You are on page 1of 12

I.

Cable ladder installation


1.cable support and cable tray construction
(1) Preparation and installation of the cable support
1) The whole factory cable tray and support shall be installed in accordance with the cable tray drawings
and specifications.
2) Cable support material should be straight without obvious deformation and galvanized layer intact. The
installation shall be firm and neat, and the screws are not loose. The orientation and elevation of the cable
support are correct, the direction meets the design requirements, the support installation is horizontal and
vertical, the deviation of the same layer height should be no more than 5mm, the left and right deviation is
not more than 10mm, and the distance between layers should meet the design and specification
requirements.
3) When installing rows of supports, the installation height is calibration to ensure that the bracket
installation height is consistent. The cutting of materials shall use a cutting machine, not electric fire
welding. The bending radius of the cable should be fully considered in the installation of the cable trench
to facilitate cable laying.
4) When the cable support is installed parallel or cross with the pipeline, the separation distance shall meet
the requirements of the specification, and sufficient distance shall be left for insulation according to the
actual situation of the site. Cable support cutting and pull holes should be filed at the burrs and paint
against corrosion. The full length of the support shall be well grounded.
(2) Cable tray installation
1) The cable tray is installed by section assembly and overall adjustment. When adjusting, the line should
be straightened to ensure that the cable tray is horizontal and vertical, neat and beautiful. The straight line
and height error of the cable tray of the same level, and the spacing of each layer is in line with the design.
2) The cable tray and support should be fixed reliably, the connection plates and bolts between the cable
tray should be complete and fastened, the nuts should be placed outside the cable tray, and the spring and
flat pads should be complete. The cutting of the cable tray adopts hand saw or cutting machine to avoid the
destruction of its galvanizing layer due to heat.
3) The installation of the cable tray should be carried out according to the design drawings and the site
situation. The cable tray should not be parallel to the upper part of the thermal pipe. The branch cable tray
and the main cable tray shall be connected in three links, and the interface transition is natural and meet
the requirements of the cable bending radius, so as to facilitate the cable laying.
4) If the design of cable tray requires the fire partition plate and cover plate, the fire partition plate should
be embedded in the bracket, and the fire cover plate should be uniformly installed first after the cable
laying, and the cable tray should be grounded reliably.
5) Site wiring cable lines and all cable line supports shall be at least 150 mm from the final outer surface
of all steam pipes, including insulation and at least 50 mm from the final outer surface of all other pipes,
including insulation (if provided). The thermal expansion position of the pipe shall be considered when
conducting cable wiring on site.
6) The field installed cable tray and all cable tray supports shall be located so that they do not interfere
with the equipment expanding, shaking or moving under normal operation, such as steam generators, flue
gas pipe systems, cable tray cranes, etc.
7) The cable tray installed on the concrete or masonry wall shall be installed in such a way that there is at
least 6mm of air space between the cable tray and the concrete or masonry wall.

