C. Write an email to the Marketing Manager and the project sponsor to address SCENARIO C.
• Inform the two stakeholders about the cut in budget and its impact on the project.
• Inform them about your strategy to address the budget change and manage the project scope.
• Ask for support and/or resources if needed.
The text of the email should be in grammatically correct English, written in an appropriate (polite,
business-like) style.
(80-120 words)
Hi Taylor,
I am writing this email to bring to yur notice about the budget change. After going through the
budget plan and discussions with the team, the steering cmmitee has decided to reduce the budget by
10%. I am very satisfied with the budget plan and I think this will in turn result a great benefit to the
organization. Kindly, go through the attached file to give the plan a go and request your suggestion to
improve the project further.
Cheers
Anupiya Amaraweera
Project Manager.
D. Lessons learned
Consider the work performed when developing the scope management plan and its implementation
when addressing Task 3.2 A, B and C.
Consider the following feedback received from the project team.
• The Marketing Officer and the Marketing Manager’s lack of project management knowledge
impacted their performance
• The Marketing Officer asked another team to send some of the invitations to the event. The
invitations were never sent.
Complete a lessons learned report (Template 3) to identify and document scope management issues and
recommend improvements for future projects.
Template 3 -Lessons Learned
Overview
A brief summary of how scope was managed, to include issues and how they were addressed.
Monitoring wrk is very important t finish the task on time and accrding to the requiremet. Here in
this case, the Marketing officer asked the team to send invitations but he did not follow with the
team because of which no invitatins were sent to some people. Therefre, it is always necessary to
follow up and mnitor the team member of their work.
Record
Complete the filing record below to save the project documentation in the project management
record system.