Kahramaa Contract # GTC/989/2020 -Routine Maintenance and Breakdown Repairs of EHV& HV overhead lines

RELOCATION OF GUARD WIRE INSTALLATION for 132 kV AL SULAIMI – DUKHAN JUMAILIYAH JUNCTION CCT-1&2
(SPAN 6-7)

LOA NO:202384476, WO NO - 804130 & 804131

REMOVAL OF EXISTING GUARD WIRE POLE

BEFORE REMOVAL OF GUARD WIRE POLE DURING REMOVAL OF GUARD POLE

PAGE 1 OF 4
GUARD WIRE POLE INSTALLATION

DURING EXCAVATION DURING GUARD POLE INSTALLATION DURING PAINTING

PAGE 2 OF 4
GUARD WIRE POLE STRINGING

DURING GUARD WIRE STRINGING

PAGE 3 OF 4
AFTER COMPLETION OF GUARD WIRE POLE INSTALLATION

PAGE 4 OF 4