1
8) Cable tray and its bracket shall not be attached to the grille. The cable tray and its supports shall not be
connected to the flange of the cold-forming support steel. Instead, the cable trays and their supports shall
be connected to the cold-bent support steel structure, walls, floors by welding or through bolts drilled in
the structure.
9) The minimum vertical spacing of the tray shall be 300mm measured from the bottom of the upper tray
to the top of the lower tray. Keep a clearance of at least 300mm between the top tray and the beams, pipes
or other obstructions to facilitate the installation of cables in the tray. At least working space of at least
600mm of each tray.
10) Cut the tray to the desired length. The trays shall be cut with saws and all surfaces of the laid wires and
cables shall be grounded or filed to remove any sharp edges that may damage the cable sheath or
insulation. The plane of all field cutting tray ends shall be square and perpendicular to the center line.
Areas where galvanized layers are removed or damaged shall be repaired with a cold-plated galvanized
zinc-rich coating.
11) Install the tray cover after cable laying and fire plugging. Attach the tray lid to the tray using a tray lid
clip or tapping screw and remove all debris from the tray immediately before installing the lid. The tray lid
cut edges shall be filed and re-galvanized or resealed. The cover edges in contact with the cable shall be
covered with protective material.
II. Cable installation
1. Cable laying
1.1. Secondary design before cable laying
Before cable laying technical personnel to be present in advance, the use of computer cable laying secondary
design, the design institute of cable inventory refinement, check the direction of the cable and channel, the
channel number (and thermal control cable channel as a whole), to compile detailed list of cable laying,
make the cable laying more neat, reduce the cable crossing.
1.2. Cable laying
(1) Cable laying should be considered with thermal control cables, and the construction should be carried out
in accordance with the principle of "unified organization, unified arrangement, unified standards and strict
requirements". The cable insulation test shall be carried out before the cable laying, and the cable laying
construction can be carried out only after passing the cable laying.
(2) Before cable laying, carefully check the outside of each cable tray, and remove the protruding nails,
fasteners or other objects that may damage the cable. A thorough visual inspection of the defects, breaks or
wear in the cable sheath and the pull rate shall be sufficiently slow to allow this inspection. Damage to the
cable sheath or surface layer shall be sufficient to justify rejecting the cable. Cables damaged in any way
during installation shall be replaced.
(3) When cable laying, the on-site command and laying personnel shall be equipped with intercom to ensure
smooth communication. When laying the laying machine, the laying should be stopped immediately when
any abnormal situation is found.
(4) Cable laying is carried out by combining manpower and machinery, and the cable conveyor lays large
section and long distance cables. After the cable laying, the sign shall be listed at the starting point, end point
and turning point, hang the temporary sign first, and then replaced with the formal cable plate. The formal
cable plate shall be printed by the computer nameplate, so that the handwriting shall be clear and never fade.
(5) Before laying cables, check and the cable laying channel should be cleaned to remove the debris in the
channels, ensure that the laying path has no sharp objects damaging the cable, and ensure that the channel is
clean and smooth.

2
(6) Before the cable passes through the cable protection pipe, the interior of the cable protection pipe should
be cleaned as required to ensure that the cable goes through without damage.
(7) The cable laying is laid in layers, and the diameter of the cable laying in the same layer is as consistent as
possible. In the cable binding unified requirements, choose the same color of the binding line, every other
section of a binding, binding spacing in line with the specification requirements.
(8) The laying distance of the cable parallel to the lower part of the thermal pipeline shall be more than 1
meter; The cross-laying distance between the cable and the thermal pipeline shall be greater than 0.5 meters;
The parallel laying distance of the cable and the insulation layer shall be more than 0.5 meters; The cross
laying distance between cable and insulation layer shall be greater than 0.2 meters; No intermediate joint is
allowed for either power cable or control cable, For long-distance power cables (generally more than 2000
meters) due to the difficulty of cable manufacturing length, Individual need to do intermediate joints, With
the permission of the Owner, And supervision side station, Keep a good record, Mark the position of the
middle head, And report it to the tenderer for the record; Cable signs shall be executed according to the
design and specification requirements; Cable support points spacing according to the design and
specification requirements; The AC single-core cable fixing fixture shall adopt a closed magnetic path free of
iron parts.
(9) During cable laying, the minimum bending radius of the cable shall be 20 times of the outer diameter of
the cable. When putting the cable on, make the transition support and hanger between the cable tray frame or
the bracket and the tray cabinet, so that the curvature and radian of the cable upper plate are consistent,
arrange neatly, and avoid crossing. The place that must cross should ensure that personnel can pass normally.
The contact cable is laid in layers in the cable interlayer and the local cable to avoid unnecessary crossing.
(10) During the process of laying a single cable and before wiring, the cable head should be sealed to prevent
the moisture intake of the cable head. Each laid cable shall be attached to a temporary cable sign and verified
before wiring.
(11) Cables shall be supported at all times, not bent or excessively drooping, and not placed on the manhole
floor. The cable ends shall not be immersed in the water. Cable racks or trays shall be provided for
permanent support. The temporary support required during placement shall be sling, timber, etc.
(12) cable tray layout should be from top to bottom successively: medium voltage cable low voltage cable
control cable instrument analog or special signal cable.
(13) A layer of power cable shall be laid in the cable tray to prevent the cable from overheating. Do not place
a multilayer power cord in one tray.
(14) All the ends of the cable shall not be crossed. After the cable laying is completed, fill in the "cable
laying installation record form" and "cable access plate acceptance form" before the connection. The cable
record sheet shall include the number, size, materials, estimated length, actual installation length, start and
end of the line, and completion date of installation.
2. Direct-buried cable laying
(1) In addition to risers above the ground terminal, cables with rated voltage of 1000V or below shall be
buried in the pipeline group, with a depth at least 600mm lower than the finished ground, and cables with
rated voltage above 1000V to 40kV shall be buried in the pipeline group, with a depth of at least 1000 mm
below the finished slope.
(2) When a cable protection pipe is laid more than a cable, the power cable should be arranged in the lower
pipe, while the lighter cable (such as control cable, communication cable) should be arranged in the higher
pipe.
(3) Medium-voltage power cables shall not share the cable protection pipes with other cables. Power cables
shall not share pipes with control, instrument or communication cables. Control cables, instrument cables
and communication cables shall be handled separately.
3
(4) Direct buried cables shall have 150mm PVC yellow warning bands 150 mm wide in the backfill at
500mm depth and 300mm above the installed cables. The warning tape shall be engraved with the warning
words "CAUTION BURIED ELECTRIC LINE BELOW" and face up. The warning belt shall be
continuously laid over the directly buried cable line.
(5) Direct buried cables should be limited to street lighting cables, and all backfill soil should meet the
requirements of landscaping design.
III. Lifting method
1. Hoisting of the high-voltage frequency conversion cabinet
The frequency conversion cabinet of this project is 4,2650mm high, 5130mm wide, 1200mm deep, weighing
about 7800 KG, the bottom height is about 15.7 meters, placed above the foundation channel steel of the
plate cabinet. In the same layer, there are 4 auxiliary induced draft fan frequency conversion cabinets, with
2650mm high, 3830mm wide, 1200mm deep, and weighing about 4400 KG.
2. Lifting process
Prerequisites confirm the end of the lifting in the lifting room
3. Lifting method
The QY 25 E truck crane shall be used to lift the cabinet in place
3.1. Confirm the received equipment, and check whether the outer package is damaged.
3.2. Select the truck to transport the truck along the designated route to the installation site. Colash vibration
should be avoided during transportation.
3.3. After the cabinet is transported to the distribution room, the 25t crane is hoisted to the lifting platform at
the entrance of 15.7 meters of the distribution room (using the existing steel structure platform), and then the
hydraulic trolley or rolling bar is used to carry in place. According to the actual situation, the crane stands on
one side of the distribution room. The weight of the plate cabinet is 7.85t. When the radius of the crane is 7m
and the main arm length is 20.85m, the rated lifting weight is 9.6T. The cabinet is 7.85t and the hook is 0.25t,
so it is concluded that (7.85+0.25)÷9.6=84%, the crane load rate is 84%, the crane load is within the safety
factor, and the weight of other cabinets is less than this weight, which can be hoisted safely safely.(Crane
station position drawing)

4
3.4. QY 25 E vehicle lifting performance table

Main Jib
Work
range Avoid the 5th leg, side and rear operation; use the 5th leg, 360° operation
(m)
10.2m 13.75m 17.3m 20.85m 24.4m 27.95m 31.5m

3.0 25000 21500

3.5 23500 21500 16500

4.0 20500 19500 16500 11500

4.5 18200 17500 15500 11500 9500

5.0 16100 16000 14500 11200 9500 8500

5.5 14800 14500 13500 10800 9500 8500

6.0 13500 13200 12500 10500 9500 8100 6500

6.5 12200 12000 11500 10100 9200 7900 6500

7.0 11200 11000 10800 9600 9000 7700 6500

7.5 10400 10200 10000 9100 8700 7300 6200

8.0 9600 9500 9400 8600 8300 7000 6000

8.5 8800 8700 8600 8200 8000 6700 5800

9.0 8200 8200 7800 7700 6500 5500

10.0 7400 7000 7000 7100 6100 5000

12.0 5000 5100 5200 5200 4300

14.0 3500 3900 3900 3900 3800

16.0 3000 3000 3000 3200

18.0 2000 2200 2300 2500

20.0 1500 1700 2000

22.0 1200 1500

24.0 800 1100

26.0 800

5
28.0 600

29.0 400

3.5. Hoisting process control


(1) Before the hoisting of the cabinet, the civil construction of the distribution room is accepted; the plate and
frame are installed and accepted.
(2) After the tray cabinet is transferred in place, the opening box acceptance is qualified.
(3) Test lifting: when lifting the cabinet is about 100mm, stop lifting, observe for 10 minutes, focus on
checking the vehicle lifting and braking mechanism; and then three times after any abnormality.
(4) Formal lifting. After everything is normal, lift the cabinet in this position, above the platform elevation of
15.7 meters, adjust the cabinet to fall. In the lifting process, the cabinet should be stabilized with the rope to
prevent rotation, keep a distance from the wall, pay attention to observation, and strictly prevent collision.
(5) when the cabinet hoisting directly above the platform, QY 25 E truck crane slowly loosen the hook, when
the cabinet drops to the platform 500mm stop the hook, under the hydraulic trailer or drum QY 25 E car
crane slowly loose hook, gradually reduce the load to no load, in this process, pay attention to observe the
steel frame stress and QY 25 E car abnormal load. Transfer the tray cabinet to the installation position
through a hydraulic trailer or drum for installation.
IV. Equipmemt Install
1. Installation scheme of plant power consumption and power distribution device
1.1 Equipment installation process and required conditions
(1) Installation and construction process

6
(2) Conditions for equipment installation
The construction works related to the installation of the plate and cabinet shall meet the relevant provisions
of the code, the position and elevation of the embedded parts shall meet the design requirements, and the site
shall meet the installation conditions. And conduct the middle handover of the building installation.
1.2. Installation of the plate and cabinet foundation
The foundation installation of the disk cabinet shall meet the specification and design requirements, and have
at least 2 reliable connection with the grounding network. According to the construction drawings, the
construction materials are calculated and the materials are collected and fed. The section steel should be
straight and rusted before production, and anti-corrosion treatment should be carried out after production.
After leveling with the level, weld and fix reliably; the levelness and straightness errors of the foundation
base shall meet the requirements.
Unpacking the cabinet for inspection and handling in place
(1) The unpacking place of the equipment shall be at the site nearest to the installation site; mainly check the
integrity of the equipment, deformation and corrosion, and check the model, specification and quantity;
(2) The loading and unloading and transportation of the equipment shall be directed by the crane and
coordinated by the electrician; the handling should not be carried out in wind and rain weather to prevent the
equipment from tipping and flooding after unpacking;
(3) The plate cabinet in the switch room with the hydraulic car and the rolling bar;
3.2.4 Installation of low-voltage power distribution cabinet and frequency conversion cabinet

7
(1) Select the cabinet of the incoming line position as the benchmark, accurately position the central position
of the cabinet, adjust the levelness and verticality, and then fix with the foundation steel, and adjust the rest
of the cabinet to install one by one with the cabinet as the benchmark.
(2) After the whole line of power distribution cabinets are corrected, check the overall vertical and horizontal
errors of the plate cabinet. After meeting the bid inspection requirements, the plate cabinet and the
foundation shall be welded or bolted according to the design requirements, and the tray shall be bolted.
(3) Install the main bus in the switch cabinet
1) The main bus in the switch cabinet shall be provided by the manufacturer. Before installation, the surface
of the bus shall be smooth and smooth and smooth, and there shall be no cracks, wrinkles, inclusions,
deformation and distortion.
2) The bus lap surface must be kept clean and coated with power grease; the bus support insulator at the
connection shall be strong, the orientation of the bus connection bolts shall meet the specification
requirements, the nuts are placed on the maintenance side, the bolts shall expose the nuts 2-3 buttons; both
sides of the bolts shall have flat washer and the nut side.
3) The bus connection bolt shall be fastened with a torque wrench, and the tightening torque value shall meet
the specification requirements.
4) When conducting equipment inspection, apply torque wrench to check and verify the torque value of
internal branch bus connection bolt of the manufacturer.
5) After the installation of the bus, the bus room shall be cleaned, and the insulation resistance of the bus
shall be checked with the corresponding meaohlim meter. Apply for the acceptance of concealed works after
meeting the requirements of the specification, and the bus room shall be closed after the acceptance.
6) During the installation of the cabinet, the protection of the finished products, especially the cabinet paint
should be protected by color strip cloth or plastic film, and the protection tarpaulin should be covered after
the installation and acceptance.
1.3. Installation scheme of local electrical box, plate and cabinet
1.3.1 Installation of equipment foundation
The allowable deviation of foundation steel installation meets the specification requirements, and is fixed
firmly and reliable, and there are 2 obvious and reliable grounding.
1.3.2 Installation of the plate and cabinet
(1) Before the installation of the cabinet, the cabinet should be opened for inspection and acceptance, and
then the front of the cabinet should be consistent with the drawings. Then the reference cabinet shall be fixed
with bolts and foundation, and the rest of the cabinet shall be adjusted and fixed in turn, and the panel shall
be connected by bolts.
(2) Check that the models and specifications of the equipment and accessories are correct, meet the design
requirements, and check as qualified. The instrument and relay are installed and fixed firmly, and meet the
design requirements on seismic resistance. The connection parts of the secondary circuit shall be made of
copper products, and the insulation parts shall be made of self-extinguishing flame retardant material.
(3) In-screen wiring: the current circuit shall be not less than 500V, and the section shall not be less than
4mm2, The cross section of the voltage circuit wire shall not be less than 2.5mm2. The wires used to connect
the electrical appliances on the door, the movable part such as the control panel should be multiple soft wires,
the laying length should be appropriate margin, and the wiring harness should be reinforced by the outer
plastic pipe. The wiring terminal on each side should be 1, not more than 2. The wiring is neat, clear and
beautiful, and the conductor is well insulated.
V. weld
8
1. Welding scheme of instrument and sampling pipeline

The instrument and sampling pipe have small pipe diameter, many types and complex materials. There are
dozens of instrument pipes arranged in the same group, with high welding process requirements and strict
control. The materials cover A213T91, A213T22,0Cr18N10Ti, TP 304, TP 316,12 CrMoV, 15 CrMo, 20 and
other different materials, and the connection mode includes docking and plugging.

(1) Alloy steel, stainless steel instruments and sampling pipelines should be subjected to spectral
analysis, and the spectral analysis should be reviewed before and after installation to ensure that the
material is consistent with the design.

(2) Be familiar with the construction drawings, do the construction planning work with the thermal
control professional and technical personnel, and clearly mark the installation parts and pipe material.

(3) Prepare the welding construction plan and process card of instrument and sampling pipe. The
process card shall cover all the involved welding process, and ensure the welding quality measures.

(4) Before welding, the oil, paint and rust on the inner and outer wall surface of the groove and the
nearby base material must be cleaned until the metallic luster. The cleaning range is 10~15mm on each
side.

(5) The instrument pipe welding quantity is large, the pipe diameter is small, the inner wall should be
flush without the wrong mouth, and the overall layout is reasonable and beautiful.

(6) It is strictly prohibited to ignite arc, test current or weld temporary support on the surface of the
welding workpiece to prevent pipe breakdown.

(7) Before welding, welding safety technology must be disclosed, and welding construction personnel
shall operate strictly according to the technical disclosure and construction process card, and be
familiar with relevant process requirements and identification. When welding multi-material pipes,
welding materials shall be clearly classified and misuse of materials is strictly prohibited.

(8) For the post-welding heat treatment weld, the welding joints with the same heat treatment process
and the same specification heater are arranged into a group for series heating. It is strictly prohibited to
heat the two groups of welding joints in parallel as a furnace.

(9) After the welding, the quality inspection personnel shall conduct a comprehensive evaluation of the
weld quality, spectrum review and nondestructive inspection, and take measures to repair the
unqualified part.
2, steel structure, support and hanger welding construction technology
(1) Welding method
Main use of full manual arc welding SMAW.
(2) Preparation before welding
A. Prepare woven cloth or peng cloth and prevent wind or rain.
B. The welded groove shall meet the specification requirements of the construction drawings.
C. Before assembly, the oil, paint and rust on the inner and outer wall surfaces of the groove and nearby base
9
material must be cleaned until the metallic luster. The cleaning range: butt welding head, 10~20mm on each
side. For each side, welding joint K + 10~20mm.
D. The weld groove shall be kept smooth without burrs, without cracks, interlayer and slag defects
E. The weld part should be straight generally. If there is a wrong opening, the wrong opening value should
meet the requirements of the regulations.
F. During welding and assembly, the workpiece to be welded should be placed firmly, and the strong pair
shall be prohibited to prevent additional stress and deformation.
G. The lap length of the lap joint shall not be less than 5 times the thickness of the steel plate, and not less
than 25mm. The weld attached to the corner weld shall be as tight as possible.
H. Welding materials shall be placed in a special warehouse with ventilation, drying, indoor temperature not
less than 5 degrees and relative humidity not exceeding 60%, and shall be kept, baked and distributed by
special personnel. Before use, the appearance shall be inspected and baked according to the requirements of
the operating manual. When welding, it shall be installed into the welding rod insulation cylinder and taken
at any use.
3) Welding process
A. When the welding environment temperature is lower than 0℃ and not lower than-10℃, the joint base
material must be preheated, not lower than the highest value of 20℃ or the specified minimum preheating
temperature, and should not be lower than this temperature during welding. The environmental wind speed
shall not be greater than 8 m/s
B. The interlayer temperature was controlled between 150 and 400℃. During multi-layer welding, the
tempering welding path can be used for welding. During multilayer welding, secondary welding must be
conducted after the upper layer welding inspection; the welding joint between the layers shall not be less
than 20mm. Except for the first and last layers, the welding path of the middle layer can be used by
hammering method to eliminate the welding stress. During welding, the quality of welding joints and arc
closing shall be guaranteed, and the arc pit molten tank shall be filled during arc closing.
C. In order to prevent welding deformation, two-person symmetrical welding should be used for column
and beam butt welding. When welding the long seam, the step-wise symmetrical welding is adopted layer by
layer.
D. It is strictly prohibited to ignite arc, test current or weld temporary support on the surface of the welded
piece. The welded grounding wire must be firmly connected.
E. Spot solid welding, welding materials, welding process, welding personnel requirements are the same as
when the formal welding. If the quality of spot solid welding shall be checked before the formal welding, the
defects shall be removed immediately and fixed again.
F. After welding, the welder shall carefully clean up the splashing slag on the surface of the weld, check the
appearance quality, and do partial repair if necessary.
VI. Circuit check
1, the cable wiring accuracy of 100% guarantee measures
(1) In order to ensure that the cable wiring is firm and reliable, and the correct rate reaches 100%, all the
cable wiring work is responsible for by the professional construction team, with monitor, technical personnel,
professional secondary wiring workers, the secondary wiring training before the work, and can take the post
after passing the examination.
(2) The wiring must be corrected before wiring, and carefully check whether the cable number, model and
specification are correct. Check whether the wiring diagram and the terminal row of the disk cabinet, and the
terminal row agree with the cable inventory. Check the secondary schematic wiring diagram, confirm
10
whether the wiring position of each cable is consistent with the schematic diagram, and use the multimeter to
carefully proofread the wiring position of each cable core. After the wiring, the wiring core must be checked
one by one to check the firm reliability of the wiring.
2. Circuit debugging measures

① Power supply circuit debugging

Check whether the cabinet KKS code and cabinet name are clear and conform to the design. Whether the
air label of each switch in the cabinet is complete, clear and consistent with the actual site. Check whether
the disk cabinet is grounded.

According to the schematic diagram of the manufacturer, check the correctness of the internal wiring of the
panel cabinet, combined with the rated power of the field equipment, check the cable section area of the
relevant power circuit, the capacity of the power fuse and the air switch capacity.

Measure loop insulation with 500V insulation resistance meter. general area shall be 1 MΩ and 0.5 MΩ in
wet area.

Contact the relevant departments to handle the required work ticket, and conduct the work / standby power
supply switching operation. The switching device should act reliably and meet the full load requirements.

② Pressure and differential pressure measurement circuit and commissioning

The input pressure and differential pressure transmitter shall be notified for operation. If necessary, relevant
operation tickets shall be handled. Check the correctness of the instrument pipe connection before input, and
then put the instrument according to the operating procedure.

During the instrument input process, the pipeline should be washed clean and observed whether the
instrument joint is tight without leakage.

Check the zero point of differential pressure measurement, if there is liquid column correction.

③ Debit measurement loop debugging

The ultrasonic (radar) bit meter shall check whether the Angle of the sensor wave Angle, the lower limit
radius of the level, the beam blind area and the distance between the beam center line and the container meet
the requirements of the manufacturer. After input, check whether the digital display and analog output truly
reflect the state of the measured medium.
VII . Grounding and Bonding
1. Ground installation
1.1 Ground construction scope

(1) The connection of the metal base and shell of each power distribution and electrical equipment with the
grounding network.

(2) Reliable connection between various cable protection pipes, cable tray, support and derrick and the
ground grid.

(3) The connection between the steel structure of each incineration line and the connecting landlord network.

11
1.2 Construction of grounding network

(1) The installation of the grounding device shall be constructed according to the approved design drawings.
The grounding materials must be accepted after the site, the specifications should meet the requirements, and
the corresponding warranty, certificate of qualification.

(2) All electrical equipment housing, generator, generator neutral cabinet, power transformer box, GCB /
TCB / UCB, IPB, auxiliary transformer, 38 kV NGR, 3.8kV NGR, switchgear, MV / LV motor, MV / LV
VSD, UPS / charger, low voltage plate / MCC, DB, high voltage cable sheath, medium and low voltage cable
armor / shielding, metal bracket, metal cable tray and metal structure shall be connected to PE ground bus
through 1000V rated PVC insulated copper cable in radial feeder. It is forbidden to ground one main device
to the other device without another coupling path. The ground joint buried in the ground should be treated
with anti-corrosion, and rust and welding residues should be removed before anti-corrosion. For the open
grounding wire, the laying position should not hinder the disassembly and maintenance of the equipment,
and the support parts meet the specification requirements and be horizontal, vertical, neat and beautiful.

(3) Copper material grounding material, adopt heat welding welding. The welding process is carried out in
strict accordance with the design and specification requirements.

(4) The branch grounding wire is connected with the equipment according to the design and specification
requirements, and the series grounding mode of the equipment is never allowed. Except for the equipment
connection, the rest should be concealed, and the visa acceptance should be made before concealment. The
identification color of the exposed part of the grounding flat iron should be uniform and the surface should
be coated with 50 ㎜ wide yellow and green stripes. The grounding flat iron should be connected to the
equipment close to the surface and should be connected with galvanized screws.

(5) Equipment grounding

1) Overground grounding shall be made of PVC insulated copper cables connected to all connecting points
by crimping patch.

2) All grounding junction rows shall be pre-drilled tin copper rows and shall be installed in the cable
basement or near the grounded equipment or objects. The structure of the ground bus by an insulator.

3) All main electrical equipment, metal frame and mechanical equipment shall be equipped with grounding
studs / wiring ds to connect the PE grounding feeder directly to the PE grounding bus and reliably with the
grounding system. The grounding of the equipment should be connected by the insulated soft copper wire
and the main grounding wire.

4) cable tray, cable vertical cable and metal frame, pipes, railings and all metal objects shall be connected
using separate PVC insulated copper grounding cable or jumper to the indoor grounding bus or the nearest
steel bar, not more than 2 0 meters apart.

5) The above-ground grounding system shall be connected by PE or IE grounding bus, and connected to the
underground ground net / horizontal electrode by riser. All electrical equipment shall be provided with
multiple contact locations, with a minimum of two.

12

You might also like